CONSTRUCTION CLAIMS MANAGEMENT
&
EOT DELAYS ANALYSIS
Presented by :
Hany Ismail, MSc, PMP
CONSTRUCTION CLAIMS MANAGEMENT
EOT DELAYS ANALYSIS
LESSON 7
TIME IMPACT WINDOW DELAY ANALYSIS
TECHNIQUE
TIME IMPACT – WINDOW ANALYSIS
WWW.PLANNINGENGINEER.NET
Construction Claims Management & EOT Delay Analysis
Agenda
• Introduction.
• Why is TIA preferred technique ?
• Window Analysis Technique
• Window Analysis Technique Steps
• Smart Windows Time Periods
WWW.PLANNINGENGINEER.NET
Construction Claims Management & EOT Delay Analysis
Introduction
Time Impact Analysis Technique is Actual Based Approach
Which depends on the actual consequence and dates
happened in the site during the execution not only the
planning schedule.
TIA is widely recognized by the construction industry as
the most accepted method to quantify schedule delay.
In this method the analyst develops and adds a model of
the change to an approved schedule to quantify the delay
to project completion WWW.PLANNINGENGINEER.NET
Construction Claims Management & EOT Delay Analysis
TIA is preferred delay analysis technique
TIA is preferred delay analysis technique for the following reasons
it allows assessment of the actual state of progress at the time the
delay event occurred.
the responsibility for delay prior to the impact of the delaying event
is not material to the calculation of the effect of the delaying event
itself.
It determines whether the delay event impacted the critical path.
The exact impact of the delay event can be calculated.
WWW.PLANNINGENGINEER.NET
Construction Claims Management & EOT Delay Analysis
Window Analysis Technique
Window analysis is a time impact technique which focus on the
impact of delays in specific periods of time , identifying gains or
losses ( delays and recovery ) to the actual critical and sub-critical
paths as they occur with each period of time.
The project life cycle is divided into a series of consecutive time
“Windows”.
WWW.PLANNINGENGINEER.NET
Construction Claims Management & EOT Delay Analysis
Window Analysis Technique – Cont’
For Each window
- Each window is analyzed to identify the activities that were
impacted , delay or recovery and the results are investigated to
identify the events that caused the deviation in progress.
- Analysis steps
WWW.PLANNINGENGINEER.NET
Construction Claims Management & EOT Delay Analysis
Window Technique – Analysis Steps
Step 1 : Incorporate delay events that have been occurred in the period
Step 2 : Establish the impact on time for Completion.
WWW.PLANNINGENGINEER.NET
Construction Claims Management & EOT Delay Analysis
Window Technique – Analysis Steps
Step 3 : Update the impacted programme with progress with in the
window period.
Step 4 : Establish the impact on the Time for Completion.
D1 : Impact delay period due to “Employer Delay Events”
D2 : Impact delay period due to “Contactor Delays ” from the
update.
WWW.PLANNINGENGINEER.NET
CONSTRUCTION CLAIMS MANAGEMENT
EOT DELAYS ANALYSIS
CASE STUDY
BANK XYZ PROJECT
WWW.PLANNINGENGINEER.NET
Construction Claims Management & EOT Delay Analysis
Window Technique – Case study
General Information
Project Planned Start Date : 12,March,2012.
Project Planned Finish Date : 22,April,2013.
Available Updates Programme : 4 Programme
WWW.PLANNINGENGINEER.NET
Construction Claims Management & EOT Delay Analysis
Window Technique – Case study- Window 0
Window Window Window Project Delay Total
Source
Window Start Finish Duration Prog. Finish Entitlemen
Programme
(1) (2) (3) = 2-1 date Contractor Employer t
Appr.
22,April,
P0 Baseline
2013
A.01
P0+Delay
W0 31 P1 Events
13,May,
2013
P1+Progress
14,May,
P2 update on
2013
DD
Total Window Entitlement
WWW.PLANNINGENGINEER.NET
Construction Claims Management & EOT Delay Analysis
Window Technique – Case study- Window 1
Window Window Window Project Delay Total
Source
Window Start Finish Duration Prog. Finish Entitlemen
Programme
(1) (2) (3) = 2-1 date Contractor Employer t
Approved
P3 P2 14,May,
2013
P3+Delay
W1 264 P4 Events
25,May,
2013
P4+Progress
3,Jun
P5 update on
, 2013
DD
Total Window Entitlement
WWW.PLANNINGENGINEER.NET
Construction Claims Management & EOT Delay Analysis
Window Technique – Case study- Window 2
Window Window Window Project Delay Total
Source
Window Start Finish Duration Prog. Finish Entitlemen
Programme
(1) (2) (3) = 2-1 date Contractor Employer t
Approved
P6 P5 3,Jun
, 2013
P6+Delay
W2 264 P7 Events
9,July,
2013
P7+Progress
21,July,
P8 update on
2013
DD
Total Window Entitlement
WWW.PLANNINGENGINEER.NET
Construction Claims Management & EOT Delay Analysis
Window Technique – Case study- Window 3
Window Window Window Project Delay Total
Source
Window Start Finish Duration Prog. Finish Entitlemen
Programme
(1) (2) (3) = 2-1 date Contractor Employer t
Approved
P9 P8 21,July,
2013
P9+Delay
W3 79 P10 Events
15,Aug,
2013
P10+Progres
15,Sep.,
P11 s update on
2013
DD
Total Window Entitlement
WWW.PLANNINGENGINEER.NET
Construction Claims Management & EOT Delay Analysis
Window Technique – Case study- Summary
Delay
window Project Finish Total
Window Window Start Window Finish Programme Programme Contractor Employer
Duration Date Entitlement
Delay Delay
Approved
P0 22-Apr-13 0 0
BaseLine
P0+Delay
Window 0 10-Mar-12 10-Apr-12 31 P1 13-May-13 21
Events
P1+Progress
P2 14-May-13 1 22
update on DD
P3 Approved P2 14-May-13
P3+Delay
P4 25-May-13 11
window 1 11-Apr-12 31-Dec-12 264 Events
P4+Progress
P5 3-Jun-13 9 20
update on DD
P6 Approved P5 3-Jun-13
P6+Delay
P7 9-Jul-13 36
Window 2 1-Jan-13 1-Feb-13 31 Events
P7+Progress
P8 21-Jul-13 12 48
update on DD
P9 Approved P8 21-Jul-13
P9+Delay
P10 15-Aug-13 25
Window 3 2-Feb-13 22-Apr-13 79 Events
P11 P10+Progress 15-Sep-13 31 56
update on DD
Total Entitlement
WWW.PLANNINGENGINEER.NET
Construction Claims Management & EOT Delay Analysis
Window Technique – Case study- Conclusion
According to the previous analysis the contractor entitled
for (93) Calendar day as Excusable Delays
Total Entitlement
146 Calendar Day
Excusable Non-Excusable
93 Day 53 Day
Non-
Compensable
Compensable
WWW.PLANNINGENGINEER.NET
Thank You …
We hope you enjoy our lecture today
Hope to receive your feedback and recommendations
Contact Info
WWW.PLANNINGENGINEER.NET
[email protected]
Mobile : +20 1277767728 /PlanningEngineerDotNet
/groups/4809645