Ngee Ann Polytechnic Marine & Offshore Technology Shiprepair and Conversion - Ship Conversion
Ngee Ann Polytechnic Marine & Offshore Technology Shiprepair and Conversion - Ship Conversion
Ship Conversion
Ship conversion may be defined as the work carried out on an existing ship so that
the vessel can perform one or more additional or new functions or to enhance her
existing performance after the conversion. Such work can be carried out in a
shipbuilding yard or shiprepair yard. It usually involves substantial amount of work
and therefore requires some time of stay in the conversion yard.
The primary function of the ship is changed after the conversion. Some
recent typical examples of conversions of this nature are from:
1
The need for the jumboisation of ships arose first in the 1960s as larger ships
especially tankers are in demand.
An interesting example of such conversion was the lengthening of the 442,000 dwt
"Sea Wise Giant" in 1981 to make her the largest tanker in the world having a
deadweight capacity of 564,000 tons.
An example of increasing the breadth is the additional fitting of pontoons on the side
of livestock carrier (converted from a cargo liner) to increase the quantity of pens on
and above main deck.
Numerous car ferries have increased their depth by adding car decks to increase
the car capacity.
2
Reasons for Ship Conversions
i. When the costs of newbuildings are high, and the returns are not justifiable,
ship conversion becomes a viable option for shipowners to acquire the
required tonnage to start up operation. This would be especially so if second-
hand vessels could be purchased at a reasonable cost.
ii. Conversion may be carried out within 2 to 6 months. Delivery time for
newbuildings generally vary from 12 to 18 months and may be even longer
when shipyards are filled with orders. This lead time may be too long for
certain projects that require a fast start-up. This could be overcome by
resorting to ship conversions if the returns are justifiable.
iii. The change in the global economic and trading patterns may render some
vessel types to be either obsolete or idle as in a prolonged oversupply
situation. Shipowners who are faced with such obsolete or idle vessels have
therefore to decide on an option, which could still recover some of their
sunken capital costs. If the opportunity permits, the vessels may be converted
to perform another function.
iv. The rapid changes in ship design, technology and operational requirement
may render existing vessels to be less efficient and less competitive as
against newbuildings. To increase the efficiency and competitiveness of the
existing vessels, some modifications to the vessel are required. For example,
some owners may carry out modernisation of the ship navigational and
machinery controls, modernisation of cargo handling and access system on
board vessels etc.
vi. The fulfillment of contract where the owner has made with the charter party
for a relatively short contract of employment may not economically justify
newbuilding. It would be viable for owner to charter and convert a vessel for
meeting the contract requirement. An example was the conversion of tankers
to FSOs to serve a marginal offshore oil field.
3
Considerations and implications of ship conversions
Shipowner's considerations
c. Operational considerations
Operation of the vessel after the conversion by competent crew must be made
available. This may involve hiring of staff from other discipline, employing supporting
offshore and onshore services.
e. Time factor
When tenders from different shipyards are received for evaluation, it is important
that the time to be taken for the conversion must meet the schedule of employment.
Owners may recourse to penalty or even termination of conversion contract if the
delivery schedule is not meet. Owners should therefore consider yards with good
track records in ensuring that the delivery is on time.
g. Sources of finance
This may come from the reserves of the owner, otherwise it may be in the form of
joint venture capital funds, bank borrowing or financing from the conversion yard. It
is important for the owner to maintain scheduled payment to the conversion yard
and
equipment vendors in order that work may not be disrupted.
4
Shipyard's considerations