Rate Analysis
Rate Analysis
LEAD IN KM
Initial rate of
COST OF material
Description Source of Conveyan Total
Sl No initial CONVEYA excluding per
of Item supply ST lead Total ce Cost /Rate
lead NCE seignorage
Conveyan excluding
charges
ce c.p
1 2 5 4 5 6 7 8 9 10 11 12=10+11 13
Coarse
1 aggregate Jaduru 15.00 1.00 14.00 194.30 194.30 170.44 875.00 1045.44 Cum
10-4.75mm
Coarse
2 aggregate Jaduru 15.00 1.00 14.00 194.30 194.30 170.44 1210.00 1380.44 Cum
20-10mm
Coarse
3 aggregate Jaduru 15.00 1.00 14.00 194.30 194.30 170.44 1145.00 1315.44 Cum
40-20mm
Fine
aggregate /
4 Sand Vamsadhara 13.00 1.00 12.00 169.50 169.50 148.68 148.68 Cum
( un
screened)
Fine
aggregate /
5 Vamsadhara 13.00 1.00 12.00 169.50 169.50 148.68 148.68 Cum
Sand
( screened)
7 Cement The rate mentioned for site of work per kg 6.40 6400.00 6400.00 MT
8 Steel The rate mentioned for site of work 42.00 42000.00 42000.00 MT
Sand for
5 Vamsadhara 13.00 1.00 12.00 172.30 172.30 151.14 151.14 Cum
Filling
8 Murrum Local 3.00 1.00 2.00 84.1 84.1 73.77 107.00 180.77 Cum
9 Gravel Local 3.00 1.00 2.00 84.1 84.1 73.77 103.00 176.77 Cum
Certificates
1)Certified that the quarries are verified and leads provided are found correct to the best of my knowledge.
2) Certified that adequate good quantity of materials are available in the quarry.
3)Certified that the cost of cement and steel Fe 415 grade are adopted as per the
Remarks
14
IRR-
CCDW-1- Excavation in all kinds of soil including boulders upto 0.30 m dia. for foundations of canal
1 cross drainage and other appurtenant structures and placing the excavated stuff neatly in
specified dump area or disposing off the same as directed etc., complete with initial lead upto
50 m and initial lift upto 3 m.
B. MACHINERY:
Sl No Description Unit Quantity Rate
in Rs.
1 NIL 0.00 0.00
0.00 0.00
Total hire charges of Machinery Rs:
C. LABOUR:
Sl No Description Unit Quantity Rate
in Rs.
1 work inspector Day 0.25 400.00
2 mazdoor Day 6.00 320.00
Total cost of Labour Rs:
labour component/unit qty 202.00
Add contractor's profit and overhead charges 13.615% 27.50
labour component/unit qty (including contractor's profit) 229.50
ABSTRACT:
A. Cost of Materials Rs:
B. Hire charges of Machinery Rs:
C. Cost of Labour Rs:
Total Rs:
D. Add for contractor's profit and overheads on (A+B+C) 0.000% Rs:
Total cost for 10.00 cum Rs:
Rate per cum (A+B+C+D)/10.0 Rs.
ions of canal
d stuff neatly in
ith initial lead upto
cum
Amount
in Rs.
0.00
0.00
0.00
Amount
in Rs.
0.00
0.00
0.00
Amount
in Rs.
100.00
1920.00
2020.00
0.00
0.00
2020.00
2020.00
0
2020.00
202.00
IRR-CCDW-2-5 Providing and laying insitu vibrated M-10 ( 28 days cube compressive strength not less than
10 N / sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, graded
aggregates for foundation filling including cost of all materials, machinery, labour, formwork,
cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc.,
complete with initial lead upto 50 m and all lifts.
(Cement content: 220 kg / cum with use of super plasticiser(0.4% by wt. of cement),
CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)
B. MACHINERY:
Sl No Description Unit Quantity Rate
in Rs.
