0% found this document useful (0 votes)
122 views

Loading On Tank

This document provides guidance on designing reinforced concrete circular water tanks. It discusses analyzing simply supported circular roof slabs through calculating radial and tangential moments based on equations provided. It also covers arranging steel reinforcement in the slab, with radial steel resisting radial moments and tangential steel resisting tangential moments. An example is presented on designing the roof slab of a tank with a diameter of 7.5 meters.

Uploaded by

HariHaran
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
122 views

Loading On Tank

This document provides guidance on designing reinforced concrete circular water tanks. It discusses analyzing simply supported circular roof slabs through calculating radial and tangential moments based on equations provided. It also covers arranging steel reinforcement in the slab, with radial steel resisting radial moments and tangential steel resisting tangential moments. An example is presented on designing the roof slab of a tank with a diameter of 7.5 meters.

Uploaded by

HariHaran
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 24

Nov-15

A Guide to Designing Reinforced Concrete


Water Tanks

Dr. Alaa Helba

Lecture 5

 Analysis of Circular R.C. slabs (Roofs – Floors)


 Design of simply supported circular roof slabs
 Arrangement of st. rft. in circular s.s. slab
 Illustrative Example

Dr. A.Helba CIV 416 E 1


Nov-15

s.s. slab R R

Fixed slab

Dr. A.Helba CIV 416 E 2


Nov-15

Moments and St. Rft. in Circular R.C Plates


Moments: r
Asr
M max
Y
Mr radial moment t
R x
Mt tangential
Steel required: Asmax
Ast
As max , Asr radial steel
and Ast tangential R = radius

Analysis of circular
Simply Supported Slab
• in a circular plate Radial Moments
(Mr) and Tangential Moments (Mt)
could be calculated from the following
equations:
Mredge=0 B.Mr .D
wR 2
at center: Mr max = M+vemax 16 (3   )

Dr. A.Helba CIV 416 E 3


Nov-15

Analysis of circular
Simply Supported Slab

• Tangential Moments (Mt)


B.Mt.D
At edge: 2
wR
Mt edge  (2  2 )
16 wR 2
at center: Mt max = M+vemax 16 (3   )

Moments at any point in S. S. circular Slab


wR 2
Mr  [(3   )(1   2 )]
16
wR 2
Mt  [(3   )  (1  3 )  2 ]
16
 = Poisson's ratio
r
and  = ( = 0 at center ,  = 1 at edge)
R

Dr. A.Helba CIV 416 E 4


Nov-15

• For concrete assume n = 0.2 then :

wR 2
Mr  (1   2 )
5
and
wR 2 2
Mt  (1  )
5 2

Table XII
coeffs. for Moment in Circular Slab / No Center
Support / Uniform Load / Fixed Edge

Fixed Fixed
+ vetension downside
- ve tension upperside
R
R
R
R
R

R
R
R
R
R
R
0.4
0.0
0.1
0.2
0.3

0.5
0.6
0.7
0.8
0.9
1.0

Dr. A.Helba CIV 416 E 5


Nov-15

Asr radial steel to resist Mr


Ast tangential steel to resist Mt
R Mr Mr
Ast r
Asr

Asr Ast
PLAN SEC. ELEV.

Dr. A.Helba CIV 416 E 6


Nov-15

Calculation and arrangement


of Asr in circular S.S. slab
The radial steel is distributed on the
perimeter which varies along the
slab radius , the radial steel should
be calculated by its total amount.
Calculate the radius (r) at which Asr (total) is
maximum dM r total
by putting 0
dr

(r) for Maximum Asr (total)


2 
   
2
wR 2 2 wR r
M r total  (1   )(2 r ) 
2
 r  r   
5 5  R  
2w 2

5
( R r r3 
2w
dM r total
dr

5
( 
R 2  3r 2  0

R 1
r    0.577
3 3

Dr. A.Helba CIV 416 E 7


Nov-15

Maximum Mr total
For simply supported circular slab the
total radial steel (the maximum area) is
only calculated at  = 1/√3 = 0.58
r 1
at   
R 3
wR 2 wR 2 2
M r total  (1   )(2 r ) 
2
( )(2 r )
5 5 3
4 rwR 2 4wR 3 wD 3
  
