This document provides a list of labor rates and material prices for construction projects in 2018 for the Public Works and Spatial Planning Department of Baik District. It includes hourly wages for various construction workers and prices per unit for common building materials like sand, gravel, cement, wood, steel, and pipes. Transportation and loading/unloading costs are also provided to determine the total price per unit of each material.

Uploaded by

Novia Delta
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
3K views

Rab Flying Fox

This document provides a list of labor rates and material prices for construction projects in 2018 for the Public Works and Spatial Planning Department of Baik District. It includes hourly wages for various construction workers and prices per unit for common building materials like sand, gravel, cement, wood, steel, and pipes. Transportation and loading/unloading costs are also provided to determine the total price per unit of each material.

Uploaded by

Novia Delta
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
You are on page 1/ 153

ESTIMATE ENGINEERS (EE)

HARGA UPAH DAN BAHAN BANGUNAN TAHUN ANGGARAN 2018


DINAS PEKERJAAN UMUM DAN PENATAAN RUANG
DAERAH BAIK

DAFTAR UPAH
NO. JENIS UPAH SATUAN UPAH KETERANGAN
1 2 3 4 5
1 Pekerja OH 67,900.00
2 Tukang Bangunan ( Batu, Kayu, Pipa, Bongkar, Cat dan Besi ) OH 83,200.00
3 Kepala Tukang OH 88,000.00
4 Mandor Bangunan OH 90,000.00

HARGA
NO. JENIS BAHAN SATUAN MUAT BONGKAR TRANSPORT JUMLAH
TOKO/QUARRY
1 2 3 4 5 6 7 ( 4+5+6)

I BAHAN PASANGAN
1 Pasir Urug (PU) M3 100,000.00 20,000.00 25,000.00 145,000.00
2 Pasir Pasang (PP) M3 100,000.00 20,000.00 25,000.00 145,000.00
3 Pasir Beton (PB) M3 100,000.00 20,000.00 25,000.00 145,000.00
4 Pasir Kuarsa M3 88,000.00 20,000.00 50,000.00 158,000.00
5 Kerikil (KR) M3 146,300.00 25,000.00 25,000.00 196,300.00
6 Sirtu M3 125,000.00 20,000.00 25,000.00 170,000.00
7 Batu Belah (gunung) 15cm/20 cm M3 230,000.00 50,000.00 75,000.00 355,000.00
8 Batu sungai (mangga) M3 250,000.00 25,000.00 25,000.00 300,000.00
9 Portland Cement (PC) Kg 1,260.00 50.00 50.00 1,360.00
10 Semen putih Kg 2,300.00 50.00 50.00 2,400.00
11 Cornite Compound Jayaboard Zak 70,000.00 2,500.00 500.00 73,000.00
12 Bata Merah (Ukuran Jumbo ) Buah 500.00 30.00 20.00 550.00
13 Kerawang (Roster semen)20x20 cm Buah 22,000.00 20.00 80.00 22,100.00
14 Kerawang (Roster semen)40x40 cm Buah 45,000.00 20.00 80.00 45,100.00
15 Rumput Gajah Mini M2 40,500.00 500.00 1,000.00 42,000.00
HARGA
NO. JENIS BAHAN SATUAN MUAT BONGKAR TRANSPORT JUMLAH
TOKO/QUARRY
1 2 3 4 5 6 7 ( 4+5+6)
16 Rumput Biasa M2 16,500.00 500.00 1,000.00 18,000.00
17 Tanah Hitam M3 55,000.00 20,000.00 25,000.00 100,000.00
18 Tanah Urug Biasa M3 20,000.00 20,000.00 25,000.00 65,000.00
19 Conblock Segi 6 Tebal 8 CM Bh 1,800.00 20.00 80.00 1,900.00
20 Conblock Segi 4 Tebal 8 CM Bh 1,800.00 20.00 80.00 1,900.00
21 Grass Block T= 6 cm Bh 20,600.00 20.00 80.00 20,700.00
22 Buis Beton Dia 20cm P= 50 Cm Bh 51,000.00 5,000.00 5,000.00 61,000.00
23 Buis Beton Dia 40cm P = 60 Cm Bh 158,000.00 10,000.00 15,000.00 183,000.00
24 Buis Beton Dia 60cm P= 80 Cm Bh 280,000.00 15,000.00 15,000.00 310,000.00
25 Buis Beton Dia 80cm P= 100 Cm Bh 350,000.00 20,000.00 20,000.00 390,000.00
26 Buis Beton Dia 100cm P = 100 Cm Bh 448,000.00 20,000.00 20,000.00 488,000.00
27 Batu Split / Pecah M3 320,000.00 20,000.00 25,000.00 365,000.00
28 Bata Beton Ringan Buah 6,000.00 300.00 400.00 6,700.00
29 Batu Tempel Uk. 20 x 20 Buah 5,000.00 50.00 50.00 5,100.00
30 Batu Tempel Uk. 20 x 40 Buah 12,500.00 50.00 50.00 12,600.00

II BAHAN KAYU
1 Kayu Kelas I M3 6,500,000.00 50,000.00 35,000.00 6,585,000.00
2 Kayu Kelas II M3 2,000,000.00 50,000.00 35,000.00 2,085,000.00
3 Kayu Kelas III M3 1,900,000.00 50,000.00 35,000.00 1,985,000.00
4 Kayu Kelas IV M3 1,210,750.00 52,500.00 36,750.00 1,300,000.00
5 Kayu List Profil siku2" M' 2,500.00 5.00 10.00 2,515.00
6 Kayu List Profil 0.8x3" M' 3,000.00 5.00 10.00 3,015.00
7 Papan 2 x 20 M3 1,800,000.00 50,000.00 35,000.00 1,885,000.00
8 Kayu Cerocok dia. 10 - 15 cm Btg 35,000.00 500.00 3,000.00 38,500.00
9 Dolken Kayu Galam, Ø (8-10)Cm,Panjang 4 M Batang 6,000.00 500.00 500.00 7,000.00
10 Kayu Bakar ( Non Kelas ) M3 200,000.00 50,000.00 35,000.00 285,000.00
11 Papan Piri - piri (Siap Ketam 3 sisi) M3 2,200,000.00 50,000.00 35,000.00 2,285,000.00
12 Papan Lebah Bergayut M' 40,000.00 500.00 1,000.00 41,500.00
13 Singap Ukir kayu M2 750,000.00 3,000.00 10,000.00 763,000.00
14 Singap Ukir GRC M2 400,000.00 3,000.00 10,000.00 413,000.00
15 Selembayung GRC Lebar 30 cm Pasang 400,000.00 1,000.00 5,000.00 406,000.00
HARGA
NO. JENIS BAHAN SATUAN MUAT BONGKAR TRANSPORT JUMLAH
TOKO/QUARRY
1 2 3 4 5 6 7 ( 4+5+6)
16 Selembayung kayu lebar 30 cm Pasang 250,000.00 1,000.00 5,000.00 256,000.00
17 Sayap layang-layang lebar 30 cm Pasang 250,000.00 1,000.00 5,000.00 256,000.00
18 Lisplank papan + anak ( + 30 cm) M' 50,000.00 1,000.00 5,000.00 56,000.00

