Schedule For Dam

This document provides a schedule for implementation of the New Assiut Barrage and Hydropower Plant project from 2012 to 2019. It lists activities, start and end dates, and milestones. The key activities include contract commencement in May 2012, completion of works in May 2018, and meeting milestones such as starting concrete works, completing structures, and making the navigation locks operational through 2018. The entire project was completed by August 2018.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
0% found this document useful (0 votes)
59 views

Schedule For Dam

This document provides a schedule for implementation of the New Assiut Barrage and Hydropower Plant project from 2012 to 2019. It lists activities, start and end dates, and milestones. The key activities include contract commencement in May 2012, completion of works in May 2018, and meeting milestones such as starting concrete works, completing structures, and making the navigation locks operational through 2018. The entire project was completed by August 2018.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
You are on page 1/ 19

New Assiut Barrage and Hydropower Plant Schedule Impletation Programme 12-Oct-18 13:45

Activity ID Activity Name Actual Actual Start Actual Finish The 2012 2013 2014 2015 2016 2017 2018 2019
Duration Contractor
M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M
New Assiut B
Barrage and Hydropower Plant 1900 02-May-12 A 02-Aug-18 A 02-Aug-18 A, New Assiut B

GENERAL 1900 02-May-12 02-Aug-18 A 02-Aug-18 A, GENERAL


A
MILESTONES 1900 02-May-12 02-Aug-18 A 02-Aug-18 A, MILESTONE
A
General 2203 02-May-12 14-May-18 A 14-May-18 A, General
230 Contract Commencement Lot 1 - Civil Works 0 A
02-May-12 AC.Lot 1 Contract Commencement Lot 1 - Civil Works, 02-May-12 A
A
231 Completion of Works 0 14-May-18 A AC.Lot 1 Completion of Works,
MILESTONE LOT 1
MILESTONES 1663 01-Oct-12 A 28-Mar-18 A 28-Mar-18 A, MILESTONES LOT 1
234 MS 1-01: Subm. of Loading-/ Foundation-/ Arrangemen 0 01-Oct-12 A AC.Lot 1 MS 1-01: Subm. of Loading-/ Foundation-/ Arrangement. / Layout Drawings, 01-Oct-12 A
235 MS 1-02: Starting of NL Concrete Works (Revised) 0 01-Oct-13 A AC.Lot 1 MS 1-02: Starting of NL Concrete Works (Revised), 01-Oct-13 A
233 MS 1-00: Completing of Housing Compound 0 01-Jan-14 A AC.Lot 1 MS 1-00: Completing of Housing Compound,
236 MS 1-03: PH-Unit 1, Step 1 Concrete Works complete 0 03-Dec-14 A AC.Lot 1 MS 1-03: PH-Unit 1, Step 1 Concrete Works complete,
238 MS 1-05: PH-Unit 1, Step 2 Concrete Works complete 0 03-Jul-15 A AC.Lot 1 MS 1-05: PH-Unit 1, Step 2 Concrete Works complete,
237 MS 1-04: SLW- Abutment & Standard Pier Axis 06 Firs 0 16-Jul-15 A AC.Lot 1 MS 1-04: SLW- Abutment & Standard Pier Axis 06 First Stage Concrete Works complete (Revised New Sequence),
240 MS 1-07: Main Gantry Crane Traffic Way passable 0 21-Feb-16 AC.Lot 1 MS 1-07: Main Gantry Crane Traffic Way passable, 21-Feb-16 A
A
239 MS 1-06: PH-Unit 4, Step 3 Concrete Works complete 0 25-May-16 A AC.Lot 1 MS 1-06: PH-Unit 4, Step 3 Concrete Works complete,
242 MS 1-09: All structures ready for impounding 0 13-Jun-16 A AC.Lot 1 MS 1-09: All structures ready for impounding, 13-Jun-16 A
241 MS 1-08: PH Units 1 & 2, u/s Trans. Zone 2nd Stage C 0 08-Aug-16 A AC.Lot 1 MS 1-08: PH Units 1 & 2, u/s Trans. Zone 2nd Stage Concrete complete (El 45.15),
244 MS 1-11: PH Units 3 & 4, u/s Trans. Zone 2nd Stage C 0 01-Sep-16 A AC.Lot 1 MS 1-11: PH Units 3 & 4, u/s Trans. Zone 2nd Stage Concrete complete,
245 MS 1-12: Switchyard Foundation Works complete 0 12-Jan-17 A AC.Lot 1 MS 1-12: Switchyard Foundation Works complete,
243 MS 1-10 (1): Navigation Locks operational (revised ac 0 23-Nov-17 A AC.Lot 1 MS 1-10 (1): Navigation Locks operational (revised acc. T
A2570 TOC for the whole of works 0 28-Mar-18 A AC.Lot 1 TOC for the whole of works,
MILESTONE LOT 2
MILESTONES 1662 01-Oct-12 A 26-Mar-18 A 26-Mar-18 A, MILESTONES LOT 2
247 MS 2-01: Subm. of Loading-/ Found.-/ Arr.-/ Layout Dr 0 01-Oct-12 A AC.Lot 2 MS 2-01: Subm. of Loading-/ Found.-/ Arr.-/ Layout Draw.
248 MS 2-02: Ready for Impounding 0 13-Jun-16 A AC.Lot 2 MS 2-02: Ready for Impounding
250 MS 2-03 : Navigation Locks operational (requested by 0 23-Nov-17 A AC.Lot 2 MS 2-03 : Navigation Locks operational (requested by RG
A2580 TOC for the whole of works 0 26-Mar-18 A AC.Lot 2 TOC for the whole of works
MILESTONE LOT 3
MILESTONES 1772 01-Oct-12 A 02-Aug-18 A 02-Aug-18 A, MILESTONE
252 MS 3-01: Subm. of Loading-/ Found.-/ Arr.-/ Layout Dr 0 01-Oct-12 A AC.Lot 3 MS 3-01: Subm. of Loading-/ Found.-/ Arr.-/ Layout Draw.
253 MS 3-02: Unit 1&2 Draft Tube Erec. ready for Step 2 C 0 30-Jan-15 A AC.Lot 3 MS 3-02: Unit 1&2 Draft Tube Erec. ready for Step 2 Concr. Works
254 MS 3-03: Unit 3&4 Draft Tube Erec. ready for Step 2 C 0 01-Apr-15 A AC.Lot 3 MS 3-03: Unit 3&4 Draft Tube Erec. ready for Step 2 Concr. Works
255 MS 3-04: Unit 1&2 Stayring Inst. ready for 2nd Stage C 0 30-Jan-16 A AC.Lot 3 MS 3-04: Unit 1&2 Stayring Inst. ready for 2nd Stage Concrete
256 MS 3-05: Unit 3&4 Stayring Inst. ready for 2nd Stage C 0 01-May-16 AC.Lot 3 MS 3-05: Unit 3&4 Stayring Inst. ready for 2nd Stage Concrete
A
257 MS 3-06: Ready for Impounding 0 31-May-16 AC.Lot 3 MS 3-06: Ready for Impounding
A
A2600 TOC for the whole of works 0 02-Aug-18 A AC.Lot 3 TOC for the whole of works
MS 3-07: Operational Acceptance Certificate 80 24-Mar-18 12-Jun-18 A 12-Jun-18 A, MS 3-07: Operation
260 MS 3-07.2: Turbine & Generator and common equipme 0 A
24-Mar-18 AC.Lot 3 MS 3-07.2: Turbine & Generator and comm
A
261 MS 3-07.3: Turbine & Generator and common equipme 0 02-Apr-18 A AC.Lot 3 MS 3-07.3: Turbine & Generator and comm
262 MS 3-07.4: Turbine & Generator and common equipme 0 18-Apr-18 A AC.Lot 3 MS 3-07.4: Turbine & Generator and com
259 MS 3-07.1: Turbine & Generator and common equipme 0 12-Jun-18 A AC.Lot 3 MS 3-07.1: Turbine & Generator a
MILESTONE LOT 4
MILESTONES 1773 01-Oct-12 A 02-Aug-18 A 02-Aug-18 A, MILESTONE
264 MS 4-01: Subm. of Loading-/ Found.-/ Arr.-/ Layout Dr 0 01-Oct-12 A AC.Lot 4 MS 4-01: Subm. of Loading-/ Found.-/ Arr.-/ Layout Draw.
265 MS 4-02: Ready for Impounding 0 31-May-16 AC.Lot 4 MS 4-02: Ready for Impounding
A
268 MS 4-04: Ready for Testing/ Commissioning and Trial 0 19-Nov-17 AC.Lot 4 MS 4-04: Ready for Testing/ Commissioning and Trial Oper
A
267 MS 4-03 : Navigation Locks operational (requested by 0 23-Nov-17 A AC.Lot 4 MS 4-03 : Navigation Locks operational (requested by RG
A2590 TOC for the whole of works 0 02-Aug-18 A AC.Lot 4 TOC for the whole of works
TAREGT DATES
DAT 1639 01-Oct-12 A 28-Feb-18 A 28-Feb-18 A, TAREGT DATES
TARGET DA
DATES LOT 1 1403 15-Jul-13 A 28-Feb-18 A 28-Feb-18 A, TARGET DATES LOT 1
DIAPHRAGM WALLS & CUT-OFF WALLS
DIAPHRA 0 15-Jul-13 A 15-Jul-13 A 15-Jul-13 A, DIAPHRAGM WALLS & CUT-OFF WALLS
5 TD 101:Start to Trenching for Permanent COW 0 15-Jul-13 A AC.Lot 1 TD 101:Start to Trenching for Permanent COW, 15-Jul-13 A
NAVIGAT
NAVIGATION LOCK 1019 01-Jun-14 A 09-Oct-17 A 09-Oct-17 A, NAVIGATION LOCK
7 TD 102:u/s Head ready for fixed Parts installation 0 01-Jun-14 A AC.Lot 1 TD 102:u/s Head ready for fixed Parts installation, 01-Jun-14 A
8 TD 104: d/s Head ready for fixed Parts installation 0 17-Jul-14 A AC.Lot 1 TD 104: d/s Head ready for fixed Parts installation, 17-Jul-14 A
10 TD 109: Approach Area su/s completed 0 27-Apr-17 A AC.Lot 1 TD 109: Approach Area su/s completed,
11 TD 110: Removal of Old Barrage Parts complete (rev 0 09-Oct-17 A AC.Lot 1 TD 110: Removal of Old Barrage Parts complete (revised acc.
SLUICEW
SLUICEWAY 792 14-Apr-14 A 03-Dec-16 A 03-Dec-16 A, SLUICEWAY
ABUTMENT PIER, AXIS 1
ABUT 0 16-Apr-15 A 16-Apr-15 A 16-Apr-15 A, ABUTMENT PIER, AXIS 1
46 TD 213: Main Gantry Crane Extension Beams Comple 0 16-Apr-15 A AC.Lot 1 TD 213: Main Gantry Crane Extension Beams Complete,
SLUIC
SLUICEWAY, AXES 1-6 558 14-Apr-14 A 21-Feb-16 A 21-Feb-16 A, SLUICEWAY, AXES 1-6
65 TD 224: Pier 6, Axis 6, Access Lot 2, Trunnion Erectio 0 14-Apr-14 A AC.Lot 1 TD 224: Pier 6, Axis 6, Access Lot 2, Trunnion Erection, 14-Apr-14 A
60 TD 201:Start SLW-Axes 01-06 Concrete Works 0 03-Aug-14 AC.Lot 1 TD 201:Start SLW-Axes 01-06 Concrete Works, 03-Aug-14 A
A
61 TD 205: Pier 1, Axis 1, Access Lot 2, Trunnion Erectio 0 18-Dec-14 AC.Lot 1 TD 205: Pier 1, Axis 1, Access Lot 2, Trunnion Erection, 18-Dec-14 A
A
64 TD 208: Pier 2, Axis 2, Access Lot 2, Trunnion Erectio 0 30-Dec-14 AC.Lot 1 TD 208: Pier 2, Axis 2, Access Lot 2, Trunnion Erection, 30-Dec-14 A
A
62 TD 211: Pier 3, Axis 3, Access Lot 2, Trunnion Erectio 0 07-Feb-15 AC.Lot 1 TD 211: Pier 3, Axis 3, Access Lot 2, Trunnion Erection, 07-Feb-15 A
A
66 TD 219: Pier 5, Axis 5, Access Lot 2, Trunnion Erectio 0 24-Mar-15 AC.Lot 1 TD 219: Pier 5, Axis 5, Access Lot 2, Trunnion Erection, 24-Mar-15 A
A
63 TD 216: Pier 4, Axis 4, Access Lot 2, Trunnion Erectio 0 21-Feb-16 AC.Lot 1 TD 216: Pier 4, Axis 4, Access Lot 2, Trunnion Erection, 21-Feb-16 A
A
ABUT
ABUTMENT PIER, AXIS 16 0 21-Feb-16 21-Feb-16 A 21-Feb-16 A, ABUTMENT PIER, AXIS 16
44 TD 270: Auxiliary Building concrete Works complete 0 21-Feb-16 A AC.Lot 1 TD 270: Auxiliary Building concrete Works complete,
SLUIC
SLUICEWAY, AXES 13-16 225 17-Sep-14 16-Jun-15 A 16-Jun-15 A, SLUICEWAY, AXES 13-16
48 TD 202:Start SLW-Axes 13-16 Concrete Works 0 17-Sep-14 AC.Lot 1 TD 202:Start SLW-Axes 13-16 Concrete Works, 17-Sep-14 A
A
49 TD 204: Pier 9, Axis 15, Access Lot 2, Trunnion Erecti 0 15-Mar-15 AC.Lot 1 TD 204: Pier 9, Axis 15, Access Lot 2, Trunnion Erection, 15-Mar-15 A
A
52 TD 203: Pier 10, Axis 16, Access Lot 2, Trunnion Erec 0 15-Mar-15 AC.Lot 1 TD 203: Pier 10, Axis 16, Access Lot 2, Trunnion Erection, 15-Mar-15 A
A
50 TD 206: Pier 8, Axis 14, Access Lot 2, Trunnion Erecti 0 17-May-15 AC.Lot 1 TD 206: Pier 8, Axis 14, Access Lot 2, Trunnion Erection, 17-May-15 A
A
51 TD 209: Pier 7, Axis 13, Access Lot 2, Trunnion Erecti 0 16-Jun-15 A AC.Lot 1 TD 209: Pier 7, Axis 13, Access Lot 2, Trunnion Erection, 16-Jun-15 A
BAY 1,
1 AXES 1-2 199 29-Mar-15 28-Nov-15 A 28-Nov-15 A, BAY 1, AXES 1-2
A
Milestone Lot 1 Lot 2 Page 1 of 19
Milestone Lot 2 Lot 3
Milestone Lot 3 Lot 4
Milestone Lot 4 Remaining Work
Lot 1 Critical Remaining Work
New Assiut Barrage and Hydropower Plant Schedule Impletation Programme 12-Oct-18 13:45

Activity ID Activity Name Actual Actual Start Actual Finish The 2012 2013 2014 2015 2016 2017 2018 2019
Duration Contractor
M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M
20 TD 217: Bay 1, Axes 1-2, Access Lot 2, fixed Parts Ins 0 29-Mar-15 AC.Lot 1 TD 217: Bay 1, Axes 1-2, Access Lot 2, fixed Parts Installation, 29-Mar-15 A
A
18 TD 243: Bay 1 Start of SLW Gantry Crane u/s Beam (r 0 03-Sep-15 AC.Lot 1 TD 243: Bay 1 Start of SLW Gantry Crane u/s Beam (revised Sequence), 03-Sep-15 A
A
19 TD 233: Bay 1, 2nd Stage Concrete Works complete 0 28-Nov-15 AC.Lot 1 TD 233: Bay 1, 2nd Stage Concrete Works complete, 28-Nov-15 A
A
BAY 2,
2 AXES 2-3 126 03-May-15 03-Oct-15 A 03-Oct-15 A, BAY 2, AXES 2-3
14 TD 221: Bay 2, Axes 2-3, Access Lot 2, fixed Parts Ins 0 03-May-15 AC.Lot 1 TD 221: Bay 2, Axes 2-3, Access Lot 2, fixed Parts Installation, 03-May-15 A
A
15 TD 242: Bay 2, 2nd Stage Concrete Works complete ( 0 13-May-15 AC.Lot 1 TD 242: Bay 2, 2nd Stage Concrete Works complete (revised Sequence), 13-May-15 A
A
16 TD 251: Bay 2, Start of SLW Gantry Crane u/s Beam ( 0 03-Oct-15 A AC.Lot 1 TD 251: Bay 2, Start of SLW Gantry Crane u/s Beam (revised Sequence), 03-Oct-15 A
BAY 3,
3 AXES 3-4 158 02-Nov-15 10-May-16 A 10-May-16 A, BAY 3, AXES 3-4
23 TD 257: Bay 3, Start of SLW Gantry Crane u/s Beam 0 A
02-Nov-15 AC.Lot 1 TD 257: Bay 3, Start of SLW Gantry Crane u/s Beam, 02-Nov-15 A
A
24 TD 250: Bay 3,2nd Stage Concrete Works complete 0 18-Apr-16 A AC.Lot 1 TD 250: Bay 3,2nd Stage Concrete Works complete,
22 TD 226: Bay 3, Axes 3-4, Access Lot 2, fixed Parts Ins 0 10-May-16 AC.Lot 1 TD 226: Bay 3, Axes 3-4, Access Lot 2, fixed Parts Installation, 10-May-16 A
A
BAY 4,
4 AXES 4-5 179 25-Apr-16 A 03-Dec-16 A 03-Dec-16 A, BAY 4, AXES 4-5
57 TD 256: Bay4, 2nd Stage Concrete Works complete 0 25-Apr-16 A AC.Lot 1 TD 256: Bay4, 2nd Stage Concrete Works complete,
55 TD 235: Bay 4, Axes 4-5, Access Lot 2, fixed Parts Ins 0 06-Jun-16 A AC.Lot 1 TD 235: Bay 4, Axes 4-5, Access Lot 2, fixed Parts Installation, 06-Jun-16 A
56 TD 262: Bay 4, Start of SLW Gantry Crane u/s Beam ( 0 03-Dec-16 AC.Lot 1 TD 262: Bay 4, Start of SLW Gantry Crane u/s Beam (revised Sequence), 03-Dec-16 A
A
BAY 5,
5 AXES 5-6 468 08-May-15 28-Nov-16 A 28-Nov-16 A, BAY 5, AXES 5-6
33 TD 261: Bay 5 , 2nd Stage Concrete Works complete 0 08-May-15 A AC.Lot 1 TD 261: Bay 5 , 2nd Stage Concrete Works complete,
30 TD 245: Bay 5, Axes 5-6, Access Lot 2, fixed Parts Ins 0 02-Sep-15 AC.Lot 1 TD 245: Bay 5, Axes 5-6, Access Lot 2, fixed Parts Installation, 02-Sep-15 A
A
31 TD 266: Bay 5, Start of SLW Gantry Crane u/s Beam ( 0 03-Jan-16 A AC.Lot 1 TD 266: Bay 5, Start of SLW Gantry Crane u/s Beam (revised Sequence), 03-Jan-16 A
32 TD 269: Bays 1-5, Gantry Crane Beams ready for Rail 0 28-Nov-16 AC.Lot 1 TD 269: Bays 1-5, Gantry Crane Beams ready for Rail Installation (revised Sequence), 28-Nov-16 A
A
BAY 6,
6 AXES 13-14 388 21-May-15 02-Sep-16 A 02-Sep-16 A, BAY 6, AXES 13-14
40 TD 237:Bay6, 2nd Stage Concrete Works complete 0 21-May-15 A AC.Lot 1 TD 237:Bay6, 2nd Stage Concrete Works complete,
39 TD 248 : Bay6, Start of SLW Gantry Crane u/s Beam 0 17-Oct-15 A AC.Lot 1 TD 248 : Bay6, Start of SLW Gantry Crane u/s Beam, 17-Oct-15 A
42 TD 253: Bays 6-8 Gantry Crane Beams Ready for Rai 0 21-Feb-16 AC.Lot 1 TD 253: Bays 6-8 Gantry Crane Beams Ready for Rail Installation, 21-Feb-16 A
A
41 TD 218: Bay 6, Axes 13-14, Access Lot 2, fixed Parts 0 02-Sep-16 AC.Lot 1 TD 218: Bay 6, Axes 13-14, Access Lot 2, fixed Parts Installation, 02-Sep-16 A
A
BAY 7,
7 AXES 14-15 104 12-May-15 13-Sep-15 A 13-Sep-15 A, BAY 7, AXES 14-15
26 TD 228: Bay7,2nd Stage Concrete Works complete 0 A 12-May-15 A AC.Lot 1 TD 228: Bay7,2nd Stage Concrete Works complete,
28 TD 215: Bay 7, Axes 14-15, Access Lot 2, fixed Parts 0 02-Aug-15 AC.Lot 1 TD 215: Bay 7, Axes 14-15, Access Lot 2, fixed Parts Installation, 02-Aug-15 A
A
27 TD 239:Bay7,Start of SLW Gantry Cran/S Beam 0 13-Sep-15 AC.Lot 1 TD 239:Bay7,Start of SLW Gantry Cran/S Beam, 13-Sep-15 A
A
BAY 8,
8 AXES 15-16 139 11-May-15 28-Oct-15 A 28-Oct-15 A, BAY 8, AXES 15-16
36 TD 222: Bay 8, 2nd Stage Concrete Works complete 0 A 11-May-15 A AC.Lot 1 TD 222: Bay 8, 2nd Stage Concrete Works complete,
35 TD 210: Bay 8, Axes 15-16, Access Lot 2, fixed Parts 0 01-Jun-15 A AC.Lot 1 TD 210: Bay 8, Axes 15-16, Access Lot 2, fixed Parts Installation, 01-Jun-15 A
37 TD 230: Bay 8, Start of SLW Gantry Crane u/s Beam 0 28-Oct-15 A AC.Lot 1 TD 230: Bay 8, Start of SLW Gantry Crane u/s Beam, 28-Oct-15 A
POWERH
POWERHOUSE 631 23-Jul-14 A 28-Aug-16 A 28-Aug-16 A, POWERHOUSE
Unit-1 576 23-Jul-14 A 21-Jun-16 A 21-Jun-16 A, Unit-1
69 TD 301: Start U1 First Stage Concrete Works 0 23-Jul-14 A AC.Lot 1 TD 301: Start U1 First Stage Concrete Works, 23-Jul-14 A
70 TD 315: U1, Step 2a (Inlet Part u/s Axis B) Concrete W 0 12-Sep-15 A AC.Lot 1 TD 315: U1, Step 2a (Inlet Part u/s Axis B) Concrete Works completed,
72 TD 329: Start U1 u/s Transition Zone Concrete Works 0 02-Feb-16 AC.Lot 1 TD 329: Start U1 u/s Transition Zone Concrete Works up to EL. 42.10, 02-Feb-16 A
A
A11 TD 324: U1, Step 3 (Draft Tube d/s Axis C) Concrete 0 05-Mar-16 A AC.Lot 1 TD 324: U1, Step 3 (Draft Tube d/s Axis C) Concrete Works completed,
73 TD 346: U1 u/s Transition Zone Concrete Works up to 0 21-Jun-16 A AC.Lot 1 TD 346: U1 u/s Transition Zone Concrete Works up to EL. 42.10 completed,
Unit-2 596 04-Aug-14 26-Jul-16 A 26-Jul-16 A, Unit-2
A11 TD 302: Start U2 First Stage Concrete Works 0 04-Aug-14 AC.Lot 1 TD 302: Start U2 First Stage Concrete Works, 04-Aug-14 A
A
A11 TD 306: U2, Step 1 (Draft Tube Steel Liner Foundation 0 18-Dec-14 AC.Lot 1 TD 306: U2, Step 1 (Draft Tube Steel Liner Foundation) Concrete Works completed, 18-Dec-14 A
A
A11 TD 313: U2, Step 2 (Central Part Axes B-C) Concrete 0 19-Aug-15 A AC.Lot 1 TD 313: U2, Step 2 (Central Part Axes B-C) Concrete Works completed,
A11 TD 316: U2, Step 2a (Inlet Part u/s Axis B) Concrete W 0 11-Oct-15 A AC.Lot 1 TD 316: U2, Step 2a (Inlet Part u/s Axis B) Concrete Works completed,
A12 TD 344: Start U2 u/s Transition Zone Concrete Works 0 01-Feb-16 AC.Lot 1 TD 344: Start U2 u/s Transition Zone Concrete Works up to EL. 42.10, 01-Feb-16 A
A
A12 TD 352: U2 u/s Transition Zone Concrete Works up to 0 17-Jul-16 A AC.Lot 1 TD 352: U2 u/s Transition Zone Concrete Works up to EL. 42.10 completed ( revised ),
A11 TD 326: U2, Step 3 (Draft Tube d/s Axis C) Concrete 0 26-Jul-16 A AC.Lot 1 TD 326: U2, Step 3 (Draft Tube d/s Axis C) Concrete Works completed,
Unit-3 598 25-Aug-14 17-Aug-16 A 17-Aug-16 A, Unit-3
A12 TD 303: Start U3 First Stage Concrete Works 0 25-Aug-14 AC.Lot 1 TD 303: Start U3 First Stage Concrete Works, 25-Aug-14 A
A
A12 TD 308: U3, Step 1 (Draft Tube Steel Liner Foundation 0 29-Jan-15 A AC.Lot 1 TD 308: U3, Step 1 (Draft Tube Steel Liner Foundation) Concrete Works completed,
A12 TD 331: U3, Step 2a (Inlet Part u/s Axis B) Concrete W 0 13-Dec-15 A AC.Lot 1 TD 331: U3, Step 2a (Inlet Part u/s Axis B) Concrete Works completed,
A12 TD 317: U3, Step 2 (Central Part Axes B-C) Concrete 0 10-Jan-16 A AC.Lot 1 TD 317: U3, Step 2 (Central Part Axes B-C) Concrete Works completed,
A12 TD 349: Start U3 u/s Transition Zone Concrete Works 0 12-Apr-16 A AC.Lot 1 TD 349: Start U3 u/s Transition Zone Concrete Works up to EL. 42.10, 12-Apr-16 A
A12 TD 341: U3, Step 3 (Draft Tube d/s Axis C) Concrete 0 25-May-16 A AC.Lot 1 TD 341: U3, Step 3 (Draft Tube d/s Axis C) Concrete Works completed,
A12 TD 355: U3 u/s Transition Zone Concrete Works up to 0 17-Aug-16 A AC.Lot 1 TD 355: U3 u/s Transition Zone Concrete Works up to EL. 42.10 completed,
Unit-4 599 02-Sep-14 28-Aug-16 A 28-Aug-16 A, Unit-4
A12 TD 304: Start U4 First Stage Concrete Works 0 02-Sep-14 AC.Lot 1 TD 304: Start U4 First Stage Concrete Works, 02-Sep-14 A
A
A13 TD 310: U4, Step 1 (Draft Tube Steel Liner Foundation 0 13-Sep-15 A AC.Lot 1 TD 310: U4, Step 1 (Draft Tube Steel Liner Foundation) Concrete Works completed,
A13 TD 332: U4, Step 2a (Inlet Part u/s Axis B) Concrete W 0 31-Jan-16 A AC.Lot 1 TD 332: U4, Step 2a (Inlet Part u/s Axis B) Concrete Works completed,
A13 TD 320: U4, Step 2 (Central Part Axes B-C) Concrete 0 11-Feb-16 A AC.Lot 1 TD 320: U4, Step 2 (Central Part Axes B-C) Concrete Works completed,
A13 TD 354: Start U4 u/s Transition Zone Concrete Works 0 01-May-16 AC.Lot 1 TD 354: Start U4 u/s Transition Zone Concrete Works up to EL. 42.10, 01-May-16 A
A
A13 MS 1-06: PH-Unit 4, Step 3 Concrete Works complete 0 25-May-16 A AC.Lot 1 MS 1-06: PH-Unit 4, Step 3 Concrete Works complete,
A13 TD 359: U4 u/s Transition Zone Concrete Works up to 0 28-Aug-16 A AC.Lot 1 TD 359: U4 u/s Transition Zone Concrete Works up to EL. 42.10 completed,
GANT
GANTRY CRANES, TRASH R.C.& JIP CRANE 0 24-Jun-15 A 24-Jun-15 A 24-Jun-15 A, GANTRY CRANES, TRASH R.C.& JIP CRANE
98 TD 312: Crane Runway Axes 6-8 ready for Rail Installa 0 24-Jun-15 A AC.Lot 1 TD 312: Crane Runway Axes 6-8 ready for Rail Installation, 24-Jun-15 A
PUBLIC B
BRIDGE AND PUBLIC ROAD 628 13-Feb-16 28-Feb-18 A 28-Feb-18 A, PUBLIC BRIDGE AND PUBLIC R
59 TD 264: Public road Bridge Axes 01-06 complete (revi 0 A 13-Feb-16 A AC.Lot 1 TD 264: Public road Bridge Axes 01-06 complete (revised Sequence),
53 TD 271: Public road Bridge Axes13-16 complete (revis 0 02-Apr-16 A AC.Lot 1 TD 271: Public road Bridge Axes13-16 complete (revised Sequence),
9 TD 107 : Public road Bridge from Right Bridge Abutme 0 17-Sep-16 A AC.Lot 1 TD 107 : Public road Bridge from Right Bridge Abutment to Axis 16 complete,
A1390 Connection between Temp. Road and Existing East R 0 21-Jul-17 A AC.Lot 1 Connection between Temp. Road and Existing East Road to be completed
A1400 Connection between Permanent Road and Existing ro 0 28-Feb-18 AC.Lot 1 Connection between Permanent Road and Ex
A
TARGET DA
DATES LOT 2 1210 01-Oct-12 A 15-Oct-16 A 15-Oct-16 A, TARGET DATES LOT 2
Design a
and Fabrication 0 01-Oct-12 A 01-Oct-12 A 01-Oct-12 A, Design and Fabrication

Milestone Lot 1 Lot 2 Page 2 of 19


Milestone Lot 2 Lot 3
Milestone Lot 3 Lot 4
Milestone Lot 4 Remaining Work
Lot 1 Critical Remaining Work
New Assiut Barrage and Hydropower Plant Schedule Impletation Programme 12-Oct-18 13:45

