Cve431 Course Work.
Cve431 Course Work.
FACULTY OF ENGINEERING
DEPARTMENT OF CIVIL ENGINEERING
BY
1
Proposed Road Development
2
a. List of Plants items required for the road construction
Road Rollers
Excavators
Bulldozers
Concrete mixer
Asphalt Pavers
Hauler
Grader
1. Site Clearance:
Area of surface to be cleared = sum of all the flat surfaces (width) x length of
the road
Slope = 2.5%
3
X = 0.9997 x 9
X = 8.9971 = 9.0m
Total Area = L x w
Quantity = 36000m3.
4
4. Sub base Material to required thickness:
Thickness= 0.06m
For Walkway:
For Median:
5
Width = 3m
Length = 5000m
7. Prime Coast binder material and wearing course for vehicular running
sections:
Length = 5000m
Depth = 0.04m
6
Quantity = Sectional Area x Length
= 19 excavators needed.
= N 950000.
9
ASSUMED RATES OF ITEMS
ITEM RATE
DESCRIPTION
NO (N/Unit)
1 SITE CLEARING
230.50
2 EXCARVATION OF UNSUITABLE SOIL
500.50
3 CUT AND FILL MATERIALS FROM SUITABLE BORROW PIT
620.20
4 FILLING SUB BASE MATERIAL TO REQUIRED THICKNESS
900.50
5 FILLING OF STONE BASE MATERIALS TO REQUIRED THICKNESS
850.30
6 FILL LATERITE IN WALKWAY AND MEDIAN
300.20
PRIME COAST BINDER MATERIAL AND WEARING COURSE FOR VEHICULAR
7
RUNNING SECTIONS 500.00
8 EXCARVATION FOR THE DRAINAGE
1,000.00
9 CONCRETING FOR THE DRAINAGE
350.00
10 KERBS FOR THE ROAD WORK
200.00
10
TOTAL COST (N) = RATE x QUANTITY
TOTAL
92,516,725.00
11
ID Task Name Duration Start MarFinish
31, '19 Apr 21, '19 May 12, '19 Jun 2, '19 Jun 23, '19 Jul 14, '19 Aug 4, '19 Aug 25, '19
M T W T F S S M T W T F S S M T W T F S
0 Proposed Road Development 87 days Fri 5/3/19 Wed 9/4/19
1 Site Preparation Phase 10 days Fri 5/3/19 Thu 5/16/19
2 Site Clearing 10 days Fri 5/3/19 Thu 5/16/19
3 Earth Work 8 days Fri 5/17/19 Thu 5/30/19
4 Excarvation of Unsuitable Soil 6 days Fri 5/17/19 Sun 5/19/19
5 Cut and Fill 7 days Mon 5/20/19 Thu 5/30/19
6 Pavement and Surfacing 22 days Fri 5/31/19 Mon 7/1/19
7 Placing Sub base Materials 9 days Fri 5/31/19 Mon 6/3/19
8 Stone base materials to required thickness 6 days Fri 5/31/19 Fri 6/7/19
9 Laterite in walkway and median 8 days Mon 6/10/19 Wed 6/19/19
10 Prime Coast binder Application 8 days Thu 6/20/19 Mon 7/1/19
11 Culvert and Drainage 35 days Mon 7/8/19 Fri 8/23/19
12 Excarvation of Drainage 15 days Mon 7/8/19 Fri 7/26/19
13 Concreting of Drainage 20 days Mon 7/29/19 Fri 8/23/19
14 Concrete Kerbs for Roadwork 6 days Wed 8/28/19 Wed 9/4/19
15 Kerbs for Road Work 6 days Wed 8/28/19 Wed 9/4/19
Project: Proposed Road Develo Split Inactive Task Duration-only Finish-only Progress
Date: Sun 5/12/19 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress
Page 1