Assignment 2
Assignment 2
𝜌𝐴𝑠𝑒𝑙𝑙 = 0.4𝑃𝐺𝐴 + 15
𝜌𝐵𝑠𝑒𝑙𝑙 = 0.15𝑃𝐺𝐵 + 11
𝑏𝑢𝑦
𝜌𝑋 = 235 − 0.45𝑃𝐷𝑋
𝑏𝑢𝑦
𝜌𝑌 = 175 − 0.235𝑃𝐷𝑌
𝜌∗ − 15 𝜌∗ − 11 235 − 𝜌∗ 175 − 𝜌∗
+ = +
0.4 0.15 0.45 0.235
b. Taking the transmission limits into account, the market will be split into two regions, east and
west:
A Tmax B
Y X
𝝆𝑬 = 𝟔𝟕 + 𝟎. 𝟏𝟏𝟐𝟓𝑻𝒎𝒂𝒙 … (𝟏)
1
c. 𝐶𝑜𝑛𝑔𝑒𝑠𝑡𝑖𝑜𝑛 𝑟𝑒𝑛𝑡 = (𝜌𝑊 − 𝜌𝐸 ) ∗ 𝑇𝑚𝑎𝑥
d. For customer-X:
𝐶𝑜𝑛𝑔𝑒𝑠𝑡𝑖𝑜𝑛 𝑐ℎ𝑎𝑟𝑔𝑒𝑋 = 0 as it’s not contributing to the congestion. Hence, it’s not liable to
charges.
2
𝐹𝑇𝑅 𝑐𝑟𝑒𝑑𝑖𝑡𝑋 = (𝜌𝑊 − 𝜌𝐸 ) ∗ 0.5𝑇𝑚𝑎𝑥 = 24.394𝑇𝑚𝑎𝑥 − 0.13𝑇𝑚𝑎𝑥
𝑵𝒆𝒕 𝒄𝒐𝒏𝒈𝒆𝒔𝒕𝒊𝒐𝒏 𝒑𝒂𝒚𝒎𝒆𝒏𝒕𝒔𝑿 = 𝑪𝒐𝒏𝒈𝒆𝒔𝒕𝒊𝒐𝒏 𝒄𝒉𝒂𝒓𝒈𝒆𝑿 − 𝑭𝑻𝑹 𝒄𝒓𝒆𝒅𝒊𝒕𝑿 = 𝟎. 𝟏𝟑𝑻𝟐𝒎𝒂𝒙 − 𝟐𝟒. 𝟑𝟗𝟒𝑻𝒎𝒂𝒙
This number will be negative. Hence, customer-X will be earning money.
For generator-A
𝐶𝑜𝑛𝑔𝑒𝑠𝑡𝑖𝑜𝑛 𝑐ℎ𝑎𝑟𝑔𝑒𝐴 = 0 as it’s not contributing to the congestion. Hence, it’s not liable to
charges.
2
𝐹𝑇𝑅 𝑐𝑟𝑒𝑑𝑖𝑡𝐴 = (𝜌𝐸 − 𝜌𝑊 ) ∗ 0.75𝑇𝑚𝑎𝑥 = −36.59𝑇𝑚𝑎𝑥 + 0.195𝑇𝑚𝑎𝑥
𝑵𝒆𝒕 𝒄𝒐𝒏𝒈𝒆𝒔𝒕𝒊𝒐𝒏 𝒑𝒂𝒚𝒎𝒆𝒏𝒕𝒔𝑨 = 𝑪𝒐𝒏𝒈𝒆𝒔𝒕𝒊𝒐𝒏 𝒄𝒉𝒂𝒓𝒈𝒆𝑨 − 𝑭𝑻𝑹 𝒄𝒓𝒆𝒅𝒊𝒕𝑨 = 𝟑𝟔. 𝟓𝟗𝑻𝒎𝒂𝒙 − 𝟎. 𝟏𝟗𝟓𝑻𝟐𝒎𝒂𝒙
This number will be positive. Hence, generator-A will be paying money.