Activity ID Activity Name Actual Actual Start Actual Finish The 2012 2013 2014 2015 2016 2017 2018 2019
Duration Contractor
M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M
137 TD 001: Lot 2, 1st stage concrete embedded parts av 0 01-Oct-12 A AC.Lot 2 TD 001: Lot 2, 1st stage concrete embedded parts available at Site
SLUICEW
SLUICEWAY 318 15-Dec-14 03-Jan-16 A 03-Jan-16 A, SLUICEWAY
General
Gener 77 15-Mar-15 16-Jun-15 A 16-Jun-15 A, General
A14 TD 203: Pier 10, Axis 16, Access Lot 2, Trunnion Erec 0 15-Mar-15A AC.Lot 2 TD 203: Pier 10, Axis 16, Access Lot 2, Trunnion Erection
A
A14 TD 204: Pier 09, Axis 15, Access Lot 2, Trunnion Erec 0 15-Mar-15 AC.Lot 2 TD 204: Pier 09, Axis 15, Access Lot 2, Trunnion Erection
A
A14 TD 206: Pier 08, Axis 14, Access Lot 2, Trunnion Erec 0 17-May-15 AC.Lot 2 TD 206: Pier 08, Axis 14, Access Lot 2, Trunnion Erection
A
A14 TD 209: Pier 07, Axis 13, Access Lot 2, Trunnion Erec 0 16-Jun-15 A AC.Lot 2 TD 209: Pier 07, Axis 13, Access Lot 2, Trunnion Erection
SLUIC
SLUICEWAY, AXES 1-6 100 15-Dec-14 15-Apr-15 A 15-Apr-15 A, SLUICEWAY, AXES 1-6
A14 TD 205: Pier 1, Axis 1, Access Lot 2, Trunnion Erectio 0 15-Dec-14 AC.Lot 2 TD 205: Pier 1, Axis 1, Access Lot 2, Trunnion Erection (revised Sequence)
A
A14 TD 208: Pier 2, Axis 2, Access Lot 2, Trunnion Erectio 0 15-Dec-14 AC.Lot 2 TD 208: Pier 2, Axis 2, Access Lot 2, Trunnion Erection (revised Sequence)
A
A14 TD 211: Pier 3, Axis 3, Access Lot 2, Trunnion Erectio 0 14-Jan-15 A AC.Lot 2 TD 211: Pier 3, Axis 3, Access Lot 2, Trunnion Erection (revised Sequence)
A14 TD 216: Pier 4, Axis 4, Access Lot 2, Trunnion Erectio 0 15-Feb-15 AC.Lot 2 TD 216: Pier 4, Axis 4, Access Lot 2, Trunnion Erection (revised Sequence)
A
A14 TD 219: Pier 5, Axis 5, Access Lot 2, Trunnion Erectio 0 15-Mar-15 AC.Lot 2 TD 219: Pier 5, Axis 5, Access Lot 2, Trunnion Erection (revised Sequence)
A
A15 TD 224: Pier 6, Axis 6, Access Lot 2, Trunnion Erectio 0 15-Apr-15 A AC.Lot 2 TD 224: Pier 6, Axis 6, Access Lot 2, Trunnion Erection (revised Sequence)
SLUIC
SLUICEWAY, AXES 13-16 77 15-Mar-15 16-Jun-15 A 16-Jun-15 A, SLUICEWAY, AXES 13-16
A18 TD 203: Pier 10, Axis 16, Access Lot 2, Trunnion Erec 0 15-Mar-15A AC.Lot 2 TD 203: Pier 10, Axis 16, Access Lot 2, Trunnion Erection
A
A18 TD 204: Pier 09, Axis 15, Access Lot 2, Trunnion Erec 0 15-Mar-15 AC.Lot 2 TD 204: Pier 09, Axis 15, Access Lot 2, Trunnion Erection
A
A18 TD 206: Pier 08, Axis 14, Access Lot 2, Trunnion Erec 0 17-May-15 AC.Lot 2 TD 206: Pier 08, Axis 14, Access Lot 2, Trunnion Erection
A
A19 TD 209: Pier 07, Axis 13, Access Lot 2, Trunnion Erec 0 16-Jun-15 A AC.Lot 2 TD 209: Pier 07, Axis 13, Access Lot 2, Trunnion Erection
Bay 1, AXES 1-2 154 01-Mar-15 02-Sep-15 A 02-Sep-15 A, Bay 1, AXES 1-2
A15 TD 217: Bay 1, Access Lot 2, fixed Parts Installation (r 0 01-Mar-15 AC.Lot 2 TD 217: Bay 1, Access Lot 2, fixed Parts Installation (revised Sequence)
A
A15 TD 229: Bay 1, Axes 1-2, fixed Parts Installation Comp 0 16-Apr-15 A AC.Lot 2 TD 229: Bay 1, Axes 1-2, fixed Parts Installation Complete (revised Sequence)
A15 TD 234: Bay 1, Start of Radial Gate Erection (revised S 0 16-May-15 AC.Lot 2 TD 234: Bay 1, Start of Radial Gate Erection (revised Sequence)
A
A15 TD 241: Bay 1, Radial Gate Erection Complete (revise 0 16-Jun-15 A AC.Lot 2 TD 241: Bay 1, Radial Gate Erection Complete (revised Sequence)
A15 TD 243: Bay 1 Start of SLW Gantry Crane u/s Beam (r 0 02-Sep-15 AC.Lot 2 TD 243: Bay 1 Start of SLW Gantry Crane u/s Beam (revised Sequence)
A
Bay 2, AXES 2-3 91 30-Mar-15 19-Jul-15 A 19-Jul-15 A, Bay 2, AXES 2-3
A15 TD 221: Bay 2, Access Lot 2, fixed Parts Installation (r 0 30-Mar-15A AC.Lot 2 TD 221: Bay 2, Access Lot 2, fixed Parts Installation (revised Sequence)
A
A15 TD 238: Bay 2, Axes 2-3, fixed Parts Installation Comp 0 16-May-15 AC.Lot 2 TD 238: Bay 2, Axes 2-3, fixed Parts Installation Complete (revised Sequence)
A
A15 TD 244: Bay 2, Start of Radial Gate Erection (revised S 0 16-Jun-15 A AC.Lot 2 TD 244: Bay 2, Start of Radial Gate Erection (revised Sequence)
A15 TD 249: Bay 2, Radial Gate Erection Complete (revise 0 19-Jul-15 A AC.Lot 2 TD 249: Bay 2, Radial Gate Erection Complete (revised Sequence)
Bay 3, AXES 3-4 89 02-May-15 16-Aug-15 A 16-Aug-15 A, Bay 3, AXES 3-4
A16 TD 226: Bay 3, Access Lot 2, fixed Parts Installation 0 02-May-15 AC.Lot 2 TD 226: Bay 3, Access Lot 2, fixed Parts Installation
A
A16 TD 247: Bay 3, Axes 3-4, fixed Parts Installation Comp 0 16-Jun-15 A AC.Lot 2 TD 247: Bay 3, Axes 3-4, fixed Parts Installation Complete
A16 TD 252: Bay 3, Start of Radial Gate Erection 0 16-Jul-15 A AC.Lot 2 TD 252: Bay 3, Start of Radial Gate Erection
A16 TD 255: Bay 3, Radial Gate Erection Complete 0 16-Aug-15 AC.Lot 2 TD 255: Bay 3, Radial Gate Erection Complete
A
Bay 4, AXES 4-5 91 31-May-15 16-Sep-15 A 16-Sep-15 A, Bay 4, AXES 4-5
A16 TD 235: Bay 4, Access Lot 2, fixed Parts Installation (r 0 31-May-15 AC.Lot 2 TD 235: Bay 4, Access Lot 2, fixed Parts Installation (revised Sequence)
A
A16 TD 254: Bay 4, Axes 4-5, fixed Parts Installation Comp 0 15-Jul-15 A AC.Lot 2 TD 254: Bay 4, Axes 4-5, fixed Parts Installation Complete (revised Sequence)
A16 TD 258: Bay 4, Start of Radial Gate Erection (revised S 0 16-Aug-15 AC.Lot 2 TD 258: Bay 4, Start of Radial Gate Erection (revised Sequence)
A
A16 TD 260: Bay 4, Radial Gate Erection Complete (revise 0 16-Sep-15 AC.Lot 2 TD 260: Bay 4, Radial Gate Erection Complete (revised Sequence)
A
Bay 5, AXES 5-6 90 29-Jun-15 A 20-Oct-15 A 20-Oct-15 A, Bay 5, AXES 5-6
A16 TD 245: Bay 5, Access Lot 2, fixed Parts Installation (r 0 29-Jun-15 A AC.Lot 2 TD 245: Bay 5, Access Lot 2, fixed Parts Installation (revised Sequence)
A16 TD 259: Bay 5, Axes 5-6, fixed Parts Installation Comp 0 15-Aug-15 AC.Lot 2 TD 259: Bay 5, Axes 5-6, fixed Parts Installation Complete (revised Sequence)
A
A17 TD 263: Bay 5, Start of Radial Gate Erection (revised S 0 15-Sep-15 AC.Lot 2 TD 263: Bay 5, Start of Radial Gate Erection (revised Sequence)
A
A17 TD 265: Bay 5, Radial Gate Erection Complete (revise 0 20-Oct-15 A AC.Lot 2 TD 265: Bay 5, Radial Gate Erection Complete (revised Sequence)
bay 6, AXES 13-14 101 02-Sep-15 03-Jan-16 A 03-Jan-16 A, bay 6, AXES 13-14
A17 TD 218: Bay 6, Axes 13-14, Access Lot 2, fixed Parts 0 02-Sep-15 AC.Lot 2 TD 218: Bay 6, Axes 13-14, Access Lot 2, fixed Parts Installation
A
A17 TD 232: Bay 6, Axes 13-14, fixed Parts Installation Co 0 09-Oct-15 A AC.Lot 2 TD 232: Bay 6, Axes 13-14, fixed Parts Installation Complete
A17 TD 240: Bay 6, Start of Radial Gate Erection 0 20-Nov-15 A AC.Lot 2 TD 240: Bay 6, Start of Radial Gate Erection
A17 TD 246: Bay 6, Radial Gate Erection Complete 0 24-Dec-15 A AC.Lot 2 TD 246: Bay 6, Radial Gate Erection Complete
A17 TD 253: Bays 6-8 Gantry Crane Beams Ready for Rai 0 03-Jan-16 A AC.Lot 2 TD 253: Bays 6-8 Gantry Crane Beams Ready for Rail Installation
Bay 7, AXES 14-15 103 24-Jul-15 A 26-Nov-15 A 26-Nov-15 A, Bay 7, AXES 14-15
A17 TD 215: Bay 7, Axes 15-16, Access Lot 2, fixed Parts 0 24-Jul-15 A AC.Lot 2 TD 215: Bay 7, Axes 15-16, Access Lot 2, fixed Parts Installation
A17 TD 231: Bay 7, Start of Radial Gate Erection 0 03-Sep-15 AC.Lot 2 TD 231: Bay 7, Start of Radial Gate Erection
A
A18 TD 239: Bay 7, Start of SLW Gantry Crane u/s Beam 0 13-Sep-15 AC.Lot 2 TD 239: Bay 7, Start of SLW Gantry Crane u/s Beam
A
A17 TD 225: Bay 7, Axes 14-15, fixed Parts Installation Co 0 17-Sep-15 A AC.Lot 2 TD 225: Bay 7, Axes 14-15, fixed Parts Installation Complete
A18 TD 236: Bay 7, Radial Gate Erection Complete 0 26-Nov-15 A AC.Lot 2 TD 236: Bay 7, Radial Gate Erection Complete
bay 8, AXES 15-16 94 01-Jun-15 A 21-Sep-15 A 21-Sep-15 A, bay 8, AXES 15-16
A18 TD 210: Bay 8, Axes 15-16, Access Lot 2, fixed Parts 0 01-Jun-15 A AC.Lot 2 TD 210: Bay 8, Axes 15-16, Access Lot 2, fixed Parts Installation
A18 TD 220: Bay 8, Axes 15-16, fixed Parts Installation Co 0 14-Jul-15 A AC.Lot 2 TD 220: Bay 8, Axes 15-16, fixed Parts Installation Complete
A18 TD 230: Bay 8, Start of SLW Gantry Crane u/s Beam 0 18-Jul-15 A AC.Lot 2 TD 230: Bay 8, Start of SLW Gantry Crane u/s Beam
A18 TD 223: Bay 8, Start of Radial Gate Erection 0 16-Aug-15 AC.Lot 2 TD 223: Bay 8, Start of Radial Gate Erection
A
A18 TD 227: Bay 8, Radial Gate Erection Complete 0 21-Sep-15 AC.Lot 2 TD 227: Bay 8, Radial Gate Erection Complete
A
GANT
GANTRY CRANES 191 17-May-15 03-Jan-16 A 03-Jan-16 A, GANTRY CRANES
A19 TD 207: Lot 2, Start of SLW-W Gantry Crane No. 01 E 0 17-May-15A AC.Lot 2 TD 207: Lot 2, Start of SLW-W Gantry Crane No. 01 Erection (on Abutment Pier Axis 01 & Extension Beams)
A
A19 TD 212: Lot 2, SLW-W Gantry Crane No. 01 Erection 0 30-Jul-15 A AC.Lot 2 TD 212: Lot 2, SLW-W Gantry Crane No. 01 Erection complete
A19 TD 269: Bays1-5, Gantry Crane Beams ready for Rail 0 01-Nov-15 AC.Lot 2 TD 269: Bays1-5, Gantry Crane Beams ready for Rail Installation
A
A19 TD 214: Start of SLW-E Gantry Crane No. 2 Erection 0 29-Nov-15 AC.Lot 2 TD 214: Start of SLW-E Gantry Crane No. 2 Erection
A
A19 TD 253: Bays 6-8 Gantry Crane Beams Ready for Rai 0 03-Jan-16 A AC.Lot 2 TD 253: Bays 6-8 Gantry Crane Beams Ready for Rail Installation
POWERH
POWERHOUSE 358 03-Aug-15 15-Oct-16 A 15-Oct-16 A, POWERHOUSE
Unit-1 27 03-Aug-15 03-Sep-15 A 03-Sep-15 A, Unit-1
199 TD 327: Lot 2, U1 Draft Tube Area, Start of fixed Part 0 A
03-Aug-15 AC.Lot 2 TD 327: Lot 2, U1 Draft Tube Area, Start of fixed Part Installation
A
198 TD 318: Lot 2 & 3, U1 Inlet Area, Start of fixed Part Ins 0 03-Sep-15 AC.Lot 2 TD 318: Lot 2 & 3, U1 Inlet Area, Start of fixed Part Installation
A
Unit-2 172 15-Mar-16 15-Oct-16 A 15-Oct-16 A, Unit-2
A

Milestone Lot 1 Lot 2 Page 3 of 19


Milestone Lot 2 Lot 3
Milestone Lot 3 Lot 4
Milestone Lot 4 Remaining Work
Lot 1 Critical Remaining Work
New Assiut Barrage and Hydropower Plant Schedule Impletation Programme 12-Oct-18 13:45

Activity ID Activity Name Actual Actual Start Actual Finish The 2012 2013 2014 2015 2016 2017 2018 2019
Duration Contractor
M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M
207 TD 319: Lot 2 & 3, U2 Inlet Area, Start of fixed Part Ins 0 15-Mar-16 AC.Lot 2 TD 319: Lot 2 & 3, U2 Inlet Area, Start of fixed Part Installation
A
208 TD 328: Lot 2, U2 Draft Tube Area, Start of fixed Part 0 15-Oct-16 A AC.Lot 2 TD 328: Lot 2, U2 Draft Tube Area, Start of fixed Part Installation
Unit-3 46 31-Jan-16 A 24-Mar-16 A 24-Mar-16 A, Unit-3
202 TD 342: Lot 2, U3 Draft Tube Area, Start of fixed Part 0 31-Jan-16 A AC.Lot 2 TD 342: Lot 2, U3 Draft Tube Area, Start of fixed Part Installation
201 TD 333: Lot 2 & 3, U3 Inlet Area, Start of fixed Part Ins 0 24-Mar-16 AC.Lot 2 TD 333: Lot 2 & 3, U3 Inlet Area, Start of fixed Part Installation
A
Unit-4 26 16-Jan-16 A 16-Feb-16 A 16-Feb-16 A, Unit-4
204 TD 334: Lot 2 & 3, U4 Inlet Area, Start of fixed Part Ins 0 16-Jan-16 A AC.Lot 2 TD 334: Lot 2 & 3, U4 Inlet Area, Start of fixed Part Installation
205 TD 343: Lot 2, U4 Draft Tube Area, Start of fixed Part 0 16-Feb-16 AC.Lot 2 TD 343: Lot 2, U4 Draft Tube Area, Start of fixed Part Installation
A
NAVIGAT
NAVIGATION LOCK 213 02-Jun-14 A 15-Feb-15 A 15-Feb-15 A, NAVIGATION LOCK
A1960 TD 103: Lot 2, Start of u/s Head fixed Part Installation 0 02-Jun-14 A AC.Lot 2 TD 103: Lot 2, Start of u/s Head fixed Part Installation
A1970 TD 105: Lot 2, Start of d/s Head fixed Part Installation 0 18-Jul-14 A AC.Lot 2 TD 105: Lot 2, Start of d/s Head fixed Part Installation
A1980 TD106: Start of NL Gantry Cranes Erection 0 15-Feb-15 AC.Lot 2 TD106: Start of NL Gantry Cranes Erection
A
TARGET DA
DATES LOT 3 1434 01-Oct-12 A 04-Jul-17 A 04-Jul-17 A, TARGET DATES LOT 3
Design a
and Fabrication 0 01-Oct-12 A 01-Oct-12 A 01-Oct-12 A, Design and Fabrication
101 TD 002: Lot 3, 1st stage concrete embedded parts av 0 01-Oct-12 A AC.Lot 3 TD 002: Lot 3, 1st stage concrete embedded parts available at Site
POWERH
POWERHOUSE 783 03-Dec-14 04-Jul-17 A 04-Jul-17 A, POWERHOUSE
Unit-1 636 03-Dec-14 13-Jan-17 A 13-Jan-17 A, Unit-1
A19 TD 305: Start DT Steel Liner U1 erection 0 A
03-Dec-14 AC.Lot 3 TD 305: Start DT Steel Liner U1 erection
A
A20 TD 318: Lot 2 & 3, U1 Inlet Area, Start of fixed Part Ins 0 02-Sep-15 AC.Lot 3 TD 318: Lot 2 & 3, U1 Inlet Area, Start of fixed Part Installation
A
104 TD 321: PH Main Gantry Crane operational 0 03-Oct-15 A AC.Lot 3 TD 321: PH Main Gantry Crane operational
A20 TD 327: Lot 2, U1 Draft Tube Area, Start of fixed Part 0 03-Dec-15 AC.Lot 3 TD 327: Lot 2, U1 Draft Tube Area, Start of fixed Part Installation
A
A20 TD 323: Stayring and Pier Nose U1 installation in pit ( r 0 15-Dec-15 AC.Lot 3 TD 323: Stayring and Pier Nose U1 installation in pit ( revised )
A
A20 TD 325: Stayring & Pier Nose U1 Installation in the pit 0 14-Jan-16 A AC.Lot 3 TD 325: Stayring & Pier Nose U1 Installation in the pit ready for concrete
108 TD 314: Start of PH Main Gantry Crane Erection (Inter 0 22-Jun-16 A AC.Lot 3 TD 314: Start of PH Main Gantry Crane Erection (Intermediate Pier/Unit1)
A20 TD 357: Start Turbine and Generator Erection U1 0 21-Jul-16 A AC.Lot 3 TD 357: Start Turbine and Generator Erection U1
A20 TD 347: Generator hatch cover installation 0 13-Jan-17 A AC.Lot 3 TD 347: Generator hatch cover installation
Unit-2 770 18-Dec-14 04-Jul-17 A 04-Jul-17 A, Unit-2
A20 TD 307: Start DT Steel Liner U2 erection 0 18-Dec-14A AC.Lot 3 TD 307: Start DT Steel Liner U2 erection
A
A21 TD 319: Lot 2 & 3, U2 Inlet Area, Start of fixed Part Ins 0 02-Sep-15 AC.Lot 3 TD 319: Lot 2 & 3, U2 Inlet Area, Start of fixed Part Installation
A
A20 TD 328: Lot 2, U2 Draft Tube Area, Start of fixed Part 0 03-Dec-15 AC.Lot 3 TD 328: Lot 2, U2 Draft Tube Area, Start of fixed Part Installation
A
A20 TD 335: Stayring and Pier Nose U2 installation in pit ( r 0 31-Dec-15 AC.Lot 3 TD 335: Stayring and Pier Nose U2 installation in pit ( revised )
A
A21 TD 358: Start Turbine and Generator Erection U2 0 08-Aug-16 AC.Lot 3 TD 358: Start Turbine and Generator Erection U2
A
A21 TD 353: Generator hatch cover installation 0 04-Jul-17 A AC.Lot 3 TD 353: Generator hatch cover installation
Unit-3 672 31-Jan-15 A 21-Apr-17 A 21-Apr-17 A, Unit-3
A21 TD 309: Start DT Steel Liner U3 erection 0 31-Jan-15 A AC.Lot 3 TD 309: Start DT Steel Liner U3 erection
A21 TD 333: Lot 2 & 3, U3 Inlet Area, Start of fixed Part Ins 0 02-Nov-15 AC.Lot 3 TD 333: Lot 2 & 3, U3 Inlet Area, Start of fixed Part Installation
A
A21 TD 342: Lot 2, U3 Draft Tube Area, Start of fixed Part 0 31-Jan-16 A AC.Lot 3 TD 342: Lot 2, U3 Draft Tube Area, Start of fixed Part Installation
A21 TD 345: Stayring and Pier Nose U3 installation in pit ( r 0 10-Feb-16 AC.Lot 3 TD 345: Stayring and Pier Nose U3 installation in pit ( revised )
A
A21 TD 348: Stayring & Pier Nose U3 Installation in the pit 0 10-Mar-16 AC.Lot 3 TD 348: Stayring & Pier Nose U3 Installation in the pit ready for concrete
A
A21 TD 361: Start Turbine and Generator Erection U3 0 04-Sep-16 AC.Lot 3 TD 361: Start Turbine and Generator Erection U3
A
A21 TD 356: Generator hatch cover installation 0 21-Apr-17 A AC.Lot 3 TD 356: Generator hatch cover installation
Unit-4 608 10-Jan-15 A 17-Jan-17 A 17-Jan-17 A, Unit-4
A22 TD 311: Start DT Steel Liner U4 erection 0 10-Jan-15 A AC.Lot 3 TD 311: Start DT Steel Liner U4 erection
A22 TD 334: Lot 2 & 3, U4 Inlet Area, Start of fixed Part Ins 0 02-Nov-15 AC.Lot 3 TD 334: Lot 2 & 3, U4 Inlet Area, Start of fixed Part Installation
A
A22 TD 343: Lot 2, U4 Draft Tube Area, Start of fixed Part 0 31-Jan-16 A AC.Lot 3 TD 343: Lot 2, U4 Draft Tube Area, Start of fixed Part Installation
A22 TD 351: Stayring and Pier Nose U4 installation in pit 0 27-Mar-16 AC.Lot 3 TD 351: Stayring and Pier Nose U4 installation in pit
A
A22 TD 362: Start Turbine and Generator Erection U4 0 26-Sep-16 AC.Lot 3 TD 362: Start Turbine and Generator Erection U4
A
A22 TD 360: Generator hatch cover installation 0 17-Jan-17 A AC.Lot 3 TD 360: Generator hatch cover installation
TARGET DA
DATES LOT 4 947 03-Sep-13 31-Oct-16 A 31-Oct-16 A, TARGET DATES LOT 4
Design a
and Fabrication 0 03-Sep-13 03-Sep-13 A 03-Sep-13 A, Design and Fabrication
215 TD 003: Lot 4, grounding system parts available at Site 0 03-Sep-13A AC.Lot 4 TD 003: Lot 4, grounding system parts available at Site
A
SLUICEW
SLUICEWAY 33 29-Jan-16 A 08-Mar-16 A 08-Mar-16 A, SLUICEWAY
A2390 TD 267: SLW, Axes 13-16, Access Lot 4, Cable Tray I 0 29-Jan-16 A AC.Lot 4 TD 267: SLW, Axes 13-16, Access Lot 4, Cable Tray Installation
A2400 TD 268 lot 4: SLW, Axes 1-6, Access Lot 4, Cable Tra 0 08-Mar-16 AC.Lot 4 TD 268 lot 4: SLW, Axes 1-6, Access Lot 4, Cable Tray Installation
A
POWERH
POWERHOUSE 0 03-Jan-16 A 03-Jan-16 A 03-Jan-16 A, POWERHOUSE
A2350 TD 337: U1 ready for cable tray installation 0 03-Jan-16 A AC.Lot 4 TD 337: U1 ready for cable tray installation
A2360 TD 338: U2 ready for cable tray installation 0 03-Jan-16 A AC.Lot 4 TD 338: U2 ready for cable tray installation
A2370 TD 339: U3 ready for cable tray installation 0 03-Jan-16 A AC.Lot 4 TD 339: U3 ready for cable tray installation
A2380 TD 340: U4 ready for cable tray installation 0 03-Jan-16 A AC.Lot 4 TD 340: U4 ready for cable tray installation
NAVIGAT
NAVIGATION LOCK 0 31-Oct-16 A 31-Oct-16 A 31-Oct-16 A, NAVIGATION LOCK
1193 TD 108: Lot 4, Start of Cable Tray Installation 0 31-Oct-16 A AC.Lot 4 TD 108: Lot 4, Start of Cable Tray Installation

CONSTRUCTION
CONSTRUC 1900 02-May-12 02-Aug-18 A 02-Aug-18 A, CONSTRUC
A
SITE INSTALLATION
INSTALL 1790 02-May-12 28-Mar-18 A 28-Mar-18 A, SITE INSTALLATION
A
SITE INSTA
INSTALLATION AREA Lot 1 1790 02-May-12 28-Mar-18 A 28-Mar-18 A, SITE INSTALLATION AREA L
280 Design - Procurement 65 02-May-12 16-Jul-12 A AC.Lot 1 Design - Procurement
A
281 Clearing, Grubbing & Site Stripping - Site Installation Ar 21 02-May-12 26-May-12 A AC.Lot 1 Clearing, Grubbing & Site Stripping - Site Installation Area
A
282 Contract Stockpile has been prevented to accessed to 0 22-May-12 AC.Lot 1 Contract Stockpile has been prevented to accessed to on 22/5/12, 22-May-12 A
A
283 100 cm Top Soil Removal - Site installation area 38 27-May-12 09-Jul-12 A AC.Lot 1 100 cm Top Soil Removal - Site installation area
A
284 Opening of quarries 100 04-Jun-12 A 01-Oct-12 A AC.Lot 1 Opening of quarries
285 Quay construction 88 01-Jul-12 A 15-Oct-12 A AC.Lot 1 Quay construction
288 Geotextile Installation and Sub-Base Crushed Stone w 68 09-Jul-12 A 30-Sep-12 A AC.Lot 1 Geotextile Installation and Sub-Base Crushed Stone where pertinent
286 Water supply and sewage treatment 68 10-Jul-12 A 30-Sep-12 A AC.Lot 1 Water supply and sewage treatment
287 Site communications 55 22-Jul-12 A 26-Sep-12 A AC.Lot 1 Site communications
291 Materials laboratory 32 24-Jul-12 A 02-Sep-12 A AC.Lot 1 Materials laboratory

Milestone Lot 1 Lot 2 Page 4 of 19


Milestone Lot 2 Lot 3
Milestone Lot 3 Lot 4
Milestone Lot 4 Remaining Work
Lot 1 Critical Remaining Work
New Assiut Barrage and Hydropower Plant Schedule Impletation Programme 12-Oct-18 13:45

