Inspection Test Record (Itr) - A Jacket Post Loadout ST09-A

This document provides an inspection test record for a jacket post loadout. It lists several items to check on the jacket launch barge and piles barge prior to sailaway, including emergency lines, navigation lights, towing lines, manholes, and barge condition. It also lists items to check on the drilling deck, such as dimensions, lifting rigging, padeyes, deck leg welds, stairways, bolted connections, and potential interference points for stabbing. The inspection aims to verify the barge and drilling deck meet specifications and are safe for transport.

Uploaded by

Momo Itachi
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
142 views

Inspection Test Record (Itr) - A Jacket Post Loadout ST09-A

This document provides an inspection test record for a jacket post loadout. It lists several items to check on the jacket launch barge and piles barge prior to sailaway, including emergency lines, navigation lights, towing lines, manholes, and barge condition. It also lists items to check on the drilling deck, such as dimensions, lifting rigging, padeyes, deck leg welds, stairways, bolted connections, and potential interference points for stabbing. The inspection aims to verify the barge and drilling deck meet specifications and are safe for transport.

Uploaded by

Momo Itachi
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

INSPECTION TEST RECORD (ITR) - A

JACKET POST LOADOUT ST09-A


Project No.
Project Title
Facilities
INFORMATION
Area No Ref Drawing
System Inspection Date
Sub System Location

INSPECTION / TEST OK N/A P/L No.


GENERAL CHECKLIST ITEMS ON JACKET LAUNCH BARGE & PILES BARGE: POST
LOADOUT
• Check for barge emergency lines are installed complete with Norwegian buoy and
located at accessible location.
• Check navigation lights are operational.
• Check condition of emergency towing line operational (if any).
1 • Check and confirm all manholes are closed prior to sailaway.
• Check barge condition for any damage prior to sailaway.
• Check ballast pattern as per approved transportation study and identify draft mark
at bow and stern of the barge.
• Brief personnel in charge for sailaway i.e Tug boat captain and crews on passage
plan and Emergency Response Plan (ERP).
• Check weather forecast prior sailaway.
DRILLING DECK
• Check overall dimension especially deck leg spacing (as-built).
• Check stabbing cone OD to be verified.
• Check level/vertical height length dimension (as-built).
• Check pre-installed lifting rigging make-up, layout, and I.D. and tie-down
arrangement.
• Check padeyes as-built-NDT reports.
• Position of bottom Deck leg seam weld especially relative to top stub piles(as
built).

2 • Review ship loose arrangement layout on top of deck for potential interferences
when rigging up and de-rigging lifting slings (if applicable).
• Stairway hinged up and secured under deck. Vertical ladder from access deck to
jacket seadeck secured on access deck.
• Check all bolted connections secured.
• Check grating clip secured.
• Review any structure/piping/cable tray protruding 1.5 meter radius around design elevation
of deck that may interfere with stabbing point or any permanent structure
at the jacket.
• Check dimensions of stabbing cones and painted on each deck leg for offshore
identification i.e B1, B2, C1&C2.