Direct Manpower Deployment Schedule: Total Manhours
Direct Manpower Deployment Schedule: Total Manhours
MONTH
Sr. No Description Apr-19 May-19 Jun-19 Jul-19 Total Manhours
1 2 3 4
1 Carpenter 18.00 23.00 30.00 34.00 27,300
2 Steel Fixer 10.00 18.00 23.00 27.00 20,280
3 Mason 10.00 12.00 15.00 18.00 14,300
4 Helper 13.00 23.00 32.00 37.00 27,300
5 Painter & Finisher - 4.00 7.00 9.00 5,200
6 Scaffolder 7.00 10.00 14.00 18.00 12,740
7 Signal Man 2.00 2.00 3.00 3.00 2,600
8 LD Driver 2.00 5.00 6.00 6.00 4,940
9 Operator 3.00 4.00 4.00 4.00 3,900
TOTAL 65.00 101.00 134.00 156.00 118,560.00