Activity ID Activity Name Actual Actual Start Actual Finish The 2012 2013 2014 2015 2016 2017 2018 2019
Duration Contractor
M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M
289 Installation of Fences 225 02-Aug-12 04-May-13 A AC.Lot 1 Installation of Fences
A
293 Offices for employer/ employers representatives 46 05-Aug-12 30-Sep-12 A AC.Lot 1 Offices for employer/ employers representatives
A
294 Offices for Contractor 46 05-Aug-12 30-Sep-12 A AC.Lot 1 Offices for Contractor
A
290 NAB-JV Camp. 55 14-Aug-12 21-Oct-12 A AC.Lot 1 NAB-JV Camp.
A
292 Site Installation zone temporary roads 45 22-Aug-12 15-Oct-12 A AC.Lot 1 Site Installation zone temporary roads
A
295 Steel Reinforcement Yard 60 14-Feb-13 27-Apr-13 A AC.Lot 1 Steel Reinforcement Yard
A
296 Concrete production facilities installation 99 02-Mar-13 30-Jun-13 A AC.Lot 1 Concrete production facilities installation
A
297 Complete Main Works for Site Installation Lot 1 0 31-Jul-13 A AC.Lot 1 Complete Main Works for Site Installation Lot 1, 31-Jul-13 A
298 Demobilization/ Restoration of site 114 15-Nov-17 28-Mar-18 A AC.Lot 1 Demobilization/ Restoration of site
A
Earth Works 1784 09-May-12 28-Mar-18 A 28-Mar-18 A, Earth Works
A
TEMPORAR WORKS
TEMPORARY 1355 30-Jul-12 A 31-Jan-17 A 31-Jan-17 A, TEMPORARY WORKS
TEMPORARY RING DAM CONSTRUCTION
TEMPOR 1179 30-Jul-12 A 30-Jun-16 A 30-Jun-16 A, TEMPORARY RING DAM CONSTRUCTION
STOCKPILE AREA ON RIGHT BANK
STOCK 186 30-Jul-12 A 12-Mar-13 A 12-Mar-13 A, STOCKPILE AREA ON RIGHT BANK
319 S&G and sand fill till base level guide wall 70 30-Jul-12 A 22-Oct-12 A AC.Lot 1 S&G and sand fill till base level guide wall
320 Guide wall incl. fill till top of wall 51 19-Sep-12 21-Nov-12 A AC.Lot 1 Guide wall incl. fill till top of wall
A
321 Slurry wall 70 06-Dec-12 27-Feb-13 A AC.Lot 1 Slurry wall
A
322 Preparation top layer 66 24-Dec-12 12-Mar-13 A AC.Lot 1 Preparation top layer
A
UPSTR
UPSTREAM 112 23-Oct-12 A 07-Mar-13 A 07-Mar-13 A, UPSTREAM
324 S&G fill till base level guide wall 60 23-Oct-12 A 03-Jan-13 A AC.Lot 1 S&G fill till base level guide wall
325 Guide wall incl. sand fill till top of wall 60 26-Nov-12 05-Feb-13 A AC.Lot 1 Guide wall incl. sand fill till top of wall
A
326 Slurry wall 77 02-Dec-12 03-Mar-13 A AC.Lot 1 Slurry wall
A
327 Preparation top layer 66 19-Dec-12 07-Mar-13 A AC.Lot 1 Preparation top layer
A
DOWN
DOWNSTREAM 93 18-Nov-12 07-Mar-13 A 07-Mar-13 A, DOWNSTREAM
329 S&G fill till base level guide wall 53 18-Nov-12A 19-Jan-13 A AC.Lot 1 S&G fill till base level guide wall
A
330 Guide wall incl. sand fill till top of wall 58 04-Dec-12 11-Feb-13 A AC.Lot 1 Guide wall incl. sand fill till top of wall
A
331 Slurry wall 65 16-Dec-12 03-Mar-13 A AC.Lot 1 Slurry wall
A
332 Preparation top layer 51 06-Jan-13 A 07-Mar-13 A AC.Lot 1 Preparation top layer
PUMP
PUMPING AND DEWATERING 1040 16-Jan-13 A 30-Jun-16 A 30-Jun-16 A, PUMPING AND DEWATERING
335 Deep Wells installation (inside pit) 160 16-Jan-13 A 28-Jul-13 A AC.Lot 1 Deep Wells installation (inside pit)
334 Surface dewatering unit installation + test 69 06-Feb-13 28-Apr-13 A AC.Lot 1 Surface dewatering unit installation + test
A
336 Pumping test 23 29-Apr-13 A 28-May-13 A AC.Lot 1 Pumping test
337 Pumping out and Dewatering of Pit 929 29-Apr-13 A 31-May-16 A AC.Lot 1 Pumping out and Dewatering of Pit
338 Impounding 25 01-Jun-16 A 30-Jun-16 A AC.Lot 1 Impounding
TEMPOR
TEMPORARY RING DAM REMOVAL 186 19-Jun-16 A 31-Jan-17 A 31-Jan-17 A, TEMPORARY RING DAM REMOVAL
340 Ring Dam removal 186 19-Jun-16 A 31-Jan-17 A AC.Lot 1 Ring Dam removal
GEOTECHN
GEOTECHNICAL INVESTIGATIONS 108 24-May-12 30-Sep-12 A 30-Sep-12 A, GEOTECHNICAL INVESTIGATIONS
General 108 24-May-12 30-Sep-12 A 30-Sep-12 A, General
272 Drilling Two Wells for Pumping & 12 Piezometers 30 24-May-12 27-Jun-12 A AC.Lot 1 Drilling Two Wells for Pumping & 12 Piezometers
A
273 Mobilization of Geotechnical Tests 30 05-Jun-12 A 09-Jul-12 A AC.Lot 1 Mobilization of Geotechnical Tests
274 Long Term Pumping Test from Two Wells 25 28-Jun-12 A 28-Jul-12 A AC.Lot 1 Long Term Pumping Test from Two Wells
275 Site Tests ( On Shore / Off Shore ) 60 10-Jul-12 A 20-Sep-12 A AC.Lot 1 Site Tests ( On Shore / Off Shore )
276 Laboratory Tests 56 16-Jul-12 A 22-Sep-12 A AC.Lot 1 Laboratory Tests
277 Geotechnical Reports 56 25-Jul-12 A 30-Sep-12 A AC.Lot 1 Geotechnical Reports
EXCAVATIO WORKS AND TEMPORARY RIVER PROTECTION
EXCAVATION 1313 09-May-12 20-Sep-16 A 20-Sep-16 A, EXCAVATION WORKS AND TEMPORARY RIVER PROTECTION
TOP SOIL REMOVAL 145 09-May-12A 31-Oct-12 A 31-Oct-12 A, TOP SOIL REMOVAL
343 Clearing, grubbing and stripping, Bani Murr Island-Firs 14 09-May-12A 24-May-12 A AC.Lot 1 Clearing, grubbing and stripping, Bani Murr Island-First Stage
A
344 Topsoil Removal to Stockpile, Bani Murr Island-First S 12 12-May-12 24-May-12 A AC.Lot 1 Topsoil Removal to Stockpile, Bani Murr Island-First Stage
A
345 Clearing, grubbing and stripping, Bani Murr Island-Sec 12 01-Sep-12 13-Sep-12 A AC.Lot 1 Clearing, grubbing and stripping, Bani Murr Island-Second Stage
A
346 Topsoil Removal to Stockpile, Bani Murr Island-Secon 38 15-Sep-12 31-Oct-12 A AC.Lot 1 Topsoil Removal to Stockpile, Bani Murr Island-Second Stage
A
EXCAVAT
EXCAVATION UNDERWATER 126 29-Sep-12 28-Feb-13 A 28-Feb-13 A, EXCAVATION UNDERWATER
348 Connection Channel - First Phase (to el. 43) 32 A
29-Sep-12 07-Nov-12 A AC.Lot 1 Connection Channel - First Phase (to el. 43)
A
350 Inside Construction Pit (to el. 39) 56 20-Oct-12 A 26-Dec-12 A AC.Lot 1 Inside Construction Pit (to el. 39)
349 Riverbed - u/s 83 22-Nov-12 28-Feb-13 A AC.Lot 1 Riverbed - u/s
A
351 Connection Channel - Second Phase (to el. 39) 26 05-Jan-13 A 05-Feb-13 A AC.Lot 1 Connection Channel - Second Phase (to el. 39)
BACKFIL
BACKFILLING 75 19-Jun-16 A 20-Sep-16 A 20-Sep-16 A, BACKFILLING
353 Closure of connection channel 75 19-Jun-16 A 20-Sep-16 A AC.Lot 1 Closure of connection channel
RIP RAP - RIVER PROTECTION 164 15-Jan-13 A 31-Jul-13 A 31-Jul-13 A, RIP RAP - RIVER PROTECTION
355 RBP in connection channel / u/s / central part 102 15-Jan-13 A 19-May-13 A AC.Lot 1 RBP in connection channel / u/s / central part
356 RBP d/s old barrage 82 22-Apr-13 A 31-Jul-13 A AC.Lot 1 RBP d/s old barrage
EXCAVAT
EXCAVATION IN THE DRY 642 11-May-13 25-Jun-15 A 25-Jun-15 A, EXCAVATION IN THE DRY
358 Construction Pit, Bulk Exc. Step 1 (to El. 40.00m-DW) 61 11-May-13 20-Jul-13 A AC.Lot 1 Construction Pit, Bulk Exc. Step 1 (to El. 40.00m-DW)
A
359 Construction Pit, Bulk Exc. Step 2 (to El. 42.00/38.00m 120 27-Jun-13 A 21-Nov-13 A AC.Lot 1 Construction Pit, Bulk Exc. Step 2 (to El. 42.00/38.00m-pit) + inside piers
360 Construction Pit, Bulk Exc. Step 3 (to El. 36.70m-NL) 70 27-Jun-13 A 18-Sep-13 A AC.Lot 1 Construction Pit, Bulk Exc. Step 3 (to El. 36.70m-NL)
363 Grounding System Primary Grid By Lot 4 (Earth works 250 28-Jul-13 A 28-May-14 A AC.Lot 1 Grounding System Primary Grid By Lot 4 (Earth works by Lot 1)
361 Construction Pit, Bulk Exc. Step 4 (to El. 21.40/33.00m 93 20-Jan-14 A 12-May-14 A AC.Lot 1 Construction Pit, Bulk Exc. Step 4 (to El. 21.40/33.00m-PH&SLW)
362 Construction Pit, Bulk Exc. ( EL42.00:38.00m) & below 190 11-Nov-14 25-Jun-15 A AC.Lot 1 Construction Pit, Bulk Exc. ( EL42.00:38.00m) & below 38.00/Final Rip Rap
A
DIAPHRAGM WALLS & CUT-OFF WALLS 1155 15-Jul-13 A 15-May-17 A 15-May-17 A, DIAPHRAGM WALLS & CUT-OFF WALLS
General 1155 15-Jul-13 A 15-May-17 A 15-May-17 A, General
366 TD 101: Start of Trenching for Permanent COW (Revi 0 15-Jul-13 A AC.Lot 1 TD 101: Start of Trenching for Permanent COW (Revised), 15-Jul-13 A
367 Cut-off Wall, Construction Phase 1 51 15-Jul-13 A 14-Sep-13 A AC.Lot 1 Cut-off Wall, Construction Phase 1
368 PH Diaphragm Wall t=0.8m, Axis 12 42 01-Oct-13 A 24-Nov-13 A AC.Lot 1 PH Diaphragm Wall t=0.8m, Axis 12
370 PH Diaphragm Wall t=0.8m, Axis 6 42 01-Oct-13 A 24-Nov-13 A AC.Lot 1 PH Diaphragm Wall t=0.8m, Axis 6
369 SLW Diaphragm Wall t=0.8m, Axis 16 20 25-Nov-13 17-Dec-13 A AC.Lot 1 SLW Diaphragm Wall t=0.8m, Axis 16
A
371 SLW Diaphragm Wall t=0.8m, Axis 1 21 09-Dec-13 01-Jan-14 A AC.Lot 1 SLW Diaphragm Wall t=0.8m, Axis 1
A

Milestone Lot 1 Lot 2 Page 5 of 19


Milestone Lot 2 Lot 3
Milestone Lot 3 Lot 4
Milestone Lot 4 Remaining Work
Lot 1 Critical Remaining Work
New Assiut Barrage and Hydropower Plant Schedule Impletation Programme 12-Oct-18 13:45

Activity ID Activity Name Actual Actual Start Actual Finish The 2012 2013 2014 2015 2016 2017 2018 2019
Duration Contractor
M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M
372 Cut-off Wall, Construction Phase 2, Right Bank 24 01-Dec-16 30-Dec-16 A AC.Lot 1 Cut-off Wall, Construction Phase 2, Right Bank
A
373 Cut-off Wall, Construction Phase 3a, Left Bank (acc. t 3 28-Dec-16 01-Jan-17 A AC.Lot 1 Cut-off Wall, Construction Phase 3a, Left Bank (acc. to alternative 2)
A
374 Cut-off Wall, Construction Phase 3b, Left Bank (acc. t 115 01-Jan-17 A 15-May-17 A AC.Lot 1 Cut-off Wall, Construction Phase 3b, Left Bank (acc. to alternative 2)
CLOSURE DAM
D 951 15-Feb-15 28-Mar-18 A 28-Mar-18 A, CLOSURE DAM
Piezometers installation
Piezome 457 10-Oct-16 A 28-Mar-18 A 28-Mar-18 A, Piezometers installation
377 Piezometers installation 457 10-Oct-16 A 28-Mar-18 A AC.Lot 1 Piezometers installation
CLOSUR DAM INSIDE CONSTRUCTION PIT
CLOSURE 62 15-Feb-15 30-Apr-15 A 30-Apr-15 A, CLOSURE DAM INSIDE CONSTRUCTION PIT
379 Rock fill Dam Part Inside Construction Pit Axis 1 62 15-Feb-15A 30-Apr-15 A AC.Lot 1 Rock fill Dam Part Inside Construction Pit Axis 1
A
380 Class B Fill Dam Part Inside Construction Pit Axis 1 61 15-Feb-15 29-Apr-15 A AC.Lot 1 Class B Fill Dam Part Inside Construction Pit Axis 1
A
CLOSUR DAM OUTSIDE CONSTRUCTION PIT
CLOSURE 546 19-Jun-16 A 28-Mar-18 A 28-Mar-18 A, CLOSURE DAM OUTSIDE C
382 Class U/B Fill Dam Part Outside Construction Pit Upst 76 19-Jun-16 A 21-Sep-16 A AC.Lot 1 Class U/B Fill Dam Part Outside Construction Pit Upstream Dyke
384 Class U/B Fill Dam Part Outside Construction Pit Dow 206 27-Jul-16 A 31-Mar-17 A AC.Lot 1 Class U/B Fill Dam Part Outside Construction Pit Downstream Dyke (1st part) (acc. To
383 Rock fill Dam Part Outside Construction Pit 443 22-Aug-16 28-Jan-18 A AC.Lot 1 Rock fill Dam Part Outside Construction Pit
A
385 Class U/B Fill Dam Part Outside Construction Pit Dow 315 26-Mar-17 28-Mar-18 A AC.Lot 1 Class U/B Fill Dam Part Outside Construct
A
387 Class U/B Fill Dam Part Outside Construction Pit (2nd 267 24-Apr-17 A 01-Mar-18 A AC.Lot 1 Class U/B Fill Dam Part Outside Construction
386 Class U/B Fill Dam Part Outside Construction Pit (1st 80 01-Oct-17 A 02-Jan-18 A AC.Lot 1 Class U/B Fill Dam Part Outside Construction Pit (1st
BACKFILLI
BACKFILLING EMBANKMENT 477 27-Apr-14 A 26-Nov-15 A 26-Nov-15 A, BACKFILLING EMBANKMENT
General 477 27-Apr-14 A 26-Nov-15 A 26-Nov-15 A, General
392 NL, U/S + D/S Approach Areas, Right Bank Slope 477 27-Apr-14 A 26-Nov-15 A AC.Lot 1 NL, U/S + D/S Approach Areas, Right Bank Slope
391 NL, d/s Head, Axes 20/O-S 173 06-Aug-14 02-Mar-15 A AC.Lot 1 NL, d/s Head, Axes 20/O-S
A
390 NL, Guide Walls, Axes 16-17/F-S 119 18-Jan-15 A 09-Jun-15 A AC.Lot 1 NL, Guide Walls, Axes 16-17/F-S
394 Piezometers installation 70 27-Apr-15 A 19-Jul-15 A AC.Lot 1 Piezometers installation
393 PRB Ramp, Right Bank 35 11-Aug-15 20-Sep-15 A AC.Lot 1 PRB Ramp, Right Bank
A
FINAL RIP R
RAP 865 30-May-15 28-Mar-18 A 28-Mar-18 A, FINAL RIP RAP
RIVERBED UNDERNEATH RING DAM
RIVERBE 125 20-Jul-16 AA 19-Dec-16 A 19-Dec-16 A, RIVERBED UNDERNEATH RING DAM
397 Riverbed underneath ring dam 125 20-Jul-16 A 19-Dec-16 A AC.Lot 1 Riverbed underneath ring dam
Rip Rap - SLW + PH 865 30-May-15 28-Mar-18 A 28-Mar-18 A, Rip Rap - SLW + PH
RIP RAP
RA (SLW + PH) INSIDE PIT 330 30-May-15A 30-Jun-16 A 30-Jun-16 A, RIP RAP (SLW + PH) INSIDE PIT
400 u/s area, PH + SLW 300 30-May-15 26-May-16 A AC.Lot 1 u/s area, PH + SLW
A
401 d/s area, PH + SLW 300 04-Jul-15 A 30-Jun-16 A AC.Lot 1 d/s area, PH + SLW
RIP RAP
RA (SLW + PH) OUTSIDE PIT 535 02-Jul-16 A 28-Mar-18 A 28-Mar-18 A, RIP RAP (SLW + PH) OUTS
404 d/s right canal, PH + SLW + BMI reshaping 277 02-Jul-16 A 31-May-17 A AC.Lot 1 d/s right canal, PH + SLW + BMI reshaping
405 d/s left canal, PH + SLW + BMI reshaping 535 02-Jul-16 A 28-Mar-18 A AC.Lot 1 d/s left canal, PH + SLW + BMI reshaping
403 u/s area, PH + SLW 323 20-Jul-16 A 09-Aug-17 A AC.Lot 1 u/s area, PH + SLW
Rip Rap - NL 611 24-Jun-15 A 30-Jun-17 A 30-Jun-17 A, Rip Rap - NL
RIP RAP
RA (NL) INSIDE PIT 611 24-Jun-15 A 30-Jun-17 A 30-Jun-17 A, RIP RAP (NL) INSIDE PIT
408 u/s area, NL 272 24-Jun-15 A 20-May-16 A AC.Lot 1 u/s area, NL
409 d/s area, NL 278 24-Jun-15 A 28-May-16 A AC.Lot 1 d/s area, NL
410 TD 109: Approach Areas u/s completed 0 30-Jun-17 A AC.Lot 1 TD 109: Approach Areas u/s completed, 30-Jun-17 A
RIP RAP
RA (NL) OUTSIDE PIT 250 02-Jul-16 A 30-Apr-17 A 30-Apr-17 A, RIP RAP (NL) OUTSIDE PIT
413 d/s area, NL 250 02-Jul-16 A 30-Apr-17 A AC.Lot 1 d/s area, NL
412 u/s area, NL 50 20-Jul-16 A 20-Sep-16 A AC.Lot 1 u/s area, NL
Rip Rap - Closure Dam 381 15-Sep-15 25-Dec-16 A 25-Dec-16 A, Rip Rap - Closure Dam
RIP RA
RAP (CD) INSIDE PIT 113 15-Sep-15 02-Feb-16 A 02-Feb-16 A, RIP RAP (CD) INSIDE PIT
416 Riverbed Protection Closure Dam inside pit, u/s + d/s 113 15-Sep-15 02-Feb-16 A AC.Lot 1 Riverbed Protection Closure Dam inside pit, u/s + d/s
A
RIP RA
RAP (CD) OUTSIDE PIT 77 24-Sep-16 25-Dec-16 A 25-Dec-16 A, RIP RAP (CD) OUTSIDE PIT
418 Riverbed Protection Closure Dam outside pit, u/s + d/s 77 24-Sep-16A 25-Dec-16 A AC.Lot 1 Riverbed Protection Closure Dam outside pit, u/s + d/s
A
Sub Project 982 02-May-12 06-Aug-15 A 06-Aug-15 A, Sub Project
A
HOUSING F
FOR EMPLOYER/EMP. REPRES. (2 Bldgs.) 502 02-May-12 01-Jan-14 A 01-Jan-14 A, HOUSING FOR EMPLOYER/EMP. REPRES. (2 Bldgs.)
GENERAL 502 02-May-12A 01-Jan-14 A 01-Jan-14 A, GENERAL
301 Construction Permit 37 02-May-12A 13-Jun-12 A AC.Lot 1 Construction Permit
A
302 Approval of Construction Permit 0 14-Jun-12 A AC.Lot 1 Approval of Construction Permit, 14-Jun-12 A
303 Installations + Excavation 25 17-Jun-12 A 15-Jul-12 A AC.Lot 1 Installations + Excavation
304 R.C. Columns & Walls 250 11-Jul-12 A 13-May-13 A AC.Lot 1 R.C. Columns & Walls
305 R.C. Slabs & Beams 250 24-Jul-12 A 25-May-13 A AC.Lot 1 R.C. Slabs & Beams
306 Block Works 240 11-Sep-12 29-Jun-13 A AC.Lot 1 Block Works
A
307 Plastering 201 25-Nov-12 24-Jul-13 A AC.Lot 1 Plastering
A
310 Internal Electro-Mechanical Works 220 25-Nov-12 17-Aug-13 A AC.Lot 1 Internal Electro-Mechanical Works
A
308 Flooring Works 136 06-Jun-13 A 19-Nov-13 A AC.Lot 1 Flooring Works
309 Other Finishing Activities 163 06-Jun-13 A 21-Dec-13 A AC.Lot 1 Other Finishing Activities
313 Exterior E.M. Services 85 30-Jun-13 A 09-Oct-13 A AC.Lot 1 Exterior E.M. Services
311 Installation of Elevators 33 13-Nov-13 21-Dec-13 A AC.Lot 1 Installation of Elevators
A
314 Internal Furnishing 29 27-Nov-13 30-Dec-13 A AC.Lot 1 Internal Furnishing
A
312 Testing and Commissioning 12 18-Dec-13 31-Dec-13 A AC.Lot 1 Testing and Commissioning
A
315 Complete Works of Employer Housing 0 01-Jan-14 A AC.Lot 1 Complete Works of Employer Housing, 01-Jan-14 A
HEAD REGULATOR
REGU 406 01-Apr-14 A 06-Aug-15 A 06-Aug-15 A, HEAD REGULATOR
General 406 01-Apr-14 A 06-Aug-15 A 06-Aug-15 A, General
1281 Start of Works 0 01-Apr-14 A AC.Lot 1 Start of Works, 01-Apr-14 A
1282 Preparation works/ Mobilization 55 25-May-14 31-Jul-14 A AC.Lot 1 Preparation works/ Mobilization
A
1286 Piezometers 25 06-Aug-14 03-Sep-14 A AC.Lot 1 Piezometers
A
1284 Control Building and Radio Mast Foundation incl. Cable 181 23-Sep-14 01-May-15 A AC.Lot 1 Control Building and Radio Mast Foundation incl. Cable Trench
A
1285 Drilling and grouting of piers U/s Piers 124 01-Dec-14 30-Apr-15 A AC.Lot 1 Drilling and grouting of piers U/s Piers
A
1283 Install HPU and Electrical Cabinets incl. cabling in Con 7 15-Dec-14 22-Dec-14 A AC.Lot 4 Install HPU and Electrical Cabinets incl. cabling in Control Building
A
1287 End of Works 0 06-Aug-15 AC.Lot 1 End of Works, 06-Aug-15 A
A
Phase A (Left Side) 182 02-Aug-14 08-Mar-15 A 08-Mar-15 A, Phase A (Left Side)

Milestone Lot 1 Lot 2 Page 6 of 19


Milestone Lot 2 Lot 3
Milestone Lot 3 Lot 4
Milestone Lot 4 Remaining Work
Lot 1 Critical Remaining Work
New Assiut Barrage and Hydropower Plant Schedule Impletation Programme 12-Oct-18 13:45

Activity ID Activity Name Actual Actual Start Actual Finish The 2012 2013 2014 2015 2016 2017 2018 2019
Duration Contractor
M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M
Down
Downstream Concrete Works 182 02-Aug-14 08-Mar-15 A 08-Mar-15 A, Downstream Concrete Works
1295 Temporary separation wall D/S 79 A 05-Nov-14 A
02-Aug-14 AC.Lot 1 Temporary separation wall D/S
A
1290 Sheet Piling 13 01-Sep-14 15-Sep-14 A AC.Lot 1 Sheet Piling
A
1292 Removal of Stone Pitching in Area of New Weir 8 16-Sep-14 24-Sep-14 A AC.Lot 1 Removal of Stone Pitching in Area of New Weir
A
1291 Drilling and grouting of piers D/s Phase A 20 24-Sep-14 20-Oct-14 A AC.Lot 1 Drilling and grouting of piers D/s Phase A
A
1293 Concrete works for Side Wall Extension 125 11-Oct-14 A 08-Mar-15 A AC.Lot 1 Concrete works for Side Wall Extension
1294 New Weir 36 25-Nov-14 06-Jan-15 A AC.Lot 1 New Weir
A
1296 Bed Protection below Weir 23 15-Dec-14 12-Jan-15 A AC.Lot 1 Bed Protection below Weir
A
1297 Slab over old one 69 15-Dec-14 08-Mar-15 A AC.Lot 1 Slab over old one
A
Rehab
Rehabilitation of Head regulator 85 19-Nov-14 01-Mar-15 A 01-Mar-15 A, Rehabilitation of Head regulator
1299 Works on gates 1-5 by Lot 1 85 19-Nov-14A 01-Mar-15 A AC.Lot 1 Works on gates 1-5 by Lot 1
A
1301 Works + Commissioning by other Lots 85 19-Nov-14 28-Feb-15 A AC.Lot 2 Works + Commissioning by other Lots
A
1300 Cladding on old piers 28 03-Dec-14 04-Jan-15 A AC.Lot 1 Cladding on old piers
A
Phase B (Right Side) 93 14-Feb-15 04-Jun-15 A 04-Jun-15 A, Phase B (Right Side)
Downstream Concrete Works
Down 90 14-Feb-15 01-Jun-15 A 01-Jun-15 A, Downstream Concrete Works
1304 Sheet Piling 15 A 02-Mar-15 A
14-Feb-15 AC.Lot 1 Sheet Piling
A
1306 Removal of Stone Pitching in Area of New Weir 6 03-Mar-15 09-Mar-15 A AC.Lot 1 Removal of Stone Pitching in Area of New Weir
A
1307 Concrete works for Side Wall Extension 45 15-Mar-15 09-May-15 A AC.Lot 1 Concrete works for Side Wall Extension
A
1305 Drilling and grouting of piers D/s Phase B 20 18-Mar-15 09-Apr-15 A AC.Lot 1 Drilling and grouting of piers D/s Phase B
A
1308 New Weir 15 15-Apr-15 A 03-May-15 A AC.Lot 1 New Weir
1309 Bed Protection below Weir 12 04-May-15 17-May-15 A AC.Lot 1 Bed Protection below Weir
A
1310 Slab over old one 25 04-May-15 01-Jun-15 A AC.Lot 1 Slab over old one
A
Rehab
Rehabilitation of Head regulator 74 08-Mar-15 04-Jun-15 A 04-Jun-15 A, Rehabilitation of Head regulator
1312 Works on gates 6-9 by Lot 1 62 A 21-May-15 A
08-Mar-15 AC.Lot 1 Works on gates 6-9 by Lot 1
A
1314 Works + Commissioning by other Lots 71 11-Mar-15 04-Jun-15 A AC.Lot 2 Works + Commissioning by other Lots
A
1313 Cladding on old piers 22 19-Mar-15 15-Apr-15 A AC.Lot 1 Cladding on old piers
A
POWERHOUSE AND INTERMEDIATE PIERS
POWERHOU 1391 11-Jan-14 A 02-Aug-18 A 02-Aug-18 A, POWERHOU
INTERMEDI
INTERMEDIATE PIER, AXES 6-7 629 06-Mar-14 05-Apr-16 A 05-Apr-16 A, INTERMEDIATE PIER, AXES 6-7
422 d/s Part - slab 50 06-Mar-14 07-May-14 A AC.Lot 1 d/s Part - slab
A
421 Central part - slab 22 22-Mar-14 16-Apr-14 A AC.Lot 1 Central part - slab
A
423 Central Part - Superstructure 612 26-Mar-14 05-Apr-16 A AC.Lot 1 Central Part - Superstructure
A
424 d/s Part - Superstructure 399 15-May-14 08-Sep-15 A AC.Lot 1 d/s Part - Superstructure
A
INTERMEDI
INTERMEDIATE PIER, AXES 12-13 897 11-Jan-14 A 04-Jan-17 A 04-Jan-17 A, INTERMEDIATE PIER, AXES 12-13
427 d/s Part - slab 28 11-Jan-14 A 14-Feb-14 A AC.Lot 1 d/s Part - slab
426 Central part - slab 38 14-Feb-14 31-Mar-14 A AC.Lot 1 Central part - slab
A
428 Central Part - Superstructure 869 15-Feb-14 04-Jan-17 A AC.Lot 1 Central Part - Superstructure
A
429 d/s Part - Superstructure 784 05-Apr-14 A 14-Nov-16 A AC.Lot 1 d/s Part - Superstructure
PH-UNIT 1-2,
1-2 AXES 7-9 957 03-Jun-14 A 31-Jul-17 A 31-Jul-17 A, PH-UNIT 1-2, AXES 7-9
UNIT (1) 817 03-Jun-14 A 18-Feb-17 A 18-Feb-17 A, UNIT (1)
U1 Lot
Lo 1 / Concrete Works 486 23-Jul-14 A 05-Mar-16 A 05-Mar-16 A, U1 Lot 1 / Concrete Works
433 TD 301: Start U1 First Stage Concrete Works 0 23-Jul-14 A AC.Lot 1 TD 301: Start U1 First Stage Concrete Works, 23-Jul-14 A
438 U1, Step 1-a (DT Steel Liner Foundation Axis C:B ) 101 23-Jul-14 A 25-Nov-14 A AC.Lot 1 U1, Step 1-a (DT Steel Liner Foundation Axis C:B )
439 U1, Step 1-b ( U/S Axis B: A) 62 17-Sep-14 01-Dec-14 A AC.Lot 1 U1, Step 1-b ( U/S Axis B: A)
A
440 MS 1-03: PH-Unit 1, Step 1 Concrete Works complete 0 01-Dec-14 A AC.Lot 1 MS 1-03: PH-Unit 1, Step 1 Concrete Works complete,
445 U1, Step 2 (Central Part Axes B-C) 164 07-Dec-14 22-Jun-15 A AC.Lot 1 U1, Step 2 (Central Part Axes B-C)
A
444 U1, Step 2a (Inlet Part u/s Axis B) 160 23-Feb-15 03-Sep-15 A AC.Lot 1 U1, Step 2a (Inlet Part u/s Axis B)
A
447 U1, Step 3 (Draft Tube Part d/s Axis C) 296 11-Mar-15 05-Mar-16 A AC.Lot 1 U1, Step 3 (Draft Tube Part d/s Axis C)
A
446 MS 1-05: PH-Unit 1, Step 2 Concrete Works complete 0 22-Jun-15 A AC.Lot 1 MS 1-05: PH-Unit 1, Step 2 Concrete Works complete,
448 TD 315: U1, Step 2a (Inlet Part u/s Axis B) Concrete W 0 02-Sep-15 A AC.Lot 1 TD 315: U1, Step 2a (Inlet Part u/s Axis B) Concrete Works completed,
451 TD 324: U1, Step 3 (Draft Tube d/s Axis C) Concrete 0 05-Mar-16 A AC.Lot 1 TD 324: U1, Step 3 (Draft Tube d/s Axis C) Concrete Works completed,
U1, Draft
Dr Tube installation 452 03-Jun-14 A 03-Dec-15 A 03-Dec-15 A, U1, Draft Tube installation
455 Installation of Dewatering Pipes in Step 1- Raft 25 03-Jun-14 A 01-Jul-14 A AC.Lot 3 Installation of Dewatering Pipes in Step 1- Raft
453 Installation of embedded parts Phase 1/ Step 1 25 20-Jul-14 A 20-Aug-14 A AC.Lot 3 Installation of embedded parts Phase 1/ Step 1
454 TD 305: Start DT Steel Liner U1 erection 0 03-Dec-14 AC.Lot 3 TD 305: Start DT Steel Liner U1 erection
A
458 DT installation 35 03-Dec-14 13-Jan-15 A AC.Lot 3 DT installation
A
449 U1, Second Stage(Concrete for DT) 61 16-Jan-15 A 30-Mar-15 A AC.Lot 1 U1, Second Stage(Concrete for DT)
456 Draft Tube Sandblasting and painting 22 24-Feb-15 21-Mar-15 A AC.Lot 3 Draft Tube Sandblasting and painting
A
457 TD 327: Lot 2, U1 Draft Tube Area, Start of fixed Part 0 03-Dec-15 AC.Lot 3 TD 327: Lot 2, U1 Draft Tube Area, Start of fixed Part Installation
A
U1, Stayring
St installation 449 18-Aug-14 11-Feb-16 A 11-Feb-16 A, U1, Stayring installation
460 Installation of embedded parts Phase 1/ Step 1 12 18-Aug-14 31-Aug-14 A AC.Lot 3 Installation of embedded parts Phase 1/ Step 1
A
462 TD 323: Stayring and Pier Nose U1 installation in pit ( r 0 15-Dec-15 AC.Lot 3 TD 323: Stayring and Pier Nose U1 installation in pit ( revised )
A
463 Stayring installation in pit 25 15-Dec-15 13-Jan-16 A AC.Lot 3 Stayring installation in pit
A
461 TD 325: Stayring & Pier Nose U1 Installation in the pit 0 14-Jan-16 A AC.Lot 3 TD 325: Stayring & Pier Nose U1 Installation in the pit ready for concrete
464 Installation of embedded parts for horizontal adjustmen 12 30-Jan-16 A 11-Feb-16 A AC.Lot 3 Installation of embedded parts for horizontal adjustment of generator
U1, Turbine
Tu & Generator Main Installation 316 01-Feb-16 18-Feb-17 A 18-Feb-17 A, U1, Turbine & Generator Main Installation
436 TD 329: Start U1 u/s Transition Zone Concrete Works 0 01-Feb-16A AC.Lot 1 TD 329: Start U1 u/s Transition Zone Concrete Works up to EL. 42.10, 01-Feb-16 A
A
435 U1, Second Stage Concrete Works U1, EL 27.20 to 4 113 02-Feb-16 16-Jun-16 A AC.Lot 1 U1, Second Stage Concrete Works U1, EL 27.20 to 42.10, Axes B-C
A
437 TD 346: U1 u/s Transition Zone Concrete Works up to 0 16-Jun-16 A AC.Lot 1 TD 346: U1 u/s Transition Zone Concrete Works up to EL. 42.10 completed, 16-Jun-16 A
442 U1, Second Stage(Concrete for Hatch Cover) 5 26-Jun-16 A 02-Jul-16 A AC.Lot 1 U1, Second Stage(Concrete for Hatch Cover)
469 TD 357: Start Turbine and Generator Erection U1 0 21-Jul-16 A AC.Lot 3 TD 357: Start Turbine and Generator Erection U1
470 Installation Distributor anchoring, distributor & discharg 71 21-Jul-16 A 19-Oct-16 A AC.Lot 3 Installation Distributor anchoring, distributor & discharge ring
443 U1, Second stage Concrete for anchoring (Turbine & 15 20-Oct-16 A 07-Nov-16 A AC.Lot 1 U1, Second stage Concrete for anchoring (Turbine & Generator Main Installation)
471 Main installation: turbine + generator incl. Piping & aux 86 08-Nov-16 18-Feb-17 A AC.Lot 3 Main installation: turbine + generator incl. Piping & auxiliaries
A
466 TD 347: Generator hatch cover installation 0 13-Jan-17 A AC.Lot 3 TD 347: Generator hatch cover installation