15 15 3 16.5

Example: Design of Roof Slab


Data: Dtank(inner)=7.5 m , H=5 m, fcu=25 N/mm2 ,mild steel
Loads on roof slab:
Assume troof = D / 50 = 7500 / 50 = 150 mm
own wt. of slab = 0.15 X 25 = 3.75 kN/m2
covering = 1 kN/m2 (may be ass. 0.75 to 1 kN/m2)
L.L = 1 kN/m2 (inaccessible roof)
w roof = 5.75 kN/m2
wu = 1.5 w = 1.5 X 5.75 = 8.625 kN/m2
assume twall (for practical purposes) = H/20 = 5/20 = 0.25 m
radius of roof slab Rroof = 7.5/2 + 0.25 = 4 m

Dr. A.Helba CIV 416 E 8


Nov-15

Moments in Cicular Roof Slab


• Maximum Moments:
at middle of slab
• Radial Moment Mr :
Mr max +ve = wuR2/5 = 8.63 X 42 / 5 = 27.6 kN.m
• Tangential Moment Mt :
Mt max +ve = Mr max +ve = 27.6 kN.m
Mu 27.6 106
d min    88 mm
f cu 25
Rmax b (0.214) (1000)
c 1 .5

Steel Rft. in circular roof slab

Asr

As max
Asr radial steel As max
Ast
Ast tangential st.
Asmax square mesh at center in 0.25Dx0.25D

Dr. A.Helba CIV 416 E 9


Nov-15

Calculation of st. rft. in circular roof slab


1- calculate As mesh at center
As max(at middle)=Mumax/ [bcrd(1-a/2)fy/s]
= 27.6 X 106 / [ 0.9 X 110 X (1 - 0.23/2)(240/1.15)]
= 1511.4 mm2
chosen 8 f 16 / m' as a square mesh
in middle area of 2m X 2m
(area of 0.5 R X 0.5 R)
mesh 16 f 16 in 2m

(Check As min= 0.25 % Ac = 2.5 t = 2.5 x 150 = 375 mm2)

2- calculate and arrange the radial steel Asr


- Calculate Maximum Total Radial Steel Asr tot max
wD 3
M r total MAX .
16.5
Mur total max. = 8.625 X 83 / 16.5 = 267.7 kN.m
M ru  R 
A sr total  , N .B .:to get a use b  2  
 f y  a   3
bcr   1   d
 s  2
267.7 106
 12607 mm 2
 240  0.142 
bcr  1  110
 1.15  2 

Trial 1 : chosen 112 f 12 (with bcr =1)

Dr. A.Helba CIV 416 E 10


Nov-15

Arrangement of Radial Steel Asr


At circle ❷ 112 f 12 (Asr tot at r2 =
0.58 x 4 = 2.32 m) are distributed ❸
along a perimeter = 2 r2 = 14.6m
at spacing s2 = 14600/112 = 130
mm < 200 mm ❷

At the support (outer edge of roof ❶


slab) R = 4m, and perimeter = 2 R
= 25.13 m. ❹
Spacing of 112 bars at the edge circle
❸s3 = 25130/112 = 224.4 mm >
200 mm, in this case the solution is
to increase the required number of
bars so as to keep sedge to 200 mm,
so,
nreq = 25130/200 = 125.7
use 126 bars spaced with:
sat (r=0. 58R) =2 (0.58R)/126=
14577/126 = 115.7 mm. Trial 2: chosen 126 f 12

Arrangement of Radial Steel Asr


In order to cut off half the number of radial bars (63 out of 126) try the
following:
1- calculate the perimeter required to limit spacing of bars to 80 mm, = 126
x 80/1000 = 10.08 m at r = 10.08/2 = 1.6 m (at circle ❹ you can use
126/2 = 63 bars at  = 0.4)
Then As 4 total available = 63 x 113 = 7119 mm2
Check with Asr required at circle ❹ as follows:
- Calculate Mr4 at r4 = 1.6 m,  = 0.4
Mr4 = wR2(1-2)/5 = 8.63(4)2[1-(.4)2]/5
= 23.2 kN.m
Mr4 total = (2 r4) x 23.2 = 233.2 kN.m

M ru 4 233.2 106
Then As 4 total required    10807 mm 2
 f y  a   240  0.12 
bcr  1   d bcr  1  110
 s  2   1.15  2 
This trial cannot be done as As 4 total required >> As 4 total available .. Cancel it ..