1 Concrete mixer 300/200 ltr ( diesel ) Hour 8.00 53.50
Fuel / Energy charges Hour 8.00 78.40
2 5 hp pump ( diesel ) Hour 0.50 10.20
Fuel / Energy charges Hour 0.50 78.40
3 Water tanker 8000 ltr Hour 1.00 402.50
Fuel / Energy charges Hour 1.00 296.30
4 Needle vibrator 40 mm dia ( petrol ) Hour 8.00 7.60
Fuel / Energy charges Hour 8.00 19.00
Total hire charges of Machinery Rs:
C. LABOUR:
Sl No Description Unit Quantity Rate
in Rs.
1 Crew for Concrete mixer Hour 8.00 206.70
2 Crew for Pump Hour 0.50 104.80
3 Crew for Water tanker Hour 1.00 166.70
4 Crew for Vibrator Hour 8.00 148.80
5 Mason Class-I Day 1.00 420.00
6 work inspector Day 1.00 400.00
7 mazdoor
for batching materials Day 11.00 320.00
for loading mortar pans Day 4.00 320.00
for laying Day 3.00 320.00
for conveying concrete Day 16.36 320.00
8 for cleaning/ washing/ curing Day 1.00 320.00
9 Labour cost for shuttering sqm 16.36 81.75
Total cost of Labour Rs:
labour component/unit qty 1010.70
Add contractor's profit and overhead charges 13.615% 137.60
labour component/unit qty (including contractor's profit) 1148.30
ABSTRACT:
A. Cost of Materials Rs:
B. Hire charges of Machinery Rs:
C. Cost of Labour Rs:
Total Rs:
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs:
Total cost for 16.36 cum Rs:
Rate per cum (A+B+C+D)/16.36 Rs.
cum
Amount
in Rs.
23034.88
314.11
9684.26
6097.67
3078.61
972.99
3969.08
396.91
20.50
47569.01
Amount
in Rs.
428.00
627.20
5.10
39.20
402.50
296.30
60.80
152.00
2011.10
Amount
in Rs.
1653.60
52.40
166.70
1190.40
420.00
400.00
3520.00
1280.00
960.00
5235.20
320.00
1337.43
16535.73
47569.01
2011.10
16535.73
66115.84
66115.84
4041.31
IRR-CCDW-2-21 Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less than
15 N / sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, graded
aggregates with placing and sinking plums of size 150 to 80 mm upto 15 percent for gravity
type retaining walls / piers / abutments etc., including cost of all materials, machinery,
labour, formwork, scaffolding, cleaning, batching, mixing, placing in position, levelling, vibrating,
finishing, curing etc.,complete with initial lead upto 50 m and all lifts.
Note: If water is to be brought from other place add only lead charges @ 500 ltr / cum.
(Cement content: 260 kg / cum with use of super plasticiser(0.4% by wt. of cement),
CA : 0.765cum, Blending Ratio of CA--50:30:20, FA : 0.34 cum,
plums of size 150 to 80 mm : 0.25cum )
B. MACHINERY:
Sl No Description Unit Quantity Rate
in Rs.
1 Concrete mixer 300/200 ltr ( diesel ) Hour 8.00 53.50
Fuel / Energy charges Hour 8.00 78.40
2 5 hp pump ( diesel ) Hour 0.50 10.20
Fuel / Energy charges Hour 0.50 78.40
3 Needle vibrator 60 mm dia ( petrol ) Hour 8.00 8.20
Fuel / Energy charges Hour 8.00 28.50
Total hire charges of Machinery Rs:
C. LABOUR:
Sl No Description Unit Quantity Rate
in Rs.
