04 Method Statement For Block Work
04 Method Statement For Block Work
For UEP
Signature:
For HES/DPC
Signature:
Designation:
Date:
DPC/TENDER/2016/110
UPGRADATION OF 33/11kV JUFA/SADAH PRIMARY SUBSTATION FROM
2x6MVA TO 2X20MVA CAPACITY
Contents
1.0 Purpose 03
2.0 Scope 03
3.0 References 03
5.0 Manpower 03
6.0 Procedure 03
8.0 Responsibilities 06
9.0 Emergency 07
10.0 Records 07
DPC/TENDER/2016/110
UPGRADATION OF 33/11kV JUFA/SADAH PRIMARY SUBSTATION FROM
2x6MVA TO 2X20MVA CAPACITY
1.0 Purpose
The purpose of this method statement is to define the general sequence of events and
responsibilities for carrying out Block Work and the measures adopted for safe and
systematic completion of the same.
2.0 Scope
This procedure shall be applicable for Bock works of DPC/2016/110 - Upgradation of
33/11kV Jufa/Sadha Primary Substation form 2x6 MVA to 2x20 MVA Capacity. This
Method Statement provides to control sequence of Construction & Methodology that
will be used for the supply, installation & maintenance of Block works. This Works
shall be done in accordance with Approved Drawings and in accordance with
DPC/HES specification.
3.0 Reference
- Approved civil drawing.
- Project HSE Plan.
- Project Quality Plan.
- Tender Specification
4.0 Plant, Machinery and Tools
- Transit mixers
- Hand Tools
- Floaters machines for finishing.
- Water Tankers.
5.0 Man power
a) Project Engineer - 01
b) Civil Engineer - 01
c) HSE Officer - 01
d) Site Supervisor - 01
e) Civil helpers - 12
6.0 Procedure
6.1 SETOUT:
All the works will be set out and checked with reference to the certified survey
points/lines/axis. The dimensions of the elements will be as per the relevant drawings and the
same will be recorded in the checklist.
DPC/TENDER/2016/110
UPGRADATION OF 33/11kV JUFA/SADAH PRIMARY SUBSTATION FROM
2x6MVA TO 2X20MVA CAPACITY
Walls shall be carried up regularly without leaving any part more than one metre
lower than other. The blocks with broken corners shall not be incorporated in the
works. Curing to be done minimum five days.
The non – load bearing walls shall not be constructed prior to structure works and
there shall be gap of at least two weeks between removal of shuttering and block
work.
Voids in hollow concrete blocks to be filled with mortar every two metres.
Mortar joints shall be straight, clean & uniform in thickness. After a section of wall
completed, all joints shall be pointed with a round bar to produce a dense, concave
surface and well bonded to the block at the edges.
Both skins of cavity walls shall be tied together with Butterfly wall tie, spaced at the
rate of every 800 mm horizontally and 400 mm vertically at ends, jambs, quoins.
Approved polystyrene rigid foam insulation board (50 mm thick) shall be used
between both skins of cavity walls.
The top of wall shall be finished with a layer of 10 mm easily compressible material
the joint shall be sealed with a non-hardening mastic sealant.
All masonry openings for door/ window shall be 20 mm more on either side and it
shall be measured from finished floor level.
Lintels over door / window openings shall be provided continuous for the full length
of the wall panel. In walls of more than 3m heights, intermediate beam of 400 mm
deep shall be provided at 3-mtr heights.
6.4 STACKING AND STORAGE OF BLOCKS:
All blocks are to be stored on plain ground surface and the stacks of the blocks are to
be protected from splashing by mud or contamination by other materials.
7.0 Safety Precautions and Measures
7.1 Significant Hazards
Poor condition of tools.
Open / unprotected trench / excavation.
Cave in / collapse of sides.
Back filled trenches
Toxic / flammable gases / oxygen deficiency
7.2 Control Measures
Calibration/fitness certificates shall be provided for all equipment and machinery to
be used for the works by defining their suitability depending on the areas of usage
DPC/TENDER/2016/110
UPGRADATION OF 33/11kV JUFA/SADAH PRIMARY SUBSTATION FROM
2x6MVA TO 2X20MVA CAPACITY
9.0 Emergency
In case of Emergency,
Stop the work.
Switch off the work equipment, tools and machineries
Alert the nearby workers to reach to the nearest assembly point
Do not to get panic and do not run.
Inform the site HSE officer and other key personnel from the emergency
contacts numbers displayed in the site.
Call emergency services (9999) if required.
Supervisor shall make head count and report.
10.0 Records
Quality Records (Approved drawings & Shop drawings)
Inspection forms ( RFI/MRDR)
Test Reports
As Built drawings