Schlumberger Production Logging Tool Program
Schlumberger Production Logging Tool Program
Objective:
Perform PLT to get the total production and zonal contribution of every perforated interval.
Outline:
Before the job is scheduled in the 14-day plan, please complete the following:
2. Risk assessment and Permit to Work are required before proceed the job.
5. O/P should test the well and collect wellhead sample for W.C% before proceeding with the job.
6. Risk assessment, Permit to Work, W/L checklist, and Well Handover Certificate are required before
proceed the job.
7. Check safety equipment available, work vest, life jacket, inflatable raft, ring buoy and ropes.
8. Check the X-tree valves for leaking and stuck. Make sure that the Cap is working OK. In addition, the
Header production and test valves should be OK. (PSS should make this survey).
9. Measure the delta pressure across the flow line to be sure the flow line is free from scale.
10. Make sure that the P/F is clean and not slippery.
11. Collect wellhead sample from the well for chloride and water cut.
12. Check the last reading for H2S value. If it is above 10 PPM, TOTAL should be ready before starting
the job.
13. Check the X-tree height and the availability of ladder to R/U the equipment.
14. O/P should prepare ½” HP hose for pressure testing.
15. O/P should have tested the well before proceeding with the job.
16. O/P should help for stabilization the well by increasing the gas on the well or put the well on a
test line lonely or adjust the chemical on HPG line to reduce the emulsion on the well.
17. O/P should have tested the well during the stabilization period to get a representative test for
the well
18. Pressure gauge with proper ranges available with fitting to connect gauges.
1. Check the QC of all sensor that will be used (GR-CCL, Gradio, Press., Temp., and Spinner)
2. Check the data acquisition program and the battery are working OK.
3. It should be an auxiliary cord that connecting the SONDX box to the reel back drum.
4. All the service personnel should have the PPE for safety.
1. Hold a pre-job safety meeting, clarify job procedure, and ensure every one is clear on his
responsibilities. Any information and change in the procedure should be through the Dist Eng
witness.
2. R/U W/L lubricator on the X-tree, then pressure test the lubricator to 1200 Psi against swab valve
as GUPCO R/U procedure.
3. Shut-in both the gas line header and gas wing valves, and close both the production line header
and wing valves.
4. R/U xxx MPL tools, open the swab valve, and then RIH.
5. While the well is shut-in perform five shut-in passes (UP and DOWN) with different constant
cable speed (i.e. 30, 60, 80, 100, 120 Ft/Min) from above all perforation by +50` to top of sand.
6. Stop above all interval by +50` @????` THF.
7. Open the well to production by opening both the gas line header and gas wing valves, and open
both the production line header and wing valves slowly.
8. Switch the well to test line for testing, and monitor the surface data until stabilization occurs.
9. After stabilization period and while the well on production, perform five flowing passes (UP and
DOWN) from above all perforation by +50` to top of sand.
10. Perform stationary stops above and below every perforated intervals and inside long intervals as
shown in the table.
11. Shut-in both the gas line header and gas wing valves, and close both the production line header
and wing valves.
12. POOH with xxx MPLT.
13. When the tools at surface, close the swab valve and bleed the lubricator pressure.
14. R/D both xxx MPL tools and W/L lubricator.