III BAHAN BESI DAN BAJA


1 Baja Beton Polos U 24 Kg 10,200.00 50.00 50.00 10,300.00
2 Baja Beton Ulir U 39 Kg 20,000.00 50.00 50.00 20,100.00
3 Baja Beton Ulir U 32 Kg 10,400.00 50.00 50.00 10,500.00
4 Besi Plat rata2 Kg 11,000.00 100.00 100.00 11,200.00
5 Besi Tempa M2 244,900.00 100.00 100.00 245,100.00
6 Kawat Beton Kg 18,000.00 20.00 50.00 18,070.00
7 Kawat Ø 4 mm Kg 16,000.00 20.00 50.00 16,070.00
8 Kawat Las Listrik Kg 20,000.00 20.00 50.00 20,070.00
9 Kawat Ayam M2 13,800.00 20.00 200.00 14,020.00
10 Besi Strip Tebal 5 mm Kg 12,900.00 20.00 150.00 13,070.00
11 Terali besi (Non Motif) M2 250,000.00 1,000.00 1,000.00 252,000.00
12 Baja Profil Kg 18,000.00 20.00 200.00 18,220.00
13 Besi Siku Kg 16,500.00 300.00 100.00 16,900.00
14 Wiremesh M6 Kg 12,500.00 100.00 100.00 12,700.00
15 Wiremesh M8 Kg 12,500.00 100.00 100.00 12,700.00

IV BAHAN PAKU
1 Paku 1 Cm - 2,5 Cm Kg 15,000.00 80.00 100.00 15,180.00
2 Paku 5 Cm - 12 Cm Kg 15,000.00 80.00 100.00 15,180.00
3 Paku Skrup Kg 40,000.00 80.00 100.00 40,180.00
4 Paku Skrup 5 Cm Kg 40,000.00 80.00 100.00 40,180.00
5 Paku Skrup 10 Cm Kg 40,000.00 80.00 100.00 40,180.00
6 Paku Asbes Kg 20,000.00 80.00 100.00 20,180.00
7 Paku Atap Genteng Metal Kg 24,000.00 80.00 100.00 24,180.00
8 Paku Atap Seng Gelombang Kg 20,000.00 80.00 100.00 20,180.00
9 Skrup Fixer Buah 300.00 25.00 25.00 350.00
HARGA
NO. JENIS BAHAN SATUAN MUAT BONGKAR TRANSPORT JUMLAH
TOKO/QUARRY
1 2 3 4 5 6 7 ( 4+5+6)
V BAHAN ALLUMUNIUM
1 Profil Allumunium "T" M' 23,000.00 275.00 1,100.00 24,375.00
2 Kusen Alumunium 3'' M' 193,000.00 500.00 1,500.00 195,000.00
3 Rangka Jendela Almunium M' 193,000.00 500.00 1,500.00 195,000.00
4 Rangka Pintu Almunium M' 193,000.00 500.00 1,500.00 195,000.00

VI BAHAN LANTAI
1 Homogenius Ukuran ( 60 x 60 ) Cm Buah 59,800.00 100.00 100.00 60,000.00
2 Homogenius Ukuran ( 40 x 40 ) cm Buah 31,700.00 100.00 100.00 31,900.00
3 Homogenius Ukuran ( 30 x 30 ) cm Buah 15,500.00 100.00 100.00 15,700.00
4 Keramik (40x40) Cm Buah 8,850.00 100.00 100.00 9,050.00
5 Keramik (30x30) Cm Buah 4,350.00 100.00 100.00 4,550.00
6 Keramik (20x20) Cm Buah 2,100.00 75.00 75.00 2,250.00
7 Keramik (20x25) Cm Buah 2,700.00 75.00 75.00 2,850.00
8 Granit Warna (60x60) Cm Buah 85,000.00 100.00 100.00 85,200.00
9 Keramik Warna (40x40) Cm Buah 9,400.00 100.00 100.00 9,600.00
10 Keramik Warna (30x30) Cm Buah 4,900.00 75.00 75.00 5,050.00
11 Keramik Warna (20x20) Cm Buah 2,300.00 75.00 75.00 2,450.00
12 Plint Keramik (10x20) Cm Buah 1,400.00 50.00 50.00 1,500.00
13 Plint Keramik (10x30) Cm Buah 2,300.00 25.00 25.00 2,350.00
14 Plint Keramik (10x40) Cm Buah 3,200.00 25.00 25.00 3,250.00
15 Plint Homogenius (10x60) Cm Buah 12,000.00 25.00 25.00 12,050.00
16 Plint Homogenius (10x40) Cm Buah 11,000.00 50.00 100.00 11,150.00
17 Plint Keramik Warna (10x20) Cm Buah 1,300.00 50.00 50.00 1,400.00
18 Plint Keramik Warna (10x30) Cm Buah 2,300.00 50.00 50.00 2,400.00
19 Plint Keramik Warna (10x40) Cm Buah 3,200.00 25.00 25.00 3,250.00
20 Plint Granit Warna (10x60) Cm Buah 13,300.00 25.00 25.00 13,350.00
21 Bon-bon Keramik M' 7,700.00 25.00 25.00 7,750.00
22 Floor hardener M2 34,800.00 100.00 100.00 35,000.00
23 Parquette M2 225,000.00 100.00 100.00 225,200.00
24 Karpet M2 12,900.00 350.00 3,400.00 16,650.00
HARGA
NO. JENIS BAHAN SATUAN MUAT BONGKAR TRANSPORT JUMLAH
TOKO/QUARRY
1 2 3 4 5 6 7 ( 4+5+6)

VII BAHAN ATAP


1 Asbes Gelombang Lbr 34,000.00 100.00 200.00 34,300.00
2 Genteng Metal gelombang Tebal 0,30 MM Lbr 40,000.00 100.00 200.00 40,300.00
3 Genteng Metal alur lurus Tebal 0,30 MM Lbr 40,000.00 100.00 200.00 40,300.00
4 Perabung genteng metal Lbr 25,000.00 100.00 200.00 25,300.00
5 Seng Gelombang BJLS 020 K Lbr 42,000.00 100.00 200.00 42,300.00
6 Seng Gelombang Alumunium 0,25 Lbr 71,000.00 100.00 200.00 71,300.00
7 Seng Plat BJLS 20 Lbr 59,000.00 100.00 200.00 59,300.00
8 Atap Multi Sirap Lbr 5,000.00 100.00 200.00 5,300.00
9 EDF M2 250,000.00 100.00 200.00 250,300.00
10 Genteng Beton warna BH 21,500.00 100.00 200.00 21,800.00
11 Bubungan beton warna BH 28,000.00 100.00 200.00 28,300.00
12 Allumunium Foil / Sisalation M2 13,000.00 100.00 200.00 13,300.00
13 Formika M2 40,000.00 500.00 1,000.00 41,500.00
14 Spandek Tebal 0,30 MM M2 40,000.00 100.00 200.00 40,300.00
15 Genteng Keramik Bh 6,750.00 100.00 250.00 7,100.00
16 Genteng Keramik Glazur Bh 10,250.00 100.00 250.00 10,600.00
17 Nok Genteng Keramik Bh 4,150.00 100.00 250.00 4,500.00
18 Nok Genteng Keramik Glazur Bh 6,150.00 100.00 250.00 6,500.00
19 Nok Genteng Metal ( Panjang 90 CM ) Bh 35,000.00 500.00 700.00 36,200.00
20 Terpal Khusus untuk Atap ( Lebar 50 CM ) M1 19,000.00 500.00 500.00 20,000.00

