Introduction To RAM
Introduction To RAM
What is RAM?
RAM refers to Reliability, Availability and Maintainability. Reliability is the
probability of survival after the unit/system operates for a certain period of
time (e.g. a unit has a 95% probability of survival after 8000 hours). Reliability
defines the failure frequency and determines the uptime patterns.
Maintainability describes how soon the unit/system can be repaired, which
determines the downtime patterns. Availability is the percentage of uptime
over the time horizon, and is determined by reliability and maintainability.
RBD or Fault
Basic Analysis – System Tree
Failure mode and distribution parameters can be obtained for each unit in the
system. Reliability Block Diagrams (RBD) or Fault Trees (FT) can be used to
represent the logic relationships between component failures and system
failures, and provide the basis for a RAM study. With the failure distribution
data input into an RBD/FT, engineers will be able to understand the RAM
performances of the current system and carry on further developments and
optimisations. In fact, there is a direct relationship between RBD and FT, but
most engineers find RBD easier to use, as it can be more easily related to a
process flowsheet. The approach to RAM analysis adopted by Process
Integration Limited exploits RBDs.
In the design stage, RAM analysis can be integrated into the design of the
system configuration, which will ensure the optimum design with balanced
RAM performance and total investment. Moreover, the qualitative and
quantitative analysis of process unit failures can help designers to modify the
structure of a specific process unit to improve the process design.
An Event Tree uses binary branching to identify the events leading to system
failures or successes. In a Fault Tree, system failures can be expressed in terms
of combinations of component failure modes, as illustrated in Figure 4a. A Fault
Tree is part of Event Tree and can be transformed from an Event Tree. An RBD,
as illustrated in Figure 4b, is a logical inverse of a Fault Tree. As shown in Figure
4b, blocks are used to represent component failures or failure modes for a
certain component. The approach to RAM analysis adopted by Process
Integration Limited exploits RBDs because most engineers find the RBD easier
to use, as it can be more easily related to a process flowsheet.
With distribution parameters input into an RBD (or ET or FTA), system RAM
performance will be obtained by simulations.
a) Deterministic Approach
According to the data in Table.1, Mean Time Between Failure (MTBF) = 7142
day/ 40 = 178 day. Using a deterministic approach, it is assumed the component
will fail every 178 days, as shown in Fig.5.
Up
Time
178 day 178 day 178 day
Based on the economic data, total annual costs with different maintenance
policies are listed in Table.3. The cost comprises corrective maintenance cost,
preventive maintenance cost and lost production cost. As a result, preventive
But it is dangerous to use the rule of thumb for every unit, since each unit has
different failure distribution patterns as well as different maintenance cost,
associated penalty cost, etc. It is not possible to find a “golden rule” which can
be applied for all of the process units. Costs could even be increased with a
wrong rule.
b) Probabilistic Approach
Using a probabilistic approach, the failures are represented by a probability
distribution. The Reliability curve and Probability Density Function curve are
shown in Fig.6. From this:
The probability that the component will fail in 60 days is 10%.
The probability that the component will fail in 120 days is 32%.
The probability that the component will fail in 180 days is 57%.
The probability that the component will fail in 300 days is 90%.
The component will fail most likely around 140 days, although MTBF is 178 days.
This indicates that the component is more likely to fail after 140 days.
1 0.005
0.9 0.0045
0.8 0.004
0.7 0.0035
0.6 0.003
Probability
Reliability
0.5 0.0025
0.4 0.002
0.3 0.0015
0.2 0.001
0.1 0.0005
0 0
0 100 200 300 400 500 600 700 800 0 100 200 300 400 500 600 700 800
Tim e(day) Tim e (days)
Redundancy Optimisation
Using standby components (sometimes referred to as spare or redundant
components) is a common way to increase system availability and profit in the
design stage, or even in retrofit. In addition to the inclusion of standby
equipment, the standby equipment can be exploited in different ways. Instead
A mathematical tool can help engineers make the best decisions on a sound
basis.
Table.5 Basic Information of Pumps
MTBF MTBF
Capacity MTTR Capital Cost
Pump ID (operation) (standby) Availability
(%) (days) (K$)
(days) (days)
Pump A 100% 300 4000 4 0.9868 320
Pump B 100% 300 4000 5 0.9836 628
Pump C 100% 200 2000 10 0.9524 8000
Pump D1 100% 220 4000 10 0.9565 4660
Pump D2 75% 220 4000 8 0.9649 4200
Pump D3 50% 250 4000 8 0.9690 3600
Pump E 100% 330 4000 4 0.9880 1116
Pump F 100% 280 4000 5 0.9825 176
Pump G 100% 300 4000 4 0.9868 1316
Pump H 100% 290 4000 4 0.9864 676
Pump I 100% 300 4000 4 0.9868 820
Pump J1 100% 310 4000 4 0.9873 504
Pump J2 75% 330 4000 4 0.9880 450
Pump J3 50% 350 4000 4 0.9887 390
1800 80
1700
1600
1500 70
1400
1300
1200 60
50 100 150 200 No CBM Inspection/6 Inspection/4 Inspection/2 Inspection/1 Real-time
w eeks w eeks w eeks w eek
PM interval (Days)
4.5
3.5
Cost (K$/year)
1.5
0.5
0
5/3 4/2 3/1 2/0
Max/Min Stocking No