Dr. A.Helba CIV 416 E 11


Nov-15

Arrangement of Radial Steel Asr


2- calculate and check Asr required at mesh outer perimeter
(at circle ❶ , r1 = R/4 = 1 m,  = 0.25 and perimeter = 6.28
m):
- calculate Mr1 at r1 = 1.0 m ,  = 0.25:
Mr1 = wR2(1-2)/5 = 8.63(4)2[1-(.25)2]/5
= 25.9 kN.m
Mr1 total = (2 r1) x 25.9
= 162.7 kN.m
M 162.7 106
Then As 1 total required   f  ru 1 a    240  0.12   7540 mm 2
bcr  y
  1
 d bcr   1  110
 s  2   1.15  2 
Then Asr1 total required (7540 mm2) > As cut off avilable (7119 mm2)
It needs 67 f 12 at s1 = 6280/67= 94 mm > 80 mm o.K
That means using 67 x 2 = 134 bars
Ld = 40 f = 40 x 12 = 480 mm
use extension 0.5 m for overlap.
Finally: chosen 134 f 12

Arrangement of Radial Steel Asr


Finally: ❸
Then Asr total required =
134 f 12 to be arranged as follows:
67 f 12 with length L1 and another 67 f 12 ❷
with length L2 :

L1 = R – r1 – cover + val part + 2 hook ❶


= 4 – 1 - .030 + (0.15 -2 x .03) + 2 X 6f
= 3.204 m
L1 = 3.25 m

L2 = R – r1 – cover + ld + 2 hook
= 4 – 1 - .030 + 0.5 + 2 x 6 x 0.012
= 3.614 m
L2 = 3.75 m

Dr. A.Helba CIV 416 E 12


Nov-15

3- calculate and arrange the tangential steel Ast


- Calculate Maximum tangential Steel Ast max/m’
(at r = R/4 , r = 0.25)
Mtu1 = wuR2(1-12/2)/5
=8.625 X 42 (1 – 0.252/2)/ 5 = 26.74 kN.m
M tu 1 27.7 106
A st 1  
 f y  a   240   0.12 
bcr   1   d bcr   1  110
 s  2  1.15   2 
= 1377 mm2 (bcr = 0.9)
chosen 7 f 16 / m’
And use 6 f 16 / m’ at Mt = 1206 x 0.9 x (240/1.15) x 0.95 x110
= 23.67 kN.m (corresponding to 2 = 2(1-5M/wR2) = 0.29 ,  = 0.535)
at r5 = .535 x 4 = 2.14 m and so on .) starting from r = 2.2 m .

0.25 m

150
mm
3.75 m

3.75 m

PLAN
0.25 m Roof Slab rft.

Dr. A.Helba CIV 416 E 13


Nov-15

C.L.

0.15 m

square mesh 16 f 16 in 2m

5.0 m
SEC. ELEV.
Roof Slab rft.

Alternative choice and


Arrangement of Radial Steel Asr
(Note: if f 16 mm is chosen bcr = 0.9 and As = 13954 mm2 )

Trial 1 : chosen 70 f 16 (with bcr = 0.9)


At circle ❷ 70 f 16 (Asr tot at r2 = 0.58 x 4 = 2.32 m) are distributed along a
perimeter = 2 r2 = 14.6m at spacing s2 = 14600/70 = 209 mm > 200 mm
then the number of f 16 mm bars should be increased from 70 to
14600/200 = 73 bars to keep spacing of bars =< 200 mm)

Check At the support (outer edge of roof slab) R = 4m, and perimeter =
2R = 25.13 m.
Spacing of 73 bars at the edge sedge = 25130/73 = 344 mm >> 200 mm, in
this case the solution is to use 73 f 12 amid the other number of bars
so as to get sedge = 25130/146 = 172 mm < 200 mm, so, these
additional 73 f 12 are ended at s = 200mm at r = r2 = 2.32 m
L = R – r2 = 4 – 2.32 = 1.68 m use L = 1.75

Trial 2 : chosen 73 f 16 & add 73 f 12

Dr. A.Helba CIV 416 E 14


Nov-15

Alternative choice and


Arrangement of Radial Steel Asr
Finally:
Then Asr total required = ❸
73 f 16 with length L1 and 73 f 12 with length L2 :

L1 = R – r1 – cover + ld + 2 hook ❷
= 4 – 1 - .030 + 0.5 + 2 X 6f
= 3.614 m
L1 = 3.75 m ❶

L2 = R – r2 – cover + val part + 2 hook


= 4 – 2.32 - .030 + (0.15 -2 x .03) + 2 x 6 x 0.012
= 1.884 m
L2 = 2 m

r2 = 2.3 m

0.25 m

150
mm
3.75 m

3.75 m
PLAN
0.25 m
Roof Slab rft.
Alternative choice and Arrangement of Radial Steel Asr