1 Crew for Concrete mixer Hour 8.00 206.70
2 Crew for Pump Hour 0.50 104.80
3 Crew for Needle vibrator Hour 8.00 148.80
4 Mason Class-I Day 1.00 420.00
5 work inspector Day 1.00 400.00
6 mazdoor
for batching materials Day 11.00 320.00
for loading mortar pans Day 4.00 320.00
for laying Day 5.00 320.00
for placing plums Day 2.00 320.00
for conveying concrete Day 15.38 320.00
for conveying plums Day 2.00 320.00
for cleaning/ washing/ curing Day 1.00 320.00
7 Labour for shuttering sqm 49.75 81.75
Labour for scaffolding @ 30%
Total cost of Labour Rs:
labour component/unit qty 1212.00
Add contractor's profit and overhead charges 13.615% 165.00
labour component/unit qty (including contractor's profit) 1377.00
ABSTRACT:
A. Cost of Materials Rs:
B. Hire charges of Machinery Rs:
C. Cost of Labour Rs:
Total Rs:
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs:
Total cost for 18.09 cum Rs:
Rate per cum (A+B+C+D)/18.09 Rs.
cum per day
/ sqm
/ sqm
cum
Amount
in Rs.
30101.76
463.10
9102.08
5731.10
2893.53
914.50
12069.19
3620.76
64896.02
Amount
in Rs.
428.00
627.20
5.10
39.20
65.60
228.00
1393.10
Amount
in Rs.
1653.60
52.40
1190.40
420.00
400.00
3520.00
1280.00
1600.00
640.00
4921.60
640.00
320.00
4066.86
1220.06
21924.92
64896.02
1393.10
21924.92
88214.04
88214.04
4876.40
IRR-CCDW-2-10 Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less than
15 N / sq mm ) grade cement concrete using 20 mm down size approved, clean, hard, graded
aggregates for sub-structure / super- structure works including cost of all materials,
machinery, labour, formwork, scaffolding, cleaning, batching, mixing, placing in position,
levelling, vibrating, finishing, curing etc., complete with initial lead upto 50 m and all lifts.
(Cement content: 280 kg / cum with use of super plasticiser(0.4% by wt. of cement),
CA : 0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum)
B. MACHINERY:
Sl No Description Unit Quantity Rate
in Rs.
1 Concrete mixer 300/200 ltr ( diesel ) Hour 8.00 53.50
Fuel / Energy charges Hour 8.00 78.40
2 5 hp pump ( diesel ) Hour 0.50 10.20
Fuel / Energy charges Hour 0.50 78.40
3 Water tanker 8000 ltr Hour 1.00 402.50
Fuel / Energy charges Hour 1.00 296.30
4 Needle vibrator 40 mm dia ( petrol ) Hour 8.00 7.60
Fuel / Energy charges Hour 8.00 19.00
Total hire charges of Machinery Rs:
C. LABOUR:
Sl No Description Unit Quantity Rate
in Rs.
1 Crew for Concrete mixer Hour 8.00 206.70
2 Crew for Pump Hour 0.50 104.80
3 Crew for Water tanker Hour 1.00 166.70
4 Crew for Vibrator Hour 8.00 148.80
5 Mason Class-I Day 1.00 420.00
6 work inspector Day 1.00 400.00
7 mazdoor
for batching materials Day 11.00 320.00
for loading mortar pans Day 4.00 320.00
for laying Day 4.00 320.00
for conveying concrete Day 15.71 320.00
for cleaning/ washing/ curing Day 1.00 320.00
8 Labour cost for shuttering sqm 31.42 81.75
Labour cost for scaffolding @ 25%
Total cost of Labour Rs:
labour component/unit qty 1178.90
Add contractor's profit and overhead charges 13.615% 160.50
labour component/unit qty (including contractor's profit) 1339.40
ABSTRACT:
A. Cost of Materials Rs:
B. Hire charges of Machinery Rs:
C. Cost of Labour Rs:
Total Rs:
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs:
Total cost for 15.71 cum Rs:
Rate per cum (A+B+C+D)/15.71 Rs.
cum
Amount
in Rs.