Milestone Lot 1 Lot 2 Page 7 of 19


Milestone Lot 2 Lot 3
Milestone Lot 3 Lot 4
Milestone Lot 4 Remaining Work
Lot 1 Critical Remaining Work
New Assiut Barrage and Hydropower Plant Schedule Impletation Programme 12-Oct-18 13:45

Activity ID Activity Name Actual Actual Start Actual Finish The 2012 2013 2014 2015 2016 2017 2018 2019
Duration Contractor
M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M
467 Generator hatch cover installation 1 13-Jan-17 A 15-Jan-17 A AC.Lot 3 Generator hatch cover installation
468 Sandblasting and painting hatch cover 0 15-Jan-17 A 15-Jan-17 A AC.Lot 3 Sandblasting and painting hatch cover
U1, Trash
Tra Rack installation 456 21-Oct-14 A 21-Apr-16 A 21-Apr-16 A, U1, Trash Rack installation
474 Installation of embedded parts - 1st stage 25 21-Oct-14 A 18-Nov-14 A AC.Lot 3 Installation of embedded parts - 1st stage
475 Installation of embedded parts - 2nd stage 50 02-Feb-15 01-Apr-15 A AC.Lot 3 Installation of embedded parts - 2nd stage
A
476 Installation of fish beams u1 & u2 50 02-Aug-15 01-Oct-15 A AC.Lot 3 Installation of fish beams u1 & u2
A
473 TD 318: Lot 2 & 3, U1 Inlet Area, Start of fixed Part Ins 0 02-Sep-15 AC.Lot 3 TD 318: Lot 2 & 3, U1 Inlet Area, Start of fixed Part Installation
A
441 U1, Second Stage(Concrete for Fish Beam) 27 09-Nov-15 10-Dec-15 A AC.Lot 1 U1, Second Stage(Concrete for Fish Beam)
A
477 TR installation 118 03-Dec-15 21-Apr-16 A AC.Lot 3 TR installation
A
U1, Stop
St log U/S 223 03-Sep-15 01-Jun-16 A 01-Jun-16 A, U1, Stop log U/S
479 Installation of embedded parts - 1st stage 7 A 12-Sep-15 A
03-Sep-15 AC.Lot 2 Installation of embedded parts - 1st stage
A
480 Installation of embedded parts - 2nd stage (sill beam + 87 12-Sep-15 28-Dec-15 A AC.Lot 2 Installation of embedded parts - 2nd stage (sill beam + side guides)
A
450 U1, Second Stage(Concrete for U/S Stop Log) 74 29-Dec-15 27-Mar-16 A AC.Lot 1 U1, Second Stage(Concrete for U/S Stop Log)
A
481 Stop log U/S installation 54 27-Mar-16 01-Jun-16 A AC.Lot 2 Stop log U/S installation
A
U1, Stop
St log D/S (DS Draft Tube Bulkheads ) 236 03-Aug-15 16-May-16 A 16-May-16 A, U1, Stop log D/S (DS Draft Tube Bulkheads )
483 Installation of embedded parts - 1st stage 164 03-Aug-15 18-Feb-16 A AC.Lot 2 Installation of embedded parts - 1st stage
A
484 Installation of embedded parts - 2nd stage (sill beam + 40 18-Feb-16 05-Apr-16 A AC.Lot 2 Installation of embedded parts - 2nd stage (sill beam + side guides)
A
434 U1, Second Stage(Concrete for D/S Stop Log) 20 05-Apr-16 A 30-Apr-16 A AC.Lot 1 U1, Second Stage(Concrete for D/S Stop Log)
485 Stop log D/S installation 8 07-May-16 16-May-16 A AC.Lot 2 Stop log D/S installation
A
UNIT (2) 907 04-Aug-14 31-Jul-17 A 31-Jul-17 A, UNIT (2)
U2 Lot
Lo 1 / Concrete Works 596 A 26-Jul-16 A
04-Aug-14 26-Jul-16 A, U2 Lot 1 / Concrete Works
489 TD 302: Start U2 First Stage Concrete Works 0 04-Aug-14 AC.Lot 1 TD 302: Start U2 First Stage Concrete Works, 04-Aug-14 A
A
488 U2, Step 1-a (DT Steel Liner Foundation Axis C:B ) 112 05-Aug-14 17-Dec-14 A AC.Lot 1 U2, Step 1-a (DT Steel Liner Foundation Axis C:B )
A
490 U2, Step 1-b ( U/S Axis B: A) 60 08-Oct-14 A 16-Dec-14 A AC.Lot 1 U2, Step 1-b ( U/S Axis B: A)
495 TD 306: U2, Step 1 (Draft Tube Steel Liner Foundation 0 18-Dec-14 AC.Lot 1 TD 306: U2, Step 1 (Draft Tube Steel Liner Foundation) Concrete Works completed, 18-Dec-14 A
A
491 U2, Step 2 (Central Part Axes B-C) 200 21-Dec-14 19-Aug-15 A AC.Lot 1 U2, Step 2 (Central Part Axes B-C)
A
504 U2, Step 2a (Inlet Part u/s Axis B) 167 18-Mar-15 11-Oct-15 A AC.Lot 1 U2, Step 2a (Inlet Part u/s Axis B)
A
505 U2, Step 3 (Draft Tube Part d/s Axis C) 308 14-Jul-15 A 25-Jul-16 A AC.Lot 1 U2, Step 3 (Draft Tube Part d/s Axis C)
502 TD 313: U2, Step 2 (Central Part Axes B-C) Concrete 0 19-Aug-15 A AC.Lot 1 TD 313: U2, Step 2 (Central Part Axes B-C) Concrete Works completed,
503 TD 316: U2, Step 2a (Inlet Part u/s Axis B) Concrete W 0 11-Oct-15 A AC.Lot 1 TD 316: U2, Step 2a (Inlet Part u/s Axis B) Concrete Works completed,
506 TD 326: U2, Step 3 (Draft Tube d/s Axis C) Concrete 0 26-Jul-16 A AC.Lot 1 TD 326: U2, Step 3 (Draft Tube d/s Axis C) Concrete Works completed,
U2, Draft
Dr Tube installation 392 16-Aug-14 03-Dec-15 A 03-Dec-15 A, U2, Draft Tube installation
508 Installation of embedded parts 25 16-Aug-14A 13-Sep-14 A AC.Lot 3 Installation of embedded parts
A
509 TD 307: Start DT Steel Liner U2 erection 0 18-Dec-14 AC.Lot 3 TD 307: Start DT Steel Liner U2 erection
A
513 DT installation 35 18-Dec-14 29-Jan-15 A AC.Lot 3 DT installation
A
492 U2, Second Stage(Concrete for DT) 65 21-Jan-15 A 08-Apr-15 A AC.Lot 1 U2, Second Stage(Concrete for DT)
511 MS 3-02: Unit 1&2 Draft Tube Erec. ready for Step 2 C 0 30-Jan-15 A AC.Lot 3 MS 3-02: Unit 1&2 Draft Tube Erec. ready for Step 2 Concr. Works
510 Draft Tube Sandblasting and painting 22 11-Mar-15 05-Apr-15 A AC.Lot 3 Draft Tube Sandblasting and painting
A
512 TD 328: Lot 2, U2 Draft Tube Area, Start of fixed Part 0 03-Dec-15 AC.Lot 3 TD 328: Lot 2, U2 Draft Tube Area, Start of fixed Part Installation
A
U2, Stayring
St installation 468 10-Aug-14 25-Feb-16 A 25-Feb-16 A, U2, Stayring installation
515 Installation of embedded parts 12 A
10-Aug-14 23-Aug-14 A AC.Lot 3 Installation of embedded parts
A
516 TD 335: Stayring and Pier Nose U2 installation in pit ( r 0 31-Dec-15 AC.Lot 3 TD 335: Stayring and Pier Nose U2 installation in pit ( revised )
A
517 Stayring installation in pit 25 31-Dec-15 31-Jan-16 A AC.Lot 3 Stayring installation in pit
A
518 Installation of embedded parts for horizontal adjustmen 12 13-Feb-16 25-Feb-16 A AC.Lot 3 Installation of embedded parts for horizontal adjustment of generator
A
U2, Turbine
Tu & Generator Main Installation 456 01-Feb-16 31-Jul-17 A 31-Jul-17 A, U2, Turbine & Generator Main Installation
500 TD 344: Start U2 u/s Transition Zone Concrete Works 0 A
01-Feb-16 AC.Lot 1 TD 344: Start U2 u/s Transition Zone Concrete Works up to EL. 42.10, 01-Feb-16 A
A
498 U2, Second Stage Concrete Works U2, EL 27.20 to 42 137 02-Feb-16 17-Jul-16 A AC.Lot 1 U2, Second Stage Concrete Works U2, EL 27.20 to 42.10, Axes B-C
A
501 TD 352: U2 u/s Transition Zone Concrete Works up to 0 17-Jul-16 A AC.Lot 1 TD 352: U2 u/s Transition Zone Concrete Works up to EL. 42.10 completed ( revised ),
496 U2, Second Stage(Concrete for Hatch Cover) 5 18-Jul-16 A 25-Jul-16 A AC.Lot 1 U2, Second Stage(Concrete for Hatch Cover)
521 TD 358: Start Turbine and Generator Erection U2 0 08-Aug-16 AC.Lot 3 TD 358: Start Turbine and Generator Erection U2
A
523 Installation Distributor anchoring, distributor & discharg 8 17-Aug-16 27-Aug-16 A AC.Lot 3 Installation Distributor anchoring, distributor & discharge ring
A
497 U2, Second stage Concrete for anchoring (Turbine & 63 28-Aug-16 15-Nov-16 A AC.Lot 1 U2, Second stage Concrete for anchoring (Turbine & Generator Main Installation)
A
525 Main installation: turbine + generator incl. Piping & aux 219 16-Nov-16 31-Jul-17 A AC.Lot 3 Main installation: turbine + generator incl. Piping & auxiliaries
A
520 TD 353: Generator hatch cover installation 0 04-Jul-17 A AC.Lot 3 TD 353: Generator hatch cover installation
522 Generator hatch cover installation 1 04-Jul-17 A 05-Jul-17 A AC.Lot 3 Generator hatch cover installation
524 Sandblasting and painting hatch cover 12 05-Jul-17 A 19-Jul-17 A AC.Lot 3 Sandblasting and painting hatch cover
U2, Trash
Tra Rack installation 339 17-Dec-14 01-Feb-16 A 01-Feb-16 A, U2, Trash Rack installation
528 Installation of embedded parts - 1st stage 25 17-Dec-14 15-Jan-15 A AC.Lot 3 Installation of embedded parts - 1st stage
A
529 Installation of embedded parts - 2nd stage 50 30-May-15 28-Jul-15 A AC.Lot 3 Installation of embedded parts - 2nd stage
A
530 Installation of fish beams 50 29-Jul-15 A 28-Sep-15 A AC.Lot 3 Installation of fish beams
527 TD 319: Lot 2 & 3, U2 Inlet Area, Start of fixed Part Ins 0 02-Sep-15 AC.Lot 3 TD 319: Lot 2 & 3, U2 Inlet Area, Start of fixed Part Installation
A
494 U2, Second Stage(Concrete for Fish Beam) 28 08-Nov-15 10-Dec-15 A AC.Lot 1 U2, Second Stage(Concrete for Fish Beam)
A
531 TR installation 43 12-Dec-15 01-Feb-16 A AC.Lot 3 TR installation
A
U2, Stop
St log U/S 165 15-Oct-15 A 28-Apr-16 A 28-Apr-16 A, U2, Stop log U/S
533 Installation of embedded parts - 1st stage 11 15-Oct-15 A 28-Oct-15 A AC.Lot 2 Installation of embedded parts - 1st stage
534 Installation of embedded parts - 2nd stage (sill beam + 65 29-Oct-15 A 14-Jan-16 A AC.Lot 2 Installation of embedded parts - 2nd stage (sill beam + side guides)
493 U2, Second Stage(Concrete for U/S Stop Log) 76 15-Jan-16 A 14-Apr-16 A AC.Lot 1 U2, Second Stage(Concrete for U/S Stop Log)
535 Stop log U/S installation 11 14-Apr-16 A 28-Apr-16 A AC.Lot 2 Stop log U/S installation
U2, Stop
St log D/S (DS Draft Tube Bulkheads ) 62 15-Mar-16 30-May-16 A 30-May-16 A, U2, Stop log D/S (DS Draft Tube Bulkheads )
537 Installation of embedded parts - 1st stage 18 15-Mar-16 05-Apr-16 A AC.Lot 2 Installation of embedded parts - 1st stage
A
538 Installation of embedded parts - 2nd stage (sill beam + 7 06-Apr-16 A 14-Apr-16 A AC.Lot 2 Installation of embedded parts - 2nd stage (sill beam + side guides)
499 U2, Second Stage(Concrete for D/S Stop Log) 22 15-Apr-16 A 15-May-16 A AC.Lot 1 U2, Second Stage(Concrete for D/S Stop Log)
539 Stop log D/S installation 8 21-May-16 30-May-16 A AC.Lot 2 Stop log D/S installation
A
MIDDLE PIER
PIE 1183 11-May-14 28-Mar-18 A 28-Mar-18 A, MIDDLE PIER
A

Milestone Lot 1 Lot 2 Page 8 of 19


Milestone Lot 2 Lot 3
Milestone Lot 3 Lot 4
Milestone Lot 4 Remaining Work
Lot 1 Critical Remaining Work
New Assiut Barrage and Hydropower Plant Schedule Impletation Programme 12-Oct-18 13:45

Activity ID Activity Name Actual Actual Start Actual Finish The 2012 2013 2014 2015 2016 2017 2018 2019
Duration Contractor
M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M
Lot 1 ( C
Concrete & Elevators ) 1183 11-May-14 28-Mar-18 A 28-Mar-18 A, Lot 1 ( Concrete & Elevators
542 Middle Pier 646 11-May-14A 29-Jun-16 A AC.Lot 1 Middle Pier
A
543 Elevator - installation & testing 471 21-Sep-16 28-Mar-18 A AC.Lot 1 Elevator - installation & testing
A
Fixed pa
parts installation 336 25-May-14 02-Jul-15 A 02-Jul-15 A, Fixed parts installation
545 Embedded pipes installation in raft 12 25-May-14A 07-Jun-14 A AC.Lot 1 Embedded pipes installation in raft
A
546 Drainage pit cover / Dewatering pit cover installation 25 04-Jun-15 A 02-Jul-15 A AC.Lot 1 Drainage pit cover / Dewatering pit cover installation
PH-UNIT 3-4,
3-4 AXES 10-12 1011 25-Aug-14 20-Dec-17 A 20-Dec-17 A, PH-UNIT 3-4, AXES 10-12
UNIT (3) 983 25-Aug-14A 18-Nov-17 A 18-Nov-17 A, UNIT (3)
U3 Lot
Lo 1 / Concrete Works 528 25-Aug-14A 25-May-16 A 25-May-16 A, U3 Lot 1 / Concrete Works
568 TD 303: Start U3 First Stage Concrete Works 0 25-Aug-14 AC.Lot 1 TD 303: Start U3 First Stage Concrete Works, 25-Aug-14 A
A
550 U3, Step 1-a (DT Steel Liner Foundation Axis C:B ) 48 26-Aug-14 23-Oct-14 A AC.Lot 1 U3, Step 1-a (DT Steel Liner Foundation Axis C:B )
A
552 U2, Step 1-b ( U/S Axis B: A) 60 19-Nov-14 29-Jan-15 A AC.Lot 1 U2, Step 1-b ( U/S Axis B: A)
A
551 U3, Step 2 (Central Part Axes B-C) 297 14-Jan-15 A 10-Jan-16 A AC.Lot 1 U3, Step 2 (Central Part Axes B-C)
553 TD 308: U3, Step 1 (Draft Tube Steel Liner Foundation 0 29-Jan-15 A AC.Lot 1 TD 308: U3, Step 1 (Draft Tube Steel Liner Foundation) Concrete Works completed,
554 U3, Step 2a (Inlet Part u/s Axis B) 229 09-Mar-15 13-Dec-15 A AC.Lot 1 U3, Step 2a (Inlet Part u/s Axis B)
A
555 U3, Step 3 (Draft Tube Part d/s Axis C) 226 24-Aug-15 25-May-16 A AC.Lot 1 U3, Step 3 (Draft Tube Part d/s Axis C)
A
563 TD 331: U3, Step 2a (Inlet Part u/s Axis B) Concrete W 0 13-Dec-15 A AC.Lot 1 TD 331: U3, Step 2a (Inlet Part u/s Axis B) Concrete Works completed,
562 TD 317: U3, Step 2 (Central Part Axes B-C) Concrete 0 10-Jan-16 A AC.Lot 1 TD 317: U3, Step 2 (Central Part Axes B-C) Concrete Works completed,
567 TD 341: U3, Step 3 (Draft Tube d/s Axis C) Concrete 0 25-May-16 A AC.Lot 1 TD 341: U3, Step 3 (Draft Tube d/s Axis C) Concrete Works completed,
U3, Draft
Dr Tube installation 421 07-Sep-14 31-Jan-16 A 31-Jan-16 A, U3, Draft Tube installation
570 Installation of embedded parts 25 07-Sep-14A 08-Oct-14 A AC.Lot 3 Installation of embedded parts
A
571 TD 309: Start DT Steel Liner U3 erection 0 31-Jan-15 A AC.Lot 3 TD 309: Start DT Steel Liner U3 erection
574 DT installation 35 31-Jan-15 A 11-Mar-15 A AC.Lot 3 DT installation
572 Draft Tube Sandblasting and painting 22 23-Apr-15 A 19-May-15 A AC.Lot 3 Draft Tube Sandblasting and painting
556 U3, Second Stage(Concrete for DT) 67 25-May-15 13-Aug-15 A AC.Lot 1 U3, Second Stage(Concrete for DT)
A
573 TD 342: Lot 2, U3 Draft Tube Area, Start of fixed Part 0 31-Jan-16 A AC.Lot 3 TD 342: Lot 2, U3 Draft Tube Area, Start of fixed Part Installation
U3, Stayring
St installation 472 01-Sep-14 23-Mar-16 A 23-Mar-16 A, U3, Stayring installation
576 Installation of embedded parts 12 01-Sep-14 14-Sep-14 A AC.Lot 3 Installation of embedded parts
A
579 TD 345: Stayring and Pier Nose U3 installation in pit ( r 0 10-Feb-16 AC.Lot 3 TD 345: Stayring and Pier Nose U3 installation in pit ( revised )
A
580 Stayring installation in pit 25 10-Feb-16 09-Mar-16 A AC.Lot 3 Stayring installation in pit
A
577 Installation of embedded parts for horizontal adjustmen 12 10-Mar-16 23-Mar-16 A AC.Lot 3 Installation of embedded parts for horizontal adjustment of generator
A
578 TD 348: Stayring & Pier Nose U3 Installation in the pit 0 10-Mar-16 AC.Lot 3 TD 348: Stayring & Pier Nose U3 Installation in the pit ready for concrete
A
U3, Turbine
Tu & Generator Main Installation 489 12-Apr-16 A 18-Nov-17 A 18-Nov-17 A, U3, Turbine & Generator Main Installation
565 TD 349: Start U3 u/s Transition Zone Concrete Works 0 12-Apr-16 A AC.Lot 1 TD 349: Start U3 u/s Transition Zone Concrete Works up to EL. 42.10, 12-Apr-16 A
564 U3, Second Stage Concrete Works U3, EL 27.20 to 42 102 13-Apr-16 A 17-Aug-16 A AC.Lot 1 U3, Second Stage Concrete Works U3, EL 27.20 to 42.10, Axes B-C
566 TD 355: U3 u/s Transition Zone Concrete Works up to 0 17-Aug-16 A AC.Lot 1 TD 355: U3 u/s Transition Zone Concrete Works up to EL. 42.10 completed,
560 U3, Second Stage(Concrete for Hatch Cover) 4 18-Aug-16 23-Aug-16 A AC.Lot 1 U3, Second Stage(Concrete for Hatch Cover)
A
583 TD 361: Start Turbine and Generator Erection U3 0 04-Sep-16 AC.Lot 3 TD 361: Start Turbine and Generator Erection U3
A
582 Installation Distributor anchoring, distributor & discharg 63 05-Sep-16 23-Nov-16 A AC.Lot 3 Installation Distributor anchoring, distributor & discharge ring
A
561 U3, Second stage Concrete for anchoring (Turbine & 19 24-Nov-16 17-Dec-16 A AC.Lot 1 U3, Second stage Concrete for anchoring (Turbine & Generator Main Installation)
A
587 Main installation: turbine + generator incl. Piping & aux 286 18-Dec-16 18-Nov-17 A AC.Lot 3 Main installation: turbine + generator incl. Piping & auxiliarie
A
585 Generator hatch cover installation 0 21-Apr-17 A 22-Apr-17 A AC.Lot 3 Generator hatch cover installation
586 TD 356: Generator hatch cover installation 0 21-Apr-17 A AC.Lot 3 TD 356: Generator hatch cover installation
584 Sandblasting and painting hatch cover 5 24-Apr-17 A 30-Apr-17 A AC.Lot 3 Sandblasting and painting hatch cover
U3, Trash
Tra Rack installation 353 31-Jan-15 A 30-Mar-16 A 30-Mar-16 A, U3, Trash Rack installation
590 Installation of embedded parts - 1st stage 25 31-Jan-15 A 28-Feb-15 A AC.Lot 3 Installation of embedded parts - 1st stage
591 Installation of embedded parts - 2nd stage 50 29-Jul-15 A 28-Sep-15 A AC.Lot 3 Installation of embedded parts - 2nd stage
592 Installation of fish beams 50 29-Sep-15 28-Nov-15 A AC.Lot 3 Installation of fish beams
A
589 TD 333: Lot 2 & 3, U3 Inlet Area, Start of fixed Part Ins 0 02-Nov-15 AC.Lot 3 TD 333: Lot 2 & 3, U3 Inlet Area, Start of fixed Part Installation
A
558 U3, Second Stage(Concrete for Fish Beam) 17 07-Feb-16 27-Feb-16 A AC.Lot 1 U3, Second Stage(Concrete for Fish Beam)
A
593 TR installation 27 29-Feb-16 30-Mar-16 A AC.Lot 3 TR installation
A
U3, Stop
St log U/S 98 31-Jan-16 A 28-May-16 A 28-May-16 A, U3, Stop log U/S
595 Installation of embedded parts - 1st stage 12 31-Jan-16 A 14-Feb-16 A AC.Lot 2 Installation of embedded parts - 1st stage
596 Installation of embedded parts - 2nd stage (sill beam + 31 15-Feb-16 22-Mar-16 A AC.Lot 2 Installation of embedded parts - 2nd stage (sill beam + side guides)
A
557 U3, Second Stage(Concrete for U/S Stop Log) 38 26-Mar-16 12-May-16 A AC.Lot 1 U3, Second Stage(Concrete for U/S Stop Log)
A
597 Stop log U/S installation 12 13-May-16 28-May-16 A AC.Lot 2 Stop log U/S installation
A
U3, Stop
St log D/S (DS Draft Tube Bulkheads ) 57 24-Mar-16 02-Jun-16 A 02-Jun-16 A, U3, Stop log D/S (DS Draft Tube Bulkheads )
599 Installation of embedded parts - 1st stage 13 A 09-Apr-16 A
24-Mar-16 AC.Lot 2 Installation of embedded parts - 1st stage
A
600 Installation of embedded parts - 2nd stage (sill beam + 21 10-Apr-16 A 08-May-16 A AC.Lot 2 Installation of embedded parts - 2nd stage (sill beam + side guides)
559 U3, Second Stage(Concrete for D/S Stop Log) 16 27-Apr-16 A 18-May-16 A AC.Lot 1 U3, Second Stage(Concrete for D/S Stop Log)
601 Stop log D/S installation 13 18-May-16 02-Jun-16 A AC.Lot 2 Stop log D/S installation
A
UNIT (4) 1004 02-Sep-14 20-Dec-17 A 20-Dec-17 A, UNIT (4)
U4 Lot
Lo 1 / Concrete Works 559 02-Sep-14A 10-Jul-16 A 10-Jul-16 A, U4 Lot 1 / Concrete Works
604 TD 304: Start U4 First Stage Concrete Works 0 02-Sep-14A AC.Lot 1 TD 304: Start U4 First Stage Concrete Works, 02-Sep-14 A
A
605 U4, Step 1-a (DT Steel Liner Foundation Axis C:B ) 63 02-Sep-14 17-Nov-14 A AC.Lot 1 U4, Step 1-a (DT Steel Liner Foundation Axis C:B )
A
607 U2, Step 1-b ( U/S Axis B: A) 47 04-Dec-14 31-Jan-15 A AC.Lot 1 U2, Step 1-b ( U/S Axis B: A)
A
606 U4, Step 2 (Central Part Axes B-C) 324 14-Jan-15 A 11-Feb-16 A AC.Lot 1 U4, Step 2 (Central Part Axes B-C)
610 U4, Step 3 (Draft Tube Part d/s Axis C) 132 09-Aug-15 16-Jan-16 A AC.Lot 1 U4, Step 3 (Draft Tube Part d/s Axis C)
A
609 U4, Step 2a (Inlet Part u/s Axis B) 121 02-Sep-15 30-Jan-16 A AC.Lot 1 U4, Step 2a (Inlet Part u/s Axis B)
A
623 d/s Separation Bored Pile Wall 170 17-Dec-15 10-Jul-16 A AC.Lot 1 d/s Separation Bored Pile Wall
A
617 TD 332: U4, Step 2a (Inlet Part u/s Axis B) Concrete W 0 31-Jan-16 A AC.Lot 1 TD 332: U4, Step 2a (Inlet Part u/s Axis B) Concrete Works completed,
613 TD 320: U4, Step 2 (Central Part Axes B-C) Concrete 0 11-Feb-16 A AC.Lot 1 TD 320: U4, Step 2 (Central Part Axes B-C) Concrete Works completed,
611 MS 1-06: PH-Unit 4, Step 3 Concrete Works complete 0 25-May-16 A AC.Lot 1 MS 1-06: PH-Unit 4, Step 3 Concrete Works complete,
U4, Draft
Dr Tube installation 380 28-Oct-14 A 31-Jan-16 A 31-Jan-16 A, U4, Draft Tube installation

Milestone Lot 1 Lot 2 Page 9 of 19


Milestone Lot 2 Lot 3
Milestone Lot 3 Lot 4
Milestone Lot 4 Remaining Work
Lot 1 Critical Remaining Work
New Assiut Barrage and Hydropower Plant Schedule Impletation Programme 12-Oct-18 13:45