2
Problem 2:
a. With the transmission line limits ignored, the total load is 500 MW. Hence, it will be supplied by
the cheaper generator (G1). So,
b. With the impedances of the transmission lines as shown and using superposition, the power flows
will be as follows:
G1 G1
320 MW 180 MW 180 MW
1 2 1 2
2z 2z
z 120 MW z
266.67 MW + z 53.333 MW + z
60 MW
2z 2z
3 4 3 4
320 MW
G1
500 MW 180 MW
1 2
2z
173.333 MW z
326.67 MW z 6.67 MW
6.67 MW
2z
3 4
320 MW
3
c. If the transmission lines limit of 250 MW is considered, it can be seen from the results in point (b)
that line 1-3 is congested. So, generator G2 will have to supply some power so as to restrict the
power flow in line 1-3 to 250 MW. Due to the transmission line impedances, the power flow for
this additional power (x) from G2 will be:
1 G1 2
2z
x/2 z
z
x/2
2z
3 4 x
G2
𝑥
≥ 326.67 − 250
2
𝑥 = 153.33 𝑀𝑊
G1 346.67 MW 180 MW
1 2
2z
𝑳𝑴𝑷𝟏 = 𝟏𝟎 $/𝑴𝑾𝐡
𝑳𝑴𝑷𝟒 = 𝟐𝟎 $/𝑴𝑾𝐡
4
To get 𝐿𝑀𝑃2 , we assume a 1 MW increase in the load at bus-2 and see the impact on the
generation levels at G1 and G2 (∆𝑃𝐺1 and ∆𝑃𝐺2 ) as follows:
- To meet this 1 MW increase in load, the increase in generation levels will be:
- Also, to keep the power flow in line 1-3 at its capacity limit of 250 MW, the additional power
flows in line 1-3 (from 1 to 3) from both generators due to this change in generation should
cancel each other (considering transmission line impedances) as indicated in the figure below:
G1
+∆𝑃𝐺1 +1 MW
1 2
2z
+2∆𝑃𝐺1 /3 z +5∆𝑃𝐺2 /6
+∆𝑃𝐺2 /6 z
+∆𝑃𝐺1 /3
2z
3 4
+∆𝑃𝐺2
G2
1 1
∗ ∆𝑃𝐺1 − ∗ ∆𝑃𝐺2 = 0 … (2)
3 6
1 2
∆𝑃𝐺1 = 3 𝑀𝑊 and ∆𝑃𝐺2 = 3 𝑀𝑊. So,
𝟏 𝟐