VIII BAJA RINGAN


1 Baja Ringan C75. 100INT M' 25,000.00 100.00 200.00 25,300.00
2 Baja Ringan C75. 75INT M' 12,000.00 100.00 200.00 12,300.00
3 Topspan 40,055 INT M' 31,000.00 100.00 200.00 31,300.00
4 Wteks 12-14x20 HWFS Kls II Pc 650.00 100.00 200.00 950.00
5 CSP 10-16X16 HWFS Kls II Pc 650.00 100.00 200.00 950.00
6 SG10 Multiplate Pc 8,000.00 100.00 200.00 8,300.00
7 Reng Baja Ringan M' 6,500.00 100.00 200.00 6,800.00
HARGA
NO. JENIS BAHAN SATUAN MUAT BONGKAR TRANSPORT JUMLAH
TOKO/QUARRY
1 2 3 4 5 6 7 ( 4+5+6)
IX BAHAN LANGIT-LANGIT
1 Teakwood Tebal 3,6 mm Lembar 150,000.00 500.00 1,000.00 151,500.00
2 Triplek Tebal 12 MM Lembar 202,000.00 500.00 1,000.00 203,500.00
3 Triplek Tebal 9,0 MM Lembar 145,000.00 500.00 1,000.00 146,500.00
4 Triplek Tebal 3,6 MM Lembar 65,000.00 500.00 1,000.00 66,500.00
5 Triplek Tebal 3,0 MM Lembar 57,200.00 500.00 1,000.00 58,700.00
6 Gypsum Board 9 mm Lembar 85,000.00 500.00 1,000.00 86,500.00
7 List Gypsum lbr 15-20cm M' 17,600.00 500.00 1,000.00 19,100.00
8 Asbes Semen M2 50,000.00 500.00 1,000.00 51,500.00
9 Triplek melamin Lembar 75,000.00 500.00 1,000.00 76,500.00

X BAHAN PIPA DAN SANITAIR


1 Pipa PVC Type AW Ø 1/2" M' 3,900.00 50.00 200.00 4,150.00
2 Pipa PVC Type AW Ø 3/4" M' 6,250.00 50.00 200.00 6,500.00
3 Pipa PVC Type AW Ø 1" M' 8,950.00 50.00 200.00 9,200.00
4 Pipa PVC Type AW Ø 2" M' 15,000.00 50.00 200.00 15,250.00
5 Pipa PVC Type AW Ø 2,50 " M' 17,500.00 50.00 200.00 17,750.00
6 Pipa PVC Type AW Ø 3" M' 30,000.00 50.00 200.00 30,250.00
7 Pipa PVC Type AW Ø 4" M' 40,000.00 50.00 200.00 40,250.00
8 Pipa PVC Type AW Ø 6" M' 110,000.00 50.00 200.00 110,250.00
9 Pipa Abu-abu 4" M' 15,000.00 50.00 200.00 15,250.00
10 Pipa Galvanis dia 1" M' 60,000.00 50.00 200.00 60,250.00
11 Pipa Galvanis dia 1,5" M' 90,000.00 50.00 200.00 90,250.00
12 Pipa Galvanis dia 2" M' 123,000.00 50.00 200.00 123,250.00
13 Pipa Besi dia 1" M' 39,000.00 50.00 200.00 39,250.00
14 Pipa Besi dia 1,5" M' 21,000.00 50.00 200.00 21,250.00
15 Pipa Besi dia 3/4" M' 31,000.00 50.00 200.00 31,250.00
16 Stop kran 3/4" Bh 52,000.00 50.00 200.00 52,250.00
17 Kran Air Ø 1/2" atau 3/4" plastik Bh 10,000.00 50.00 200.00 10,250.00
18 Kran Air Ø 1/2" atau 3/4" stainless Bh 100,000.00 50.00 200.00 100,250.00
19 Bak Fiberglass Kap. Kecil Bh 220,000.00 5,000.00 20,000.00 245,000.00
20 Bak Fiberglass Kap. Besar Bh 300,000.00 5,000.00 20,000.00 325,000.00
HARGA
NO. JENIS BAHAN SATUAN MUAT BONGKAR TRANSPORT JUMLAH
TOKO/QUARRY
1 2 3 4 5 6 7 ( 4+5+6)
21 Kloset Duduk Monoblok Bh 1,750,000.00 5,000.00 20,000.00 1,775,000.00
22 Kloset Jongkok Porselen Bh 250,000.00 5,000.00 20,000.00 275,000.00
23 Urinoir Bh 1,300,000.00 5,000.00 20,000.00 1,325,000.00
24 Wastafel kecil standard dinding Bh 450,000.00 5,000.00 20,000.00 475,000.00
25 Seal Tape Bh 5,100.00 50.00 75.00 5,225.00
26 Floor Drain stainless Bh 160,000.00 50.00 200.00 160,250.00
27 Floor Drain plastik Bh 15,000.00 50.00 200.00 15,250.00
28 Tangki Plastik 250 Liter Unit 500,000.00 5,000.00 20,000.00 525,000.00
29 Tangki Plastik 500 Liter Unit 600,000.00 5,000.00 20,000.00 625,000.00
30 Tangki Plastik 1000 Liter Unit 1,350,000.00 5,000.00 20,000.00 1,375,000.00
31 Tangki Stainless 500 Liter + Kaki Unit 1,600,000.00 5,000.00 20,000.00 1,625,000.00
32 Tangki Stainless 1100 Liter + Kaki Unit 3,200,000.00 5,000.00 20,000.00 3,225,000.00
33 Pipa Baja Kg 17,500.00 50.00 50.00 17,600.00