28152.32
502.72
11277.08
4598.68
1051.12
7622.77
1905.69
20.50
55130.88
Amount
in Rs.
428.00
627.20
5.10
39.20
402.50
296.30
60.80
152.00
2011.10
Amount
in Rs.
1653.60
52.40
166.70
1190.40
420.00
400.00
3520.00
1280.00
1280.00
5027.20
320.00
2568.59
642.15
18521.03
55130.88
2011.10
18521.03
75663.02
75663.02
4816.23
IRR-
CCDW-2-
26 Providing and laying insitu M- 20 ( 28 days cube compressive strength not less than 20 N /
sqmm ) grade cement concrete using 20 mm down size approved, clean, hard, graded
aggregates for wearing coat including cost of all materials, machinery, labour, formwork,
cleaning, batching, mixing, placing in position in alternate panels, levelling, compacting,
finishing, curing, packing joints with asphalt mortar etc., complete with initial lead upto 50 m
and all lifts.
Note: If water is to be brought from other place add only lead charges @ 500 ltr / cum. to the data
(Cement content: 330 kg / cum with use of super plasticiser(0.4% by wt. of cement),
CA : 0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum)
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Concrete mixer 300/200 ltr ( diesel ) Hour 8.00 53.50 428.00
Fuel / Energy charges Hour 8.00 78.40 627.20
2 5 hp pump ( diesel ) Hour 0.50 10.20 5.10
Fuel / Energy charges Hour 0.50 78.40 39.20
3 Needle vibrator 40 mm dia ( petrol ) Hour 8.00 7.60 60.80
Fuel / Energy charges Hour 8.00 19.00 152.00
Total hire charges of Machinery Rs: 1312.30
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Concrete mixer Hour 8.00 206.70 1653.60
2 Crew for Pump Hour 0.50 104.80 52.40
3 Crew for Needle vibrator Hour 8.00 148.80 1190.40
4 Mason Class-I Day 2.00 420.00 840.00
5 work inspector Day 1.00 400.00 400.00
6 mazdoor
for batching materials Day 11.00 320.00 3520.00
for loading mortar pans Day 4.00 320.00 1280.00
for laying Day 4.00 320.00 1280.00
for conveying concrete Day 15.76 320.00 5043.20
for cleaning/ washing/ curing Day 2.00 320.00 640.00
7 Labour cost for shuttering sqm 7.88 81.75 644.19
Total cost of Labour Rs: 16543.79
labour component/unit qty 1049.70
Add contractor's profit and overhead charges 13.615% 142.90
labour component/unit qty (including contractor's profit) 1192.60
ABSTRACT:
A. Cost of Materials Rs: 52886.95
B. Hire charges of Machinery Rs: 1312.30
C. Cost of Labour Rs: 16543.79
Total Rs: 70743.04
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs:
Total cost for 15.76 cum Rs: 70743.04
Rate per cum (A+B+C+D)/15.76 Rs. 4488.77
Providing 20 mm thick plastering in cement mortar 1:4 proportion by volume including cost
IRR-CCDW-4-10
of all materials, machinery, labour, scaffolding, cleaning joints, smooth finishing, curing etc.,
complete with initial lead upto 50 m and all lifts.
B. MACHINERY:
Sl No Description Unit Quantity Rate
in Rs.
1 Nil 0.00 0.00
( Manual mixing) 0.00 0.00
Total hire charges of Machinery Rs:
C. LABOUR:
Sl No Description Unit Quantity Rate
in Rs.
1 Mason Cl- I Day 15.00 420.00
2 work inspector Day 1.00 400.00
3 mazdoor Day 25.00 320.00
Total cost of Labour Rs:
labour component/unit qty 147.00
Add contractor's profit and overhead charges 13.615% 20.00
labour component/unit qty (including contractor's profit) 167.00
ABSTRACT:
A. Cost of Materials Rs:
B. Hire charges of Machinery Rs:
C. Cost of Labour Rs:
Total Rs:
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs:
Total cost for 100.00 sqm Rs:
Rate per sqm (A+B+C+D)/100.0 Rs.
cum
sqm
Amount
in Rs.