𝑳𝑴𝑷𝟐 = ∗ 𝟏𝟎 + ∗ 𝟐𝟎 = 𝟏𝟔. 𝟔𝟕 $/𝑴𝑾𝒉
𝟑 𝟑
Applying the same steps to get 𝐿𝑀𝑃3 , for a 1 MW load increase at bus-3 we get:
5 1
∗ ∆𝑃𝐺1 + ∗ ∆𝑃𝐺2 = 0 … (4)
6 3
−2 5
∆𝑃𝐺1 = 3
𝑀𝑊 and ∆𝑃𝐺2 = 3 𝑀𝑊. So,
−𝟐 𝟓
𝑳𝑴𝑷𝟑 = ∗ 𝟏𝟎 + ∗ 𝟐𝟎 = 𝟐𝟔. 𝟔𝟕 $/𝑴𝑾𝒉
𝟑 𝟑
5
Problem 3:
G1
1 3
z
z
z 5
z
z
4 2
G2
At bus-3:
1 2
∗ ∆𝑃𝐺1 − ∗ ∆𝑃𝐺2 = 0 … (2)
5 5
2 1
∆𝑃𝐺1 = 3 𝑀𝑊 and ∆𝑃𝐺2 = 3 𝑀𝑊. So,
𝟐 𝟏
𝑳𝑴𝑷𝟑 = ∗ 𝟏𝟎 + ∗ 𝟐𝟎 = 𝟏𝟑. 𝟑𝟑 $/𝑴𝑾𝒉
𝟑 𝟑
Similarly, at bus-4:
−1 4
∆𝑃𝐺1 = 3
𝑀𝑊 and ∆𝑃𝐺2 = 3 𝑀𝑊. So,
−𝟏 𝟒
𝑳𝑴𝑷𝟒 = ∗ 𝟏𝟎 + ∗ 𝟐𝟎 = 𝟐𝟑. 𝟑𝟑 $/𝑴𝑾𝒉
𝟑 𝟑
6
Also, at bus-5:
1 2
∆𝑃𝐺1 = 𝑀𝑊 and ∆𝑃𝐺2 = 𝑀𝑊. So,
3 3
𝟏 𝟐
𝑳𝑴𝑷𝟓 = ∗ 𝟏𝟎 + ∗ 𝟐𝟎 = 𝟏𝟔. 𝟔𝟕 $/𝑴𝑾𝒉
𝟑 𝟑
7
Problem 4:
2
𝐶1 (𝑃𝐺1 ) = 0.001𝑃𝐺1 + 2.5𝑃𝐺1 + 450
2
𝐶2 (𝑃𝐺2 ) = 0.0025𝑃𝐺2 + 2𝑃𝐺2 + 250
8
𝜕𝐹
= 0 = −4.25 + 𝜆3 … (6)
𝜕𝑃𝐷3
𝜕𝐹
= 0 = 500𝜆2 − 500𝜆3 … (7)
𝜕𝛿2
𝜕𝐹
= 0 = −1000𝜆1 − 500𝜆2 + 1500𝜆3 … (8)
𝜕𝛿3
𝜕𝐹
= 0 = −1000𝛿3 − 𝑃𝐺1 + 200 … (9)
𝜕𝜆1
𝜕𝐹
= 0 = 500𝛿2 − 500𝛿3 − 𝑃𝐺2 + 1500 … (10)
𝜕𝜆2
𝜕𝐹
= 0 = −500𝛿2 + 1500𝛿3 + 𝑃𝐷3 … (11)
𝜕𝜆3
From equation (6), we get: 𝜆3 = 4.25 $/𝑀𝑊ℎ
So,
−1000𝛿3 − 500 ≤ 0
Hence, a new lagrangian is formed as follows:
9
The KKT conditions for optimality are obtained as follows:
𝜕𝐹
= 0 = 0.002𝑃𝐺1 + 2.5 − 𝜆1 … (12)
𝜕𝑃𝐺1
𝜕𝐹
= 0 = 0.005𝑃𝐺2 + 2 − 𝜆2 … (13)
𝜕𝑃𝐺2
𝜕𝐹
= 0 = −4.25 + 𝜆3 … (14)
𝜕𝑃𝐷3
𝜕𝐹
= 0 = 500𝜆2 − 500𝜆3 … (15)
𝜕𝛿2
𝜕𝐹
= 0 = −1000𝜆1 − 500𝜆2 + 1500𝜆3 − 1000µ13 … (16)
𝜕𝛿3
𝜕𝐹
= 0 = −1000𝛿3 − 𝑃𝐺1 + 200 … (17)
𝜕𝜆1
𝜕𝐹
= 0 = 500𝛿2 − 500𝛿3 − 𝑃𝐺2 + 1500 … (18)
𝜕𝜆2
𝜕𝐹
= 0 = −500𝛿2 + 1500𝛿3 + 𝑃𝐷3 … (19)
𝜕𝜆3
𝜕𝐹
= 0 = −1000𝛿3 − 500 … (20)
𝜕µ13
From equation (14), we get: 𝝀𝟑 = 𝟒. 𝟐𝟓 $/𝑴𝑾𝒉
10
Problem 5:
𝜌𝐴𝑠𝑒𝑙𝑙 = 0.5𝑃𝐺𝐴 + 20
𝜌𝐵𝑠𝑒𝑙𝑙 = 0.2𝑃𝐺𝐵 + 10
𝜌𝐶𝑠𝑒𝑙𝑙 = 0.4𝑃𝐺𝐶 + 25
𝑏𝑢𝑦
𝜌𝑋 = 200 − 0.5𝑃𝐷𝑋
