Project Standard and Specifications Project Control Procedure Rev01 Web
Project Standard and Specifications Project Control Procedure Rev01 Web
Rev: 01
KLM Technology PROJECT CONTROL
Group
PROCEDURE
Project Engineering Standard
Feb 2012
(PROJECT STANDARDS AND
SPECIFICATIONS)
TABLE OF CONTENTS
PURPOSE 2
SCOPE 2
DEFINITION 2
PROCEDURE 7
Introduction 7
Planning and Scheduling 7
Progress Planning 9
Progress Reporting 13
Progress Meeting 14
RECORDS 16
REFERENCES 16
ATTACHMENTS 17
Attachment 1 CONTRACTORS Organization Chart 17
Attachment 2 Manpower Histogram 18
Page 2 of 18
Rev: 01
KLM Technology PROJECT CONTROL
Group
PROCEDURE
Project Engineering Standard
Feb 2012
(PROJECT STANDARDS AND
SPECIFICATIONS)
PURPOSE
The purpose of this procedure Is to establish a method for planning and control for the
execution of the PROJECT This procedure describes the approach to the planning
and controls that are to be performed In the PROJECT In case of any conflict and
inconsistency between this procedure and Contract, the Contract will prevail.
SCOPE
This procedure defines the Planning, Scheduling. Progress Control and Reporting
requirements for each phase of the PROJECT implementation including:
DEFINITION
The responsibility for the overall project control will rest with the Project Management
Team in CONTRACTOR Office until engineering has almost been completed (over
90% progress) and all major equipment have been delivered to the Site, alter which
Page 3 of 18
Rev: 01
KLM Technology PROJECT CONTROL
Group
PROCEDURE
Project Engineering Standard
Feb 2012
(PROJECT STANDARDS AND
SPECIFICATIONS)
the overall project control function will pass to the Field Control Team at the Site as at
that time the majority of the project activities will be carried out at the Site.
A. Organization
After engineering has substantially been completed and ell major equipments have
been delivered to the Site, the Field Control Team at the Site will be responsible for
overall project control.
The Project Control Team will be organized under the Project Control Manager for:
1. Schedule Control
2. Cost Control
3. Change Control
4. Document Control
The Field Control team at the Site will be organized under the Field Control Manager
for:
B. Responsibilities
1. The Project Control Manager will be responsible for all project control matters,
such as planning, controlling and reporting for the Project and will report to the
Project Manager. The Field Control Manager will be responsible for ell project
control matters at the Site and will report to the Construction Manager.
Page 4 of 18
Rev: 01
KLM Technology PROJECT CONTROL
Group
PROCEDURE
Project Engineering Standard
Feb 2012
(PROJECT STANDARDS AND
SPECIFICATIONS)
The prime duties of the Project Control Manager and Field Control Manager
will, as appropriate, be
Rev: 01
KLM Technology PROJECT CONTROL
Group
PROCEDURE
Project Engineering Standard
Feb 2012
(PROJECT STANDARDS AND
SPECIFICATIONS)