Project Planners' Tips Excel Based Summary Schedule (Lv1 Schedule)

This Excel schedule summarizes the key activities and timeline for a multi-building construction project from 2010-2014. It shows the planned completion of major structural elements and interior/exterior work for each building on a monthly basis. Key milestones include completion of building pads, structural elements like slabs and roofs, exterior shell work, interior finishes, and site work/landscaping over the 4 year period. Precast garage structures, site utilities and amenities are also scheduled. The high-level Gantt chart format provides a concise overview of the critical path and sequencing of construction activities across the project.

Uploaded by

Vasatore
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
73 views

Project Planners' Tips Excel Based Summary Schedule (Lv1 Schedule)

This Excel schedule summarizes the key activities and timeline for a multi-building construction project from 2010-2014. It shows the planned completion of major structural elements and interior/exterior work for each building on a monthly basis. Key milestones include completion of building pads, structural elements like slabs and roofs, exterior shell work, interior finishes, and site work/landscaping over the 4 year period. Precast garage structures, site utilities and amenities are also scheduled. The high-level Gantt chart format provides a concise overview of the critical path and sequencing of construction activities across the project.

Uploaded by

Vasatore
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

PROJECT PLANNERS' TIPS

Excel Based Summary Schedule (Lv1 Schedule)

2010 2011 2012 2013 2014


Activity Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Building 1 Structure

Building Pad Including UG Utils


Floor Completion 1st 2nd 3rd 4th
Slabs, Collar Beam & Masonry Structure

Roof Slab & Collar Beam (inc Stair & Elevator


Masonry Structure)
Building 1 Roof
Place Roof Trusses, Sheathing & Mechanical
Equipment Supports
Asphalt

Roofing (Built-Up Asphalt, Felt & Tile)


Felt & Tile
Building 1 Shell

Set-up Scaffolding
Floor Completion 1st 2nd 3rd 4th
Install Ext Windows & Sliding Glass Doors
Floor Completion 1st 2nd 3rd 4th
Install Backing & Cauld Windows

Apply Stucco (incl Caulking)

Paint Exterior & Install Railings (incl Scaffolding


Removal)
Building 1 Interior Finishes/ Courtyard
Floor Completion 1st 2nd 3rd 4th
Unit Finishes Building North & South

Building 2 Elevator, Tenant Finishes for Building 2 Elevator Tenant Finishes for Clubhouse Areas & Final Inspection

Clubhouse Areas & Final Inspection


Pool & Deck Pergola & Amenities
Pool & Deck / Pergola & Amenities

Building 2 Structure

Building Pad Including UG Utils


Floor Completion 1st 2nd 3rd 4th
Slabs, Collar Beam & Masonry Structure

Roof Slab & Collar Beam (inc Stair & Elevator


Masonry Structure)
Building 2 Roof
Place Roof Trusses, Sheathing & Mechanical
Equipment Supports
Asphalt
Roofing (Built-Up Asphalt, Felt & Tile)
Felt & Tile
Building 2 Shell

Set-up Scaffolding
Floor Completion 1st 2nd 3rd 4th
Install Ext Windows & Sliding Glass Doors
Floor Completion 1st 2nd 3rd 4th
Install Backing & Cauld Windows

Apply Stucco (incl Caulking)


Remove Scaffolding
Paint Exterior & Install Railings (incl Scaffolding
Removal)
Building 2 Interior Finishes/ Courtyard
Floor Completion 1st 2nd 3rd 4th
Unit Finishes Building North & South
Building 1 Elevator Final Inspection
Building 1 Elevator & Final Inspection

Courtyard Walks & Amenities

Garages, Utilities & Landscape


Drawing, Fabrication & Delivery Erect Precast Structure Fire Protection & Lighting / Finishes, Barrier Cables & Striping
Garage 1 Punchlist

Drawing, Fabrication & Delivery Erect Precast Structure Fire Protection & Lighting, Finishes & Striping, Punchlist
Garage 2
to Buildings 4 & 3 to Buildings 2 & 1
Electric to Buildings Power Vault
Storm Drainage, Walkways, Roadway Pavers, Finish Paving, Striping & Signs Curbs & Paving Fountain/Water Feature, Entry Feature/Sign Wall, Curbs & Paving
Roads & Pavers
Site Cleanup Landscape & Irrigation
Landscape & Irrigation

Actual Bar Remain Bar Actual Milestone Remain Milestone