Dr. A.Helba CIV 416 E 15


Nov-15

n = number of Columns
Case 1 = 4 or 6 or 8

t D 0.71 D

Plan (Sec. under floor level)


An elevated Tank (Floor rests directly on 4 Columns)

Case 1
H D
Hw
(+…. m)

SEC. PLAN
V (Tank Capacity) SEC. ELEV.
= (πD2/4)x Hw

Dr. A.Helba CIV 416 E 16


Nov-15

t D
Sec. Elev.

H
Water Pressure

Dead Load (D.L.)

Loads on
Wall and Floor of an elevated Tank
(Floor rests directly on columns)

1- An elevated Tank rests directly on Columns


Floor structural system

MFinal at connection >> MF wall


Calculate MFinal at connection by
Moment Distribution

MFinal

Final B.M.D. on Walls and Floor

Dr. A.Helba CIV 416 E 17


Nov-15

Case 1 Options of wall thickness t


t1 t1 = twall at top

t2 = twall at base t
tfloor t2 tfloor
2Haunches
in wall & Haunch t1/t2 Tapered t1/t2 Uniform t
floor
Sec. ELEV.
An elevated Tank (Floor rests directly on Columns)

Case 2
Main Beam
0.15 D

D t Paneled Beams 0.71 D

Main Beam
Wall act as a Deep Beam
between columns
Plan (Sec. under floor level)
An elevated Tank (Floor rests on Beams on Columns)

Dr. A.Helba CIV 416 E 18


Nov-15

2-An elevated Tank rests on Beams on Columns

Wall acts as Deep Beam


Final B.M.D. on Walls and Floor
Floor is divided to slabs with Mx & My
Floor structural system

C.L M2
M1
M1 & M 2
From MFwall
3-mom. Eq.

MFinal at connection = MF wall

Db diameter of C.L.
Case 3 of Circular beam

t Db D 0.71 Db

b=bbeam
Plan (Sec. under floor level)
An elevated Tank rests on Circular Beam on Columns

Dr. A.Helba CIV 416 E 19


Nov-15

Case 4 Dsh diameter of C.L.


of Circular shaft

t Dsh D

tsh=thickness
of shaft wall
Plan (Sec. under floor level)
An elevated Tank rests on Circular Shaft

3- Elevated Tank rests on Circular Beam on Columns


4- Elevated Tank rests on Circular Shaft
Floor is circular slab with Mr & Mt
(Use superposition)
Floor structural system

Mr1 = C.L
MF wall + Final B.M.D. Mr1
on Wall and
M due to P wall Floor
+ M due to MFwall
floor cant. part

Mr2 = Mt2
MFinal at connection = MF wall

Dr. A.Helba CIV 416 E 20


Nov-15

Study of Case 1
An elevated Tank
Floor rests directly on Columns
Final B.M.D. on Wall and Floor

Tension and Shear


in Wall and Floor

Dr. A.Helba CIV 416 E 21


Nov-15

Tension and Shear


in Wall and Floor

Final Results of
B.M & N.F

1
Tring acts horizontally
in Wall
2

3 4 Mt
Mr

Dr. A.Helba CIV 416 E 22


Nov-15

Distribution of Mr & Mt in Floor slab


(Values from table XII)
-0.15

-0.1

-0.05
Mr
0 0.2 0.4 0.6 0.8 1 Mt
0

0.05

0.1

Ring Tension in wall


for Different Base Conditions

Dr. A.Helba CIV 416 E 23


Nov-15

Case 1 An elevated Tank


(Floor rests directly on Columns)

Open Tank B.M.D


1 1
3
2 2
4 3 4
Sections 1 & 4 Tension due to B.M is on
Air-Side (design as Cracked sec.)
Sections 2 & 3 Tension due to B.M is on
Water-Side (design as uncracked sec.)

General Procedure for Design( 7 steps)


• Assign the overall Dimensions for tank (D & H)
• Consider the Connection (distribute DM– get Mf)
• Define sections for design & design values (M,Q,N)
• Calculate t for different sections
& Choose proper thicknesses.
• Calculate As required for different sections.
• Arrange steel at sections and connections.
• Draw steel arrangements in plan and elevation

Dr. A.Helba CIV 416 E 24

You might also like