The Job Safety Analysis sheet summarizes the potential hazards and required precautions for mechanical excavation work. It identifies personal protective equipment needed, which includes a hard hat, safety shoes, safety goggles, hand gloves, dust mask, barriers, ladder, guardrail and polling board. Potential hazards of the excavation work include cave-ins, collapse of excavated materials, accidental falls, toxic/flammable gases, and blocked emergency equipment. Precautions include inspecting soil conditions, keeping excavated material away from trench edges, barricading and closing trenches when work is complete.

Uploaded by

abou bakar
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
433 views1 page

JSA-02-trench Excavation by Equipment

The Job Safety Analysis sheet summarizes the potential hazards and required precautions for mechanical excavation work. It identifies personal protective equipment needed, which includes a hard hat, safety shoes, safety goggles, hand gloves, dust mask, barriers, ladder, guardrail and polling board. Potential hazards of the excavation work include cave-ins, collapse of excavated materials, accidental falls, toxic/flammable gases, and blocked emergency equipment. Precautions include inspecting soil conditions, keeping excavated material away from trench edges, barricading and closing trenches when work is complete.

Uploaded by

abou bakar
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
You are on page 1/ 1

Job Safety Analysis Sheet

Job: Mechanical Excavation JSA Ref. No. JSA / KOC / 02


Facility: Work Area / Equipment: Permit No.
Date:
PERSONAL PROTECTIVE EQUIPMENT & TOOLS NEEDED FOR WORK ACTIVITIES: Hard Hat, Safety Shoes, Safety
Goggles, Hand Gloves, Dust Mask, Barriers, Ladder, Guardrail, Polling Board
SEQUENCE OF Yes /
POTENTIAL HAZARDS PRECAUTIONS
BASIC JOB STEPS No

Presence of EOD  Ensure the area to be excavated is declared EOD


cleared.
 Locate underground / aboveground services referring
to the site map / drawing.
Location of Underground /
Aboveground Services (such  Endorsements in Excavation Notification from the
Pre - work pipeline, cables etc) concerned Teams for the services in the area to be
excavated.
 Hold pre-job safety meeting
Non-compliance of KOC
-HSEMS Procedures, F & S  Get authorization for Hot Work Permit
Regulations or Engineering  Conduct Toolbox Talk
Standards
 Check for underground / aboveground services
Damage to underground /
through metal detectors
aboveground Services (such
pipeline, cables etc)  Isolate services as needed through authorized
permit
Cave-in's of excavation  Utilize sloping, benching & shoring as needed
 Keep excavated material at least 1 meter away from
Collapse of Excavated the edge of the trench.
Excavation Materials  Inspection for soil condition before starting
excavation work.
 Keep the equipment / mobile plant at least 3 meters
Accidental fall of equipment /
away from the edge of the trench.
mobile plant
 Wear appropriate PPE
Possibility of toxic / flammable  Carry out gas test before excavating in hazardous
gas area.
Blocking Emergency  Ensure the approach to Emergency Equipment is not
Equipment blocked due to open trenches.
 Barricade the trenches
Unattended trenches
 Use of Warning signs
Post Excavation  Close the trench, backfill and compact the area.
Trenches left open for
extended period  Close the permit after making the site clean & tidy.

Additional Hazards
(Other than indicated
above)

Name: Designation:
KOC / ID. No. Company:
JSA Done By
Controlling Team: Contract No .(If Applicable):
Signature: Date:

You might also like