Final
Final
Group Members:
Table Of Contents
Introduction:……………………………………………………………………….………………3
Procedure………………………………………………………………………….……………....4
Analysis:……………………………………………………………………….………………….5
Data:…………………………………………………………………………….………………....6
Results:…………………………………………………………………………..……………..….7
Discussion:……………………………………………………………………………………..….9
Appendix:…………………………………………………………………………..…………….12
3
Introduction:
The motivation behind the design was increasing max load and load-cost ratio. As such,
almost every proposed design utilized as much of the 320$ budget as possible. This is because
higher budgets tended to allow many different potential designs that fulfilled the constraints
(span, load application distance) whereas lower budget trusses were much more constrained and
difficult to design. In fact, most of the groups from the A3 load ranking utilized around 300$ in
their designs (found by dividing the max load by the load-cost ratio). Of course, this meant that
achieving a high load-cost ratio was more difficult since a considerably higher max load would
be needed.
To design and construct the final truss, the group has to use MATLAB code to test and
analyze the truss designed with matrices which contain the position of each joint and straw, and
the direction of each straw. Thus, the theoretical maximum load magnitude of each straw can be
calculated which is very helpful to predict the maximum load magnitude of the whole truss.
Several designs of truss from members will be analyzed with the MATLAB code. The design
Procedure:
Design Restrictions:
2. The relation between the number of joints (J) and members (M): M = 2J - 3.
3. The total cost ( cost = $10J + $1L) must be less than $320.
6. The distance between adjacent joints must be at least 10 cm and no longer than 15 cm
7. The distance between the load and the pin joint must be 21 cm ± 0.5 cm.
8. Each straw should be surrounded between two gusset plates and double pinned in their
center. (outer pin 5 mm from the straw end and the inner pin another 5 mm from the outer
pin)
Detailed Procedure:
1. Choose one design of truss with the maximum theoretical load capacity.
2. Decide the actual straw length and joint-to-joint length, according to the restrictions.
4. Place straws on the gusset plates. Restructure the shape of gussets plates, according to the
position of straws.
Analysis:
I jj
a) F actual = ( I )α F theoretical
actual
b) F f it (l) = Cl−α
1384
Equation b) is a match to our previous Euler fitted equation of F (l) = l2
. As a result,
the 𝛼 is 2. We can use the 𝛼 to be able to use equation a). However, we must take notice that the
We are still using the same formulas and MATLAB program from the previous report to
Data:
*Tension members do not have buckling force so they are marked as blank
7
Results:
Theoretical Calculations:
Internal
Theoretical Theoretical Buckling Force for
Member Member Tension/ Theoretical Buckling Uncertainty Each Member
Number Length (cm) Compression Strength (N) +/- (N) (N)
1 11 Compression 11.4 0.531 17.0
2 14.9 Tension -6.90
3 10 Compression 13.8 0.707 22.7
4 14.1 Tension -8.00
5 10 Tension -20.6
6 10 Compression 13.8 0.707 10.8
7 10 Tension -35.6
8 11 Compression 11.4 0.531 13.4
9 14.9 Compression 6.24 0.214 10.8
10 11 Tension -8.92
11 10 Zero 0.00
12 11 Compression 11.4 0.531 13.4
13 14.9 Tension -10.8
14 11 Tension -26.7
15 11 Compression 11.4 0.531 26.7
16 10 Compression 13.8 0.707 35.6
17 14.9 Tension -10.8
Figure 3: Table of Theoretical and Actual Truss Design
Joint to Joint
Member # Length
F Adjusted Actual U Adjusted Actual
This also reveals that the critical member is member 9 when corrected using the joint to
joint ratio. Previously the value for member 6 was about .02 less than member 9 theoretically,
but with the correction member, 9 is the clear winner. Therefore we will predict that member 9
will fail, though there is a remote possibility that member 6 will fail as shown by the high
Discussion:
Unfortunately, almost all of the designs that were made after the preliminary report were
inferior in every way to the preliminary designs. Certain factors were adjusted in an attempt to
reduce cost. Some features included fewer joints, shorter straw lengths (or at least as short as
geometry allowed for), and using shorter span (53.5 cm). Different types of geometry were
tested: right, equilateral, isosceles, and scalene. The right triangles (in square shaped pairs)
resulted in the highest max load. This was most likely because the right triangles allowed us to
use smaller lengths and stay within the constraint of having 21cm from joint A to the load joint.