𝑏𝑢𝑦
𝜌𝑌 = 167 − 0.135𝑃𝐷𝑌
𝑏𝑢𝑦
𝜌𝑍 = 252 − 0.412𝑃𝐷𝑍
Area-1 Area-2
A B
Y Pmax = 200 X
MW
Pmax = 100
MW
Area-3
C
Z
11
b. From part (a):
𝑃21 = 𝑃𝐺𝐵 − 𝑃𝐷𝑋 = 337.843 𝑀𝑊
𝑃13 = 𝑃𝐺𝐵 − 𝑃𝐷𝑋 + 𝑃𝐺𝐴 − 𝑃𝐷𝑌 = 119.6 𝑀𝑊
It can be seen that both lines are congested. So, the market should be split. First, we split the
market into three areas as follows:
A Pmax = 200
B
Y MW X
TL-2
Pmax = 100
TL-1 MW
Area-3
C
Z
𝜌2 − 10 200 − 𝜌2
= + 200
0.2 0.5
So, 𝝆𝟐 = 𝟗𝟐. 𝟖𝟓𝟕 $/𝑴𝑾𝒉 at which 𝑷𝑮𝑩 = 𝟒𝟏𝟒. 𝟐𝟖𝟔 𝑴𝑾 and 𝑷𝑫𝑿 = 𝟐𝟏𝟒. 𝟐𝟖𝟔 𝑴𝑾
𝜌1 − 20 167 − 𝜌1
+ 200 = + 100
0.5 0.135
So, 𝝆𝟏 = 𝟏𝟐𝟓. 𝟏𝟏𝟖 $/𝑴𝑾𝒉 at which 𝑷𝑮𝑨 = 𝟐𝟏𝟎. 𝟐𝟑𝟔 𝑴𝑾 and 𝑷𝑫𝒀 = 𝟑𝟏𝟎. 𝟐𝟑𝟔 𝑴𝑾
𝜌3 − 25 252 − 𝜌3
+ 100 =
0.4 0.412
So, 𝝆𝟑 = 𝟏𝟏𝟔. 𝟓𝟐𝟕𝟏 $/𝑴𝑾𝒉 at which 𝑷𝑮𝑪 = 𝟐𝟐𝟖. 𝟖𝟏𝟕𝟕 𝑴𝑾 and 𝑷𝑫𝒁 = 𝟑𝟐𝟖. 𝟖𝟏𝟕𝟕 𝑴𝑾
12
From the results obtained above, it can be seen that:
- 𝜌2 < 𝜌1 and line 1-2 was congested in the direction from area-2 to area-1. Hence, this split is
correct.
- 𝜌3 < 𝜌1 and line 1-3 was congested in the direction from area-1 to area-3. Hence, this split is
incorrect.
Hence, the market should be split into two areas as follows:
Area-1 Area-2
A Pmax = 200
B
Y MW X
TL-2
Pmax = 100
TL-1 MW
C
Z
TL-2 is operating at its capacity limit and we will check the power flowing in TL-1 based on the
solution obtained.
𝜌2 − 10 200 − 𝜌2
= + 200
0.2 0.5
So, 𝝆𝟐 = 𝟗𝟐. 𝟖𝟓𝟕 $/𝑴𝑾𝒉 at which 𝑷𝑮𝑩 = 𝟒𝟏𝟒. 𝟐𝟖𝟔 𝑴𝑾 and 𝑷𝑫𝑿 = 𝟐𝟏𝟒. 𝟐𝟖𝟔 𝑴𝑾
𝜌1 − 20 𝜌1 − 25 167 − 𝜌1 252 − 𝜌1
+ + 200 = +
0.5 0.4 0.135 0.412
13
The power flowing in line TL-1 in the figure above is then:
c. For customer-X:
𝐶𝑜𝑛𝑔𝑒𝑠𝑡𝑖𝑜𝑛 𝑐ℎ𝑎𝑟𝑔𝑒𝑋 = 0 as it’s not contributing to the congestion. Hence, it’s not liable to
charges.