XI BAHAN PINTU
1 Pintu Besi M2 660,000.00 5,000.00 20,000.00 685,000.00
2 Pintu Fiber Warna Lbr 754,000.00 5,000.00 20,000.00 779,000.00
3 Pintu Fiber KM/WC (lengkap) Lbr 300,000.00 5,000.00 20,000.00 325,000.00
4 Pintu Panel kelas I Lbr 850,000.00 5,000.00 20,000.00 875,000.00
5 Pintu Panel Kelas II Lbr 700,000.00 5,000.00 20,000.00 725,000.00
6 Pintu Plywood (triplek depan blkg) Lbr 190,000.00 5,000.00 20,000.00 215,000.00
7 Pintu Teakwood (lapis jati) depan belakang Lbr 620,000.00 5,000.00 20,000.00 645,000.00
8 Vertical Blind M2 90,000.00 5,000.00 2,650.00 97,650.00
9 Rolling Door M2 500,000.00 5,000.00 10,000.00 515,000.00
10 Folding Gate M2 650,000.00 5,000.00 10,000.00 665,000.00
11 Pintu Aluminium Kaca Lbr 2,100,000.00 5,000.00 10,000.00 2,115,000.00

XII BAHAN PENGGANTUNG / KUNCI


1 Kunci Tanam Antik kuningan (standard) Bh 200,000.00 50.00 150.00 200,200.00
2 Kunci Tanam Biasa (minimalis) Bh 130,000.00 50.00 150.00 130,200.00
3 Kunci Tanam Kamar Mandi Bh 50,000.00 50.00 150.00 50,200.00
HARGA
NO. JENIS BAHAN SATUAN MUAT BONGKAR TRANSPORT JUMLAH
TOKO/QUARRY
1 2 3 4 5 6 7 ( 4+5+6)
4 Kunci Silinder Bh 50,000.00 50.00 150.00 50,200.00
5 Engsel Pintu 4" Bh 7,500.00 50.00 150.00 7,700.00
6 Engsel Jendela 3" Bh 5,000.00 50.00 150.00 5,200.00
7 Grendel pintu 6" (krom) Bh 20,000.00 50.00 150.00 20,200.00
8 Grendel Pintu 4"(krom) Bh 11,000.00 50.00 150.00 11,200.00
9 Grendel Jendela 2" (krom) Bh 8,500.00 50.00 150.00 8,700.00
10 Kait Angin / Hak Angin Bh 6,500.00 50.00 150.00 6,700.00
11 Tarikan Tangan ( Jendela / Ventilasi ) Bh 7,500.00 50.00 150.00 7,700.00
12 Door Closer Bh 390,000.00 50.00 150.00 390,200.00
13 Door Stoper Plastik Bh 20,000.00 50.00 150.00 20,200.00
14 Selinder Bh 7,500.00 50.00 150.00 7,700.00
15 Handle Jendela Bh 7,500.00 50.00 150.00 7,700.00

XIII BAHAN KACA


1 Kaca 3 mm M2 76,500.00 800.00 5,000.00 82,300.00
2 Kaca 5 mm M2 87,000.00 800.00 5,000.00 92,800.00
3 Kaca polos 8 mm M2 360,000.00 1,000.00 1,000.00 362,000.00
4 Kaca polos 12 mm M2 504,000.00 1,000.00 1,000.00 506,000.00
5 Kaca es/buram 3 mm M2 88,400.00 800.00 5,000.00 94,200.00
6 Kaca es/buram 5 mm M2 111,000.00 800.00 5,000.00 116,800.00
7 Kaca patry M2 180,000.00 800.00 5,000.00 185,800.00
8 Kaca Rayben 3 mm M2 92,000.00 800.00 5,000.00 97,800.00
9 Kaca Rayben 5 mm M2 120,000.00 800.00 5,000.00 125,800.00
10 Jendela Nako (rangka + Kaca 5 mm) M2 89,000.00 800.00 5,000.00 94,800.00
11 Glass Block Ukuran standard BH 20,000.00 800.00 5,000.00 25,800.00

XIV BAHAN LISTRIK


1 Pemasangan Titik Lampu (termasuk kabel,teedus, fitting) Ttk 180,000.00 - - 180,000.00
2 Lampu Pijar 25 Watt Buah 6,500.00 5.00 100.00 6,605.00
3 Lampu Pijar 40 Watt Buah 8,200.00 5.00 100.00 8,305.00
4 Lampu Neon Jantung Buah 75,000.00 5.00 100.00 75,105.00
5 Lampu Save Energy (Lilin) Setara Philips Buah 50,000.00 5.00 100.00 50,105.00
HARGA
NO. JENIS BAHAN SATUAN MUAT BONGKAR TRANSPORT JUMLAH
TOKO/QUARRY
1 2 3 4 5 6 7 ( 4+5+6)
6 Lampu TL Komplit 1 x 20 watt Buah 74,000.00 50.00 200.00 74,250.00
7 Lampu TL Komplit 2 x 20 Watt Buah 310,000.00 50.00 200.00 310,250.00
8 Lampu TL Komplit 1 x 40 Watt Buah 100,000.00 50.00 200.00 100,250.00
9 Lampu Down Light 4" komplit Buah 94,000.00 50.00 100.00 94,150.00
10 Lampu Baret Buah 188,000.00 50.00 100.00 188,150.00
11 Stop Kontak (setara broco) Buah 14,500.00 50.00 100.00 14,650.00
12 Saklar Tunggal (setara broco) Buah 14,500.00 50.00 100.00 14,650.00
13 Saklar Ganda (setara broco) Buah 21,600.00 50.00 100.00 21,750.00
14 Saklar Triple (setara broco) Buah 27,000.00 50.00 100.00 27,150.00
15 Zakering Khas (setara merlin gerlin) Buah 50,000.00 50.00 100.00 50,150.00

XV BAHAN CAT
1 Cat Tembok Standar Kg 22,000.00 100.00 200.00 22,300.00
2 Cat Tembok Akrilik Kg 27,500.00 100.00 200.00 27,800.00
3 Cat Tembok Weather Shield Kg 75,000.00 100.00 200.00 75,300.00
4 Cat Kayu dan Besi ( Cat Minyak ) Kg 58,000.00 100.00 200.00 58,300.00
5 Cat Dasar / Kapur Kg 8,000.00 100.00 200.00 8,300.00
6 Cat Dasar / Menie Kayu Kg 30,000.00 100.00 200.00 30,300.00
7 Cat Vernish Kg 56,000.00 100.00 200.00 56,300.00
8 Cat Impra Kg 41,500.00 100.00 200.00 41,800.00
9 Cat Residu Kg 35,350.00 100.00 200.00 35,650.00
10 Soda Api Kg 11,600.00 100.00 200.00 11,900.00
11 Plamir setara RJ Kg 27,200.00 100.00 200.00 27,500.00
12 Dempul Kayu Kg 38,400.00 100.00 200.00 38,700.00
13 Kertas Amplas Lbr 6,100.00 25.00 50.00 6,175.00
14 Kuas 3" Bh 17,300.00 25.00 50.00 17,375.00
15 Kuas Golong/rol Bh 26,350.00 25.00 50.00 26,425.00
16 Thinner Ltr 36,400.00 100.00 200.00 36,700.00
17 Flincote / Menie Besi Kg 16,500.00 100.00 200.00 16,800.00

