CVX (1) (2) (4) Area/Building: Location of Work: Rodi Level of Work
CVX (1) (2) (4) Area/Building: Location of Work: Rodi Level of Work
CONTINUATION #: SIPP #:
SCHEDULE OF WORK ACTIVITY: START: (date/time) FINISH: (date/time):
PROJECT / TOOL NAME: ___________________CONTRACTOR: Print________________________________________
PROBABILITY OF OUTAGE OR RISK TO: MNx BLDG. [ 1 ][ 2 ][ 3 ][ 4 ][ 5 ] CVx [1] [2] [4]
WORK BEING PERFORMED AT: (Please check multiple areas, locations and levels as necessary)
Area/Building: MNx Bldg. [1] [2] [3] [4] [5] JMBC [ ] CVx [1] [2] [4] Utility Bldg. Other: _______
Location of Work: RODI AHU RM Elect. Rm Chiller Rm CIGI AWN Rm
UPS/PLC Bldg./Rm Grid/Col#’s: Other: ________
Level of Work: Roof Basement 1 Fl 2 Flr 3 Flr 4 Flr
st nd rd t
5 Flr 6Flr
Other_____________
EXISTING SERVICE(S) AT RISK: (see below and circle or identify all affected):
AIR HANDLERS DRAIN: FMS / BMS MDA TELEPHONES
BCDS ELECTRICAL: GASES BULK NETWORKS VACUUM
CDA / OFA EXHAUST: GASES INERT PAGING SYSTEM VESDA
CHILLERS EMERGENCY PHONES GASES SPECIALTY PCW WATER:
COMMUNICAITONS EMERGENCY SHOWERS HUMIDIFICATION RODI OTHER:
DEHUMIDIFICATION EVAC SPEAKER/STROBE KITCHEN SATELLITE LINK
DUMBWAITERS/ELEV FIRE PROTECTION MAKE-UP AIR SIMPLEX
SAFETY EQUIPMENT REQUIRED: (Shepherd’s Hook, Fire Extinguisher, Fall Protection, Safety Glasses, Hard Hats, Safety Boots)
SPECIAL EQUIPMENT/TOOLS: (welders, torch, forklift, scaffolds, mixer, core drill, generators, backhoe, cranes, etc.)
Rev. 0, 25/06/99
PRE-TASK PLANNING WORK SHEET
(Required for all SIPP Matrix work not covered by an approved written procedure.)
Intel Work Owner: ______________ Telephone # : _____________ Pager #: ___________
Work Plan Author: ___________________ Telephone # : _____________ Pager #: ___________
Organization: ______________________ Start Date: ____________ Finish Date: ____________
Specific Location of Work: ____________________________________________________________
System Affected: __________________________ Equipment Affected: _______________________
Task to be
Performed:________________________________________________________________
________________________________________________________________
Important !
All contractors must have attended Contractor Safety Orientation prior to starting work.
Locations of exits and emergency equipment must be communicated to all workers prior to
starting work.
All workers must review, understand, and sign the work plan prior to starting work.
MSDS’s must be available in the work area for all chemicals used.
Any questions with a “Yes” answer must be addressed in the Work Plan
Will task require working on or around live systems or equipment? (mechanical, Yes No
electrical, chemical, pneumatic, hydraulic, etc.)
Will any additional emergency equipment be needed to complete this task safely? Yes No
(extinguisher, portable eye wash/shower, radios/phones, etc.)
Does the Area Supervisor need to be notified of the work to be done? Yes No
Does the work plan need to be coordinated with other crafts in the area? Yes No
Are shop drawings, panel schedules, or as-builts needed to complete this task? Yes No
Does this task require special training or licenses? (respirator, confined space, forklift, Yes No
crane, interstitial etc.)
Will the task involve any hot work? Yes No
Will weather or other working conditions affect the safe completion of this task? Yes No
Will you need special tools or equipment to perform the task safely? (scaffolds, lifts, Yes No
jacks, nets, cranes, etc.). If so, list in Work Plan.
Will this task generate hazardous waste or material? Yes No
Will this task impact the operation or effectiveness of any pollution prevention systems Yes No
Will the task involve the removal or disturbance of asbestos, lead, or arsenic? Yes No
Will the task produce dust, vapors, fumes, mists, odors, noise, and/or vibration? Yes No
Will any workers be required to work at heights above 6 feet? Yes No
Will the task create any risk of interruption to A/T Yes No
Will any work be performed under raised floor tiles? (If yes, see Pre-Entry Checklist) Yes No
Will lifting equipment or mobile elevated work platforms (MEWPs) be used? Yes No
Will the task create hazards to people working above, below, or around the work area? Yes No
Will the task affect perimeter security, violate security guidelines, or require the Yes No
addition/deletion of security equipment?
