0% found this document useful (0 votes)
46 views

Slab Formwork and Concrete Costing Tables

The document contains cost estimates for concrete, formwork, and reinforcement for the ground floor slab of a building project. It estimates 111.19 cubic meters of concrete at a raw material cost of RM16,679.85 and placement cost of RM27,799.75. The formwork area is estimated to be 370.65 square meters at a raw material cost of RM7,413 and placement cost of RM11,119.50. Reinforcement estimates include 3,040.29 kg of bottom bar T10 rebar at RM6,080.57 for raw material and RM7,600.71 for placement.

Uploaded by

Ashraf Azhan
Copyright
© © All Rights Reserved
Available Formats
Download as RTF, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
46 views

Slab Formwork and Concrete Costing Tables

The document contains cost estimates for concrete, formwork, and reinforcement for the ground floor slab of a building project. It estimates 111.19 cubic meters of concrete at a raw material cost of RM16,679.85 and placement cost of RM27,799.75. The formwork area is estimated to be 370.65 square meters at a raw material cost of RM7,413 and placement cost of RM11,119.50. Reinforcement estimates include 3,040.29 kg of bottom bar T10 rebar at RM6,080.57 for raw material and RM7,600.71 for placement.

Uploaded by

Ashraf Azhan
Copyright
© © All Rights Reserved
Available Formats
Download as RTF, PDF, TXT or read online on Scribd
You are on page 1/ 2

_____________________________________________________________________

Company Name :
Job Description :
Designed by :
Date & Time : Tuesday, April 30, 2019 12:09:27 PM
(License Number: NetMaster-SN23-C0-1)
_____________________________________________________________________

Slab Formwork and Concrete Costing Tables

Concrete Volume and Cost


Floor Grade Volume (m³) Raw (RM) Placement (RM)
rb 30 0.000 0.00 0.00
gb 30 111.199 16,679.85 27,799.75
Total 111.199 16,679.85 27,799.75

Lean Concrete Volume and Cost


Floor Lean Concrete (m³) Raw (RM) Placement (RM)
rb 0.000 0.00 0.00
gb 0.000 0.00 0.00
Total 0.000 0.00 0.00

Formwork Area and Cost


Floor Formwork Area (m²) Raw (RM) Placement (RM)
rb 0.000 0.00 0.00
gb 370.650 7,413.00 11,119.50
Total 370.650 7,413.00 11,119.50

Slab Reinforcement Costing Tables

Bottom Bar and Cost


Floor Diameter Weight (kg) Raw (RM) Placement (RM)
gb T10 3,040.285 6,080.57 7,600.71
Total 3,040.285 6,080.57 7,600.71

Top Bar (Middle + Distribution) and Cost


Floor Diameter Weight (kg) Raw (RM) Placement (RM)
gb T10 919.981 1,839.96 2,299.95
Total 919.981 1,839.96 2,299.95
License Number: NetMaster-SN23-C0-1
1/2
Top Bar (Support) and Cost
Floor Diameter Weight (kg) Raw (RM) Placement (RM)
gb T10 1,478.643 2,957.29 3,696.61
Total 1,478.643 2,957.29 3,696.61