5043.20
327.11
5370.31
134.26
5504.56
Amount
in Rs.
0.00
0.00
0.00
Amount
in Rs.
6300.00
400.00
8000.00
14700.00
5504.56
0.00
14700.00
20204.56
20204.56
202.05
IRR-CCDW-2-1 Providing, fabricating and placing in position reinforcement steel bars for RCC works including
cleaning, straightening, cutting, bending, hooking, lapping, welding wherever required,tying with
1.25 mm dia soft annealed steel wire, including cost of all materials, machinery, labour etc.,
complete with initial lead upto 50 and all lifts.
B. MACHINERY:
Sl No Description Unit Quantity Rate
in Rs.
1 Nil 0.00 0.00
0.00 0.00
Total hire charges of Machinery Rs:
C. LABOUR:
Sl No Description Unit Quantity Rate
in Rs.
1 work inspector Day 1.00 400.00
2 Bar bender Day 6.00 490.00
3 mazdoor Day 11.00 320.00
Total cost of Labour Rs:
labour component/unit qty 6.90
Add contractor's profit and overhead charges 13.615% 0.90
labour component/unit qty (including contractor's profit) 7.80
ABSTRACT:
A. Cost of Materials Rs:
B. Hire charges of Machinery Rs:
C. Cost of Labour Rs:
Total Rs:
D. Add for contractor's profit and overheads on (A+B 13.615% Rs:
Total cost for 1000.00 kg Rs:
Rate pekg (A+B+C+D)/1000.0 Rs.
works including
red,tying with
kg
percent
& 2 mazdoors
& 4 mazdoors
& 4 mazdoors
& 1 mazdoors
kg
Amount
in Rs.
44100.00
560.00
123.00
44783.00
Amount
in Rs.
0.00
0.00
0.00
Amount
in Rs.
400.00
2940.00
3520.00
6860.00
44783.00
0.00
6860.00
51643.00
7031.19
58674.19
58.70
Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than
IRR-CCDW-2-24
20 N / sq mm ) grade cement concrete using 20 mm down size approved, clean, hard, graded
aggregates for deck slab & kerb including cost of all materials,machinery, labour, formwork,
scaffolding, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing
etc., complete with initial lead upto 50 m and all lifts.
Note: If water is to be brought from other place add only lead charges @ 500 ltr / cum.
(Cement content: 330 kg / cum with use of super plasticiser(0.4% by wt. of cement),
CA : 0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum)
B. MACHINERY:
Sl No Description Unit Quantity Rate
in Rs.
1 Concrete mixer 300/200 ltr ( diesel ) Hour 8.00 53.50
Fuel / Energy charges Hour 8.00 78.40
2 5 hp pump ( diesel ) Hour 0.50 10.20
Fuel / Energy charges Hour 0.50 78.40
3 Needle vibrator 40 mm dia ( petrol ) Hour 8.00 7.60
Fuel / Energy charges Hour 8.00 19.00
Total hire charges of Machinery Rs:
C. LABOUR:
Sl No Description Unit Quantity Rate
in Rs.
1 Crew for Concrete mixer Hour 8.00 206.70
2 Crew for Pump Hour 0.50 104.80
3 Crew for Needle vibrator Hour 8.00 148.80
4 Mason Class-I Day 2.00 420.00
5 work inspector Day 1.00 400.00
6 mazdoor
for batching materials Day 11.00 320.00
for loading mortar pans Day 4.00 320.00
for laying Day 4.00 320.00
for conveying concrete Day 15.76 320.00
for cleaning/ washing/ curing Day 1.00 320.00
7 Labour cost for shuttering sqm 39.40 81.75
Labour cost for scaffolding @ 250%
Total cost of Labour Rs:
labour component/unit qty 1703.90
Add contractor's profit and overhead charges 13.615% 232.00
labour component/unit qty (including contractor's profit) 1935.90
ABSTRACT:
A. Cost of Materials Rs:
B. Hire charges of Machinery Rs:
C. Cost of Labour Rs:
Total Rs:
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs:
Total cost for 15.76 cum Rs:
Rate per cum (A+B+C+D)/15.76 Rs.
cum per day
/ sqm
/ sqm
cum
Amount
in Rs.