Activity ID Activity Name Actual Actual Start Actual Finish The 2012 2013 2014 2015 2016 2017 2018 2019
Duration Contractor
M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M
625 Installation of embedded parts 25 28-Oct-14 A 25-Nov-14 A AC.Lot 3 Installation of embedded parts
626 TD 311: Start DT Steel Liner U4 erection 0 10-Jan-15 A AC.Lot 3 TD 311: Start DT Steel Liner U4 erection
630 DT installation 44 10-Jan-15 A 03-Mar-15 A AC.Lot 3 DT installation
629 MS 3-03: Unit 3&4 Draft Tube Erec. ready for Step 2 C 0 03-Mar-15 AC.Lot 3 MS 3-03: Unit 3&4 Draft Tube Erec. ready for Step 2 Concr. Works
A
618 U4, Second Stage(Concrete for DT) 160 04-Mar-15 13-Sep-15 A AC.Lot 1 U4, Second Stage(Concrete for DT)
A
608 TD 310: U4, Step 1 (Draft Tube Steel Liner Foundation 0 13-Sep-15 A AC.Lot 1 TD 310: U4, Step 1 (Draft Tube Steel Liner Foundation) Concrete Works completed,
628 Draft Tube Sandblasting and painting 35 14-Sep-15 30-Oct-15 A AC.Lot 3 Draft Tube Sandblasting and painting
A
627 TD 343: Lot 2, U4 Draft Tube Area, Start of fixed Part 0 31-Jan-16 A AC.Lot 3 TD 343: Lot 2, U4 Draft Tube Area, Start of fixed Part Installation
U4, Stayring
St installation 476 20-Oct-14 A 16-May-16 A 16-May-16 A, U4, Stayring installation
632 Installation of embedded parts 12 20-Oct-14 A 02-Nov-14 A AC.Lot 3 Installation of embedded parts
633 TD 351: Stayring and Pier Nose U4 installation in pit 0 27-Mar-16 AC.Lot 3 TD 351: Stayring and Pier Nose U4 installation in pit
A
635 Stayring installation in pit 25 31-Mar-16 30-Apr-16 A AC.Lot 3 Stayring installation in pit
A
634 Installation of embedded parts for horizontal adjustmen 12 03-May-16 16-May-16 A AC.Lot 3 Installation of embedded parts for horizontal adjustment of generator
A
U4, Turbine
Tu & Generator Main Installation 502 01-May-16 20-Dec-17 A 20-Dec-17 A, U4, Turbine & Generator Main Installation
615 TD 354: Start U4 u/s Transition Zone Concrete Works 0 A
01-May-16 AC.Lot 1 TD 354: Start U4 u/s Transition Zone Concrete Works up to EL. 42.10, 01-May-16 A
A
614 U4, Second Stage Concrete Works U4, EL 27.20 to 42 96 02-May-16 27-Aug-16 A AC.Lot 1 U4, Second Stage Concrete Works U4, EL 27.20 to 42.10, Axes B-C
A
616 TD 359: U4 u/s Transition Zone Concrete Works up to 0 28-Aug-16 A AC.Lot 1 TD 359: U4 u/s Transition Zone Concrete Works up to EL. 42.10 completed,
622 U4, Second Stage(Concrete for Hatch Cover) 6 28-Aug-16 04-Sep-16 A AC.Lot 1 U4, Second Stage(Concrete for Hatch Cover)
A
637 TD 362: Start Turbine and Generator Erection U4 0 26-Sep-16 AC.Lot 3 TD 362: Start Turbine and Generator Erection U4
A
638 Installation Distributor anchoring, distributor & discharg 46 26-Sep-16 20-Nov-16 A AC.Lot 3 Installation Distributor anchoring, distributor & discharge ring
A
612 U4, Second stage Concrete for anchoring (Turbine & 15 21-Nov-16 08-Dec-16 A AC.Lot 1 U4, Second stage Concrete for anchoring (Turbine & Generator Main Installation)
A
642 Main installation: turbine + generator incl. Piping & aux 321 09-Dec-16 20-Dec-17 A AC.Lot 3 Main installation: turbine + generator incl. Piping & auxil
A
641 TD 360: Generator hatch cover installation 0 17-Jan-17 A AC.Lot 3 TD 360: Generator hatch cover installation
640 Generator hatch cover installation 12 17-Jul-17 A 31-Jul-17 A AC.Lot 3 Generator hatch cover installation
639 Sandblasting and painting hatch cover 12 04-Oct-17 A 18-Oct-17 A AC.Lot 3 Sandblasting and painting hatch cover
U4, Trash
Tra Rack installation 347 15-Feb-15 08-Apr-16 A 08-Apr-16 A, U4, Trash Rack installation
645 Installation of embedded parts - 1st stage 25 15-Feb-15 15-Mar-15 A AC.Lot 3 Installation of embedded parts - 1st stage
A
646 Installation of embedded parts - 2nd stage 50 30-Jul-15 A 29-Sep-15 A AC.Lot 3 Installation of embedded parts - 2nd stage
647 Installation of fish beams 50 30-Sep-15 29-Nov-15 A AC.Lot 3 Installation of fish beams
A
644 TD 334: Lot 2 & 3, U4 Inlet Area, Start of fixed Part Ins 0 02-Nov-15 AC.Lot 3 TD 334: Lot 2 & 3, U4 Inlet Area, Start of fixed Part Installation
A
620 U4, Second Stage(Concrete for Fish Beam) 17 07-Feb-16 27-Feb-16 A AC.Lot 1 U4, Second Stage(Concrete for Fish Beam)
A
648 TR installation 35 28-Feb-16 08-Apr-16 A AC.Lot 3 TR installation
A
U4, Stop
St log U/S 116 16-Jan-16 A 04-Jun-16 A 04-Jun-16 A, U4, Stop log U/S
650 Installation of embedded parts - 1st stage 12 16-Jan-16 A 31-Jan-16 A AC.Lot 2 Installation of embedded parts - 1st stage
651 Installation of embedded parts - 2nd stage (sill beam + 60 01-Feb-16 11-Apr-16 A AC.Lot 2 Installation of embedded parts - 2nd stage (sill beam + side guides)
A
619 U4, Second Stage(Concrete for U/S Stop Log) 29 12-Apr-16 A 19-May-16 A AC.Lot 1 U4, Second Stage(Concrete for U/S Stop Log)
652 Stop log U/S installation 13 19-May-16 04-Jun-16 A AC.Lot 2 Stop log U/S installation
A
U4, Stop
St log D/S (DS Draft Tube Bulkheads ) 83 16-Feb-16 26-May-16 A 26-May-16 A, U4, Stop log D/S (DS Draft Tube Bulkheads )
654 Installation of embedded parts - 1st stage 10 16-Feb-16 28-Feb-16 A AC.Lot 2 Installation of embedded parts - 1st stage
A
655 Installation of embedded parts - 2nd stage (sill beam + 41 29-Feb-16 17-Apr-16 A AC.Lot 2 Installation of embedded parts - 2nd stage (sill beam + side guides)
A
621 U4, Second Stage(Concrete for D/S Stop Log) 17 18-Apr-16 A 11-May-16 A AC.Lot 1 U4, Second Stage(Concrete for D/S Stop Log)
656 Stop log D/S installation 13 11-May-16 26-May-16 A AC.Lot 2 Stop log D/S installation
A
FINISHING W
WORKS 512 01-Aug-16 28-Mar-18 A 28-Mar-18 A, FINISHING WORKS
658 Finishing works 512 A 28-Mar-18 A
01-Aug-16 AC.Lot 1 Finishing works
A
GANTRY CR
CRANES, TRASH R.C.& JIP CRANE 853 16-Apr-15 A 31-Jan-18 A 31-Jan-18 A, GANTRY CRANES, TRASH R.C.& J
PH Main Gantry Crane 407 16-Apr-15 A 22-Aug-16 A 22-Aug-16 A, PH Main Gantry Crane
665 PH Main Gantry Crane Rail on Pier 01 - Extension Bea 105 16-Apr-15 A 20-Aug-15 A AC.Lot 3 PH Main Gantry Crane Rail on Pier 01 - Extension Beam
663 TD 321: PH Main Gantry Crane operational 0 02-May-15 AC.Lot 3 TD 321: PH Main Gantry Crane operational
A
667 PH Main Gantry Crane Pre-assembly 24 07-May-15 04-Jun-15 A AC.Lot 3 PH Main Gantry Crane Pre-assembly
A
661 TD 312: Crane Runway Axes 6-8 ready for Rail Installa 0 04-Jul-15 A AC.Lot 3 TD 312: Crane Runway Axes 6-8 ready for Rail Installation
664 TD 314: Start of PH Main Gantry Crane Erection (Inter 0 20-Aug-15 AC.Lot 3 TD 314: Start of PH Main Gantry Crane Erection (Intermediate Pier/Unit1)
A
A2270 Commissioning and Load-Test 5 20-Sep-15 29-Sep-15 A AC.Lot 3 Commissioning and Load-Test
A
662 PH Main Gantry Crane Installation in unloading Area/ E 27 30-Nov-15 31-Dec-15 A AC.Lot 3 PH Main Gantry Crane Installation in unloading Area/ Extension Beams axis 1
A
666 Pouring fort PH Main G. Crane 24 07-May-16 04-Jun-16 A AC.Lot 1 Pouring fort PH Main G. Crane
A
A2280 Final Acceptance Test 0 22-Aug-16 A AC.Lot 3 Final Acceptance Test
Jib Crane 343 30-Jun-15 A 21-Aug-16 A 21-Aug-16 A, Jib Crane
669 Embedded plates fort Jib crane ( Pier axis 16 ) 22 30-Jun-15 A 28-Jul-15 A AC.Lot 3 Embedded plates fort Jib crane ( Pier axis 16 )
670 Concreteting fort Jib crane ( Pier axis 16 ) 27 28-Jul-15 A 29-Aug-15 A AC.Lot 1 Concreteting fort Jib crane ( Pier axis 16 )
671 Installation of Jib crane ( Pier axis 16 ) 2 29-Aug-15 31-Aug-15 A AC.Lot 3 Installation of Jib crane ( Pier axis 16 )
A
A2290 Commissioning and Load-Test 7 11-Aug-16 20-Aug-16 A AC.Lot 3 Commissioning and Load-Test
A
A2300 Final Acceptance Test 0 21-Aug-16 A
DT Gantry
Gantr Crane 561 21-Feb-16 20-Dec-17 A 20-Dec-17 A, DT Gantry Crane
674 Concreteting for DT Gantry Crane 561 A 20-Dec-17 A
21-Feb-16 AC.Lot 1 Concreteting for DT Gantry Crane
A
675 DT Gantry Crane Erection 25 01-Mar-16 29-Mar-16 A AC.Lot 3 DT Gantry Crane Erection
A
673 DT Gantry Crane Rail Installation 46 02-Mar-16 25-Apr-16 A AC.Lot 3 DT Gantry Crane Rail Installation
A
A2310 Commissioning and Load-Test 9 25-Apr-16 A 09-May-16 A AC.Lot 3 Commissioning and Load-Test
A2320 Final Acceptance Test 0 10-May-16 A AC.Lot 3 Final Acceptance Test
PWH / Bridge
Br Crane 254 10-Apr-17 A 31-Jan-18 A 31-Jan-18 A, PWH / Bridge Crane
677 PWH / Bridge Crane Rail Installation 218 10-Apr-17 A 20-Dec-17 A AC.Lot 3 PWH / Bridge Crane Rail Installation
678 Concreteting fort PWH / Bridge Crane 209 30-Apr-17 A 30-Dec-17 A AC.Lot 1 Concreteting fort PWH / Bridge Crane
679 PWH / Bridge Crane Erection 198 13-Jun-17 A 30-Jan-18 A AC.Lot 3 PWH / Bridge Crane Erection
A2330 Commissioning and Load-Test 9 20-Jan-18 A 30-Jan-18 A AC.Lot 3 Commissioning and Load-Test
A2340 Final Acceptance Test 0 31-Jan-18 A AC.Lot 3 Final Acceptance Test
PH Trash Rack Cleaning Machine TRCM 225 21-Oct-15 A 17-Jul-16 A 17-Jul-16 A, PH Trash Rack Cleaning Machine TRCM

Milestone Lot 1 Lot 2 Page 10 of 19


Milestone Lot 2 Lot 3
Milestone Lot 3 Lot 4
Milestone Lot 4 Remaining Work
Lot 1 Critical Remaining Work
New Assiut Barrage and Hydropower Plant Schedule Impletation Programme 12-Oct-18 13:45

Activity ID Activity Name Actual Actual Start Actual Finish The 2012 2013 2014 2015 2016 2017 2018 2019
Duration Contractor
M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M
681 PWH Trash Conveyor Rail Installation 25 21-Oct-15 A 18-Nov-15 A AC.Lot 3 PWH Trash Conveyor Rail Installation
682 Concreteting fort TRCM 25 04-Nov-15 02-Dec-15 A AC.Lot 1 Concreteting fort TRCM
A
683 PWH Trash Rack Cleaning Machine (2x) Installation 50 18-May-16 17-Jul-16 A AC.Lot 3 PWH Trash Rack Cleaning Machine (2x) Installation
A
ELECTRICA WORKS
ELECTRICAL 517 03-Jan-16 A 13-Sep-17 A 13-Sep-17 A, ELECTRICAL WORKS
685 TD 337: U1 ready for cable tray installation 0 03-Jan-16 A AC.Lot 4 TD 337: U1 ready for cable tray installation
686 TD 338: U2 ready for cable tray installation 0 03-Jan-16 A AC.Lot 4 TD 338: U2 ready for cable tray installation
687 TD 339: U3 ready for cable tray installation 0 03-Jan-16 A AC.Lot 4 TD 339: U3 ready for cable tray installation
688 TD 340: U4 ready for cable tray installation 0 03-Jan-16 A AC.Lot 4 TD 340: U4 ready for cable tray installation
689 Cable Tray installation at level 42.75 and below 244 04-Jan-16 A 30-Oct-16 A AC.Lot 4 Cable Tray installation at level 42.75 and below
690 Installation of cables 494 01-Feb-16 13-Sep-17 A AC.Lot 4 Installation of cables
A
691 U1 - Installation of electrical equipment at level 45.15 a 401 01-Mar-16 26-Jun-17 A AC.Lot 4 U1 - Installation of electrical equipment at level 45.15 and below
A
692 U2 - Installation of electrical equipment at level 45.15 a 395 01-Apr-16 A 20-Jul-17 A AC.Lot 4 U2 - Installation of electrical equipment at level 45.15 and below
693 U3 - Installation of electrical equipment at level 45.15 a 392 01-May-16 14-Aug-17 A AC.Lot 4 U3 - Installation of electrical equipment at level 45.15 and below
A
694 U4 - Installation of electrical equipment at level 45.15 a 393 01-Jun-16 A 13-Sep-17 A AC.Lot 4 U4 - Installation of electrical equipment at level 45.15 and below
TESTING / C
COMMISSIONING & TRIAL OPERATION 471 31-Jan-17 A 02-Aug-18 A 02-Aug-18 A, TESTING / C
Unit 1 471 31-Jan-17 A 02-Aug-18 A 02-Aug-18 A, Unit 1
1321 U1 Tests Lot3 & Lot 4 228 31-Jan-17 A 24-Oct-17 A AC.Lot 3 U1 Tests Lot3 & Lot 4
1317 U1 DT Gate, Intake Stoplogs Commissioning 62 07-Nov-17 18-Jan-18 A AC.Lot 2 U1 DT Gate, Intake Stoplogs Commissioning
A
1322 U1 Commissioning Lot3 & Lot 4 0 14-May-18 14-May-18 A AC.Lot 3 U1 Commissioning Lot3 & Lot 4
A
1323 U1 Trial Operation Lot3 & Lot 4 44 12-Jun-18 A 02-Aug-18 A AC.Lot 3 U1 Trial Operation Lot3 & L
A2560 Effective Date TOC,TURBINE, GENERATOR UNIT 1, 0 02-Aug-18 A AC.Lot 3 Effective Date TOC,TURB
Unit 2 285 01-Jun-17 A 30-Apr-18 A 30-Apr-18 A, Unit 2
1324 U2 Tests Lot3 & Lot 4 138 01-Jun-17 A 09-Nov-17 A AC.Lot 3 U2 Tests Lot3 & Lot 4
1325 U2 Commissioning Lot3 & Lot 4 114 09-Nov-17 22-Mar-18 A AC.Lot 3 U2 Commissioning Lot3 & Lot 4
A
1318 U2 DT Gate, Intake Stoplogs Commissioning 52 13-Nov-17 13-Jan-18 A AC.Lot 2 U2 DT Gate, Intake Stoplogs Commissioning
A
1326 U2 Trial Operation Lot3 & Lot 4 32 24-Mar-18 30-Apr-18 A AC.Lot 3 U2 Trial Operation Lot3 & Lot 4
A
A2530 Effective Date TOC,TURBINE, GENERATOR UNIT 2, 0 30-Apr-18 A AC.Lot 3 Effective Date TOC,TURBINE, GENER
Unit 3 324 23-May-17 05-Jun-18 A 05-Jun-18 A, Unit 3
1327 U3 Tests Lot3 & Lot 4 167 23-May-17A 04-Dec-17 A AC.Lot 3 U3 Tests Lot3 & Lot 4
A
1319 U3 DT Gate, Intake Stoplogs Commissioning 35 16-Dec-17 25-Jan-18 A AC.Lot 2 U3 DT Gate, Intake Stoplogs Commissioning
A
1328 U3 Commissioning Lot3 & Lot 4 58 28-Jan-18 A 05-Apr-18 A AC.Lot 3 U3 Commissioning Lot3 & Lot 4
1329 U3 Trial Operation Lot3 & Lot 4 55 02-Apr-18 A 05-Jun-18 A AC.Lot 3 U3 Trial Operation Lot3 & Lot 4
A2540 Effective Date TOC,TURBINE, GENERATOR UNIT 3, 0 05-Jun-18 A AC.Lot 3 Effective Date TOC,TURBINE, GE
Unit 4 327 28-May-17 13-Jun-18 A 13-Jun-18 A, Unit 4
1330 U4 Tests Lot3 & Lot 4 237 28-May-17 28-Feb-18 A AC.Lot 3 U4 Tests Lot3 & Lot 4
A
1320 U4 DT Gate, Intake Stoplogs Commissioning 17 06-Feb-18 26-Feb-18 A AC.Lot 2 U4 DT Gate, Intake Stoplogs Commissioning
A
1331 U4 Commissioning Lot3 & Lot 4 42 28-Feb-18 18-Apr-18 A AC.Lot 3 U4 Commissioning Lot3 & Lot 4
A
1332 U4 Trial Operation Lot3 & Lot 4 48 18-Apr-18 A 13-Jun-18 A AC.Lot 3 U4 Trial Operation Lot3 & Lot 4
A2550 Effective Date TOC,TURBINE, GENERATOR UNIT 4, 0 13-Jun-18 A AC.Lot 3 Effective Date TOC,TURBINE, G
SLUICEWAY A
AND ABUTMENT PIERS 1214 01-Apr-14 A 28-Mar-18 A 28-Mar-18 A, SLUICEWAY AND ABUTMEN
ABUTMENT PIER, AXIS 16 657 08-Apr-14 A 13-Jun-16 A 13-Jun-16 A, ABUTMENT PIER, AXIS 16
699 d/s Part - Slab 7 08-Apr-14 A 15-Apr-14 A AC.Lot 1 d/s Part - Slab
697 Central part - slab 58 15-Apr-14 A 25-Jun-14 A AC.Lot 1 Central part - slab
698 Central Part - Superstructure 312 01-Jul-14 A 13-Jul-15 A AC.Lot 1 Central Part - Superstructure
700 d/s Part - Superstructure 450 16-Dec-14 13-Jun-16 A AC.Lot 1 d/s Part - Superstructure
A
701 Main Gantry Crane Extension Beam Axis 16 8 01-Nov-15 10-Nov-15 A AC.Lot 1 Main Gantry Crane Extension Beam Axis 16
A
702 Auxiliary Building 65 05-Dec-15 21-Feb-16 A AC.Lot 1 Auxiliary Building
A
703 electrical works incl. commissioning 123 02-Jan-16 A 29-May-16 A AC.Lot 4 electrical works incl. commissioning
704 TD 270: Auxiliary Building concrete Works complete 0 31-Jan-16 A AC.Lot 1 TD 270: Auxiliary Building concrete Works complete,
ABUTMENT PIER, AXIS 1 628 01-Apr-14 A 03-May-16 A 03-May-16 A, ABUTMENT PIER, AXIS 1
708 d/s Part - Slab 12 01-Apr-14 A 15-Apr-14 A AC.Lot 1 d/s Part - Slab
706 Central part - slab 49 15-Apr-14 A 15-Jun-14 A AC.Lot 1 Central part - slab
707 Central Part - Superstructure 497 16-Apr-14 A 12-Dec-15 A AC.Lot 1 Central Part - Superstructure
709 US & DS Part - Superstructure 606 29-Apr-14 A 03-May-16 A AC.Lot 1 US & DS Part - Superstructure
710 Main Gantry Crane Extension Beam Axis 1 17 25-Mar-15 16-Apr-15 A AC.Lot 1 Main Gantry Crane Extension Beam Axis 1
A
711 TD 213: Main Gantry Crane Extension Beams Comple 0 18-Apr-15 A AC.Lot 1 TD 213: Main Gantry Crane Extension Beams Complete,
SLUICEWAY AXES 13-16
SLUICEWAY, 512 18-Sep-14 31-May-16 A 31-May-16 A, SLUICEWAY, AXES 13-16
GENERAL 512 18-Sep-14 31-May-16 A 31-May-16 A, GENERAL
Lot 1 / Concrete Works 512 18-Sep-14 31-May-16 A 31-May-16 A, Lot 1 / Concrete Works
722 TD 202: Start SLW - Axes 13-16 Concrete Works 0 A
18-Sep-14 AC.Lot 1 TD 202: Start SLW - Axes 13-16 Concrete Works, 18-Sep-14 A
A
716 Standard Pier 09, Axis 15 First Phase (Trun. Area On 146 20-Sep-14 15-Mar-15 A AC.Lot 1 Standard Pier 09, Axis 15 First Phase (Trun. Area On Hold)
A
723 Standard Pier 10, Axis 16 First Phase (Trun. Area On 131 10-Oct-14 A 15-Mar-15 A AC.Lot 1 Standard Pier 10, Axis 16 First Phase (Trun. Area On Hold)
718 Standard Pier 08, Axis 14 First Phase (Trun. Area On 139 24-Nov-14 11-May-15 A AC.Lot 1 Standard Pier 08, Axis 14 First Phase (Trun. Area On Hold)
A
715 Standard Pier 10, Axis 16 Second Phase 123 17-Mar-15 13-Aug-15 A AC.Lot 1 Standard Pier 10, Axis 16 Second Phase
A
721 Standard Pier 07, Axis 13 First Phase (Trun. Area On 51 07-Apr-15 A 09-Jun-15 A AC.Lot 1 Standard Pier 07, Axis 13 First Phase (Trun. Area On Hold)
717 Standard Pier 09, Axis 15 Second Phase 26 16-Apr-15 A 17-May-15 A AC.Lot 1 Standard Pier 09, Axis 15 Second Phase
720 Standard Pier 08, Axis 14 Second Phase 72 15-May-15 10-Aug-15 A AC.Lot 1 Standard Pier 08, Axis 14 Second Phase
A
719 Standard Pier 07, Axis 13 Second Phase 160 12-Jun-15 A 24-Dec-15 A AC.Lot 1 Standard Pier 07, Axis 13 Second Phase
725 Downstream Slab / between axes ( 16:13 ) 98 03-Feb-16 31-May-16 A AC.Lot 1 Downstream Slab / between axes ( 16:13 )
A
Lot 2 //Fixed parts installation 265 14-Mar-15 31-Jan-16 A 31-Jan-16 A, Lot 2 /Fixed parts installation
731 Trunnion installation Pier 10 69 14-Mar-15 06-Jun-15 A AC.Lot 2 Trunnion installation Pier 10
A
732 Trunnion installation Pier 09 20 14-Mar-15 06-Apr-15 A AC.Lot 2 Trunnion installation Pier 09
A
727 TD 203: Pier 10, Axis 16, Access Lot 2, Trunnion Erec 0 15-Mar-15 AC.Lot 2 TD 203: Pier 10, Axis 16, Access Lot 2, Trunnion Erection
A
729 TD 204: Pier 09, Axis 15, Access Lot 2, Trunnion Erec 0 15-Mar-15 AC.Lot 2 TD 204: Pier 09, Axis 15, Access Lot 2, Trunnion Erection
A

Milestone Lot 1 Lot 2 Page 11 of 19


Milestone Lot 2 Lot 3
Milestone Lot 3 Lot 4
Milestone Lot 4 Remaining Work
Lot 1 Critical Remaining Work
New Assiut Barrage and Hydropower Plant Schedule Impletation Programme 12-Oct-18 13:45