Check ALL PPE, permits, forms, and checklists required and address in the Work Plan
Rev. 0, 25/06/99
Permits: SIPP ECP Hot Work Scaffold EEW Excavation
Confined Space Interstitial Work LSS/Yellow Card
Other _________________
Contact EHS if assistance is needed in completing this work review or work plan
SIGNATURES:
Rev. 0, 25/06/99
WORK PLAN
Project Name: _________________ Start Date: _________________ Finish Date: ________________
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
This Work Plan must be reviewed with all workers involved prior to starting any work.
Work Supervisor: _______________________________Petsa: ________________
Mga Manggagawa: _____________________________Petsa: ________________
_______________________________Petsa: ________________
_______________________________Petsa: ________________
Important !
All contractors must have attended Contractor Safety Orientation prior to starting work.
Locations of exits and emergency equipment must be communicated to all workers prior to
starting work.
All workers must review, understand, and sign the work plan prior to starting work.
MSDS’s must be available in the work area for all chemicals used.
Any questions with a “Yes” answer must be addressed in the Work Plan
Will task require working on or around live systems or equipment? (mechanical, Yes No
electrical, chemical, pneumatic, hydraulic, etc.)
Will any additional emergency equipment be needed to complete this task safely? Yes No
(extinguisher, portable eye wash/shower, radios/phones, etc.)
Does the Area Supervisor need to be notified of the work to be done? Yes No
Does the work plan need to be coordinated with other crafts in the area? Yes No
Are shop drawings, panel schedules, or as-builts needed to complete this task? Yes No
Does this task require special training or licenses? (respirator, confined space, forklift, Yes No
crane, interstitial etc.)
Will the task involve any hot work? Yes No
Will weather or other working conditions affect the safe completion of this task? Yes No
Will you need special tools or equipment to perform the task safely? (scaffolds, lifts, Yes No
jacks, nets, cranes, etc.). If so, list in Work Plan.
Will this task generate hazardous waste or material? Yes No
Will this task impact the operation or effectiveness of any pollution prevention systems Yes No
Will the task involve the removal or disturbance of asbestos, lead, or arsenic? Yes No
Will the task produce dust, vapors, fumes, mists, odors, noise, and/or vibration? Yes No
Will any workers be required to work at heights above 6 feet? Yes No
Will the task create any risk of interruption to A/T Yes No
Will any work be performed under raised floor tiles? (If yes, see Pre-Entry Checklist) Yes No
Will lifting equipment or mobile elevated work platforms (MEWPs) be used? Yes No
Will the task create hazards to people working above, below, or around the work area? Yes No
Will the task affect perimeter security, violate security guidelines, or require the Yes No
addition/deletion of security equipment?
Task to be accomplished
Steps To Take To Complete Task Hazards Required Actions To Eliminate Or
Control The Hazard
Notify concerned parties of the project Miscommunication Notify intel owner of work, systems engineer and
area supervisor.
Termination of wires to panels and eqpt. Hand & eye injury Wear cotton gloves , PPE’s
Electrocution Install individual Lo|to at panel ckt. breakers
Laceration Only approved elec’l knife will be used
Testing and commissioning
De-installation of interstitial devices Slip / hand injury Pull out excess materials and garbage.
(planks, lifelines, tasklights) Wear gloves
General housekeeping Don’t leave debris in interstitial
This Work Plan must be reviewed with all workers involved prior to starting any work.
Bago umpisahan ang anumang trabaho, ang work plan na ito ay dapat masuri kasama ang lahat ng
manggagawa.
Important !
All contractors must have attended Contractor Safety Orientation prior to starting work.
Locations of exits and emergency equipment must be communicated to all workers prior to
starting work.
All workers must review, understand, and sign the work plan prior to starting work.
MSDS’s must be available in the work area for all chemicals used.
Any questions with a “Yes” answer must be addressed in the Work Plan
Will task require working on or around live systems or equipment? (mechanical, Yes No
electrical, chemical, pneumatic, hydraulic, etc.)
Will any additional emergency equipment be needed to complete this task safely? Yes No
(extinguisher, portable eye wash/shower, radios/phones, etc.)
