ITR-C (Instrument) 16c
ITR-C (Instrument) 16c
2 Verify no damage to the Fire & Gas device during transportation (offshore)
5 Verify the correct electric power supply is connected to the Fire and Gas panel
6 Verify all tools/equipment/test kits for the loop test are available
7 Verify local indication/display (if applicable), are correctly activated upon testing of the loop
8 Verify all theindication/display in FGS Panel are correctly activated upon testing of the loop
Verify the indication/display in DCS (if applicable) are correctly activated upon testing of the
9
loop
Verify the indication/display and actions in Shutdown Systems (if applicable) are correctly
10
activated upon testing of the loop as per cause and effect matrix
11 Verify no dust inside Enclosure /Cabinet / Panel and insulation surfaces are clean.
REFERENCE DRAWINGS
1 Loop Drawings
2 FGS Cause & Effect Matrix (if applicable)
3 Vendor Drawings
OBSERVATION / REMARKS