Saep 351
Saep 351
1 Scope............................................................. 2
2 References..................................................... 2
3 Responsibilities.............................................. 3
4 General Requirement..................................... 3
5 Qualification of Joint Assembler…................. 3
6 Mechanical Joint Requirement....................... 4
7 Alignment of Mechanical Joints……………… 5
8 Equipment Tools............................................ 6
9 Tightening Sequence…………………………. 6
10 Torque Values………..................................... 6
1 Scope
This procedure may be used for bolted flange joints in heat exchangers and pressure
vessels.
2 References
Page 2 of 19
Document Responsibility: Piping Standards Committee SAEP-351
Issue Date: 1 December 2013
Next Planned Update: 1 December 2018 Bolted Flange Joints Assembly
3 Responsibilities
3.1.2 The maintenance personnel executing the flange assembly activities shall
be qualified per Section 5.
3.1.3 Operation inspection shall witness all critical mechanical joints per
paragraph 4.1.
3.2 For new capital program projects the following shall apply:
3.2.1 The Saudi Aramco PMT is responsible for ensuring that the Construction
Contractor is following this procedure or specific bolt up procedures.
3.2.2 The contractor personnel executing the flange assembly shall adhere to
flange assembly procedure.
3.2.3 The construction personnel executing the flange assembly activities shall
be qualified per Section 5.
3.2.3 Project inspection shall witness all critical mechanical joints per
paragraph 4.1.
4 General Requirements
4.1 Mechanical joints criticality assessment for the facility shall be conducted to
identify critical flanges.
4.2 A bolt up procedure based on the requirement of this document and ASME PCC-1
shall be developed for each flange assembly and shall be approved by Saudi
Aramco per Section 3.
4.3 All personnel executing the flange assembly shall be qualified according to
Section 5.
Page 3 of 19
Document Responsibility: Piping Standards Committee SAEP-351
Issue Date: 1 December 2013
Next Planned Update: 1 December 2018 Bolted Flange Joints Assembly
There are five ECITB approved technical tests covering mechanical joint integrity.
5.2 After successfully completing the required training courses, a record shall be
maintained to demonstrate the technician’s competency.
Commentary Note:
Hydrocarbon release incident data for oil and gas industry indicate that poor
bolted flange assembly is a major cause of leaks. A review of historical causes
confirms that the skills and practices used have not assured leak-free joint.
Therefore, any technician working on a flange assembly shall be trained and
assessed as component to perform the task.
6.1 Gasket
6.1.1 The gasket rating and dimension for piping system shall be verified as
required by ASME B16.20 and ASME B16.21. For other gaskets that
are not within the scope of ASME, the rating and the dimensions shall be
according to the manufacturer’s specification.
6.1.2 The gasket type and application for piping system shall be verified as
required base on the line class for the piping system.
6.1.3 Gasket shall not be damaged or distorted and free of all foreign particles.
6.1.4 The gaskets shall not have any defects. Gaskets with defects shall be
replaced.
6.1.5 The gaskets shall be marked to identify rating and size and other
principal characteristics. Gaskets with no marking shall not be installed.
Commentary Note:
Marking may be on the gasket packaging for some type of gaskets that
are not intended for piping system.
6.1.6 The seal rings for the clamp connectors shall be provided from the clamp
connector manufactures.
6.2 Bolts
6.2.1 Bolts, nuts and washers shall be visually checked for proper size, grade,
Page 4 of 19
Document Responsibility: Piping Standards Committee SAEP-351
Issue Date: 1 December 2013
Next Planned Update: 1 December 2018 Bolted Flange Joints Assembly
and dimension and for any physical damage such as corrosion, rust and
burrs. Also, the suitability of the stud bolts and nuts material for the
service temperature and the compatibility with the flange material shall
be checked.
6.2.2 The bolts/nuts combinations for which the nuts will not turn freely by
hand shall be verified.
6.2.3 Bolts and nuts shall be replaced when reassembling existing flanges.
6.2.4 Any abuse bolts and nuts shall be replaced even after the flange assembly.
6.2.5 The nuts shall have full thread engagement after the flange assembly.
6.3.1 The gasket contact surface shall be examined for compliance with the
recommended surface finish and for damage to surface finish such as
scratches, nicks, gouges and burrs.
6.3.2 When reassembling flange joint, all indications of the previous gasket
installation shall be removed.
