Method of Statement.
Method of Statement.
LOCATIONS : A) TANGKI MENARA BEJAYA PARK, WILAYAH KLANG. B) KOLAM AIR SETIA ALAM R9, WILAYAH
KLANG. C) RUMAH PAM BUKIT LIPAT KAJANG, WILAYAH KLANG. D) KOLAM SEDUT DESA SERDANG, HULU
LANGAT.
METHOD OF STATEMENTS.
SCOPE OF WORK : -
METHOD OF STATEMENTS.
2. GEOCELL.
• Upon completed works of soil nailing at designated area, slope surface protection start.
• 100mm thick of geocell lay on the top of slope surface.
• Ensure that the geocell is properly lay on top of the slope surface. The geocell should be
diagonally open as per construction drawing.
• In case of side to side geocell placement, tie both geocells with cable tie as shown in
drawing.
• 600mm length R6 J-pin is used as reinforcement for the geocell at spacing as shown in
the construction drawing depending on slope angle. The J-pin reinforcement is to be
grout with cement grade 30 mix.
• Prior to hydroseeding, fill the geocell with soil.
DESIGN AND BUILD FOR THE PROPOSED SLOPE IMPROVEMENT WORKS TO FAILED AT THE FOLLOWING
LOCATIONS : A) TANGKI MENARA BEJAYA PARK, WILAYAH KLANG. B) KOLAM AIR SETIA ALAM R9, WILAYAH
KLANG. C) RUMAH PAM BUKIT LIPAT KAJANG, WILAYAH KLANG. D) KOLAM SEDUT DESA SERDANG, HULU
LANGAT.
METHOD OF STATEMENTS.
3. HYDROSEEDING.
• The required areas to be treated are to be marked and verified prior to any treatment.
• The marked areas stated in the above are then scarified where needed.
• Fibromat will be laid on top surface of soil.
• Our method of treatment is by manually. This treatment will provide a conducive
environment for vegetation growth together with rapid surface fibromat stability
control.
• Watering and fertilising will be carried out from time to time when required, depending
on the actual site condition Subsequent field checking & monitoring will be carried out
at 2 – 4 weeks interval as required at earlier stage and 4 – 6 weeks at later stage.
• Site condition growth of grass will be monitored closely. Any localised site problem that
affects the growth of vegetation, will be monitor. The respective solution will be devised
and the proper amelioration will be carried out to achieve healthy growth of the
vegetation on the affected areas.
To carry out joint site demarcation to determine the exact location and alignment of
surface drainage and R.C sumps.
Demolish related existing drain (if necessary) and remove all unsuitable material.
Excavation will follow the depth and profile as stated in the construction drawing.
Excavate trench to the required depth. Check invert level and alignment of the drainage
to ensure required gradient is achieved before preparation of concrete base.
Lay 50mm thick of lean concrete as base concrete except for roadside drain and berm
drain.
Once base is prepared, install the reinforcement as per construction drawing. The cover
of 25mm for reinforcement should be provided.
Prior to concreting work, the installation to be check and confirm by Clerk of Work / Site
Officer.
Mixture of concrete grade 25 is used for concreting work.
To carry out joint final survey upon completion of drainage works.
All specification for installation of reinforcements and concreting work should follow as
per construction drawings.
DESIGN AND BUILD FOR THE PROPOSED SLOPE IMPROVEMENT WORKS TO FAILED AT THE FOLLOWING
LOCATIONS : A) TANGKI MENARA BEJAYA PARK, WILAYAH KLANG. B) KOLAM AIR SETIA ALAM R9, WILAYAH
KLANG. C) RUMAH PAM BUKIT LIPAT KAJANG, WILAYAH KLANG. D) KOLAM SEDUT DESA SERDANG, HULU
LANGAT.
METHOD OF STATEMENTS.
5. SPRAY CONCRETE.
6. ROCKFILL.
METHOD OF STATEMENTS.
7. GABION WALL.
8. STONE PITCHING.
Determine the area to be treated.
Loose materials will be cleared and the slope will be trimmed.
Lay non – woven geotextile Grade TS30 as separator.
Laid on a cement mortar bed with the spaces between stones.
Filled with cement grout of the same compostion as the mortar (grouted stone
pitching).
All specification for installation of reinforcements and concreting work should follow as
per construction drawings.