33285.12
504.32
11312.97
4613.31
1054.47
11620.84
29052.11
41.00
91484.15
Amount
in Rs.
428.00
627.20
5.10
39.20
60.80
152.00
1312.30
Amount
in Rs.
1653.60
52.40
1190.40
840.00
400.00
3520.00
1280.00
1280.00
5043.20
320.00
3220.95
8052.38
26852.93
91484.15
1312.30
26852.93
119649.37
119649.37
7591.97
Excavation and removal of silt and silt mixed with sand from canal bed in dry condition
IRR-PMW-3-20
including disposing off the same in spoil bank or on the canal embankment in layers as
directed etc., complete with initial lead upto 50 m and all lifts.
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 NIL 0.00 0.00 0.00
0.00 0.00 0.00
Total hire charges of Machinery Rs: 0.00
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 mazdoor Day 4.00 320.00 1280.00
Total cost of Labour Rs: 1280.00
labour component/unit qty 128.00
Add contractor's profit and ove 13.615% 17.40
labour component/unit qty (including contractor's profit) 145.40
ABSTRACT:
A. Cost of Materials Rs: 0.00
B. Hire charges of Machinery Rs: 0.00
C. Cost of Labour Rs: 1280.00
Total Rs: 1280.00
in Rs. in Rs.
1 NIL 0.00 0.00 0.00
0.00 0.00 0.00
Total cost of Materials Rs: 0.00
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Shovel 0.85 cum capacity Hour 8.00 1706.60 13652.80
Fuel / Energy charges Hour 8.00 862.10 6896.80
Tippers 5 cum capacity 6
2 Nos Hour 48.00 446.70 21441.60
Fuel / Energy charges Hour 48.00 296.30 14222.40
Total hire charges of
Machinery Rs: 56213.60
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs.
1 Crew for Shovel Hour 8.00 222.30 1778.40
2 Crew for Tipper Hour 48.00 166.70 8001.60
3 work inspector Day 1.00 400.00 400.00
4 mazdoor Day 30.00 320.00 9600.00
Total cost of Labour Rs: 19780.00
labour component/unit qty 21.40
Add contractor's profit and overhead char 13.615% 2.90
labour component/unit qty (including contractor's profit) 24.30
ABSTRACT:
A. Cost of Materials Rs: 0.00
B. Hire charges of Machinery Rs: 56213.60
C. Cost of Labour Rs: 19780.00
Total Rs: 75993.60
D. Add for contractor's profit and overheads on (A+B+C) 13.615% Rs: 10346.53
Total cost for 925.00 cum Rs: 86340.13
Rate per cum (A+B+C+D)/925 Rs. 93.30
IRR-PMW-3-2Providing homogeneous embankment using soil from approved borrow
New Item6 -
2010-11 area in layers of 25 to 30 cm before compaction including cost of all
(For Minor Womaterials, machinery, labour, all operations such as watering, compacting
to density control of not less than 95 percent or as stipulated using
8T roller etc., complete with initial lead upto 1 km and all lifts.