6.3.4 Lubricant shall not be used in the gasket and the gasket seating area.
6.4 Lubricant
6.4.1 Lubricant shall be applied to both the nut bearing surface and the male
threads.
6.4.2 Friction factors for some common lubricant are addressed in Appendix B,
Table B-1.
6.4.3 The nuts shall be turned freely by hand before applying the lubricant.
7.1 The joint should be aligned without any external forces. Appendix C shall be
followed.
Page 5 of 19
Document Responsibility: Piping Standards Committee SAEP-351
Issue Date: 1 December 2013
Next Planned Update: 1 December 2018 Bolted Flange Joints Assembly
7.2 For clamp connector, the hubs shall be aligned to allow engagement of the seal
ring lips to hub sealing surfaces. Clamp connector installation guideline line is
addressed in Appendix D.
8.2 Tightening tools shall be checked for adequacy, performance and calibration.
The tools accuracy should not exceed ±5%.
8.3 Manual torque wrenches shall not be used for 1” bolts size and larger. All manual
torque wrenches shall have calibrated torque measurement.
9 Tightening Sequence
9.3 Flange load factor shall be considered when using blot tensioner less than 100%.
10 Torque Values
10.1 Torque values shall be determined according to flange rating, bolt size, type of
gasket, and the lubricant’s friction factor. The torque values addressed in this
paragraph shall not be used for other than what is specified for per paragraphs
10.2, 10.3 and 10.4.
10.2 ASME PCC-1 shall be used to developed torque values for bolted flanges.
Typical torque values for carbon steel flanges with ASTM 193, B7 bolts are
specified in Table F-1 for different coefficient of friction. The calculated torque
values shall be included in the bolt up procedure per Section 4.
Commentary Note:
There are free and commercial software for blot load calculations. The software
used in the calculation shall be included in the bolt up procedure
10.3 Table F-2 applies to bolted flanges with metal core with spring-energized Teflon
seal isolating gaskets based on a friction factor of 0.16.
Page 6 of 19
Document Responsibility: Piping Standards Committee SAEP-351
Issue Date: 1 December 2013
Next Planned Update: 1 December 2018 Bolted Flange Joints Assembly
10.4 Recommended bolt loads for two piece clamp connectors are specified in
Table F-3.
Revision Summary
1 December 2013 Major revision.
Page 7 of 19
Document Responsibility: Piping Standards Committee SAEP-351
Issue Date: 1 December 2013
Next Planned Update: 1 December 2018 Bolted Flange Joints Assembly
Corrugate metal jacket with corrugated metal core; full width and 3.2-6.4 125-250
circumference of both sides to be covered with adhesive-backed flexible
graphite tape
Grooved metal gasket with facing layers such as flexible graphite, PTFE, 3.2-6.4 125-250
or other conformable material
NOTE: Finishes listed are average surface roughness values and apply to either the serrated concentric or serrated
spiral finish on the gasket contact surface of the flange.
Page 8 of 19
Document Responsibility: Piping Standards Committee SAEP-351
Issue Date: 1 December 2013
Next Planned Update: 1 December 2018 Bolted Flange Joints Assembly
Page 9 of 19
Document Responsibility: Piping Standards Committee SAEP-351
Issue Date: 1 December 2013
Next Planned Update: 1 December 2018 Bolted Flange Joints Assembly
Parallelism
Centerline Tolerance
Spacing Rotational
Page 10 of 19
Document Responsibility: Piping Standards Committee SAEP-351
Issue Date: 1 December 2013
Next Planned Update: 1 December 2018 Bolted Flange Joints Assembly
Installation of clamp-type connectors shall strictly follow the Manufacturer recommendations. The below
guidelines may only be used in the absence of such recommendations.
D.1 Use non-abrasive material to clean all lubricants and foreign matter from the hub sealing
surfaces before installation.
D.2 Polish the hub sealing surfaces using fine steel wool to remove scale, rust, burrs or surface
scratches from the hub sealing surfaces. In case of presence of severe corrosion, deep
scratches, or crack in the sealing surfaces, use new hubs. Lapping of hub sealing surfaces can
only be done by the manufacturer.
D.3 Use light film lubricants on the seal rings if they are uncoated or re-used. Ensure that lubricants
are free from solids or foreign materials.