𝐹𝑇𝑅 𝑐𝑟𝑒𝑑𝑖𝑡𝑋 = (𝜌1 − 𝜌2 ) ∗ 50 = 1465.4 $/ℎ
For customer-Y:
𝐶𝑜𝑛𝑔𝑒𝑠𝑡𝑖𝑜𝑛 𝑐ℎ𝑎𝑟𝑔𝑒𝑌 = 200 ∗ (𝜌1 − 𝜌2 ) = 5861.6 $/ℎ
𝐹𝑇𝑅 𝑐𝑟𝑒𝑑𝑖𝑡𝑌 = (𝜌1 − 𝜌2 ) ∗ 150 = 4396.2 $/ℎ
14
Problem 6:
a. When transmission line limits are ignored:
Generator G1 was supposed to supply all the loads since it’s the cheaper generator. However,
generator G2 has a minimum power to be generated of 50 MW. So, generator G1 will supply:
𝑃𝐺1 = 150 + 200 + 250 − 50 = 550 𝑀𝑊
Generator G1 sees the load at bus-2 as 150 MW.
And generator G2 will locally supply 50 MW to the load at bus-2: 𝑃𝐺2 = 50 𝑀𝑊
Using superposition and with equal impedances for all transmission lines:
G1 G1
250 MW 150 MW 150 MW
1 2 1 2
z z
83.33 MW z 100 MW z
166.67 MW + 50 MW
z z
3 250 MW 3
G1
550 MW 50 MW 200 MW
1 2
150 MW z
183.33 MW z 33.33 MW
216.67 MW
3 250 MW
When the transmission limits are ignored, any additional load will be met by generator G1. Hence,
the marginal costs at all buses will be:
𝝀𝟏 = 𝝀𝟐 = 𝝀𝟑 = 𝟐𝟎 $/𝑴𝑾𝐡
b. If the transmission lines limit of 200 MW is considered, it can be seen from the results in point (a)
that line 1-3 is congested. So, generator G2 will have to supply some power so as to restrict the
power flow in line 1-3 to 200 MW. Due to the equal transmission line impedances, the power flow
for this additional power (x) from G2 will be:
15
G2
x
1 G1 2
z
2x/3
z
x/3
𝑥
≥ 216.67 − 200
3
𝑥 = 50 𝑀𝑊
3 250 MW
𝝀𝟏 = 𝟐𝟎 $/𝑴𝑾𝐡
𝝀𝟐 = 𝟐𝟓 $/𝑴𝑾𝐡
To get 𝜆3 , we assume a 1 MW increase in the load at bus-3 and see the impact on the generation
levels at G1 and G2 (∆𝑃𝐺1 and ∆𝑃𝐺2 ) as follows:
- To meet this 1 MW increase in load, the increase in generation levels will be:
16
∆𝑃𝐺1 + ∆𝑃𝐺2 = 1 … (1)
- Also, to keep the power flow in line 1-3 at its capacity limit of 200 MW, the additional power
flows in line 1-3 (from 1 to 3) from both generators due to this change in generation should
cancel each other (considering equal transmission line impedances):
2 1
∗ ∆𝑃𝐺1 + ∗ ∆𝑃𝐺2 = 0 … (2)
3 3
𝝀𝟑 = −𝟏 ∗ 𝟐𝟎 + 𝟐 ∗ 𝟐𝟓 = 𝟑𝟎 $/𝑴𝑾𝒉
17
Problem 7:
𝜌𝐴𝑠𝑒𝑙𝑙 = 0.5𝑃𝐺𝐴 + 25
𝜌𝐵𝑠𝑒𝑙𝑙 = 0.2𝑃𝐺𝐵 + 10
𝜌𝐶𝑠𝑒𝑙𝑙 = 0.1𝑃𝐺𝐶 + 18
𝑏𝑢𝑦
𝜌𝐷 = 180 − 0.25𝑃𝐷𝐷
𝑏𝑢𝑦
𝜌𝐸 = 210 − 0.4𝑃𝐷𝐸
𝑏𝑢𝑦
𝜌𝐹 = 195 − 0.37𝑃𝐷𝐹
A B Tmax =150 MW C
E F D
b. From part (a): 𝑃𝐸𝑊 = 𝑃𝐺𝐶 − 𝑃𝐷𝐷 = 196.39 𝑀𝑊 hence, the tie line is congested (its capacity is