Activity ID Activity Name Actual Actual Start Actual Finish The 2012 2013 2014 2015 2016 2017 2018 2019
Duration Contractor
M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M
734 Trunnion installation Pier 08 26 14-May-15 14-Jun-15 A AC.Lot 2 Trunnion installation Pier 08
A
733 TD 206: Pier 08, Axis 14, Access Lot 2, Trunnion Erec 0 17-May-15 AC.Lot 2 TD 206: Pier 08, Axis 14, Access Lot 2, Trunnion Erection
A
728 TD 209: Pier 07, Axis 13, Access Lot 2, Trunnion Erec 0 16-Jun-15 A AC.Lot 2 TD 209: Pier 07, Axis 13, Access Lot 2, Trunnion Erection
735 Cylinder Support installation Pier 09 38 15-Dec-15 31-Jan-16 A AC.Lot 2 Cylinder Support installation Pier 09
A
736 Cylinder Support installation Pier 08 27 28-Dec-15 31-Jan-16 A AC.Lot 2 Cylinder Support installation Pier 08
A
730 Cylinder Support installation Pier 07 17 10-Jan-16 A 31-Jan-16 A AC.Lot 2 Cylinder Support installation Pier 07
737 Trunnion installation Pier 07 17 10-Jan-16 A 31-Jan-16 A AC.Lot 2 Trunnion installation Pier 07
738 Cylinder Support installation Pier 10 17 10-Jan-16 A 31-Jan-16 A AC.Lot 2 Cylinder Support installation Pier 10
BAY 8, AX
AXES 15-16 298 01-Jun-15 A 28-May-16 A 28-May-16 A, BAY 8, AXES 15-16
Stop LLogs ( D/s & U/s ) 124 29-Dec-15 28-May-16 A 28-May-16 A, Stop Logs ( D/s & U/s )
745 Sill beam installation (for stop log D/S) 90 29-Dec-15A 14-Apr-16 A AC.Lot 2 Sill beam installation (for stop log D/S)
A
742 Sill beam installation (for stop log U/S) 12 13-Jan-16 A 27-Jan-16 A AC.Lot 2 Sill beam installation (for stop log U/S)
744 Side guides installation (for stop log D/S) 79 13-Jan-16 A 15-Apr-16 A AC.Lot 2 Side guides installation (for stop log D/S)
741 Side guides installation (for stop log U/S) 25 28-Jan-16 A 25-Feb-16 A AC.Lot 2 Side guides installation (for stop log U/S)
749 2nd Stage Concrete, Bay 8 for US/Stop Logs 46 27-Feb-16 20-Apr-16 A AC.Lot 1 2nd Stage Concrete, Bay 8 for US/Stop Logs
A
750 2nd Stage Concrete, Bay 8 for D/S Stop Logs 18 15-Apr-16 A 10-May-16 A AC.Lot 1 2nd Stage Concrete, Bay 8 for D/S Stop Logs
751 TD 222: Bay 8, 2nd Stage Concrete Works complete 0 11-May-16 AC.Lot 1 TD 222: Bay 8, 2nd Stage Concrete Works complete, 11-May-16 A
A
743 Stop log U/S installation 11 15-May-16 28-May-16 A AC.Lot 2 Stop log U/S installation
A
746 Stop log D/S installation 11 15-May-16 28-May-16 A AC.Lot 2 Stop log D/S installation
A
Radial Gate 94 01-Jun-15 A 21-Sep-15 A 21-Sep-15 A, Radial Gate
754 TD 210: Bay 8, Axes 15-16, Access Lot 2, fixed Parts 0 01-Jun-15 A AC.Lot 2 TD 210: Bay 8, Axes 15-16, Access Lot 2, fixed Parts Installation
759 Side guides installation (for radial gate) 32 07-Jun-15 A 14-Jul-15 A AC.Lot 2 Side guides installation (for radial gate)
760 Sill beam installation (for radial gate) 12 30-Jun-15 A 14-Jul-15 A AC.Lot 2 Sill beam installation (for radial gate)
761 TD 220: Bay 8, Axes 15-16, fixed Parts Installation Co 0 14-Jul-15 A AC.Lot 2 TD 220: Bay 8, Axes 15-16, fixed Parts Installation Complete
752 2nd Stage Concrete, Bay 8 for Radial Gate Installation 26 15-Jul-15 A 17-Aug-15 A AC.Lot 1 2nd Stage Concrete, Bay 8 for Radial Gate Installation
755 Pre erection of radial gate in storage yard, Bay 8 23 15-Jul-15 A 13-Aug-15 A AC.Lot 2 Pre erection of radial gate in storage yard, Bay 8
756 TD 223: Bay 8, Start of Radial Gate Erection 0 16-Aug-15 AC.Lot 2 TD 223: Bay 8, Start of Radial Gate Erection
A
757 Radial gate erection, Bay 8 24 17-Aug-15 14-Sep-15 A AC.Lot 2 Radial gate erection, Bay 8
A
758 TD 227: Bay 8, Radial Gate Erection Complete 0 21-Sep-15 AC.Lot 2 TD 227: Bay 8, Radial Gate Erection Complete
A
Beams for gantry crane & Service bridge 158 22-Jun-15 A 31-Dec-15 A 31-Dec-15 A, Beams for gantry crane & Service bridge
766 Service Bridge, Bay 8 12 22-Jun-15 A 06-Jul-15 A AC.Lot 1 Service Bridge, Bay 8
763 TD 230: Bay 8, Start of SLW Gantry Crane u/s Beam 0 18-Jul-15 A AC.Lot 2 TD 230: Bay 8, Start of SLW Gantry Crane u/s Beam
765 u/s Gantry Crane Beam, Bay 8 11 27-Jul-15 A 09-Aug-15 A AC.Lot 1 u/s Gantry Crane Beam, Bay 8
764 d/s Gantry Crane Beam, Bay 8 & Precast Trash Conve 11 23-Aug-15 05-Sep-15 A AC.Lot 1 d/s Gantry Crane Beam, Bay 8 & Precast Trash Conveyor channel
A
768 Installation of precast elements U/S G.Crane 4 22-Oct-15 A 27-Oct-15 A AC.Lot 1 Installation of precast elements U/S G.Crane
769 Installation of precast elements D/S ( Service Bridge & 7 28-Oct-15 A 05-Nov-15 A AC.Lot 1 Installation of precast elements D/S ( Service Bridge & D/S G.Crane )
767 Gantry crane rails installation 36 07-Nov-15 19-Dec-15 A AC.Lot 2 Gantry crane rails installation
A
748 2nd Stage Concrete, Bay 8 for G. Crane Rails 11 19-Dec-15 31-Dec-15 A AC.Lot 1 2nd Stage Concrete, Bay 8 for G. Crane Rails
A
Electri
Electrical works 158 06-Sep-15 16-Mar-16 A 16-Mar-16 A, Electrical works
771 Hydraulic SLW radial gate, Bay 8 135 06-Sep-15 18-Feb-16 A AC.Lot 4 Hydraulic SLW radial gate, Bay 8
A
772 Electrical SLW radial gate, Bay 8 158 06-Sep-15 16-Mar-16 A AC.Lot 4 Electrical SLW radial gate, Bay 8
A
BAY 7, AX
AXES 14-15 253 24-Jul-15 A 26-May-16 A 26-May-16 A, BAY 7, AXES 14-15
Stop LLogs ( D/s & U/s ) 110 14-Jan-16 A 26-May-16 A 26-May-16 A, Stop Logs ( D/s & U/s )
775 Side guides installation (for stop log U/S) 42 14-Jan-16 A 05-Mar-16 A AC.Lot 2 Side guides installation (for stop log U/S)
776 Sill beam installation (for stop log U/S) 42 14-Jan-16 A 05-Mar-16 A AC.Lot 2 Sill beam installation (for stop log U/S)
778 Side guides installation (for stop log D/S) 30 05-Feb-16 10-Mar-16 A AC.Lot 2 Side guides installation (for stop log D/S)
A
779 Sill beam installation (for stop log D/S) 48 10-Feb-16 06-Apr-16 A AC.Lot 2 Sill beam installation (for stop log D/S)
A
784 2nd Stage Concrete, Bay 7 for US/Stop Logs 49 23-Feb-16 20-Apr-16 A AC.Lot 1 2nd Stage Concrete, Bay 7 for US/Stop Logs
A
785 2nd Stage Concrete, Bay 7 for DS/Stop Logs 18 15-Apr-16 A 10-May-16 A AC.Lot 1 2nd Stage Concrete, Bay 7 for DS/Stop Logs
782 TD 228: Bay 7, 2nd Stage Concrete Works complete 0 11-May-16 A AC.Lot 1 TD 228: Bay 7, 2nd Stage Concrete Works complete,
780 Stop log D/S installation 11 14-May-16 26-May-16 A AC.Lot 2 Stop log D/S installation
A
777 Stop log U/S installation 9 16-May-16 26-May-16 A AC.Lot 2 Stop log U/S installation
A
Radial Gate 103 24-Jul-15 A 26-Nov-15 A 26-Nov-15 A, Radial Gate
788 TD 215: Bay 7, Axes 15-16, Access Lot 2, fixed Parts 0 24-Jul-15 A AC.Lot 2 TD 215: Bay 7, Axes 15-16, Access Lot 2, fixed Parts Installation
791 Side guides installation (for radial gate) 17 25-Jul-15 A 13-Aug-15 A AC.Lot 2 Side guides installation (for radial gate)
792 Sill beam installation (for radial gate) 17 25-Jul-15 A 13-Aug-15 A AC.Lot 2 Sill beam installation (for radial gate)
786 2nd Stage Concrete, Bay 7 for Radial Gate Installation 2 15-Aug-15 17-Aug-15 A AC.Lot 1 2nd Stage Concrete, Bay 7 for Radial Gate Installation
A
789 Pre erection of radial gate in storage yard, Bay 7 37 03-Sep-15 21-Oct-15 A AC.Lot 2 Pre erection of radial gate in storage yard, Bay 7
A
790 TD 231: Bay 7, Start of Radial Gate Erection 0 03-Sep-15 AC.Lot 2 TD 231: Bay 7, Start of Radial Gate Erection
A
795 Radial gate erection, Bay 7 67 03-Sep-15 26-Nov-15 A AC.Lot 2 Radial gate erection, Bay 7
A
793 TD 225: Bay 7, Axes 14-15, fixed Parts Installation Co 0 17-Sep-15 A AC.Lot 2 TD 225: Bay 7, Axes 14-15, fixed Parts Installation Complete
794 TD 236: Bay 7, Radial Gate Erection Complete 0 26-Nov-15 A AC.Lot 2 TD 236: Bay 7, Radial Gate Erection Complete
Beams for gantry crane & Service bridge 206 08-Aug-15 12-Apr-16 A 12-Apr-16 A, Beams for gantry crane & Service bridge
801 Service Bridge, Bay 7 24 08-Aug-15 05-Sep-15 A AC.Lot 1 Service Bridge, Bay 7
A
797 TD 239: Bay 7, Start of SLW Gantry Crane u/s Beam 0 13-Sep-15 AC.Lot 2 TD 239: Bay 7, Start of SLW Gantry Crane u/s Beam
A
798 d/s Gantry Crane Beam Bay 7 & Precast Trash Conve 10 18-Sep-15 05-Oct-15 A AC.Lot 1 d/s Gantry Crane Beam Bay 7 & Precast Trash Conveyor channel
A
799 u/s Gantry Crane Beam, Bay 7 10 18-Sep-15 05-Oct-15 A AC.Lot 1 u/s Gantry Crane Beam, Bay 7
A
802 Installation of precast elements U/S G.Crane 4 08-Dec-15 13-Dec-15 A AC.Lot 1 Installation of precast elements U/S G.Crane
A
803 Installation of precast elements D/S ( Service Bridge & 12 17-Dec-15 31-Dec-15 A AC.Lot 1 Installation of precast elements D/S ( Service Bridge & D/S G.Crane )
A
800 Gantry crane rails installation 37 17-Feb-16 31-Mar-16 A AC.Lot 2 Gantry crane rails installation
A
783 2nd Stage Concrete, Bay 7 for G. Crane Rails 41 24-Feb-16 12-Apr-16 A AC.Lot 1 2nd Stage Concrete, Bay 7 for G. Crane Rails
A
Electri
Electrical works 59 10-Jan-16 A 20-Mar-16 A 20-Mar-16 A, Electrical works
805 Hydraulic SLW radial gate, Bay 7 36 10-Jan-16 A 22-Feb-16 A AC.Lot 4 Hydraulic SLW radial gate, Bay 7
806 Electrical SLW radial gate, Bay 7 59 10-Jan-16 A 20-Mar-16 A AC.Lot 4 Electrical SLW radial gate, Bay 7

Milestone Lot 1 Lot 2 Page 12 of 19


Milestone Lot 2 Lot 3
Milestone Lot 3 Lot 4
Milestone Lot 4 Remaining Work
Lot 1 Critical Remaining Work
New Assiut Barrage and Hydropower Plant Schedule Impletation Programme 12-Oct-18 13:45

Activity ID Activity Name Actual Actual Start Actual Finish The 2012 2013 2014 2015 2016 2017 2018 2019
Duration Contractor
M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M
BAY 6, AX
AXES 13-14 295 06-Jun-15 A 29-May-16 A 29-May-16 A, BAY 6, AXES 13-14
Stop LLogs ( D/s & U/s ) 103 25-Jan-16 A 29-May-16 A 29-May-16 A, Stop Logs ( D/s & U/s )
809 Side guides installation (for stop log U/S) 38 25-Jan-16 A 10-Mar-16 A AC.Lot 2 Side guides installation (for stop log U/S)
810 Sill beam installation (for stop log U/S) 38 25-Jan-16 A 10-Mar-16 A AC.Lot 2 Sill beam installation (for stop log U/S)
812 Side guides installation (for stop log D/S) 46 25-Feb-16 19-Apr-16 A AC.Lot 2 Side guides installation (for stop log D/S)
A
813 Sill beam installation (for stop log D/S) 46 25-Feb-16 19-Apr-16 A AC.Lot 2 Sill beam installation (for stop log D/S)
A
817 2nd Stage Concrete, Bay 6 US/for Stop Logs 38 13-Mar-16 27-Apr-16 A AC.Lot 1 2nd Stage Concrete, Bay 6 US/for Stop Logs
A
818 2nd Stage Concrete, Bay 6 for DS/Stop Logs 22 21-Apr-16 A 21-May-16 A AC.Lot 1 2nd Stage Concrete, Bay 6 for DS/Stop Logs
811 Stop log U/S installation 11 16-May-16 29-May-16 A AC.Lot 2 Stop log U/S installation
A
814 Stop log D/S installation 11 16-May-16 29-May-16 A AC.Lot 2 Stop log D/S installation
A
819 TD 237: Bay 6, 2nd Stage Concrete Works complete 0 21-May-16 A AC.Lot 1 TD 237: Bay 6, 2nd Stage Concrete Works complete,
Radial Gate 93 02-Sep-15 24-Dec-15 A 24-Dec-15 A, Radial Gate
822 TD 218: Bay 6, Axes 13-14, Access Lot 2, fixed Parts 0 A
02-Sep-15 AC.Lot 2 TD 218: Bay 6, Axes 13-14, Access Lot 2, fixed Parts Installation
A
827 Side guides installation (for radial gate) 26 02-Sep-15 08-Oct-15 A AC.Lot 2 Side guides installation (for radial gate)
A
828 Sill beam installation (for radial gate) 26 02-Sep-15 08-Oct-15 A AC.Lot 2 Sill beam installation (for radial gate)
A
820 2nd Stage Concrete, Bay 6 for Radial Gate Installation 17 09-Oct-15 A 29-Oct-15 A AC.Lot 1 2nd Stage Concrete, Bay 6 for Radial Gate Installation
829 TD 232: Bay 6, Axes 13-14, fixed Parts Installation Co 0 09-Oct-15 A AC.Lot 2 TD 232: Bay 6, Axes 13-14, fixed Parts Installation Complete
824 Pre erection of radial gate in storage yard, Bay 6 24 21-Oct-15 A 18-Nov-15 A AC.Lot 2 Pre erection of radial gate in storage yard, Bay 6
825 Radial gate erection, Bay 6 24 29-Oct-15 A 26-Nov-15 A AC.Lot 2 Radial gate erection, Bay 6
823 TD 240: Bay 6, Start of Radial Gate Erection 0 20-Nov-15 A AC.Lot 2 TD 240: Bay 6, Start of Radial Gate Erection
826 TD 246: Bay 6, Radial Gate Erection Complete 0 24-Dec-15 A AC.Lot 2 TD 246: Bay 6, Radial Gate Erection Complete
Beams for gantry crane & Service bridge 268 06-Jun-15 A 24-Apr-16 A 24-Apr-16 A, Beams for gantry crane & Service bridge
831 TD 248: Bay 6, Start of SLW Gantry Crane u/s Beam 0 06-Jun-15 A AC.Lot 1 TD 248: Bay 6, Start of SLW Gantry Crane u/s Beam, 06-Jun-15 A
833 u/s Gantry Crane Beam, Bay 6 13 08-Oct-15 A 24-Oct-15 A AC.Lot 1 u/s Gantry Crane Beam, Bay 6
834 Service Bridge, Bay 6 25 15-Nov-15 14-Dec-15 A AC.Lot 1 Service Bridge, Bay 6
A
836 Installation of precast elements U/S G.Crane 5 10-Dec-15 16-Dec-15 A AC.Lot 1 Installation of precast elements U/S G.Crane
A
832 d/s Gantry Crane Beam, Bay 6 & Precast Trash Conve 7 15-Dec-15 23-Dec-15 A AC.Lot 1 d/s Gantry Crane Beam, Bay 6 & Precast Trash Conveyor channel
A
837 Installation of precast elements D/S ( Service Bridge & 11 02-Jan-16 A 16-Jan-16 A AC.Lot 1 Installation of precast elements D/S ( Service Bridge & D/S G.Crane )
835 TD 253: Bays 6-8 Gantry Crane Beams Ready for Rai 0 03-Jan-16 A AC.Lot 2 TD 253: Bays 6-8 Gantry Crane Beams Ready for Rail Installation
838 Gantry crane rails installation 50 17-Feb-16 16-Apr-16 A AC.Lot 2 Gantry crane rails installation
A
816 2nd Stage Concrete, Bay 6 for G. Crane Rails 5 18-Apr-16 A 24-Apr-16 A AC.Lot 1 2nd Stage Concrete, Bay 6 for G. Crane Rails
Electri
Electrical works 77 29-Jan-16 A 30-Apr-16 A 30-Apr-16 A, Electrical works
841 TD 267: SLW, Axes 13-16, Access Lot 4, Cable Tray I 0 29-Jan-16 A AC.Lot 4 TD 267: SLW, Axes 13-16, Access Lot 4, Cable Tray Installation
840 Hydraulic SLW radial gate, Bay 6 36 30-Jan-16 A 12-Mar-16 A AC.Lot 4 Hydraulic SLW radial gate, Bay 6
842 Electrical SLW radial gate, Bay 6 76 31-Jan-16 A 30-Apr-16 A AC.Lot 4 Electrical SLW radial gate, Bay 6
SLUICEWAY AXES 1-6
SLUICEWAY, 543 01-Aug-14 18-May-16 A 18-May-16 A, SLUICEWAY, AXES 1-6
GENERAL 543 01-Aug-14 18-May-16 A 18-May-16 A, GENERAL
Lot 1 / Concrete Works 543 01-Aug-14 18-May-16 A 18-May-16 A, Lot 1 / Concrete Works
846 TD 201: Start SLW - Axes 01-06 Concrete Works 0 A
01-Aug-14 AC.Lot 1 TD 201: Start SLW - Axes 01-06 Concrete Works, 01-Aug-14 A
A
852 Standard Pier 1, Axis 1 First Phase (Trun. Area On Ho 113 02-Aug-14 15-Dec-14 A AC.Lot 1 Standard Pier 1, Axis 1 First Phase (Trun. Area On Hold)
A
854 Standard Pier 2, Axis 2 First Phase (Trun. Area On Ho 84 20-Sep-14 30-Dec-14 A AC.Lot 1 Standard Pier 2, Axis 2 First Phase (Trun. Area On Hold)
A
858 Standard Pier 3, Axis 3 First Phase (Trun. Area On Ho 96 15-Oct-14 A 07-Feb-15 A AC.Lot 1 Standard Pier 3, Axis 3 First Phase (Trun. Area On Hold)
856 Standard Pier 4, Axis 4 First Phase (Trun. Area On Ho 124 16-Oct-14 A 11-Mar-15 A AC.Lot 1 Standard Pier 4, Axis 4 First Phase (Trun. Area On Hold)
853 Standard Pier 1, Axis 1 Second Phase 86 16-Dec-14 29-Mar-15 A AC.Lot 1 Standard Pier 1, Axis 1 Second Phase
A
857 Standard Pier 2, Axis 2 Second Phase 73 31-Dec-14 29-Mar-15 A AC.Lot 1 Standard Pier 2, Axis 2 Second Phase
A
862 Standard Pier 5, Axis 5 First Phase (Trun. Area On Ho 43 10-Jan-15 A 02-Mar-15 A AC.Lot 1 Standard Pier 5, Axis 5 First Phase (Trun. Area On Hold)
860 Standard Pier 6, Axis 6 First Phase (Trun. Area On Ho 51 15-Jan-15 A 17-Mar-15 A AC.Lot 1 Standard Pier 6, Axis 6 First Phase (Trun. Area On Hold)
855 Standard Pier 3, Axis 3 Second Phase 128 08-Feb-15 11-Jul-15 A AC.Lot 1 Standard Pier 3, Axis 3 Second Phase
A
861 Standard Pier 4, Axis 4 Second Phase 145 23-Feb-15 17-Aug-15 A AC.Lot 1 Standard Pier 4, Axis 4 Second Phase
A
859 Standard Pier 5, Axis 5 Second Phase 171 03-Mar-15 28-Sep-15 A AC.Lot 1 Standard Pier 5, Axis 5 Second Phase
A
847 Standard Pier 6, Axis 6 Second Phase 215 18-Mar-15 06-Dec-15 A AC.Lot 1 Standard Pier 6, Axis 6 Second Phase
A
849 MS 1-04: SLW- Abutment & Standard Pier Axis 06 Firs 0 16-Jul-15 A AC.Lot 1 MS 1-04: SLW- Abutment & Standard Pier Axis 06 First Stage Concrete Works complete (Revised New Sequence),
848 Downstream Slab / First phase between axes ( 1:3 ) 105 14-Dec-15 17-Apr-16 A AC.Lot 1 Downstream Slab / First phase between axes ( 1:3 )
A
851 Downstream Slab / Second phase between axes ( 4:6 90 01-Feb-16 18-May-16 A AC.Lot 1 Downstream Slab / Second phase between axes ( 4:6 )
A
Lot 2 //Fixed parts installation 301 15-Dec-14 15-Dec-15 A 15-Dec-15 A, Lot 2 /Fixed parts installation
864 TD 205: Pier 1, Axis 1, Access Lot 2, Trunnion Erectio 0 15-Dec-14 AC.Lot 2 TD 205: Pier 1, Axis 1, Access Lot 2, Trunnion Erection (revised Sequence)
A
870 TD 208: Pier 2, Axis 2, Access Lot 2, Trunnion Erectio 0 15-Dec-14 AC.Lot 2 TD 208: Pier 2, Axis 2, Access Lot 2, Trunnion Erection (revised Sequence)
A
869 Trunnion installation Pier 1 18 18-Dec-14 10-Jan-15 A AC.Lot 2 Trunnion installation Pier 1
A
871 Trunnion installation Pier 2 43 30-Dec-14 21-Feb-15 A AC.Lot 2 Trunnion installation Pier 2
A
872 TD 211: Pier 3, Axis 3, Access Lot 2, Trunnion Erectio 0 14-Jan-15 A AC.Lot 2 TD 211: Pier 3, Axis 3, Access Lot 2, Trunnion Erection (revised Sequence)
873 Trunnion installation Pier 3 21 07-Feb-15 03-Mar-15 A AC.Lot 2 Trunnion installation Pier 3
A
874 TD 216: Pier 4, Axis 4, Access Lot 2, Trunnion Erectio 0 15-Feb-15 AC.Lot 2 TD 216: Pier 4, Axis 4, Access Lot 2, Trunnion Erection (revised Sequence)
A
867 Trunnion installation Pier 4 52 21-Feb-15 26-Apr-15 A AC.Lot 2 Trunnion installation Pier 4
A
868 TD 219: Pier 5, Axis 5, Access Lot 2, Trunnion Erectio 0 15-Mar-15 AC.Lot 2 TD 219: Pier 5, Axis 5, Access Lot 2, Trunnion Erection (revised Sequence)
A
877 Trunnion installation Pier 5 43 24-Mar-15 17-May-15 A AC.Lot 2 Trunnion installation Pier 5
A
880 Trunnion installation Pier 6 27 14-Apr-15 A 17-May-15 A AC.Lot 2 Trunnion installation Pier 6
878 TD 224: Pier 6, Axis 6, Access Lot 2, Trunnion Erectio 0 15-Apr-15 A AC.Lot 2 TD 224: Pier 6, Axis 6, Access Lot 2, Trunnion Erection (revised Sequence)
875 Cylinder Support installation Pier 1 101 01-Jun-15 A 04-Oct-15 A AC.Lot 2 Cylinder Support installation Pier 1
865 Cylinder Support installation Pier 2 133 13-Jun-15 A 23-Nov-15 A AC.Lot 2 Cylinder Support installation Pier 2
866 Cylinder Support installation Pier 3 84 12-Aug-15 24-Nov-15 A AC.Lot 2 Cylinder Support installation Pier 3
A
876 Cylinder Support installation Pier 4 52 19-Sep-15 24-Nov-15 A AC.Lot 2 Cylinder Support installation Pier 4
A
879 Cylinder Support installation Pier 5 43 04-Oct-15 A 24-Nov-15 A AC.Lot 2 Cylinder Support installation Pier 5
881 Cylinder Support installation Pier 6 13 30-Nov-15 15-Dec-15 A AC.Lot 2 Cylinder Support installation Pier 6
A
BAY 1, AX
AXES 1-2 353 01-Mar-15 02-May-16 A 02-May-16 A, BAY 1, AXES 1-2
A
Milestone Lot 1 Lot 2 Page 13 of 19
Milestone Lot 2 Lot 3
Milestone Lot 3 Lot 4
Milestone Lot 4 Remaining Work
Lot 1 Critical Remaining Work
New Assiut Barrage and Hydropower Plant Schedule Impletation Programme 12-Oct-18 13:46

Activity ID Activity Name Actual Actual Start Actual Finish The 2012 2013 2014 2015 2016 2017 2018 2019
Duration Contractor
M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M
Stop L
Logs ( D/s & U/s ) 201 31-Aug-15 02-May-16 A 02-May-16 A, Stop Logs ( D/s & U/s )
884 Sill beam installation (for stop log D/S) 24 A
31-Aug-15 01-Oct-15 A AC.Lot 2 Sill beam installation (for stop log D/S)
A
885 Side guides installation (for stop log D/S) 24 31-Aug-15 01-Oct-15 A AC.Lot 2 Side guides installation (for stop log D/S)
A
886 Sill beam installation (for stop log U/S) 32 20-Sep-15 02-Nov-15 A AC.Lot 2 Sill beam installation (for stop log U/S)
A
887 Side guides installation (for stop log U/S) 32 20-Sep-15 02-Nov-15 A AC.Lot 2 Side guides installation (for stop log U/S)
A
895 2nd Stage Concrete Bay 1 for DS/Stop Logs 41 01-Oct-15 A 21-Nov-15 A AC.Lot 1 2nd Stage Concrete Bay 1 for DS/Stop Logs
893 2nd Stage Concrete Bay 1 for US/Stop Logs 20 03-Nov-15 26-Nov-15 A AC.Lot 1 2nd Stage Concrete Bay 1 for US/Stop Logs
A
891 TD 233: Bay 1, 2nd Stage Concrete Works complete ( 0 26-Nov-15 A AC.Lot 1 TD 233: Bay 1, 2nd Stage Concrete Works complete (revised Sequence),
888 Stop log U/S installation 12 16-Apr-16 A 02-May-16 A AC.Lot 2 Stop log U/S installation
889 Stop log D/S installation 12 16-Apr-16 A 02-May-16 A AC.Lot 2 Stop log D/S installation
Radial Gate 95 01-Mar-15 23-Jun-15 A 23-Jun-15 A, Radial Gate
897 TD 217: Bay 1, Access Lot 2, fixed Parts Installation (r 0 01-Mar-15 AC.Lot 2 TD 217: Bay 1, Access Lot 2, fixed Parts Installation (revised Sequence)
A
898 Side guides installation (for radial gate) 31 29-Mar-15 07-May-15 A AC.Lot 2 Side guides installation (for radial gate)
A
899 Sill beam installation (for radial gate) 31 29-Mar-15 07-May-15 A AC.Lot 2 Sill beam installation (for radial gate)
A
900 TD 229: Bay 1, Axes 1-2, fixed Parts Installation Comp 0 16-Apr-15 A AC.Lot 2 TD 229: Bay 1, Axes 1-2, fixed Parts Installation Complete (revised Sequence)
892 2nd Stage Concrete Bay 1 for Radial Gate Installation 15 08-May-15 26-May-15 A AC.Lot 1 2nd Stage Concrete Bay 1 for Radial Gate Installation
A
902 TD 234: Bay 1, Start of Radial Gate Erection (revised S 0 16-May-15 AC.Lot 2 TD 234: Bay 1, Start of Radial Gate Erection (revised Sequence)
A
901 Pre erection of radial gate in storage yard, Bay 1 24 26-May-15 23-Jun-15 A AC.Lot 2 Pre erection of radial gate in storage yard, Bay 1
A
903 Radial gate erection, Bay 1 24 26-May-15 23-Jun-15 A AC.Lot 2 Radial gate erection, Bay 1
A
904 TD 241: Bay 1, Radial Gate Erection Complete (revise 0 16-Jun-15 A AC.Lot 2 TD 241: Bay 1, Radial Gate Erection Complete (revised Sequence)
Beams for gantry crane & Service bridge 206 09-Mar-15 16-Nov-15 A 16-Nov-15 A, Beams for gantry crane & Service bridge
909 Service Bridge, Bay 1 18 09-Mar-15 30-Mar-15 A AC.Lot 1 Service Bridge, Bay 1
A
908 U/S Gantry Crane Beam, Bay 1 10 16-Mar-15 28-Mar-15 A AC.Lot 1 U/S Gantry Crane Beam, Bay 1
A
907 D/S Gantry Crane Beam, Bay 1 8 07-Apr-15 A 19-Apr-15 A AC.Lot 1 D/S Gantry Crane Beam, Bay 1
910 Installation of precast elements D/S ( Service Bridge & 8 17-Jun-15 A 27-Jun-15 A AC.Lot 1 Installation of precast elements D/S ( Service Bridge & D/S G.Crane )
911 Installation of precast elements U/S G.Crane 6 15-Aug-15 22-Aug-15 A AC.Lot 1 Installation of precast elements U/S G.Crane
A
906 TD 243: Bay 1 Start of SLW Gantry Crane u/s Beam (r 0 02-Sep-15 AC.Lot 2 TD 243: Bay 1 Start of SLW Gantry Crane u/s Beam (revised Sequence)
A
912 Gantry crane rails installation 23 03-Sep-15 05-Oct-15 A AC.Lot 2 Gantry crane rails installation
A
894 2nd Stage Concrete Bay 1 for G. Crane Rails 5 10-Nov-15 16-Nov-15 A AC.Lot 1 2nd Stage Concrete Bay 1 for G. Crane Rails
A
Electri
Electrical works 162 01-Jul-15 A 16-Jan-16 A 16-Jan-16 A, Electrical works
915 Electrical SLW radial gate, Bay 1 35 01-Jul-15 A 13-Aug-15 A AC.Lot 4 Electrical SLW radial gate, Bay 1
914 Hydraulic SLW radial gate, Bay 1 86 05-Oct-15 A 16-Jan-16 A AC.Lot 4 Hydraulic SLW radial gate, Bay 1
BAY 2, AX
AXES 2-3 333 29-Mar-15 08-May-16 A 08-May-16 A, BAY 2, AXES 2-3
Stop LLogs ( D/s & U/s ) 180 03-Oct-15 A 08-May-16 A 08-May-16 A, Stop Logs ( D/s & U/s )
918 Side guides installation (for stop log U/S) 180 03-Oct-15 A 08-May-16 A AC.Lot 2 Side guides installation (for stop log U/S)
919 Sill beam installation (for stop log U/S) 30 03-Oct-15 A 09-Nov-15 A AC.Lot 2 Sill beam installation (for stop log U/S)
928 2nd Stage Concrete Bay 2 for US/Stop Logs 17 10-Nov-15 30-Nov-15 A AC.Lot 1 2nd Stage Concrete Bay 2 for US/Stop Logs
A
921 Side guides installation (for stop log D/S) 56 12-Nov-15 18-Jan-16 A AC.Lot 2 Side guides installation (for stop log D/S)
A
922 Sill beam installation (for stop log D/S) 56 12-Nov-15 18-Jan-16 A AC.Lot 2 Sill beam installation (for stop log D/S)
A
927 2nd Stage Concrete Bay 2 for DS/Stop Logs 37 19-Jan-16 A 03-Mar-16 A AC.Lot 1 2nd Stage Concrete Bay 2 for DS/Stop Logs
929 TD 242: Bay 2, 2nd Stage Concrete Works complete ( 0 03-Mar-16 A AC.Lot 1 TD 242: Bay 2, 2nd Stage Concrete Works complete (revised Sequence),
920 Stop log U/S installation 11 21-Apr-16 A 08-May-16 A AC.Lot 2 Stop log U/S installation
923 Stop log D/S installation 11 21-Apr-16 A 08-May-16 A AC.Lot 2 Stop log D/S installation
Radial Gate 91 30-Mar-15 19-Jul-15 A 19-Jul-15 A, Radial Gate
931 TD 221: Bay 2, Access Lot 2, fixed Parts Installation (r 0 30-Mar-15 AC.Lot 2 TD 221: Bay 2, Access Lot 2, fixed Parts Installation (revised Sequence)
A
933 Sill beam installation (for radial gate) 28 02-May-15 03-Jun-15 A AC.Lot 2 Sill beam installation (for radial gate)
A
932 Side guides installation (for radial gate) 50 03-May-15 30-Jun-15 A AC.Lot 2 Side guides installation (for radial gate)
A
935 Pre erection of radial gate in storage yard, Bay 2 51 04-May-15 02-Jul-15 A AC.Lot 2 Pre erection of radial gate in storage yard, Bay 2
A
934 TD 238: Bay 2, Axes 2-3, fixed Parts Installation Comp 0 16-May-15 AC.Lot 2 TD 238: Bay 2, Axes 2-3, fixed Parts Installation Complete (revised Sequence)
A
925 2nd Stage Concrete, Bay 2 for Radial Gate Installation 13 04-Jun-15 A 20-Jun-15 A AC.Lot 1 2nd Stage Concrete, Bay 2 for Radial Gate Installation
936 TD 244: Bay 2, Start of Radial Gate Erection (revised S 0 16-Jun-15 A AC.Lot 2 TD 244: Bay 2, Start of Radial Gate Erection (revised Sequence)
937 Radial gate erection, Bay 2 24 20-Jun-15 A 19-Jul-15 A AC.Lot 2 Radial gate erection, Bay 2
938 TD 249: Bay 2, Radial Gate Erection Complete (revise 0 19-Jul-15 A AC.Lot 2 TD 249: Bay 2, Radial Gate Erection Complete (revised Sequence)
Beams for gantry crane & Service bridge 194 29-Mar-15 22-Nov-15 A 22-Nov-15 A, Beams for gantry crane & Service bridge
940 TD 251: Bay 2, Start of SLW Gantry Crane u/s Beam ( 0 29-Mar-15 AC.Lot 1 TD 251: Bay 2, Start of SLW Gantry Crane u/s Beam (revised Sequence), 29-Mar-15 A
A
942 u/s Gantry Crane Beam, Bay 2 43 30-Mar-15 23-May-15 A AC.Lot 1 u/s Gantry Crane Beam, Bay 2
A
943 Service Bridge, Bay 2 12 03-Apr-15 A 20-Apr-15 A AC.Lot 1 Service Bridge, Bay 2
941 d/s Gantry Crane Beam, Bay 2 15 22-Apr-15 A 11-May-15 A AC.Lot 1 d/s Gantry Crane Beam, Bay 2
945 Installation of precast elements D/S ( Service Bridge & 5 23-Jul-15 A 30-Jul-15 A AC.Lot 1 Installation of precast elements D/S ( Service Bridge & D/S G.Crane )
944 Installation of precast elements U/S G.Crane 4 22-Aug-15 26-Aug-15 A AC.Lot 1 Installation of precast elements U/S G.Crane
A
946 Gantry crane rails installation 38 17-Sep-15 07-Nov-15 A AC.Lot 2 Gantry crane rails installation
A
926 2nd Stage Concrete, Bay 2 for G. Crane Rails 10 10-Nov-15 22-Nov-15 A AC.Lot 1 2nd Stage Concrete, Bay 2 for G. Crane Rails
A
Electri
Electrical works 59 25-Oct-15 A 02-Jan-16 A 02-Jan-16 A, Electrical works
948 Hydraulic SLW radial gate, Bay 2 59 25-Oct-15 A 02-Jan-16 A AC.Lot 4 Hydraulic SLW radial gate, Bay 2
949 Electrical SLW radial gate, Bay 2 45 25-Oct-15 A 16-Dec-15 A AC.Lot 4 Electrical SLW radial gate, Bay 2
BAY 3, AX
AXES 3-4 305 02-May-15 05-May-16 A 05-May-16 A, BAY 3, AXES 3-4
Stop LLogs ( D/s & U/s ) 166 19-Oct-15 A 05-May-16 A 05-May-16 A, Stop Logs ( D/s & U/s )
952 Side guides installation (for stop log U/S) 37 19-Oct-15 A 01-Dec-15 A AC.Lot 2 Side guides installation (for stop log U/S)
953 Sill beam installation (for stop log U/S) 37 19-Oct-15 A 01-Dec-15 A AC.Lot 2 Sill beam installation (for stop log U/S)
962 2nd Stage Concrete Bay 3 for US/Stop Logs 45 21-Nov-15 13-Jan-16 A AC.Lot 1 2nd Stage Concrete Bay 3 for US/Stop Logs
A
956 Sill beam installation (for stop log D/S) 90 03-Dec-15 20-Mar-16 A AC.Lot 2 Sill beam installation (for stop log D/S)
A
955 Side guides installation (for stop log D/S) 82 13-Dec-15 20-Mar-16 A AC.Lot 2 Side guides installation (for stop log D/S)
A
961 2nd Stage Concrete, Bay 3 for DS/Stop Logs 44 26-Feb-16 18-Apr-16 A AC.Lot 1 2nd Stage Concrete, Bay 3 for DS/Stop Logs
A
963 TD 250: Bay 3, 2nd Stage Concrete Works complete 0 18-Apr-16 A AC.Lot 1 TD 250: Bay 3, 2nd Stage Concrete Works complete,