Also, with right triangles, the load is unevenly distributed between the x and y directions, so
having uneven lengths (and thus buckling loads) is the best method of maximizing the possible
load. This would explain why the equilateral and scalene triangle trusses seemed to fail at a
much lower load (as similar lengths would have similar buckling loads and thus one would be
more stressed than the other). Other classifications of trusses were tested such as the warren,
parker, and gambrel trusses (the major differences being the height of the truss and the general
Another approach was to adjust the preliminary design by changing lengths, connections,
and orientation of members. Ultimately, the best design was simply the preliminary design with
one member’s (member 9 in Figure 1) joint connections mirrored. This moved the zero force
member from member 7 to member 11, allowing the load force to be distributed over the truss
properly, and reduce the amount of force on member 8. This is the truss that we have chosen for
our final design, and which theoretically has the best load to cost ratio of all of our designs.
The intended building technique is to cut the straws shorter than the theoretical joint
length. How much shorter was determined by finding the radius of the straw, in this case, r =
0.25 cm. Thus, the straws will be cut 0.5 cm shorter than the theoretical length. This is because
when the straws are pinned as close as possible, they will be about 1 radius length away from the
center since the straws cannot touch or overlap. Next, the pinning jigs will be used on both sides
of the straws to find the ideal 0.5 cm distance between holes. To find the proper locations of the
straws on the gusset plates, the center of the plate will be found and the corresponding length of
straw will be pinned as closely as possible around the center without touching. Then, the general
shape of the straws will be traced and the gusset plate will be cut to reduce weight. Once all the
plates and straws are pinned together, identical (or as close to identical as possible) gusset plates
A 4% decrease was the final adjustment to the max loads. This is because the
construction was not perfect. Some straws were mildly bent from handling and some gusset
plates were cracked from incorrect cutting (in fact only 2 extra plates remain). Also, the angles of
the members were not perfectly perpendicular or parallel. As such, some joints have a slightly
different location on the plane. The biggest construction concern was the distance between the
11
actual joint center and the straw itself. Especially with the diagonal members, the straw was
sometimes up to 0.25 cm away from the center. These issues will most likely decrease the actual
max load. Something interesting for the actual testing will be gusset plate contact with the
straws. If the plates are pushed into contact with the straws, a moment will most likely result
from friction and thus reduce the max load. Something to note is that the Hartford study showed
that engineers can be negligent despite easily seen physical evidence of potential failure. Seeing
the final truss construction has definitely lowered team expectations of the maximum load the
Appendix:
Group Teamwork
Commenced at 1:30 pm
…………………………………………………………………………………………..
Planned Agenda:
Important Points:
● Charles: What were the major reasons for the Hartford Arena to fall?
○ Devin: The engineers depended too much on a flawed computer program. If the
program was more well adjusted to the situation, the arena would not have fallen.
○ Eric: The teams in charge of designing, constructing, and inspecting the project
were not organized resulting in lack of responsibility and the collapse of the
building.
13
○ Emanuel: If we were to make our truss in reality, we should make the stated max
○ Eric: I think we should make it 60% to allow even more possible error in our
calculations.
● Charles: How much trust should we have our program considering what we just read?
○ Eric: We shouldn’t trust it too much considering we can have different factors that
we did not consider like moments on the joints, quality of materials, etc.
○ Devin: I agree.
○ Charles: Especially since we’re probably going to accidentally bend straws and
We discussed everything we wanted about the case study, so we will not have a second meeting
for it.
Project Timeline:
Final ✔
14
Report (FINISH)
Group ✔
Meeting
Construct ✔
Truss
Choose a ✔
final
design