XVI BAHAN LAIN-LAIN


1 Mesin las Jam 98,000.00 - - 98,000.00
HARGA
NO. JENIS BAHAN SATUAN MUAT BONGKAR TRANSPORT JUMLAH
TOKO/QUARRY
1 2 3 4 5 6 7 ( 4+5+6)
2 Concrete Pump Hari 3,500,000.00 - - 3,500,000.00
3 Air Liter 20.00 10.00 20.00 50.00
4 Lem Kg 2,500.00 125.00 225.00 2,850.00
5 Sabun Kg 30,000.00 500.00 500.00 31,000.00
6 Kapur Sirih Kg 4,000.00 300.00 400.00 4,700.00
7 Alang - alang Ikat 20,000.00 250.00 350.00 20,600.00
8 Lem Kayu Kg 25,300.00 125.00 225.00 25,650.00
9 Sealant Tube 12,000.00 125.00 225.00 12,350.00
10 Profil Kaca M' 1,700.00 42.50 170.00 1,912.50
11 Solar Liter 8,400.00 100.00 200.00 8,700.00
12 Minyak Pelumas Liter 23,000.00 308.15 1,232.50 24,540.65
13 Minyak Bekisting Liter 4,000.00 182.50 695.00 4,877.50
14 Aspal Drum Kg 13,500.00 195.00 780.00 14,475.00
15 Tempat Masak Aspal BH 43,900.00 1,097.50 4,395.00 49,392.50
16 Ijuk Kg 15,000.00 100.00 200.00 15,300.00
17 Water proofing Coating Kg 30,000.00 100.00 200.00 30,300.00
18 Water proofing Membran M2 95,000.00 500.00 1,000.00 96,500.00
19 Batu Coral sikat ZAK 50,000.00 500.00 1,000.00 51,500.00
20 Alat Pemadat ( 6 s/d 8 Ton) M2 11,000.00 - - 11,000.00
21 List Profil GRC Lebar 10 CM M1 21,900.00 - - 21,900.00
22 Penjaga Jarak Bekisting / Spacer Buah 39,300.00 - - 39,300.00
23 Jump Piller Driver + Hammer Jam - - - 750,000.00
24 Pupuk Kandang Krg 25,000.00
25 Wallpaper M2 65,000.00
26 Sunscreeen Alluminium M2 200,000.00
27 Tiang Pancang Mini Pile Uk. 20 x 20 CM K-500 M1 116,000.00 6,750.00 6,750.00 129,500.00
28 Tiang Pancang Mini Pile Uk. 25 x 25 CM K-500 M1 167,000.00 6,750.00 6,750.00 180,500.00

XVII BAHAN PASANGAN


1 Plafond Kalsiboard Tebal 3,50 MM M2 75,000.00
2 Plafond Kalsiboard Tebal 3,50 MM + Rangka Kayu Kelas II M2 165,000.00
HARGA
NO. JENIS BAHAN SATUAN MUAT BONGKAR TRANSPORT JUMLAH
TOKO/QUARRY
1 2 3 4 5 6 7 ( 4+5+6)
3 Plafond Gypsum Tebal 9 MM + Rangka Hollow M2 - - - 138,500.00
4 Plafond Gypsum Tebal 9 MM+ Rangka Metal Furing M2 - - - 110,000.00
5 Sekat Dinding Gypsum Tebal 8 MM Double (Timbal Balik) M2 - - - 210,000.00
Rangka Boral
6 Sekat Dinding Gypsum Tebal 8 MM Double (Timbal Balik) M2 - - - 200,000.00
Rangka Hollow
7 Plafond PVC + Rangka Hollow M2 - - - 330,000.00
8 Pek. Memasang Kuda - Kuda Maks. Bentangan 8 M & M2 - - - 85,000.00
Rangka Atap Baja Ringan ( Bersetifikat dan Bergaransi 10
Tahun )

9 Kuda - Kuda Maks. Bentangan 8 M & Rangka Atap Baja M2 - - - 190,000.00


Ringan Setara Taso + Atap Genteng Metal Tbl. 0,25 MM

10 Kuda - Kuda Maks. Bentangan 8 M & Rangka Atap Baja M2 - - - 180,000.00


Ringan Setara Taso + Atap Longspan Setara Spandek Tbl.
0,25 MM

11 Atap Canopy ( Polycarbonat + Rangka Hollow Stalbuis ) M2 - - - 350,000.00


12 Atap Canopy ( Longspan + Rangka Hollow Stalbuis ) M2 - - - 350,000.00
13 Partisi Kaca ( Tebal 5 MM ) + Rangka U PVC M2 - - - 1,200,000.00
14 Partisi Kaca ( Tebal 8 MM ) Frameless M2 - - - 850,000.00
15 Partisi Kaca ( Tebal 12 MM ) Frameless M2 - - - 920,000.00
16 Pintu Kaca Tempered Frameless Uk. 80 x 200 CM (Tebal 12 Unit - - - 4,950,000.00
MM) Lengkap dengan Handle, Kunci dan Engsel Pivot

17 Pintu Kaca Tempered Fitting Uk. 80 x 200 CM ( Tebal 12 MM Unit - - - 5,775,000.00


) Lengkap dengan Handle, Kunci dan Engsel Pivot

18 Pintu Kaca Polos Swing Uk. 80 x 200 CM ( Tebal 5 MM ) Unit - - - 1,485,000.00


Lengkap dengan Handle, Kunci dan Engsel
HARGA
NO. JENIS BAHAN SATUAN MUAT BONGKAR TRANSPORT JUMLAH
TOKO/QUARRY
1 2 3 4 5 6 7 ( 4+5+6)
19 Pintu Kaca Polos Sliding Uk. 80 x 200 CM ( Tebal 5 MM ) Unit - - - 1,540,000.00
Lengkap dengan Handle, Kunci dan Rel

20 Partisi Kaca ( Tebal 5 MM ) + Rangka Aluminium M2 - - - 575,000.00


21 Pagar Hollow starbuss (standard minimalis) M2 - - - 350,000.00
22 Jendela Casement Kaca Tebal 5 MM Rangka Aluminium Uk.
60 x 120 CM Lengkap dengan Kunci, Engsel dan Hak Angin M2 - - - 575,000.00

23 Jendela Sliding Kaca Tebal 5 MM Rangka Aluminium Uk. 60


x 120 CM Lengkap dengan Kunci M2 - - - 600,000.00

24 Pagar Besi BRC Tinggi 1,50 Meter M1 - - - 200,000.00

Bangkinang, 2018
KEPALA DINAS PEKERJAAN UMUM DAN
PENATAAN RUANG KAB. KAMPAR

AFDAL. ST., M.Si


Pembina TK I NIP. 19700325 199903 1 004
DAFTAR HARGA SATUAN UPAH DAN BAHAN BANGUNAN
TAHUN ANGGARAN 2018
DAERAH BAIK
DAFTAR UPAH

NO. JENIS UPAH SATUAN HARGA SATUAN KET.

1 2 3 4 5
1 Pekerja OH 67,900.00
2 Tukang Bangunan ( Batu, Kayu, Pipa, Bongkar, Cat dan Besi ) OH 83,200.00
3 Kepala Tukang OH 88,000.00
4 Mandor Bangunan OH 90,000.00

DAFTAR BAHAN BANGUNAN

NO. JENIS BAHAN SATUAN HARGA SATUAN KET.