150 MW).
So, market is split into east and west regions:
18
𝜌E − 18 180 − 𝜌𝐸
= + 150
0.1 0.25
𝜌𝑊 − 25 𝜌𝑊 − 10 210 − 𝜌W 195 − 𝜌W
+ + 150 = +
0.5 0.2 0.4 0.37
So,
Where: 𝐷𝐹𝐸𝐸 = 1 (power delivery at the same bus) and 𝐺𝑆𝐹𝐸𝐸 = 0 (east region bus is the
reference bus). So,
𝑳𝑴𝑷𝑬 = 𝟕𝟓 $/𝑴𝑾𝒉
1
Where: 𝐷𝐹𝑊𝐸 = 1−0.08 = 1.087 (because of the transmission losses) and 𝐺𝑆𝐹𝑊𝐸 = −1 (1 MW
increase in west region generation relieves the tie line congestion by 1 MW). So,
19
d. 𝐶𝑜𝑛𝑔𝑒𝑠𝑡𝑖𝑜𝑛 𝑟𝑒𝑛𝑡𝑎𝑙 = 𝑇 𝑚𝑎𝑥 ∗ (𝐿𝑀𝑃𝑊 − 𝐿𝑀𝑃𝐸 )
e. For customer-D:
𝐶𝑜𝑛𝑔𝑒𝑠𝑡𝑖𝑜𝑛 𝑐ℎ𝑎𝑟𝑔𝑒𝐷 = 0 as it’s not contributing to the congestion. Hence, it’s not liable to
charges.
𝐹𝑇𝑅 𝑐𝑟𝑒𝑑𝑖𝑡𝐷 = (𝜌𝑊 − 𝜌𝐸 ) ∗ 125 = 889.396 $/ℎ
𝑵𝒆𝒕 𝒄𝒐𝒏𝒈𝒆𝒔𝒕𝒊𝒐𝒏 𝒑𝒂𝒚𝒎𝒆𝒏𝒕𝒔𝑫 = 𝑪𝒐𝒏𝒈𝒆𝒔𝒕𝒊𝒐𝒏 𝒄𝒉𝒂𝒓𝒈𝒆𝑫 − 𝑭𝑻𝑹 𝒄𝒓𝒆𝒅𝒊𝒕𝑫 = −𝟖𝟖𝟗. 𝟑𝟗𝟔 $/𝒉
So, customer-D is earning 𝟖𝟖𝟗. 𝟑𝟗𝟔 $/𝒉.
