0% found this document useful (0 votes)
239 views1 page

Direct Manpower Deployment Schedule: Total Manhours

The document outlines a direct manpower deployment schedule for various construction roles across four months. It lists nine roles including carpenter, steel fixer, mason, and helper and estimates the number of personnel required for each month as well as the total estimated manhours for each role over the period. The total estimated manhours for all roles across the four months is 118,560 hours.

Uploaded by

Dilip Kumar
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
239 views1 page

Direct Manpower Deployment Schedule: Total Manhours

The document outlines a direct manpower deployment schedule for various construction roles across four months. It lists nine roles including carpenter, steel fixer, mason, and helper and estimates the number of personnel required for each month as well as the total estimated manhours for each role over the period. The total estimated manhours for all roles across the four months is 118,560 hours.

Uploaded by

Dilip Kumar
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 1

DIRECT MANPOWER DEPLOYMENT SCHEDULE

MONTH
Sr. No Description Apr-19 May-19 Jun-19 Jul-19 Total Manhours
1 2 3 4
1 Carpenter 18.00 23.00 30.00 34.00 27,300
2 Steel Fixer 10.00 18.00 23.00 27.00 20,280
3 Mason 10.00 12.00 15.00 18.00 14,300
4 Helper 13.00 23.00 32.00 37.00 27,300
5 Painter & Finisher - 4.00 7.00 9.00 5,200
6 Scaffolder 7.00 10.00 14.00 18.00 12,740
7 Signal Man 2.00 2.00 3.00 3.00 2,600
8 LD Driver 2.00 5.00 6.00 6.00 4,940
9 Operator 3.00 4.00 4.00 4.00 3,900
TOTAL 65.00 101.00 134.00 156.00 118,560.00

Page 1 of 1