1 2 3 4 5
I BAHAN PASANGAN
1 Pasir Urug (PU) M3 145,000.00
2 Pasir Pasang (PP) M3 145,000.00
3 Pasir Beton (PB) M3 145,000.00
4 Pasir Kuarsa M3 158,000.00
5 Kerikil (KR) M3 196,300.00
6 Sirtu M3 170,000.00
7 Batu Belah (gunung) 15cm/20 cm M3 355,000.00
8 Batu sungai (mangga) M3 300,000.00
9 Portland Cement (PC) Kg 1,360.00
10 Semen putih Kg 2,400.00
11 Cornite Compound Jayaboard Zak 73,000.00
12 Bata Merah (Ukuran Jumbo ) Buah 550.00
13 Kerawang (Roster semen)20x20 cm Buah 22,100.00
14 Kerawang (Roster semen)40x40 cm Buah 45,100.00
15 Rumput Gajah Mini M2 42,000.00
16 Rumput Biasa M2 18,000.00
17 Tanah Hitam M3 100,000.00
18 Tanah Urug Biasa M3 65,000.00
19 Conblock Segi 6 Tebal 8 CM Bh 1,900.00
20 Conblock Segi 4 Tebal 8 CM Bh 1,900.00
21 Grass Block T= 6 cm Bh 20,700.00
22 Buis Beton Dia 20cm P= 50 Cm Bh 61,000.00
23 Buis Beton Dia 40cm P = 60 Cm Bh 183,000.00
24 Buis Beton Dia 60cm P= 80 Cm Bh 310,000.00
NO. JENIS BAHAN SATUAN HARGA SATUAN KET.

1 2 3 4 5
25 Buis Beton Dia 80cm P= 100 Cm Bh 390,000.00
26 Buis Beton Dia 100cm P = 100 Cm Bh 488,000.00
27 Batu Split / Pecah M3 365,000.00
28 Bata Beton Ringan Buah 6,700.00
29 Batu Tempel Uk. 20 x 20 Buah 5,100.00
30 Batu Tempel Uk. 20 x 40 Buah 12,600.00

II BAHAN KAYU
1 Kayu Kelas I M3 6,585,000.00
2 Kayu Kelas II M3 2,085,000.00
3 Kayu Kelas III M3 1,985,000.00
4 Kayu Kelas IV M3 1,300,000.00
5 Kayu List Profil siku2" M' 2,515.00
6 Kayu List Profil 0.8x3" M' 3,015.00
7 Papan 2 x 20 M3 1,885,000.00
8 Kayu Cerocok dia. 10 - 15 cm Btg 38,500.00
9 Dolken Kayu Galam, Ø (8-10)Cm,Panjang 4 M Batang 7,000.00
10 Kayu Bakar ( Non Kelas ) M3 285,000.00
11 Papan Piri - piri (Siap Ketam 3 sisi) M3 2,285,000.00
12 Papan Lebah Bergayut M' 41,500.00
13 Singap Ukir kayu M2 763,000.00
14 Singap Ukir GRC M2 413,000.00
15 Selembayung GRC Lebar 30 cm Pasang 406,000.00
16 Selembayung kayu lebar 30 cm Pasang 256,000.00
17 Sayap layang-layang lebar 30 cm Pasang 256,000.00
18 Lisplank papan + anak ( + 30 cm) M' 56,000.00

III BAHAN BESI DAN BAJA


1 Baja Beton Polos U 24 Kg 10,300.00
2 Baja Beton Ulir U 39 Kg 20,100.00
3 Baja Beton Ulir U 32 Kg 10,500.00
4 Besi Plat rata2 Kg 11,200.00
5 Besi Tempa M2 245,100.00
6 Kawat Beton Kg 18,070.00
7 Kawat Ø 4 mm Kg 16,070.00
8 Kawat Las Listrik Kg 20,070.00
9 Kawat Ayam M2 14,020.00
10 Besi Strip Tebal 5 mm Kg 13,070.00
11 Terali besi (Non Motif) M2 252,000.00
12 Baja Profil Kg 18,220.00
13 Besi Siku Kg 16,900.00
NO. JENIS BAHAN SATUAN HARGA SATUAN KET.

1 2 3 4 5
14 Wiremesh M6 Kg 12,700.00
15 Wiremesh M8 Kg 12,700.00

IV BAHAN PAKU
1 Paku 1 Cm - 2,5 Cm Kg 15,180.00
2 Paku 5 Cm - 12 Cm Kg 15,180.00
3 Paku Skrup Kg 40,180.00
4 Paku Skrup 5 Cm Kg 40,180.00
5 Paku Skrup 10 Cm Kg 40,180.00
6 Paku Asbes Kg 20,180.00
7 Paku Atap Genteng Metal Kg 24,180.00
8 Paku Atap Seng Gelombang Kg 20,180.00
9 Skrup Fixer Buah 350.00

V BAHAN ALLUMUNIUM
1 Profil Allumunium "T" M' 24,375.00
2 Kusen Alumunium 3'' M' 195,000.00
3 Rangka Jendela Almunium M' 195,000.00
4 Rangka Pintu Almunium M' 195,000.00

VI BAHAN LANTAI
1 Homogenius Ukuran ( 60 x 60 ) Cm Buah 60,000.00
2 Homogenius Ukuran ( 40 x 40 ) cm Buah 31,900.00
3 Homogenius Ukuran ( 30 x 30 ) cm Buah 15,700.00
4 Keramik (40x40) Cm Buah 9,050.00
5 Keramik (30x30) Cm Buah 4,550.00
6 Keramik (20x20) Cm Buah 2,250.00
7 Keramik (20x25) Cm Buah 2,850.00
8 Granit Warna (60x60) Cm Buah 85,200.00
9 Keramik Warna (40x40) Cm Buah 9,600.00
10 Keramik Warna (30x30) Cm Buah 5,050.00
11 Keramik Warna (20x20) Cm Buah 2,450.00
12 Plint Keramik (10x20) Cm Buah 1,500.00
13 Plint Keramik (10x30) Cm Buah 2,350.00
14 Plint Keramik (10x40) Cm Buah 3,250.00
15 Plint Homogenius (10x60) Cm Buah 12,050.00
16 Plint Homogenius (10x40) Cm Buah 11,150.00
17 Plint Keramik Warna (10x20) Cm Buah 1,400.00
18 Plint Keramik Warna (10x30) Cm Buah 2,400.00
19 Plint Keramik Warna (10x40) Cm Buah 3,250.00
20 Plint Granit Warna (10x60) Cm Buah 13,350.00
21 Bon-bon Keramik M' 7,750.00
NO. JENIS BAHAN SATUAN HARGA SATUAN KET.