RATE ANALYSIS
A. MATERIALS: UNIT : 807.00 cum
Sl No Particu Unit Quantity Rate Amount
in Rs. in Rs
1 NIL 0.00 0.00 0.00
0.00 0.00 0.00
Total cost of Materials Rs: 0.00
B. MACHINERY:
Sl No Descrip Unit Quantity Rate Amount
in Rs. in Rs
1 Angle Hour 2.70 1715.50 4631.85
Fuel / Hour 2.70 603.10 1628.37
2 Pump 5Hour 4.00 3.00 12.00
Fuel / Hour 4.00 40.70 162.80
3 Water tHour 8.00 402.50 3220.00
Fuel / Hour 8.00 296.30 2370.40
4 VibratoHour 6.40 1342.20 8590.08
Fuel / Hour 6.40 1018.90 6520.96
5 Sundri LS 2.00 41.00 82.00
Total hire charges of Machinery Rs: 27218.46
C. LABOUR:
Sl No Descrip Unit Quantity Rate Amount
in Rs. in Rs
1 Crew f Hour 2.70 222.30 600.21
4 Crew f Hour 4.00 78.60 314.40
5 Crew f Hour 8.00 166.70 1333.60
6 Crew foHour 6.40 248.00 1587.20
7 work inDay 1.00 400.00 400.00
8 mazdoDay 2.00 320.00 640.00
Total cost of Labour Rs: 4875.41
labour component/unit qty 6.00
Add contractor's pro 13.615% 0.80
labour component/unit qty (including contractor's profit) 6.80
ABSTRACT:
A. Cost of Materials Rs: 0.00
B. Hire charges of Machinery Rs: 27218.46
C. Cost of Labour Rs: 4875.41
Total Rs: 32093.87
D.Add for contractor's profit and overheads on (A+B+C) 13.615% Rs. 4369.58
Total cost
for 807.00 cum Rs: 36463.45
Rate per cum (A+B+C+D)/807 Rs: 45.20
IRR-PMW-3Providing homogeneous embankment using soil from approved borrow
New Item5
- 2010-11 area in layers of 25 to 30 cm before compaction including cost of all
(For Minor materials, machinery, labour, all operations such as excavation, sorting out,
transportation, spreading soil in layer of specified thickness, breaking clods,
sectioning,etc.,complete with initial lead upto 1 km and all lifts.
RATE ANALYSIS
A. MATERIALS: Unit: 807.00 cum
Sl No Particulars Unit Quantity Rate Amount
in Rs. in Rs
1 NIL 0.00 0.00 0.00
0.00 0.00 0.00
Total cost of Materials Rs: 0.00
B. MACHINERY:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 Angle dozer 90 hp Hour 2.70 1715.50 4631.85
Fuel / Energy charges Hour 2.70 603.10 1628.37
2 Shovel 0.85 cum capacity Hour 8.00 1706.60 13652.80
Fuel / Energy charges Hour 8.00 862.10 6896.80
3 Tippers 5.00 cum capacity 5 Nos. Hour 40.00 446.70 17868.00
Fuel / Energy charges Hour 40.00 296.30 11852.00
Total hire charges of Machinery Rs: 56529.82
C. LABOUR:
Sl No Description Unit Quantity Rate Amount
in Rs. in Rs
1 Crew for Dozer Hour 2.70 222.30 600.21
2 Crew for Shovel Hour 8.00 222.30 1778.40
3 Crew for Tipper Hour 40.00 166.70 6668.00
4 work inspector Day 1.00 400.00 400.00
5 mazdoor Day 2.00 320.00 640.00
Total cost of Labour Rs: 10086.61
labour component/unit qty 12.50
Add contractor's profit and overhead charges 13.615% 1.70
labour component/unit qty (including contractor's profit) 14.20
ABSTRACT:
A. Cost of Materials Rs: 0.00
B. Hire charges of Machinery Rs: 56529.82
C. Cost of Labour Rs: 10086.61
Total Rs: 66616.43
D.Add for contractor's profit and overheads on (A+B+C) 13.615% Rs. 9069.83
Total cost for 807.00 cum Rs: 75686.26
Rate per cum (A+B+C+D)/807 Rs: 93.80