20
Problem 8:
𝜌𝐴𝑠𝑒𝑙𝑙 = 0.5𝑃𝐺𝐴 + 20
𝜌𝐵𝑠𝑒𝑙𝑙 = 0.2𝑃𝐺𝐵 + 10
𝑏𝑢𝑦
𝜌𝑋 = 200 − 0.5𝑃𝐷𝑋
𝑏𝑢𝑦
𝜌𝑌 = 167 − 0.135𝑃𝐷𝑌
A Pmax =200 MW B
Y X
𝜌E − 10 200 − 𝜌𝐸
= + 200
0.2 0.5
So, 𝝆𝑬 = 𝟗𝟐. 𝟖𝟔 $/𝑴𝑾𝒉 at which 𝑷𝑮𝑩 = 𝟒𝟏𝟒. 𝟐𝟖𝟔 𝑴𝑾 and 𝑷𝑫𝑿 = 𝟐𝟏𝟒. 𝟐𝟖𝟔 𝑴𝑾
𝜌𝑊 − 20 167 − 𝜌W
+ 200 =
0.5 0.135
So, 𝝆𝑾 = 𝟏𝟏𝟒. 𝟒𝟖𝟖 $/𝑴𝑾𝒉 at which 𝑷𝑮𝑨 = 𝟏𝟖𝟖. 𝟗𝟕𝟔 𝑴𝑾 and 𝑷𝑫𝒀 = 𝟑𝟖𝟖. 𝟗𝟕𝟔 𝑴𝑾
21
For customer-X:
𝐶𝑜𝑛𝑔𝑒𝑠𝑡𝑖𝑜𝑛 𝑐ℎ𝑎𝑟𝑔𝑒𝑋 = 0 as it’s not contributing to the congestion. Hence, it’s not liable to
charges.
𝐹𝑇𝑅 𝑐𝑟𝑒𝑑𝑖𝑡𝑋 = (𝜌𝑊 − 𝜌𝐸 ) ∗ 50 = 1081.55 $/ℎ
For customer-Y:
𝑚𝑎𝑥 (𝜌
𝐶𝑜𝑛𝑔𝑒𝑠𝑡𝑖𝑜𝑛 𝑐ℎ𝑎𝑟𝑔𝑒𝑌 = 𝑇𝐸𝑊 ∗ 𝑊 − 𝜌𝐸 ) = 200(114.488 − 92.86) = 4326.21 $/ℎ
𝐹𝑇𝑅 𝑐𝑟𝑒𝑑𝑖𝑡𝑌 = (𝜌𝑊 − 𝜌𝐸 ) ∗ 150 = 3244.657 $/ℎ
22
Problem 9:
𝜌𝐴𝑠𝑒𝑙𝑙 = 0.6𝑃𝐺𝐴 + 100 … (1)
To maximize the profits of both A and B in this Cournot model of non-cooperative game and get the Nash
equilibrium solution, the profits are expressed as follows:
𝛺𝐴 = 𝜌 ∗ 𝑃𝐺𝐴 − 𝐶𝐴
𝛺𝐵 = 𝜌 ∗ 𝑃𝐺𝐵 − 𝐶𝐵
Where: 𝜌 ∗ 𝑃𝐺𝐴 is the revenue of Genco-A due to energy sales of 𝑃𝐺𝐴 at the market price 𝜌, and 𝐶𝐴 is the
cost incurred by Genco-A to generate this amount of power 𝑃𝐺𝐴 . The same applies for Genco-B.
−𝑃𝐺𝐴 + 535 − 𝑃𝐺𝐴 − 𝑃𝐺𝐵 − 0.6 = 0 − 𝑃𝐺𝐵 + 535 − 𝑃𝐺𝐴 − 𝑃𝐺𝐵 − 0.32 = 0
2𝑃𝐺𝐴 + 𝑃𝐺𝐵 = 534.4 𝑃𝐺𝐴 + 2𝑃𝐺𝐵 = 534.68
23
We can solve these two equations simultaneously to get:
𝑷𝑮𝑨 = 𝟏𝟕𝟖. 𝟎𝟒 𝑴𝑾
And,
𝑷𝑮𝑩 = 𝟏𝟕𝟖. 𝟑𝟐 𝑴𝑾
At which,
𝑷𝑫 = 𝟑𝟓𝟔. 𝟑𝟔 𝑴𝑾
And,
𝝆 = 𝟏𝟕𝟖. 𝟔𝟒 $/𝑴𝑾𝒉
24