1 2 3 4 5
22 Floor hardener M2 35,000.00
23 Parquette M2 225,200.00
24 Karpet M2 16,650.00

VII BAHAN ATAP


1 Asbes Gelombang Lbr 34,300.00
2 Genteng Metal gelombang Tebal 0,30 MM Lbr 40,300.00
3 Genteng Metal alur lurus Tebal 0,30 MM Lbr 40,300.00
4 Perabung genteng metal Lbr 25,300.00
5 Seng Gelombang BJLS 020 K Lbr 42,300.00
6 Seng Gelombang Alumunium 0,25 Lbr 71,300.00
7 Seng Plat BJLS 20 Lbr 59,300.00
8 Atap Multi Sirap Lbr 5,300.00
9 EDF M2 250,300.00
10 Genteng Beton warna BH 21,800.00
11 Bubungan beton warna BH 28,300.00
12 Allumunium Foil / Sisalation M2 13,300.00
13 Formika M2 41,500.00
14 Spandek Tebal 0,30 MM M2 40,300.00
15 Genteng Keramik Bh 7,100.00
16 Genteng Keramik Glazur Bh 10,600.00
17 Nok Genteng Keramik Bh 4,500.00
18 Nok Genteng Keramik Glazur Bh 6,500.00
19 Nok Genteng Metal ( Panjang 90 CM ) Bh 36,200.00
20 Terpal Khusus untuk Atap ( Lebar 50 CM ) M1 20,000.00

VIII BAJA RINGAN


1 Baja Ringan C75. 100INT M' 25,300.00
2 Baja Ringan C75. 75INT M' 12,300.00
3 Topspan 40,055 INT M' 31,300.00
4 Wteks 12-14x20 HWFS Kls II Pc 950.00
5 CSP 10-16X16 HWFS Kls II Pc 950.00
6 SG10 Multiplate Pc 8,300.00
7 Reng Baja Ringan M' 6,800.00

IX BAHAN LANGIT-LANGIT
1 Teakwood Tebal 3,6 mm Lembar 151,500.00
2 Triplek Tebal 12 MM Lembar 203,500.00
3 Triplek Tebal 9,0 MM Lembar 146,500.00
4 Triplek Tebal 3,6 MM Lembar 66,500.00
5 Triplek Tebal 3,0 MM Lembar 58,700.00
6 Gypsum Board 9 mm Lembar 86,500.00
NO. JENIS BAHAN SATUAN HARGA SATUAN KET.

1 2 3 4 5
7 List Gypsum lbr 15-20cm M' 19,100.00
8 Asbes Semen M2 51,500.00
9 Triplek melamin Lembar 76,500.00

X BAHAN PIPA DAN SANITAIR


1 Pipa PVC Type AW Ø 1/2" M' 4,150.00
2 Pipa PVC Type AW Ø 3/4" M' 6,500.00
3 Pipa PVC Type AW Ø 1" M' 9,200.00
4 Pipa PVC Type AW Ø 2" M' 15,250.00
5 Pipa PVC Type AW Ø 2,50 " M' 17,750.00
6 Pipa PVC Type AW Ø 3" M' 30,250.00
7 Pipa PVC Type AW Ø 4" M' 40,250.00
8 Pipa PVC Type AW Ø 6" M' 110,250.00
9 Pipa Abu-abu 4" M' 15,250.00
10 Pipa Galvanis dia 1" M' 60,250.00
11 Pipa Galvanis dia 1,5" M' 90,250.00
12 Pipa Galvanis dia 2" M' 123,250.00
13 Pipa Besi dia 1" M' 39,250.00
14 Pipa Besi dia 1,5" M' 21,250.00
15 Pipa Besi dia 3/4" M' 31,250.00
16 Stop kran 3/4" Bh 52,250.00
17 Kran Air Ø 1/2" atau 3/4" plastik Bh 10,250.00
18 Kran Air Ø 1/2" atau 3/4" stainless Bh 100,250.00
19 Bak Fiberglass Kap. Kecil Bh 245,000.00
20 Bak Fiberglass Kap. Besar Bh 325,000.00
21 Kloset Duduk Monoblok Bh 1,775,000.00
22 Kloset Jongkok Porselen Bh 275,000.00
23 Urinoir Bh 1,325,000.00
24 Wastafel kecil standard dinding Bh 475,000.00
25 Seal Tape Bh 5,225.00
26 Floor Drain stainless Bh 160,250.00
27 Floor Drain plastik Bh 15,250.00
28 Tangki Plastik 250 Liter Unit 525,000.00
29 Tangki Plastik 500 Liter Unit 625,000.00
30 Tangki Plastik 1000 Liter Unit 1,375,000.00
31 Tangki Stainless 500 Liter + Kaki Unit 1,625,000.00
32 Tangki Stainless 1100 Liter + Kaki Unit 3,225,000.00
33 Pipa Baja Kg 17,600.00

XI BAHAN PINTU
1 Pintu Besi M2 685,000.00
NO. JENIS BAHAN SATUAN HARGA SATUAN KET.

1 2 3 4 5
2 Pintu Fiber Warna Lbr 779,000.00
3 Pintu Fiber KM/WC (lengkap) Lbr 325,000.00
4 Pintu Panel kelas I Lbr 875,000.00
5 Pintu Panel Kelas II Lbr 725,000.00
6 Pintu Plywood (triplek depan blkg) Lbr 215,000.00
7 Pintu Teakwood (lapis jati) depan belakang Lbr 645,000.00
8 Vertical Blind M2 97,650.00
9 Rolling Door M2 515,000.00
10 Folding Gate M2 665,000.00
11 Pintu Aluminium Kaca Lbr 2,115,000.00

XII BAHAN PENGGANTUNG / KUNCI


1 Kunci Tanam Antik kuningan (standard) Bh 200,200.00
2 Kunci Tanam Biasa (minimalis) Bh 130,200.00
3 Kunci Tanam Kamar Mandi Bh 50,200.00
4 Kunci Silinder Bh 50,200.00
5 Engsel Pintu 4" Bh 7,700.00
6 Engsel Jendela 3" Bh 5,200.00
7 Grendel pintu 6" (krom) Bh 20,200.00
8 Grendel Pintu 4"(krom) Bh 11,200.00
9 Grendel Jendela 2" (krom) Bh 8,700.00
10 Kait Angin / Hak Angin Bh 6,700.00
11 Tarikan Tangan ( Jendela / Ventilasi ) Bh 7,700.00
12 Door Closer Bh 390,200.00
13 Door Stoper Plastik Bh 20,200.00
14 Selinder Bh 7,700.00
15 Handle Jendela Bh 7,700.00

XIII BAHAN KACA


1 Kaca 3 mm M2 82,300.00
2 Kaca 5 mm M2 92,800.00
3 Kaca polos 8 mm M2 362,000.00
4 Kaca polos 12 mm M2 506,000.00
5 Kaca es/buram 3 mm M2 94,200.00
6 Kaca es/buram 5 mm M2 116,800.00
7 Kaca patry M2 185,800.00
8 Kaca Rayben 3 mm M2 97,800.00
9 Kaca Rayben 5 mm M2 125,800.00
10 Jendela Nako (rangka + Kaca 5 mm) M2 94,800.00
11 Glass Block Ukuran standard BH 25,800.00

XIV BAHAN LISTRIK


NO. JENIS BAHAN SATUAN HARGA SATUAN KET.