Milestone Lot 1 Lot 2 Page 14 of 19


Milestone Lot 2 Lot 3
Milestone Lot 3 Lot 4
Milestone Lot 4 Remaining Work
Lot 1 Critical Remaining Work
New Assiut Barrage and Hydropower Plant Schedule Impletation Programme 12-Oct-18 13:46

Activity ID Activity Name Actual Actual Start Actual Finish The 2012 2013 2014 2015 2016 2017 2018 2019
Duration Contractor
M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M
954 Stop log U/S installation 11 19-Apr-16 A 05-May-16 A AC.Lot 2 Stop log U/S installation
957 Stop log D/S installation 11 19-Apr-16 A 05-May-16 A AC.Lot 2 Stop log D/S installation
Radial Gate 89 02-May-15 16-Aug-15 A 16-Aug-15 A, Radial Gate
965 TD 226: Bay 3, Access Lot 2, fixed Parts Installation 0 02-May-15 AC.Lot 2 TD 226: Bay 3, Access Lot 2, fixed Parts Installation
A
966 Side guides installation (for radial gate) 28 10-May-15 11-Jun-15 A AC.Lot 2 Side guides installation (for radial gate)
A
967 Sill beam installation (for radial gate) 28 10-May-15 11-Jun-15 A AC.Lot 2 Sill beam installation (for radial gate)
A
959 2nd Stage Concrete, Bay 3 for Radial Gate Installation 23 12-Jun-15 A 09-Jul-15 A AC.Lot 1 2nd Stage Concrete, Bay 3 for Radial Gate Installation
968 TD 247: Bay 3, Axes 3-4, fixed Parts Installation Comp 0 16-Jun-15 A AC.Lot 2 TD 247: Bay 3, Axes 3-4, fixed Parts Installation Complete
970 Pre erection of radial gate in storage yard, Bay 3 25 16-Jun-15 A 14-Jul-15 A AC.Lot 2 Pre erection of radial gate in storage yard, Bay 3
972 Radial gate erection, Bay 3 22 09-Jul-15 A 06-Aug-15 A AC.Lot 2 Radial gate erection, Bay 3
971 TD 252: Bay 3, Start of Radial Gate Erection 0 16-Jul-15 A AC.Lot 2 TD 252: Bay 3, Start of Radial Gate Erection
969 TD 255: Bay 3, Radial Gate Erection Complete 0 16-Aug-15 AC.Lot 2 TD 255: Bay 3, Radial Gate Erection Complete
A
Beams for gantry crane & Service bridge 138 05-Jun-15 A 22-Nov-15 A 22-Nov-15 A, Beams for gantry crane & Service bridge
977 Fabrication of Service Bridge, Bay 3 14 05-Jun-15 A 22-Jun-15 A AC.Lot 1 Fabrication of Service Bridge, Bay 3
976 u/s Gantry Crane Beam, Bay 3 6 12-Jul-15 A 20-Jul-15 A AC.Lot 1 u/s Gantry Crane Beam, Bay 3
979 Installation of precast elements U/S G.Crane 11 25-Aug-15 07-Sep-15 A AC.Lot 1 Installation of precast elements U/S G.Crane
A
980 Installation of precast elements D/S ( Service Bridge & 5 01-Oct-15 A 10-Oct-15 A AC.Lot 1 Installation of precast elements D/S ( Service Bridge & D/S G.Crane )
975 d/s Gantry Crane Beam, Bay 3 7 07-Oct-15 A 15-Oct-15 A AC.Lot 1 d/s Gantry Crane Beam, Bay 3
974 TD 257: Bay 3, Start of SLW Gantry Crane u/s Beam 0 02-Nov-15 AC.Lot 1 TD 257: Bay 3, Start of SLW Gantry Crane u/s Beam, 02-Nov-15 A
A
978 Gantry crane rails installation 4 07-Nov-15 11-Nov-15 A AC.Lot 2 Gantry crane rails installation
A
960 2nd Stage Concrete, Bay 3 for G. Crane Rails 8 12-Nov-15 22-Nov-15 A AC.Lot 1 2nd Stage Concrete, Bay 3 for G. Crane Rails
A
Electri
Electrical works 137 02-Aug-15 16-Jan-16 A 16-Jan-16 A, Electrical works
982 Hydraulic SLW radial gate, Bay 3 114 02-Aug-15 19-Dec-15 A AC.Lot 4 Hydraulic SLW radial gate, Bay 3
A
983 Electrical SLW radial gate, Bay 3 59 07-Nov-15 16-Jan-16 A AC.Lot 4 Electrical SLW radial gate, Bay 3
A
BAY 4, AX
AXES 4-5 291 31-May-15 18-May-16 A 18-May-16 A, BAY 4, AXES 4-5
Stop LLogs ( D/s & U/s ) 169 28-Oct-15 AA 18-May-16 A 18-May-16 A, Stop Logs ( D/s & U/s )
987 Sill beam installation (for stop log U/S) 83 28-Oct-15 A 04-Feb-16 A AC.Lot 2 Sill beam installation (for stop log U/S)
986 Side guides installation (for stop log U/S) 72 04-Jan-16 A 30-Mar-16 A AC.Lot 2 Side guides installation (for stop log U/S)
989 Side guides installation (for stop log D/S) 72 04-Jan-16 A 30-Mar-16 A AC.Lot 2 Side guides installation (for stop log D/S)
990 Sill beam installation (for stop log D/S) 72 04-Jan-16 A 30-Mar-16 A AC.Lot 2 Sill beam installation (for stop log D/S)
993 2nd Stage Concrete, Bay 4 for US/Stop Logs 32 05-Feb-16 14-Mar-16 A AC.Lot 1 2nd Stage Concrete, Bay 4 for US/Stop Logs
A
988 Stop log U/S installation 83 06-Feb-16 16-May-16 A AC.Lot 2 Stop log U/S installation
A
995 TD 256: Bay 4, 2nd Stage Concrete Works complete ( 0 20-Feb-16 AC.Lot 1 TD 256: Bay 4, 2nd Stage Concrete Works complete (revised Sequence), 20-Feb-16 A
A
994 2nd Stage Concrete, Bay 4 for D/S Stop Logs 20 01-Apr-16 A 25-Apr-16 A AC.Lot 1 2nd Stage Concrete, Bay 4 for D/S Stop Logs
991 Stop log D/S installation 11 05-May-16 18-May-16 A AC.Lot 2 Stop log D/S installation
A
Radial Gate 91 31-May-15 16-Sep-15 A 16-Sep-15 A, Radial Gate
999 TD 235: Bay 4, Access Lot 2, fixed Parts Installation (r 0 31-May-15 AC.Lot 2 TD 235: Bay 4, Access Lot 2, fixed Parts Installation (revised Sequence)
A
1003 Side guides installation (for radial gate) 26 06-Jun-15 A 06-Jul-15 A AC.Lot 2 Side guides installation (for radial gate)
1004 Sill beam installation (for radial gate) 26 06-Jun-15 A 06-Jul-15 A AC.Lot 2 Sill beam installation (for radial gate)
996 2nd Stage Concrete, Bay 4 for Radial Gate Installation 25 05-Jul-15 A 05-Aug-15 A AC.Lot 1 2nd Stage Concrete, Bay 4 for Radial Gate Installation
1001 Pre erection of radial gate in storage yard, Bay 4 25 15-Jul-15 A 15-Aug-15 A AC.Lot 2 Pre erection of radial gate in storage yard, Bay 4
1005 TD 254: Bay 4, Axes 4-5, fixed Parts Installation Comp 0 15-Jul-15 A AC.Lot 2 TD 254: Bay 4, Axes 4-5, fixed Parts Installation Complete (revised Sequence)
1006 Radial gate erection, Bay 4 24 06-Aug-15 03-Sep-15 A AC.Lot 2 Radial gate erection, Bay 4
A
1002 TD 258: Bay 4, Start of Radial Gate Erection (revised S 0 16-Aug-15 AC.Lot 2 TD 258: Bay 4, Start of Radial Gate Erection (revised Sequence)
A
1000 TD 260: Bay 4, Radial Gate Erection Complete (revise 0 16-Sep-15 AC.Lot 2 TD 260: Bay 4, Radial Gate Erection Complete (revised Sequence)
A
Beams for gantry crane & Service bridge 112 22-Jul-15 A 07-Dec-15 A 07-Dec-15 A, Beams for gantry crane & Service bridge
1010 u/s Gantry Crane Beam, Bay 4 9 22-Jul-15 A 03-Aug-15 A AC.Lot 1 u/s Gantry Crane Beam, Bay 4
1012 Installation of precast elements U/S G.Crane 3 09-Sep-15 13-Sep-15 A AC.Lot 1 Installation of precast elements U/S G.Crane
A
1011 Service Bridge, Bay 4 12 12-Sep-15 29-Sep-15 A AC.Lot 1 Service Bridge, Bay 4
A
1009 d/s Gantry Crane Beam, Bay 4 7 07-Oct-15 A 15-Oct-15 A AC.Lot 1 d/s Gantry Crane Beam, Bay 4
1013 Installation of precast elements D/S ( Service Bridge & 9 08-Nov-15 18-Nov-15 A AC.Lot 1 Installation of precast elements D/S ( Service Bridge & D/S G.Crane )
A
1014 Gantry crane rails installation 8 23-Nov-15 02-Dec-15 A AC.Lot 2 Gantry crane rails installation
A
997 2nd Stage Concrete, Bay 4 for G. Crane Rails 3 03-Dec-15 07-Dec-15 A AC.Lot 1 2nd Stage Concrete, Bay 4 for G. Crane Rails
A
1008 TD 262: Bay 4, Start of SLW Gantry Crane u/s Beam ( 0 05-Dec-15 AC.Lot 1 TD 262: Bay 4, Start of SLW Gantry Crane u/s Beam (revised Sequence), 05-Dec-15 A
A
Electri
Electrical works 59 05-Dec-15 14-Feb-16 A 14-Feb-16 A, Electrical works
1016 Hydraulic SLW radial gate, Bay 4 36 05-Dec-15A 17-Jan-16 A AC.Lot 4 Hydraulic SLW radial gate, Bay 4
A
1017 Electrical SLW radial gate, Bay 4 59 05-Dec-15 14-Feb-16 A AC.Lot 4 Electrical SLW radial gate, Bay 4
A
BAY 5, AX
AXES 5-6 387 04-Feb-15 18-May-16 A 18-May-16 A, BAY 5, AXES 5-6
Stop LLogs ( D/s & U/s ) 387 04-Feb-15A 18-May-16 A 18-May-16 A, Stop Logs ( D/s & U/s )
1029 Side guides installation (for stop log D/S) 55 04-Feb-15 09-Apr-15 A AC.Lot 2 Side guides installation (for stop log D/S)
A
1030 Sill beam installation (for stop log D/S) 55 04-Feb-15 09-Apr-15 A AC.Lot 2 Sill beam installation (for stop log D/S)
A
1026 Side guides installation (for stop log U/S) 24 23-Jan-16 A 21-Feb-16 A AC.Lot 2 Side guides installation (for stop log U/S)
1027 Sill beam installation (for stop log U/S) 24 23-Jan-16 A 21-Feb-16 A AC.Lot 2 Sill beam installation (for stop log U/S)
1022 2nd Stage Concrete, Bay 5 for US/Stop Logs 46 05-Feb-16 30-Mar-16 A AC.Lot 1 2nd Stage Concrete, Bay 5 for US/Stop Logs
A
1023 2nd Stage Concrete, Bay 5 for DS/Stop Logs 62 22-Feb-16 08-May-16 A AC.Lot 1 2nd Stage Concrete, Bay 5 for DS/Stop Logs
A
1028 Stop log U/S installation 11 05-May-16 18-May-16 A AC.Lot 2 Stop log U/S installation
A
1031 Stop log D/S installation 11 05-May-16 18-May-16 A AC.Lot 2 Stop log D/S installation
A
1024 TD 261: Bay 5, 2nd Stage Concrete Works complete ( 0 10-May-16 A AC.Lot 1 TD 261: Bay 5, 2nd Stage Concrete Works complete (revised Sequence),
Radial Gate 109 29-Jun-15 A 11-Nov-15 A 11-Nov-15 A, Radial Gate
1033 TD 245: Bay 5, Access Lot 2, fixed Parts Installation (r 0 29-Jun-15 A AC.Lot 2 TD 245: Bay 5, Access Lot 2, fixed Parts Installation (revised Sequence)
1038 TD 259: Bay 5, Axes 5-6, fixed Parts Installation Comp 0 15-Aug-15 AC.Lot 2 TD 259: Bay 5, Axes 5-6, fixed Parts Installation Complete (revised Sequence)
A
1036 Side guides installation (for radial gate) 15 02-Sep-15 20-Sep-15 A AC.Lot 2 Side guides installation (for radial gate)
A
1037 Sill beam installation (for radial gate) 15 02-Sep-15 20-Sep-15 A AC.Lot 2 Sill beam installation (for radial gate)
A
1035 TD 263: Bay 5, Start of Radial Gate Erection (revised S 0 15-Sep-15 AC.Lot 2 TD 263: Bay 5, Start of Radial Gate Erection (revised Sequence)
A

Milestone Lot 1 Lot 2 Page 15 of 19


Milestone Lot 2 Lot 3
Milestone Lot 3 Lot 4
Milestone Lot 4 Remaining Work
Lot 1 Critical Remaining Work
New Assiut Barrage and Hydropower Plant Schedule Impletation Programme 12-Oct-18 13:46

Activity ID Activity Name Actual Actual Start Actual Finish The 2012 2013 2014 2015 2016 2017 2018 2019
Duration Contractor
M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M
1020 2nd Stage Concrete, Bay 5 for Radial Gate Installation 14 21-Sep-15 13-Oct-15 A AC.Lot 1 2nd Stage Concrete, Bay 5 for Radial Gate Installation
A
1034 Pre erection of radial gate in storage yard, Bay 5 24 21-Sep-15 25-Oct-15 A AC.Lot 2 Pre erection of radial gate in storage yard, Bay 5
A
1039 Radial gate erection, Bay 5 24 14-Oct-15 A 11-Nov-15 A AC.Lot 2 Radial gate erection, Bay 5
1040 TD 265: Bay 5, Radial Gate Erection Complete (revise 0 20-Oct-15 A AC.Lot 2 TD 265: Bay 5, Radial Gate Erection Complete (revised Sequence)
Beams for gantry crane & Service bridge 116 16-Aug-15 04-Jan-16 A 04-Jan-16 A, Beams for gantry crane & Service bridge
1045 u/s Gantry Crane Beam, Bay 5 11 A
16-Aug-15 28-Aug-15 A AC.Lot 1 u/s Gantry Crane Beam, Bay 5
A
1047 Service Bridge, Bay 5 10 13-Oct-15 A 25-Oct-15 A AC.Lot 1 Service Bridge, Bay 5
1044 d/s Gantry Crane Beam, Bay 5 6 25-Oct-15 A 01-Nov-15 A AC.Lot 1 d/s Gantry Crane Beam, Bay 5
1048 Installation of precast elements U/S G.Crane 5 01-Nov-15 07-Nov-15 A AC.Lot 1 Installation of precast elements U/S G.Crane
A
1042 TD 269: Bays 1-5, Gantry Crane Beams ready for Rail 0 02-Nov-15 AC.Lot 1 TD 269: Bays 1-5, Gantry Crane Beams ready for Rail Installation (revised Sequence), 02-Nov-15 A
A
1049 Installation of precast elements D/S ( Service Bridge & 7 19-Nov-15 28-Nov-15 A AC.Lot 1 Installation of precast elements D/S ( Service Bridge & D/S G.Crane )
A
1046 Gantry crane rails installation 11 28-Nov-15 10-Dec-15 A AC.Lot 2 Gantry crane rails installation
A
1021 2nd Stage Concrete, Bay 5 for G. Crane Rails 4 10-Dec-15 14-Dec-15 A AC.Lot 1 2nd Stage Concrete, Bay 5 for G. Crane Rails
A
1043 TD 266: Bay 5, Start of SLW Gantry Crane u/s Beam ( 0 04-Jan-16 A AC.Lot 1 TD 266: Bay 5, Start of SLW Gantry Crane u/s Beam (revised Sequence), 04-Jan-16 A
Electri
Electrical works 59 28-Dec-15 08-Mar-16 A 08-Mar-16 A, Electrical works
1051 Hydraulic SLW radial gate, Bay 5 36 28-Dec-15A 10-Feb-16 A AC.Lot 4 Hydraulic SLW radial gate, Bay 5
A
1053 Electrical SLW radial gate, Bay 5 59 28-Dec-15 08-Mar-16 A AC.Lot 4 Electrical SLW radial gate, Bay 5
A
1052 TD 268 lot 4: SLW, Axes 1-6, Access Lot 4, Cable Tra 0 08-Mar-16 AC.Lot 4 TD 268 lot 4: SLW, Axes 1-6, Access Lot 4, Cable Tray Installation
A
FINISHING W
WORKS 83 29-Dec-15 05-Apr-16 A 05-Apr-16 A, FINISHING WORKS
1055 Finishing works 83 29-Dec-15A 05-Apr-16 A AC.Lot 1 Finishing works
A
GANTRY CR
CRANES 197 17-May-15 10-Jan-16 A 10-Jan-16 A, GANTRY CRANES
1059 TD 207: Lot 2, Start of SLW-W Gantry Crane No. 01 E 0 17-May-15A AC.Lot 2 TD 207: Lot 2, Start of SLW-W Gantry Crane No. 01 Erection (on Abutment Pier Axis 01 & Extension Beams)
A
1058 SLW-W Gantry Crane Rail Installation 25 18-May-15 15-Jun-15 A AC.Lot 2 SLW-W Gantry Crane Rail Installation
A
1060 SLW-W Gantry Crane Pre-assembly & Erection 25 16-Jun-15 A 14-Jul-15 A AC.Lot 2 SLW-W Gantry Crane Pre-assembly & Erection
1061 SLW-W Gantry Crane Testing 10 15-Jul-15 A 28-Jul-15 A AC.Lot 2 SLW-W Gantry Crane Testing
1062 TD 212: Lot 2, SLW-W Gantry Crane No. 01 Erection 0 30-Jul-15 A AC.Lot 2 TD 212: Lot 2, SLW-W Gantry Crane No. 01 Erection complete
1057 TD 269: Bays1-5, Gantry Crane Beams ready for Rail 0 01-Nov-15 AC.Lot 2 TD 269: Bays1-5, Gantry Crane Beams ready for Rail Installation
A
1063 SLW-E Gantry Crane Rail Installation 25 01-Nov-15 29-Nov-15 A AC.Lot 2 SLW-E Gantry Crane Rail Installation
A
1067 TD 214: Start of SLW-E Gantry Crane No. 2 Erection 0 29-Nov-15 AC.Lot 2 TD 214: Start of SLW-E Gantry Crane No. 2 Erection
A
1065 SLW-E Gantry Crane Pre-assembly & Erection 25 30-Nov-15 28-Dec-15 A AC.Lot 2 SLW-E Gantry Crane Pre-assembly & Erection
A
1066 SLW-E Gantry Crane Testing 10 29-Dec-15 10-Jan-16 A AC.Lot 2 SLW-E Gantry Crane Testing
A
1064 TD 253: Bays 6-8 Gantry Crane Beams Ready for Rai 0 03-Jan-16 A AC.Lot 2 TD 253: Bays 6-8 Gantry Crane Beams Ready for Rail Installation
Test & Commissioning
Com 412 01-Dec-16 28-Mar-18 A 28-Mar-18 A, Test & Commissioning
Dry Test 220 01-Dec-16 16-Aug-17 A 16-Aug-17 A, Dry Test
A2410 LV Common Equipment 220 01-Dec-16 16-Aug-17 A AC.Lot 4 LV Common Equipment
A
A2420 Sluiceway Common Control Board [+50CXA11] 7 28-Feb-17 08-Mar-17 A AC.Lot 4 Sluiceway Common Control Board [+50CXA11]
A
Wet Test 83 21-Dec-17 28-Mar-18 A 28-Mar-18 A, Wet Test
A2430 Wet Test 83 21-Dec-17 28-Mar-18 A AC.Lot 2 Wet Test
A
NAVIGATION LOCK, GUIDE WALLS AND SEPARATION PIERS 1278 04-Sep-13 23-Nov-17 A 23-Nov-17 A, NAVIGATION LOCK, GUIDE WALLS AND S
A
NAVIGATION LOCK 1278 04-Sep-13 23-Nov-17 A 23-Nov-17 A, NAVIGATION LOCK
Upstream head 504 04-Sep-13 11-May-15 A 11-May-15 A, Upstream head
1071 Plain Concrete Under Raft Foundation of u/s Head, Ax 40 04-Sep-13A 24-Oct-13 A AC.Lot 1 Plain Concrete Under Raft Foundation of u/s Head, Axes 17-20/F-J
A
1072 Raft Foundation of u/s Head, Axes 17-20/F-J 95 10-Nov-13 04-Mar-14 A AC.Lot 1 Raft Foundation of u/s Head, Axes 17-20/F-J
A
1074 Superstructure of u/s Head, Axes 17-20/F-J 357 04-Mar-14 11-May-15 A AC.Lot 1 Superstructure of u/s Head, Axes 17-20/F-J
A
1073 TD 103: Lot 2, Start of u/s Head fixed Part Installation 0 02-Jun-14 A AC.Lot 2 TD 103: Lot 2, Start of u/s Head fixed Part Installation
1075 TD 102: u/s Head ready for fixed Parts installation 0 02-Jun-14 A AC.Lot 1 TD 102: u/s Head ready for fixed Parts installation, 02-Jun-14 A
Fixed pa
parts installation U/S 888 02-Jun-14 A 10-May-17 A 10-May-17 A, Fixed parts installation U/S
Culvert Gates and Bulkheads
Culver 299 02-Jun-14 A 30-May-15 A 30-May-15 A, Culvert Gates and Bulkheads
1081 guiding rails G-J / 20 93 02-Jun-14 A 22-Sep-14 A AC.Lot 2 guiding rails G-J / 20
1078 guiding rails G-J / 17 87 12-Jul-14 A 28-Oct-14 A AC.Lot 2 guiding rails G-J / 17
1080 guiding rails G-J / 19 101 23-Jul-14 A 25-Nov-14 A AC.Lot 2 guiding rails G-J / 19
1079 guiding rails G-J / 18 72 11-Sep-14 08-Dec-14 A AC.Lot 2 guiding rails G-J / 18
A
1082 2nd stage concrete (civil contractor) 145 11-Nov-14 05-May-15 A AC.Lot 1 2nd stage concrete (civil contractor)
A
1083 Culvert gate and Bulkhead Lock 1 17 09-May-15 28-May-15 A AC.Lot 2 Culvert gate and Bulkhead Lock 1
A
1084 Culvert gate and Bulkhead Lock 2 18 09-May-15 30-May-15 A AC.Lot 2 Culvert gate and Bulkhead Lock 2
A
Stoplo between axes H & J
Stoplogs 353 08-Nov-14 09-Jan-16 A 09-Jan-16 A, Stoplogs between axes H & J
1088 guiding rails Lock 2 150 08-Nov-14A 07-May-15 A AC.Lot 2 guiding rails Lock 2
A
1089 2nd stage concrete (civil contractor) 174 09-May-15 06-Dec-15 A AC.Lot 1 2nd stage concrete (civil contractor)
A
1086 guiding rails Lock 1 46 04-Jun-15 A 30-Jul-15 A AC.Lot 2 guiding rails Lock 1
1087 2nd stage concrete (civil contractor) 27 05-Oct-15 A 07-Nov-15 A AC.Lot 1 2nd stage concrete (civil contractor)
1091 Stop log Lock 2 13 07-Dec-15 22-Dec-15 A AC.Lot 2 Stop log Lock 2
A
1090 Stop log Lock 1 13 23-Dec-15 09-Jan-16 A AC.Lot 2 Stop log Lock 1
A
Sector Gates 521 11-Mar-15 05-Dec-16 A 05-Dec-16 A, Sector Gates
1095 emb. Parts + gate frames Lock 2 216 A
11-Mar-15 30-Nov-15 A AC.Lot 2 emb. Parts + gate frames Lock 2
A
1099 trunnion Lock 2 186 19-May-15 30-Dec-15 A AC.Lot 2 trunnion Lock 2
A
1093 emb. Parts + gate frames Lock 1 46 14-Nov-15 06-Jan-16 A AC.Lot 2 emb. Parts + gate frames Lock 1
A
1096 2nd stage concrete (civil contractor) 107 24-Nov-15 30-Mar-16 A AC.Lot 1 2nd stage concrete (civil contractor)
A
1097 trunnion Lock 1 97 25-Nov-15 20-Mar-16 A AC.Lot 2 trunnion Lock 1
A
1100 2nd stage concrete (civil contractor) 285 23-Dec-15 05-Dec-16 A AC.Lot 1 2nd stage concrete (civil contractor)
A
1094 2nd stage concrete (civil contractor) 23 09-Jan-16 A 06-Feb-16 A AC.Lot 1 2nd stage concrete (civil contractor)
1103 Sector Gate Lock 2 97 18-Jan-16 A 15-May-16 A AC.Lot 2 Sector Gate Lock 2
1098 2nd stage concrete (civil contractor) 19 08-Mar-16 30-Mar-16 A AC.Lot 1 2nd stage concrete (civil contractor)
A
1101 Sector Gate Lock 1 37 30-Mar-16 16-May-16 A AC.Lot 2 Sector Gate Lock 1
A
1104 Hydraulic Lock 2 24 30-Apr-16 A 30-May-16 A AC.Lot 2 Hydraulic Lock 2

Milestone Lot 1 Lot 2 Page 16 of 19


Milestone Lot 2 Lot 3
Milestone Lot 3 Lot 4
Milestone Lot 4 Remaining Work
Lot 1 Critical Remaining Work
New Assiut Barrage and Hydropower Plant Schedule Impletation Programme 12-Oct-18 13:46