Note: Seal rings may be used if they are free from damage, severe corrosion, or cracks.
In case of any doubt, use new seal rings. New seal rings normally have coating
(PTFE, MoS2 with graphite) which acts as a lubricant.
D.4 Align the hubs so that the seal ring can be installed. In case of misalignment, contact the
manufacturer for maximum allowable values.
D.5 Install the seal ring in the sealing surface of the hubs. The seal ring should rock slightly; i.e., the
seal ring rib should not be able to fully contact the hub face (Free Position, Figure D-1). If it
does not rock, use a new seal ring.
D.6 Apply lubricant to the hub clamp contact area, clamp ears, stud bolts and spherical faces of the
nut. This is to reduce friction and required torque during assembly.
D.8 Insert the bolts in the bolt holes of the clamp ears.
Page 11 of 19
Document Responsibility: Piping Standards Committee SAEP-351
Issue Date: 1 December 2013
Next Planned Update: 1 December 2018 Bolted Flange Joints Assembly
D.9 Tighten the spherical nuts noting that the spherical face shall fit into the spherical seats of the
clamp ears. The order of bolt tightening shall be in criss-cross pattern (i.e., bolt #1, #3, #2, #4)
while keeping the spacing between the clamp halves approximately equal.
D.10 Torque the bolts to the recommended torque value. Then, the clamp should be with a soft
hammer (jarred) and re-tightened. This procedure should be repeated until bolt torques does
not change after jarring.
D.11 Check that hub faces are in full contact with the seal ring rib after assembly (Make-Up Position,
Figure D-2).
Page 12 of 19
Document Responsibility: Piping Standards Committee SAEP-351
Issue Date: 1 December 2013
Next Planned Update: 1 December 2018 Bolted Flange Joints Assembly
Page 13 of 19
Document Responsibility: Piping Standards Committee SAEP-351
Issue Date: 1 December 2013
Next Planned Update: 1 December 2018 Bolted Flange Joints Assembly
Appendix F – Torque Load Values for Friction Coefficients 0.11, 0.13 and 0.15
Page 14 of 19
Document Responsibility: Piping Standards Committee SAEP-351
Issue Date: 1 December 2013
Next Planned Update: 1 December 2018 Bolted Flange Joints Assembly
Page 15 of 19
Document Responsibility: Piping Standards Committee SAEP-351
Issue Date: 1 December 2013
Next Planned Update: 1 December 2018 Bolted Flange Joints Assembly
Page 16 of 19
Document Responsibility: Piping Standards Committee SAEP-351
Issue Date: 1 December 2013
Next Planned Update: 1 December 2018 Bolted Flange Joints Assembly
Page 17 of 19
Document Responsibility: Piping Standards Committee SAEP-351
Issue Date: 1 December 2013
Next Planned Update: 1 December 2018 Bolted Flange Joints Assembly
Note: Torque values based on 30,000 psi tension load and 0.16 Friction Factor from
API BULL 5A2 thread compound. See Table-SAEP-351-01 Notes.
Commentary Notes:
a) For ASME Class 900 through Class 2500, API-6B and API-6BX Class 2000 through Class 15000, and
RTJ Flanges, the maximum compressive stresses induced during installation should not exceed
25,000 psi. Design to 12,500 psi when possible.
b) Calculations for compressive stresses applied during torque-up procedures must account for ring joint
grooves, gasket seal grooves, raised face diameters, and gasket inside diameter. (See PIKOTEK
Gasket User's manual).
c) Bolt tensioning equipment may be used for class 900 and above resulting in a minimum residual bolt
stress of 30000 psi and a maximum of 50,000 psi. Refer to PIKOTEK Gasket User's manual for
specific bolting instructions.
Page 18 of 19
Document Responsibility: Piping Standards Committee SAEP-351
Issue Date: 1 December 2013
Next Planned Update: 1 December 2018 Bolted Flange Joints Assembly
Table F-3 – Recommended Torque Values for Two-Piece, Four-Bolt Clamp Connector
Using B7/B7M Lubricated Bolting (Coefficient of friction=0.1)
3 0.750 65
4 0.875 100
5 1.000 160
6 1.125 210
8 1.250 300
Heavy Duty Series
2 0.875 136
3 0.875 163
4 1.000 190
8 1.375 529
10 1.625 949
12 1.750 1,220
Page 19 of 19