Transmission Line Schedule

The document outlines a schedule for the construction of a transmission line from Q2 2018 to Q4 2019. It details the key milestones and tasks required for the project including contract award, site preparation, construction of foundations, erection of towers, installation of equipment and final testing and commissioning.

Uploaded by

KAmi KaMran
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
384 views

Transmission Line Schedule

The document outlines a schedule for the construction of a transmission line from Q2 2018 to Q4 2019. It details the key milestones and tasks required for the project including contract award, site preparation, construction of foundations, erection of towers, installation of equipment and final testing and commissioning.

Uploaded by

KAmi KaMran
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

Construction of Transmission Line Classic Schedule Layout 21-Mar-19 13:56

Qtr 2, 2018 Qtr 3, 2018 Qtr 4, 2018 Qtr 1, 2019 Qtr 2, 2019 Qtr 3, 2019 Qtr 4, 2019
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
30-Jul-19, SKHPTL Construction of Transmission Line

30-Aug-18, SKHPTL.1 ContractAward and Mobilization


ContractAward, 08-Jun-18*
Commencement,
Mobilization & Site Facilities
16-Jul-19, SKHPTL.2 Construction of 11KV transmission Line
Demarcation of Tower LocationlPoints
Land Acquisition for Towers/Poles
Land Acquisition for ROW
Clearance of ROW
Issuance of Construction drawings
Approval of Construction Materials
Layout of the Towers/Poles Foundation
Excavation for Foundations
Construction of Foundations
Errection of Towers
Installation of Hardwares
Stinging of Conductors
16-May-19, SKHPTL.3 Construction of 33 KV line
Demarcation of Tower LocationlPoints
Land Acquisition for Towers/Poles
Land Acquisition for ROW
Clearance of ROW
Issuance of Construction drawings
Approval of Construction Materials
Layout of the Towers/Poles Foundation
Excavation for Foundations
Construction of Foundations
Errection of Towers
Installation of Hardwares
Stinging of Conductors

Actual Level of Effort Remaining Work Page 1 of 2 TASK filter: All Activities
Actual Work Critical Remaining Work © Oracle Corporation
Construction of Transmission Line Classic Schedule Layout 21-Mar-19 13:56
Qtr 2, 2018 Qtr 3, 2018 Qtr 4, 2018 Qtr 1, 2019 Qtr 2, 2019 Qtr 3, 2019 Qtr 4, 2019
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
30-Jul-19, SKHPTL.4 Project Completion
Testing and Commissioning
Handing over,

Actual Level of Effort Remaining Work Page 2 of 2 TASK filter: All Activities
Actual Work Critical Remaining Work © Oracle Corporation