Does the Area Supervisor need to be notified of the work to be done? Yes No
Does the work plan need to be coordinated with other crafts in the area? Yes No
Are shop drawings, panel schedules, or as-builts needed to complete this task? Yes No
Does this task require special training or licenses? (respirator, confined space, forklift, Yes No
crane, interstitial etc.)
Will the task involve any hot work? Yes No
Will weather or other working conditions affect the safe completion of this task? Yes No
Will you need special tools or equipment to perform the task safely? (scaffolds, lifts, Yes No
jacks, nets, cranes, etc.). If so, list in Work Plan.
Will this task generate hazardous waste or material? Yes No
Will this task impact the operation or effectiveness of any pollution prevention systems Yes No
Will the task involve the removal or disturbance of asbestos, lead, or arsenic? Yes No
Will the task produce dust, vapors, fumes, mists, odors, noise, and/or vibration? Yes No
Will any workers be required to work at heights above 6 feet? Yes No
Will the task create any risk of interruption to A/T Yes No
Will any work be performed under raised floor tiles? (If yes, see Pre-Entry Checklist) Yes No
Will lifting equipment or mobile elevated work platforms (MEWPs) be used? Yes No
Will the task create hazards to people working above, below, or around the work area? Yes No
Will the task affect perimeter security, violate security guidelines, or require the Yes No
addition/deletion of security equipment?
Interstitial works for
Notify concerned parties of the project Miscommunication Notify intel ownerof work, systems engineer and
area supervisor.
Important !
All contractors must have attended Contractor Safety Orientation prior to starting work.
Locations of exits and emergency equipment must be communicated to all workers prior to
starting work.
All workers must review, understand, and sign the work plan prior to starting work.
MSDS’s must be available in the work area for all chemicals used.
Any questions with a “Yes” answer must be addressed in the Work Plan
Will task require working on or around live systems or equipment? (mechanical, Yes No
electrical, chemical, pneumatic, hydraulic, etc.)
Will any additional emergency equipment be needed to complete this task safely? Yes No
(extinguisher, portable eye wash/shower, radios/phones, etc.)
Does the Area Supervisor need to be notified of the work to be done? Yes No
Does the work plan need to be coordinated with other crafts in the area? Yes No
Are shop drawings, panel schedules, or as-builts needed to complete this task? Yes No
Does this task require special training or licenses? (respirator, confined space, forklift, Yes No
crane, interstitial etc.)
Will the task involve any hot work? Yes No
Will weather or other working conditions affect the safe completion of this task? Yes No
Will you need special tools or equipment to perform the task safely? (scaffolds, lifts, Yes No
jacks, nets, cranes, etc.). If so, list in Work Plan.
Will this task generate hazardous waste or material? Yes No
Will this task impact the operation or effectiveness of any pollution prevention systems Yes No
Will the task involve the removal or disturbance of asbestos, lead, or arsenic? Yes No
Will the task produce dust, vapors, fumes, mists, odors, noise, and/or vibration? Yes No
Will any workers be required to work at heights above 6 feet? Yes No
Will the task create any risk of interruption to A/T Yes No
Will any work be performed under raised floor tiles? (If yes, see Pre-Entry Checklist) Yes No
Will lifting equipment or mobile elevated work platforms (MEWPs) be used? Yes No
Will the task create hazards to people working above, below, or around the work area? Yes No
Will the task affect perimeter security, violate security guidelines, or require the Yes No
addition/deletion of security equipment?
Task to be accomplished
Steps To Take To Complete Task Hazards Required Actions To Eliminate Or
Control The Hazard
3. Mobilization of tools and materials Might struck other person and Assign guide person
Equipment. Install Barricades
4. Conduct tool box meeting Miscommunication Conduct meeting on site prior to start
Read and sign on workplan
5. Barricade the area of work Struck others Isolate the area, post proper signs
Wear PPE’s
6. Application of patching compound Dizziness Wear mask and follow Odor form
( weather can affect the task) Slip \ fever protocol checklist.
Stop work if raining
Sanding of wall to smoothes Allergies Wear mask and other PPE’s
surface.
7. Application of paint to the walls Asthma and skin allergy Wear gloves and respirator
and doors. Post Odor notification forms
Provide CUA, MSDS
8. Removal of barricade after Conflict Coordinate properly \
appropriate curing of paint. Post Wet paint signs
This Work Plan must be reviewed with all workers involved prior to starting any work.
Work Supervisor: ___________________________________ Petsa: ________________
Mga Manggagawa: ___________________________________ Petsa: ________________
___________________________________ Petsa: ________________
___________________________________ Petsa: ________________
___________________________________ Petsa: ________________