Lecture 5 (Change Management)
Lecture 5 (Change Management)
Project Management
Change Management
1
Change Management
Change
Management
3
Change Orders
1. For any changes to the scope of work, a
written document of the change – called a
change order - is submitted. This document
is to verify and attain that a change to the
original contract has occurred, and
accordingly, time and cost implications might
occur
2. Change orders are written for:
- Alterations to the original scope of work
- Increasing or decreasing the contract
quantities
4
Change Order Form
5
Change Orders
3. Change orders state the basis and amount
of payment and time extension entitlement,
and hence, the basis of a claim
6
Claims in the Construction Domain
7
Claims in the Construction Domain
Contractor Owner
8
Claims in the Construction Domain
Causes:
1. Owner changes
2. Design errors/omissions
3. Wrong specifications
5. Weather…etc
9
Claims in the Construction Domain
Categories of Claims
10
Impact of Construction Claims
11
Impact of Construction Claims
- Cost
- Time
12
Types of Impact
Impacts
13
Types of Impact
14
Incremental vs. Cumulative Impact
Cumulative
Impact
Sub- Sub-
Incremental Incremental
Impact 1 Impact 2
15
Incremental vs. Cumulative Impact
16
Incremental vs. Cumulative Impact
18
Delay Analysis in Construction Projects
19
Delay Analysis in Construction Projects
20
Delay Analysis in Construction Projects
Categories of Delays
21
Delay Analysis in Construction Projects
Classification
of Delays
Excusable Non-Excusable
Delays Delays
Compensation is paid to the owner in
the form of liquidated damages due
The contractor is entitled to to the actions or inactions of the
Compensable time extension as well as
monetary compensation
contractor
22
Delay Analysis in Construction Projects
Concurrent Delays:
1- Two or more separate delays that occur in the same time period
2- Two or more separate delays that occur in the same time period
but in two parallel critical paths
3- Two or more separate delays that occur in the same time; even
if one had not occurred, the project would have been delayed
by the SAME amount of time
4- Concurrent delays must fulfill the following requirements:
- Occur in the same time period
- Each of them has the ability to affect project duration
23
Delay Analysis in Construction Projects
Ex cusable Extension of
com pensable Time + Extension of Extension of
delay Damages Time for the Time for the
Compensation Contractor Contractor
for the
Contractor
Ex cusable non- Extension of Extension of Extension of
com pensable Time for the Time for the Time for the
delay Contractor Contractor Contractor
7 days
(1 day delay) 6 days
3 days
(3 days delay)
- No CPM required
Disadvantages:
- Concurrency is neglected in this technique
26
Delay Analysis Techniques
As-Planned Method
Delay
As-Planned Method
Advantages:
- Comparison done relative to the as-planned
schedule
Disadvantages:
- Does not identify types or responsibility of
delays
- Assumes static critical path
28
Delay Analysis Techniques
- Logic is identified
Disadvantages:
- Does not deal with types and responsibility of
delays
30
Delay Analysis Techniques
Other Techniques:
- Net Impact Method
- As-Built Method
- But-for “Collapsing” Technique
- Snapshots “Windows” Technique
- Time Impact Analysis Technique
- Delay Section Method
- Isolated Delay Type Method
- Float Allocation Method (U.S Board of Contracts
Appeal)
- Concurrent Delay Method 31
Prolongation Cost Calculation and
Assessment
32
Prolongation Cost Calculation and
Assessment
33
Prolongation Cost Components
34
Prolongation Cost Components
35
Prolongation Cost
Concurrent Delays:
“If the Contractor incurs additional costs that
are caused both by an Employer Delay and
concurrent Contractor Delay, then the
Contractor should only recover compensation to
the extent it is able to separately identify the
additional costs caused by Employer Delay from
those caused by the Contractor Delay”
The Society of Construction Law (SCL) Delay and Disruption Protocol
36
Methods for Quantifying Delay Cost
37
Methods for Quantifying Delay Cost
38
Methods for Quantifying Delay Cost
39
Measured Mile Analysis
LOP = Loss of productivity Timothy T. Calvey, and William R. Zollinger III (2003). Measured
Mile Labor Analysis.
41
Measured Mile Analysis
Loss of
productivity
Cost Impact Labour = [X Impacted Conditions (hrs) -X Normal Conditions (hrs)] * Average hourly cost
43
Measured Mile Analysis
Example:
Given the previous case:
1 crew = 8 mhrs/hr
@ $168.25/hr (for the crew)
What is the cost impact for the disruption of work?
Cost Impact Labour=[32,668 mhrs/8 mhrs/hr – 24,000 mhrs
/8 mhrs/hr] * $168.25/hr
Cost Impact Labour = $182,298.88
44
Time & Cost Entitlement
45
Time & Cost Entitlement
46
Example
Oliveros, A.V. Ordonez, and Fayek, A. Robinson (2005). Fuzzy logic approach
for activity delay analysis and schedule updating. 47
Example
49
Example
50
Example
51
Example
Non-Excusable delay
Excusable compensable delay (resulting from owner’s 1 Week 1 Week (resulting from
changed design) + non excusable delay (resulting contractor’s pump
from contractor’s pump breakdown) = Extension of breakdown) resulting
Time (contractor entitled to an extension of time in liquidated damages
without any prolongation costs) 52
Example
53
Example
54
Examples of Types of Changes
Turnover of personnel
Lack of funding to complete work (Owner)
Communication breakdown within organizations
Lack of skill and experience level to execute work
Lack of quality of engineering
Late delivery of engineering design and materials
Compounding impact of numerous small changes
55