Activity ID Activity Name Actual Actual Start Actual Finish The 2012 2013 2014 2015 2016 2017 2018 2019
Duration Contractor
M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M
1102 Hydraulic Lock 1 24 03-May-16 31-May-16 A AC.Lot 2 Hydraulic Lock 1
A
Stoplo between axes G & H
Stoplogs 413 30-Jan-15 A 13-Jun-16 A 13-Jun-16 A, Stoplogs between axes G & H
1108 guiding rails Lock 2 53 30-Jan-15 A 02-Apr-15 A AC.Lot 2 guiding rails Lock 2
1109 2nd stage concrete (civil contractor) 189 04-Apr-15 A 22-Nov-15 A AC.Lot 1 2nd stage concrete (civil contractor)
1106 guiding rails Lock 1 48 19-Nov-15 16-Jan-16 A AC.Lot 2 guiding rails Lock 1
A
1111 Stop log Lock 2 168 23-Nov-15 12-Jun-16 A AC.Lot 2 Stop log Lock 2
A
1107 2nd stage concrete (civil contractor) 30 17-Jan-16 A 22-Feb-16 A AC.Lot 1 2nd stage concrete (civil contractor)
1110 Stop log Lock 1 92 23-Feb-16 13-Jun-16 A AC.Lot 2 Stop log Lock 1
A
Arrest Cable Systems
Arrester 340 26-Mar-16 10-May-17 A 10-May-17 A, Arrester Cable Systems
NL1 338 A 10-May-17 A
28-Mar-16 10-May-17 A, NL1
1 Arrester cable system incl. hoists Lock 1 163 A 17-Oct-16 A
28-Mar-16 AC.Lot 2 Arrester cable system incl. hoists Lock 1
A
1 embedded parts Lock 1 56 16-Apr-16 A 23-Jun-16 A AC.Lot 2 embedded parts Lock 1
1 2nd stage concrete (civil contractor) 35 17-Oct-16 A 27-Nov-16 A AC.Lot 1 2nd stage concrete (civil contractor)
1 deflection sheet without rail 26 27-Nov-16 28-Dec-16 A AC.Lot 2 deflection sheet without rail
A
1 2nd stage concrete (Deflection Sheet) 18 29-Dec-16 19-Jan-17 A AC.Lot 1 2nd stage concrete (Deflection Sheet)
A
1 motor console and double chain wheels,vertical rails o 68 20-Jan-17 A 10-Apr-17 A AC.Lot 2 motor console and double chain wheels,vertical rails on deflection sheets,Lower chain
1 hydraulic & flushing devices Lock 1 26 10-Apr-17 A 10-May-17 A AC.Lot 2 hydraulic & flushing devices Lock 1
NL2 340 26-Mar-16 10-May-17 A 10-May-17 A, NL2
1 embedded parts Lock 2 74 26-Mar-16 23-Jun-16 A AC.Lot 2 embedded parts Lock 2
A
1 Arrester cable system incl. hoists Lock 2 174 28-Mar-16 30-Oct-16 A AC.Lot 2 Arrester cable system incl. hoists Lock 2
A
1 deflection sheet without rail 24 03-Oct-16 A 01-Nov-16 A AC.Lot 2 deflection sheet without rail
1 2nd stage concrete (civil contractor) 31 30-Oct-16 A 05-Dec-16 A AC.Lot 1 2nd stage concrete (civil contractor)
1 2nd stage concrete (Deflection Sheet) 75 01-Nov-16 29-Jan-17 A AC.Lot 1 2nd stage concrete (Deflection Sheet)
A
1 motor console and double chain wheels,vertical rails o 74 29-Jan-17 A 24-Apr-17 A AC.Lot 2 motor console and double chain wheels,vertical rails on deflection sheets,Lower cha
1 hydraulic & flushing devices Lock 2 14 24-Apr-17 A 10-May-17 A AC.Lot 2 hydraulic & flushing devices Lock 2
Middle Part
P 641 12-Dec-13 30-Jan-16 A 30-Jan-16 A, Middle Part
1122 Plain Concrete Under Raft Foundation of Middle Part, A 35 12-Dec-13 23-Jan-14 A AC.Lot 1 Plain Concrete Under Raft Foundation of Middle Part, Axes 17-20/J-O
A
1123 Raft Foundation of Middle Part, Axes 17-20/J-O 109 01-May-14 10-Sep-14 A AC.Lot 1 Raft Foundation of Middle Part, Axes 17-20/J-O
A
1124 Superstructure of Middle Part, Axes 17-20/J-O 411 17-Sep-14 30-Jan-16 A AC.Lot 1 Superstructure of Middle Part, Axes 17-20/J-O
A
Downstr
Downstream head 568 26-Oct-13 A 12-Sep-15 A 12-Sep-15 A, Downstream head
1126 Plain Concrete Under Raft Foundation of d/s Head, Ax 40 26-Oct-13 A 11-Dec-13 A AC.Lot 1 Plain Concrete Under Raft Foundation of d/s Head, Axes 17-20/O-S
1127 Raft Foundation of d/s Head, Axes 17-20/O-S 108 12-Dec-13 23-Apr-14 A AC.Lot 1 Raft Foundation of d/s Head, Axes 17-20/O-S
A
1128 Superstructure of u/s Head, Axes 17-20/O-S 444 24-Mar-14 12-Sep-15 A AC.Lot 1 Superstructure of u/s Head, Axes 17-20/O-S
A
1130 TD 104: d/s Head ready for fixed Parts installation 0 18-Jul-14 A AC.Lot 1 TD 104: d/s Head ready for fixed Parts installation, 18-Jul-14 A
1129 TD 105: Lot 2, Start of d/s Head fixed Part Installation 0 18-Jul-14 A AC.Lot 2 TD 105: Lot 2, Start of d/s Head fixed Part Installation
Fixed pa
parts installation D/S 837 02-Sep-14 08-Jun-17 A 08-Jun-17 A, Fixed parts installation D/S
Culvert Gates and Bulkheads
Culver 632 02-Sep-14A 11-Oct-16 A 11-Oct-16 A, Culvert Gates and Bulkheads
1136 guiding rails O-Q / 20 94 02-Sep-14A 24-Dec-14 A AC.Lot 2 guiding rails O-Q / 20
A
1134 guiding rails O-Q / 18 125 10-Dec-14 11-May-15 A AC.Lot 2 guiding rails O-Q / 18
A
1135 guiding rails O-Q / 19 91 01-Jan-15 A 22-Apr-15 A AC.Lot 2 guiding rails O-Q / 19
1133 guiding rails O-Q / 17 122 12-Mar-15 08-Aug-15 A AC.Lot 2 guiding rails O-Q / 17
A
1137 2nd stage concrete (civil contractor) 133 23-Aug-15 02-Feb-16 A AC.Lot 1 2nd stage concrete (civil contractor)
A
1138 Culvert gate and Bulkhead Lock 1 254 09-Nov-15 10-Sep-16 A AC.Lot 2 Culvert gate and Bulkhead Lock 1
A
1139 Culvert gate and Bulkhead Lock 2 142 16-Apr-16 A 11-Oct-16 A AC.Lot 2 Culvert gate and Bulkhead Lock 2
Stoplo between axes P & O
Stoplogs 225 12-Dec-15 08-Sep-16 A 08-Sep-16 A, Stoplogs between axes P & O
1141 guiding rails Lock 1 119 12-Dec-15 04-May-16 A AC.Lot 2 guiding rails Lock 1
A
1143 guiding rails Lock 2 84 12-Dec-15 21-Mar-16 A AC.Lot 2 guiding rails Lock 2
A
1142 2nd stage concrete (civil contractor) 37 22-Mar-16 08-May-16 A AC.Lot 1 2nd stage concrete (civil contractor)
A
1144 2nd stage concrete (civil contractor) 91 05-May-16 23-Aug-16 A AC.Lot 1 2nd stage concrete (civil contractor)
A
1146 Stop log Lock 2 13 09-May-16 24-May-16 A AC.Lot 2 Stop log Lock 2
A
1145 Stop log Lock 1 13 24-Aug-16 08-Sep-16 A AC.Lot 2 Stop log Lock 1
A
Mitre Gates
G 370 01-Dec-15 21-Feb-17 A 21-Feb-17 A, Mitre Gates
1148 emb. Parts + gate frames Lock 1 60 01-Dec-15 11-Feb-16 A AC.Lot 2 emb. Parts + gate frames Lock 1
A
1150 emb. Parts + gate frames Lock 2 66 12-Dec-15 29-Feb-16 A AC.Lot 2 emb. Parts + gate frames Lock 2
A
1149 2nd stage concrete (civil contractor) 20 13-Feb-16 07-Mar-16 A AC.Lot 1 2nd stage concrete (civil contractor)
A
1151 2nd stage concrete (civil contractor) 22 01-Mar-16 27-Mar-16 A AC.Lot 1 2nd stage concrete (civil contractor)
A
1154 Mitre Gate Lock 1 114 08-Mar-16 26-Jul-16 A AC.Lot 2 Mitre Gate Lock 1
A
1158 Mitre Gate Lock 2 139 28-Mar-16 17-Sep-16 A AC.Lot 2 Mitre Gate Lock 2
A
1152 Collar Bearing / Servomotor / Sill Beam Lock 1 24 27-Jul-16 A 24-Aug-16 A AC.Lot 2 Collar Bearing / Servomotor / Sill Beam Lock 1
1159 2nd stage concrete (civil contractor) 49 25-Aug-16 27-Oct-16 A AC.Lot 1 2nd stage concrete (civil contractor)
A
1153 Collar Bearing / Servomotor / Sill Beam Lock 2 36 02-Sep-16 20-Oct-16 A AC.Lot 2 Collar Bearing / Servomotor / Sill Beam Lock 2
A
1156 Mechanical final works 49 15-Oct-16 A 11-Dec-16 A AC.Lot 2 Mechanical final works
1155 2nd stage concrete (civil contractor) 49 22-Oct-16 A 18-Dec-16 A AC.Lot 1 2nd stage concrete (civil contractor)
1160 Mechanical final works 49 05-Dec-16 01-Feb-17 A AC.Lot 2 Mechanical final works
A
1157 Hydraulic Lock 1 52 08-Dec-16 08-Feb-17 A AC.Lot 2 Hydraulic Lock 1
A
1161 Hydraulic Lock 2 16 02-Feb-17 21-Feb-17 A AC.Lot 2 Hydraulic Lock 2
A
Stoplo between axes O & Q
Stoplogs 225 12-Dec-15 08-Sep-16 A 08-Sep-16 A, Stoplogs between axes O & Q
1163 guiding rails Lock 1 84 12-Dec-15 21-Mar-16 A AC.Lot 2 guiding rails Lock 1
A
1164 2nd stage concrete (civil contractor) 37 22-Mar-16 08-May-16 A AC.Lot 1 2nd stage concrete (civil contractor)
A
1165 guiding rails Lock 2 15 13-Apr-16 A 04-May-16 A AC.Lot 2 guiding rails Lock 2
1166 2nd stage concrete (civil contractor) 91 05-May-16 23-Aug-16 A AC.Lot 1 2nd stage concrete (civil contractor)
A
1168 Stop log Lock 2 19 21-May-16 12-Jun-16 A AC.Lot 2 Stop log Lock 2
A
1167 Stop log Lock 1 13 24-Aug-16 08-Sep-16 A AC.Lot 2 Stop log Lock 1
A
Arrester Cable Systems
Arrest 347 16-Apr-16 A 08-Jun-17 A 08-Jun-17 A, Arrester Cable Systems

Milestone Lot 1 Lot 2 Page 17 of 19


Milestone Lot 2 Lot 3
Milestone Lot 3 Lot 4
Milestone Lot 4 Remaining Work
Lot 1 Critical Remaining Work
New Assiut Barrage and Hydropower Plant Schedule Impletation Programme 12-Oct-18 13:46

Activity ID Activity Name Actual Actual Start Actual Finish The 2012 2013 2014 2015 2016 2017 2018 2019
Duration Contractor
M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M
NL1 347 16-Apr-16 A 08-Jun-17 A 08-Jun-17 A, NL1
A Arrester cable system incl. hoists Lock 1 214 16-Apr-16 A 04-Jan-17 A AC.Lot 2 Arrester cable system incl. hoists Lock 1
A embedded parts Lock 1 13 18-Jul-16 A 03-Aug-16 A AC.Lot 2 embedded parts Lock 1
A 2nd stage concrete (civil contractor) 57 17-Oct-16 A 22-Dec-16 A AC.Lot 1 2nd stage concrete (civil contractor)
A deflection sheet without rail 22 27-Nov-16 22-Dec-16 A AC.Lot 2 deflection sheet without rail
A
A 2nd stage concrete (Deflection Sheet) 27 22-Dec-16 24-Jan-17 A AC.Lot 1 2nd stage concrete (Deflection Sheet)
A
A motor console and double chain wheels,vertical rails o 92 24-Jan-17 A 11-May-17 A AC.Lot 2 motor console and double chain wheels,vertical rails on deflection sheets,Lower ch
A hydraulic & flushing devices Lock 1 24 11-May-17 08-Jun-17 A AC.Lot 2 hydraulic & flushing devices Lock 1
A
NL2 314 26-Apr-16 A 10-May-17 A 10-May-17 A, NL2
A embedded parts Lock 2 67 26-Apr-16 A 18-Jul-16 A AC.Lot 2 embedded parts Lock 2
A Arrester cable system incl. hoists Lock 2 126 29-Apr-16 A 04-Oct-16 A AC.Lot 2 Arrester cable system incl. hoists Lock 2
A 2nd stage concrete (civil contractor) 52 04-Oct-16 A 05-Dec-16 A AC.Lot 1 2nd stage concrete (civil contractor)
A deflection sheet without rail 75 04-Oct-16 A 02-Jan-17 A AC.Lot 2 deflection sheet without rail
A 2nd stage concrete (Deflection Sheet) 26 02-Jan-17 A 01-Feb-17 A AC.Lot 1 2nd stage concrete (Deflection Sheet)
A motor console and double chain wheels,vertical rails o 71 01-Feb-17 24-Apr-17 A AC.Lot 2 motor console and double chain wheels,vertical rails on deflection sheets,Lower cha
A
A hydraulic & flushing devices Lock 2 14 24-Apr-17 A 10-May-17 A AC.Lot 2 hydraulic & flushing devices Lock 2
Gantry cranes
cr 532 15-Feb-15 23-Nov-16 A 23-Nov-16 A, Gantry cranes
NL 1 GGantry Crane 197 26-Mar-16A 23-Nov-16 A 23-Nov-16 A, NL 1 Gantry Crane
1180 gantry crane rails 78 26-Mar-16 28-Jun-16 A AC.Lot 2 gantry crane rails
A
1181 2nd stage concrete gantry crane rails (civil contractor) 49 12-Jun-16 A 11-Aug-16 A AC.Lot 1 2nd stage concrete gantry crane rails (civil contractor)
1182 pre assembly gantry crane 11 30-Jul-16 A 11-Aug-16 A AC.Lot 2 pre assembly gantry crane
1183 installation gantry crane 12 13-Aug-16 26-Aug-16 A AC.Lot 2 installation gantry crane
A
1184 testing gantry crane 5 17-Nov-16 23-Nov-16 A AC.Lot 2 testing gantry crane
A
NL 2 G
Gantry Crane 532 15-Feb-15 23-Nov-16 A 23-Nov-16 A, NL 2 Gantry Crane
1187 TD106: Start of NL Gantry Cranes Erection 0 A
15-Feb-15 AC.Lot 2 TD106: Start of NL Gantry Cranes Erection
A
1186 gantry crane rails 448 16-Mar-15 10-Sep-16 A AC.Lot 2 gantry crane rails
A
1188 2nd stage concrete gantry crane rails (civil contractor) 148 24-Apr-16 A 26-Oct-16 A AC.Lot 1 2nd stage concrete gantry crane rails (civil contractor)
1189 pre assembly gantry crane 49 24-Aug-16 26-Oct-16 A AC.Lot 2 pre assembly gantry crane
A
1190 installation gantry crane 11 27-Oct-16 A 09-Nov-16 A AC.Lot 2 installation gantry crane
1191 testing gantry crane 5 17-Nov-16 23-Nov-16 A AC.Lot 2 testing gantry crane
A
Electrica works
Electrical 332 31-Oct-16 A 23-Nov-17 A 23-Nov-17 A, Electrical works
1195 Ship arrester NL1 & NL2 174 31-Oct-16 A 23-May-17 A AC.Lot 4 Ship arrester NL1 & NL2
1196 Mitre gate / Sector gate NL1 & NL2 248 31-Oct-16 A 17-Aug-17 A AC.Lot 4 Mitre gate / Sector gate NL1 & NL2
1194 Culvert gate NL1 & NL2 268 15-Jan-17 A 23-Nov-17 A AC.Lot 4 Culvert gate NL1 & NL2
U/S GUIDE W
WALL, AXES 16-17/P-F 342 15-Feb-15 03-Apr-16 A 03-Apr-16 A, U/S GUIDE WALL, AXES 16-17/P-F
1198 Guide Wall, Axes 16-17/F-H 155 15-Feb-15A 20-Aug-15 A AC.Lot 1 Guide Wall, Axes 16-17/F-H
A
1199 Guide Wall, Axes 16-17/M-H 335 23-Feb-15 03-Apr-16 A AC.Lot 1 Guide Wall, Axes 16-17/M-H
A
1200 Guide Wall, Axes 16-17/P-M 130 05-May-15 12-Oct-15 A AC.Lot 1 Guide Wall, Axes 16-17/P-M
A
D/S GUIDE W
WALL, AXES 17 251 05-Jun-15 A 04-Apr-16 A 04-Apr-16 A, D/S GUIDE WALL, AXES 17
1202 Guide Wall, Part 1, Axes 17/S 98 05-Jun-15 A 05-Oct-15 A AC.Lot 1 Guide Wall, Part 1, Axes 17/S
1203 Guide Wall, Middle Part 121 16-Jun-15 A 11-Nov-15 A AC.Lot 1 Guide Wall, Middle Part
1204 Guide Wall, Part 3 187 22-Aug-15 04-Apr-16 A AC.Lot 1 Guide Wall, Part 3
A
U/S APPROACH
APPROA AREA, SEPARATION PIER 525 01-Sep-15 28-May-17 A 28-May-17 A, U/S APPROACH AREA, SEPARATION PIER
1207 Contiguous Bored Pile Walls 107 01-Sep-15 11-Jan-16 A AC.Lot 1 Contiguous Bored Pile Walls
A
1206 Fill Separation Dyke 44 08-Sep-15 04-Nov-15 A AC.Lot 1 Fill Separation Dyke
A
1210 Fender walls + mooring structures 422 05-Jan-16 A 28-May-17 A AC.Lot 1 Fender walls + mooring structures
1208 Separation Pier Concrete Superstructure 338 15-Mar-16 27-Apr-17 A AC.Lot 1 Separation Pier Concrete Superstructure
A
1209 Removal Separation Dyke 11 29-Apr-17 A 11-May-17 A AC.Lot 1 Removal Separation Dyke
REMOVAL OF
O OLD BARRAGE PARTS 320 10-Oct-16 A 19-Oct-17 A 19-Oct-17 A, REMOVAL OF OLD BARRAGE PARTS
1213 Removal of Bridge and Arches 320 10-Oct-16 A 19-Oct-17 A AC.Lot 1 Removal of Bridge and Arches
1212 Strengthening of adjacent Vent 163 20-Oct-16 A 30-Apr-17 A AC.Lot 1 Strengthening of adjacent Vent
1214 TD 110 (1): Removal of Old Barrage Parts complete (s 0 19-Oct-17 A AC.Lot 1 TD 110 (1): Removal of Old Barrage Parts complete (suggestio
FINISHING W
WORKS 234 19-Apr-16 A 31-Jan-17 A 31-Jan-17 A, FINISHING WORKS
1216 Finishing works 234 19-Apr-16 A 31-Jan-17 A AC.Lot 1 Finishing works
Test & Commissioning
Com 173 06-May-17 23-Nov-17 A 23-Nov-17 A, Test & Commissioning
Dry Test 130 06-May-17A 04-Oct-17 A 04-Oct-17 A, Dry Test
A2450 US Culvert Gate , Sector Gate & Ship Arrester 113 06-May-17 14-Sep-17 A AC.Lot 2 US Culvert Gate , Sector Gate & Ship Arrester
A
A2460 DS Culvert Gate , Sector Gate & Ship Arrester 113 06-May-17 14-Sep-17 A AC.Lot 2 DS Culvert Gate , Sector Gate & Ship Arrester
A
A2440 Gantry Crane -NL#1 & NL #2 82 01-Jul-17 A 04-Oct-17 A AC.Lot 2 Gantry Crane -NL#1 & NL #2
Wet TesT 46 01-Oct-17 A 23-Nov-17 A 23-Nov-17 A, Wet TesT
A2470 Wet Test NL 1 & 2 46 01-Oct-17 A 23-Nov-17 A AC.Lot 2 Wet Test NL 1 & 2
PUBLIC BRIDGE
BRID AND PUBLIC ROAD 1069 24-Sep-14 28-Mar-18 A 28-Mar-18 A, PUBLIC BRIDGE AND PUBL
A
General 1069 24-Sep-14 28-Mar-18 A 28-Mar-18 A, General
1219 PRB Beams, Axes 18-19 317 A
24-Sep-14 15-Oct-15 A AC.Lot 1 PRB Beams, Axes 18-19
A
1223 PRB Abutment / Piers (Axis 20-Right Bank) 75 07-Oct-14 A 01-Jan-15 A AC.Lot 1 PRB Abutment / Piers (Axis 20-Right Bank)
1220 PRB Beams, Axes 17-18 295 23-Oct-14 A 15-Oct-15 A AC.Lot 1 PRB Beams, Axes 17-18
1221 PRB Beams, Axes 19-20 273 18-Nov-14 15-Oct-15 A AC.Lot 1 PRB Beams, Axes 19-20
A
1225 PRB Beams, Axes 17-16 256 14-Dec-14 21-Oct-15 A AC.Lot 1 PRB Beams, Axes 17-16
A
1224 PRB Beams, Axes 20 ( E. Side) 242 03-Jan-15 A 25-Oct-15 A AC.Lot 1 PRB Beams, Axes 20 ( E. Side)
1226 PRB Beams, Axes 16-17 234 10-Jan-15 A 21-Oct-15 A AC.Lot 1 PRB Beams, Axes 16-17
1236 Bridge Beams, SW Bay 1 218 05-Feb-15 28-Oct-15 A AC.Lot 1 Bridge Beams, SW Bay 1
A
1222 PRB Pier between Abut Pier 16 and N.L D/S 25 03-Mar-15 31-Mar-15 A AC.Lot 1 PRB Pier between Abut Pier 16 and N.L D/S
A
1235 Bridge Beams, SW Bay 2 196 03-Mar-15 28-Oct-15 A AC.Lot 1 Bridge Beams, SW Bay 2
A
1234 Bridge Beams, SW Bay 3 172 29-Mar-15 26-Oct-15 A AC.Lot 1 Bridge Beams, SW Bay 3
A

Milestone Lot 1 Lot 2 Page 18 of 19


Milestone Lot 2 Lot 3
Milestone Lot 3 Lot 4
Milestone Lot 4 Remaining Work
Lot 1 Critical Remaining Work
New Assiut Barrage and Hydropower Plant Schedule Impletation Programme 12-Oct-18 13:46

Activity ID Activity Name Actual Actual Start Actual Finish The 2012 2013 2014 2015 2016 2017 2018 2019
Duration Contractor
M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M
1233 Bridge Beams, SW Bay 4 148 27-Apr-15 A 24-Oct-15 A AC.Lot 1 Bridge Beams, SW Bay 4
1232 Bridge Beams, SW Bay 5 129 23-May-15 27-Oct-15 A AC.Lot 1 Bridge Beams, SW Bay 5
A
1228 Bridge Beams, SW Bay 8 105 17-Jun-15 A 25-Oct-15 A AC.Lot 1 Bridge Beams, SW Bay 8
1229 Bridge Beams, SW Bay 7 85 13-Jul-15 A 27-Oct-15 A AC.Lot 1 Bridge Beams, SW Bay 7
1230 Bridge Beams, SW Bay 6 72 27-Jul-15 A 24-Oct-15 A AC.Lot 1 Bridge Beams, SW Bay 6
1231 TD 264: Public road Bridge Axes 01-06 complete 0 19-Dec-15 AC.Lot 1 TD 264: Public road Bridge Axes 01-06 complete, 19-Dec-15 A
A
1239 Public Road Works 396 02-Apr-16 A 21-Jul-17 A AC.Lot 1 Public Road Works
1237 TD 271: Public road Bridge Axes 13-16 complete 0 02-Apr-16 A AC.Lot 1 TD 271: Public road Bridge Axes 13-16 complete, 02-Apr-16 A
1240 Temporary Road Works Right and Left Bank (acc. to a 253 27-Sep-16 21-Jul-17 A AC.Lot 1 Temporary Road Works Right and Left Bank (acc. to alternative 2)
A
1227 TD 107: Public road Bridge from Right Bridge Abutmen 0 21-Jul-17 A AC.Lot 1 TD 107: Public road Bridge from Right Bridge Abutment to Axis 16 comple
1238 Connection between Temp. Road and Existing East R 0 21-Jul-17 A AC.Lot 1 Connection between Temp. Road and Existing East Road to be completed
1242 Permanent Road Works at Service Area Right and Le 214 21-Jul-17 A 28-Mar-18 A AC.Lot 1 Permanent Road Works at Service Area R
1241 Connection between Permanent Road and Existing ro 0 28-Feb-18 AC.Lot 1 Connection between Permanent Road and Ex
A
ADMINISTRATION BUILDING
ADMINISTRA 721 22-Nov-15 28-Mar-18 A 28-Mar-18 A, ADMINISTRATION BUILDIN
A
General 721 22-Nov-15 28-Mar-18 A 28-Mar-18 A, General
1245 Civil Works 489 22-Nov-15 30-Jun-17 A AC.Lot 1 Civil Works
A
1247 Electrical works 521 20-Jul-16 A 28-Mar-18 A AC.Lot 4 Electrical works
1246 Finishing and Installation Works 496 20-Aug-16 28-Mar-18 A AC.Lot 1 Finishing and Installation Works
A
1249 Finishing of Control Room & Ready to Install Other Lot 389 20-Aug-16 23-Nov-17 A AC.Lot 4 Finishing of Control Room & Ready to Install Other Lots Eq
A
A2480 11KV MV Equipment 38 14-Oct-17 A 27-Nov-17 A AC.Lot 4 11KV MV Equipment
A2490 Protection System 104 19-Oct-17 A 18-Feb-18 A AC.Lot 4 Protection System
A2510 Fire Fighting System 21 20-Jan-18 A 13-Feb-18 A AC.Lot 4 Fire Fighting System
1248 Elevator - installation & testing 57 21-Jan-18 A 28-Mar-18 A AC.Lot 1 Elevator - installation & testing
A2500 Fire detection system 15 27-Jan-18 A 13-Feb-18 A AC.Lot 4 Fire detection system
SWITCHYARD 417 29-Oct-16 A 28-Feb-18 A 28-Feb-18 A, SWITCHYARD
General 417 29-Oct-16 A 28-Feb-18 A 28-Feb-18 A, General
1252 Primary Earthing 25 29-Oct-16 A 26-Nov-16 A AC.Lot 4 Primary Earthing
1253 Foundation Works 37 29-Nov-16 12-Jan-17 A AC.Lot 1 Foundation Works
A
1255 SWY Erection Works 92 12-Jan-17 A 30-Apr-17 A AC.Lot 4 SWY Erection Works
1254 Control Building, Fence, Cable Trenches 186 13-Jan-17 A 19-Aug-17 A AC.Lot 1 Control Building, Fence, Cable Trenches
1256 Control Building Equipment , Cable Trenches 318 22-Feb-17 28-Feb-18 A AC.Lot 4 Control Building Equipment , Cable Trenches
A
A2520 Lighting system 33 08-Jan-18 A 15-Feb-18 A AC.Lot 4 Lighting system
ANCILLARY BUILDINGS
B 396 20-Dec-16 28-Mar-18 A 28-Mar-18 A, ANCILLARY BUILDINGS
A
RIGHT BANK
BAN BUILDINGS 344 20-Feb-17 28-Mar-18 A 28-Mar-18 A, RIGHT BANK BUILDINGS
1261 Mosque 344 20-Feb-17 28-Mar-18 A AC.Lot 1 Mosque
A
1260 Auxiliary transformer and fire fighting tank building 138 20-Sep-17 28-Feb-18 A AC.Lot 1 Auxiliary transformer and fire fighting tank build
A
1263 Electrical works 137 21-Sep-17 28-Feb-18 A AC.Lot 4 Electrical works
A
1259 Guard houses and towers 60 20-Dec-17 28-Feb-18 A AC.Lot 1 Guard houses and towers
A
1262 Sewage treatment plant building 59 20-Dec-17 27-Feb-18 A AC.Lot 1 Sewage treatment plant building
A
LEFT BANK BUILDINGS 371 20-Dec-16 27-Feb-18 A 27-Feb-18 A, LEFT BANK BUILDINGS
1267 Pump house 222 20-Dec-16A 06-Sep-17 A AC.Lot 1 Pump house
A
1268 Electrical works 232 01-Jun-17 A 27-Feb-18 A AC.Lot 4 Electrical works
1266 Guard houses and towers 50 30-Nov-17 27-Jan-18 A AC.Lot 1 Guard houses and towers
A
1265 Sewage treatment plant building 15 01-Jan-18 A 18-Jan-18 A AC.Lot 1 Sewage treatment plant building
EXTERIOR A
ARRANGEMENTS 75 31-Dec-17 28-Mar-18 A 28-Mar-18 A, EXTERIOR ARRANGEMENT
A
RIGHT BANK
BAN 75 31-Dec-17 28-Mar-18 A 28-Mar-18 A, RIGHT BANK
1271 Bus parking area 75 31-Dec-17 28-Mar-18 A AC.Lot 1 Bus parking area
A
1273 Maintenance area / crane zone 75 31-Dec-17 28-Mar-18 A AC.Lot 1 Maintenance area / crane zone
A
1272 Fence 25 18-Jan-18 A 16-Feb-18 A AC.Lot 1 Fence
1274 Car parking area 59 18-Jan-18 A 28-Mar-18 A AC.Lot 1 Car parking area
LEFT BANK 60 17-Jan-18 A 28-Mar-18 A 28-Mar-18 A, LEFT BANK
1276 Fence 60 17-Jan-18 A 28-Mar-18 A AC.Lot 1 Fence
1278 Unloading area 47 01-Feb-18 28-Mar-18 A AC.Lot 1 Unloading area
A
1277 Car parking area 34 17-Feb-18 28-Mar-18 A AC.Lot 1 Car parking area
A

Milestone Lot 1 Lot 2 Page 19 of 19


Milestone Lot 2 Lot 3
Milestone Lot 3 Lot 4
Milestone Lot 4 Remaining Work
Lot 1 Critical Remaining Work