1) The document outlines the process for setting out lines, levels, and control points for a construction project. 2) Key steps include identifying the location and area, determining if a soil investigation is needed, conducting on-site and laboratory tests if required, establishing control points and calibration methods, recording inspection results, and ensuring results meet contractual acceptance criteria. 3) Management and supervision is provided by various roles including the site manager, site engineer, supervisor, surveyor, and QC engineer at different stages of the process.

Uploaded by

Setiadi Margono
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
714 views

Concrete Works Flowchart

1) The document outlines the process for setting out lines, levels, and control points for a construction project. 2) Key steps include identifying the location and area, determining if a soil investigation is needed, conducting on-site and laboratory tests if required, establishing control points and calibration methods, recording inspection results, and ensuring results meet contractual acceptance criteria. 3) Management and supervision is provided by various roles including the site manager, site engineer, supervisor, surveyor, and QC engineer at different stages of the process.

Uploaded by

Setiadi Margono
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

Project Title

Client Logo Doc Title


Doc No Date

No Incharge Process Documents Notes / Remarks

Setting Out of Lines, Levels, & Control Points

START

1 Site Manager Pre-construction


Soil Investigation Identification
Site Engineer (Geo) Progress - Intermediate
Post-construction

2 Site Engineer Identify Location & Area


Supervisor
Surveyor
No
Yes / No

Yes

3 Supervisor Inspection Form Soil Investigation


NFI
Surveyor Schedule
Witness / No witness

4 Supervisor Requirement Technical Specs


Surveyor

5 Site Engineer
On Site Laboratory
Lab Engineer

Inspection Form WMS


6 Site Engineer Documentation ITP
Yes / No
Supervisor

7 Supervisor Equipment
Control Point
Surveyor Calibration
Methods

No
6 Site Engineer Yes / No

Yes

7 Supervisor Soil Investigation


Surveyor

8 Supervisor Inspection Record (Berita Acara) Inspection Form


Surveyor Documentation

9 Site Engineer Layout/Section Properties Contract


Result data
Supervisor Soil Investigation Report Acceptance Criteria

No
10 Site Manager
Yes / No
QC Engineer

Yes