1 2 3 4 5
1 Pemasangan Titik Lampu (termasuk kabel,teedus, fitting) Ttk 180,000.00
2 Lampu Pijar 25 Watt Buah 6,605.00
3 Lampu Pijar 40 Watt Buah 8,305.00
4 Lampu Neon Jantung Buah 75,105.00
5 Lampu Save Energy (Lilin) Setara Philips Buah 50,105.00
6 Lampu TL Komplit 1 x 20 watt Buah 74,250.00
7 Lampu TL Komplit 2 x 20 Watt Buah 310,250.00
8 Lampu TL Komplit 1 x 40 Watt Buah 100,250.00
9 Lampu Down Light 4" komplit Buah 94,150.00
10 Lampu Baret Buah 188,150.00
11 Stop Kontak (setara broco) Buah 14,650.00
12 Saklar Tunggal (setara broco) Buah 14,650.00
13 Saklar Ganda (setara broco) Buah 21,750.00
14 Saklar Triple (setara broco) Buah 27,150.00
15 Zakering Khas (setara merlin gerlin) Buah 50,150.00

XV BAHAN CAT
1 Cat Tembok Standar Kg 22,300.00
2 Cat Tembok Akrilik Kg 27,800.00
3 Cat Tembok Weather Shield Kg 75,300.00
4 Cat Kayu dan Besi ( Cat Minyak ) Kg 58,300.00
5 Cat Dasar / Kapur Kg 8,300.00
6 Cat Dasar / Menie Kayu Kg 30,300.00
7 Cat Vernish Kg 56,300.00
8 Cat Impra Kg 41,800.00
9 Cat Residu Kg 35,650.00
10 Soda Api Kg 11,900.00
11 Plamir setara RJ Kg 27,500.00
12 Dempul Kayu Kg 38,700.00
13 Kertas Amplas Lbr 6,175.00
14 Kuas 3" Bh 17,375.00
15 Kuas Golong/rol Bh 26,425.00
16 Thinner Ltr 36,700.00
17 Flincote / Menie Besi Kg 16,800.00

XVI BAHAN LAIN-LAIN


1 Mesin las Jam 98,000.00
2 Concrete Pump Hari 3,500,000.00
3 Air Liter 50.00
4 Lem Kg 2,850.00
5 Sabun Kg 31,000.00
6 Kapur Sirih Kg 4,700.00
NO. JENIS BAHAN SATUAN HARGA SATUAN KET.

1 2 3 4 5
7 Alang - alang Ikat 20,600.00
8 Lem Kayu Kg 25,650.00
9 Sealant Kg 12,350.00
10 Profil Kaca M' 1,912.50
11 Solar Liter 8,700.00
12 Minyak Pelumas Liter 24,540.65
13 Minyak Bekisting Liter 4,877.50
14 Aspal Drum Kg 14,475.00
15 Tempat Masak Aspal BH 49,392.50
16 Ijuk Kg 15,300.00
17 Water proofing Coating Kg 30,300.00
18 Water proofing Membran M2 96,500.00
19 Batu Coral sikat ZAK 51,500.00
20 Alat Pemadat ( 6 s/d 8 Ton) M2 11,000.00
21 List Profil GRC Lebar 10 CM M1 21,900.00
22 Penjaga Jarak Bekisting / Spacer Buah 39,300.00
23 Jump Piller Driver + Hammer Jam 750,000.00
24 Pupuk Kandang Krg 25,000.00
25 Wallpaper M2 65,000.00
26 Sunscreeen Alluminium M2 200,000.00
27 Tiang Pancang Mini Pile Uk. 20 x 20 CM K-500 M1 129,500.00
28 Tiang Pancang Mini Pile Uk. 25 x 25 CM K-500 M1 180,500.00

XVII BAHAN PASANGAN


1 Plafond Kalsiboard Tebal 3,50 MM M2 75,000.00
2 Plafond Kalsiboard Tebal 3,50 MM + Rangka Kayu Kelas II M2 165,000.00
3 Plafond Gypsum Tebal 9 MM + Rangka Hollow M2 138,500.00
4 Plafond Gypsum Tebal 9 MM+ Rangka Metal Furing M2 110,000.00
5 Sekat Dinding Gypsum Tebal 8 MM Double (Timbal Balik) M2 210,000.00
Rangka Boral
6 Sekat Dinding Gypsum Tebal 8 MM Double (Timbal Balik) M2 200,000.00
Rangka Hollow
7 Plafond PVC + Rangka Hollow M2 330,000.00
Pek. Memasang Kuda - Kuda Maks. Bentangan 8 M & Rangka
Atap Baja Ringan ( Bersetifikat dan Bergaransi 10 Tahun )
8 M2 85,000.00

Kuda - Kuda Maks. Bentangan 8 M & Rangka Atap Baja Ringan


Setara Taso + Atap Genteng Metal Tbl. 0,25 MM
9 M2 190,000.00
NO. JENIS BAHAN SATUAN HARGA SATUAN KET.

1 2 3 4 5
Kuda - Kuda Maks. Bentangan 8 M & Rangka Atap Baja Ringan
Setara Taso + Atap Longspan Setara Spandek Tbl. 0,25 MM
10 M2 180,000.00

11 Atap Canopy ( Polycarbonat + Rangka Hollow Stalbuis ) M2 350,000.00


12 Atap Canopy ( Longspan + Rangka Hollow Stalbuis ) M2 350,000.00
13 Partisi Kaca ( Tebal 5 MM ) + Rangka U PVC M2 1,200,000.00
14 Partisi Kaca ( Tebal 8 MM ) Frameless M2 850,000.00
15 Partisi Kaca ( Tebal 12 MM ) Frameless M2 920,000.00
16 Pintu Kaca Tempered Frameless Uk. 80 x 200 CM (Tebal 12 MM) Unit 4,950,000.00
Lengkap dengan Handle, Kunci dan Engsel Pivot
17 Pintu Kaca Tempered Fitting Uk. 80 x 200 CM ( Tebal 12 MM ) Unit 5,775,000.00
Lengkap dengan Handle, Kunci dan Engsel Pivot
18 Pintu Kaca Polos Swing Uk. 80 x 200 CM ( Tebal 5 MM ) Lengkap Unit 1,485,000.00
dengan Handle, Kunci dan Engsel
19 Pintu Kaca Polos Sliding Uk. 80 x 200 CM ( Tebal 5 MM ) Lengkap Unit 1,540,000.00
dengan Handle, Kunci dan Rel
20 Partisi Kaca ( Tebal 5 MM ) + Rangka Aluminium M2 575,000.00
21 Pagar Hollow starbuss (standard minimalis) M2 350,000.00
22 Jendela Casement Kaca Tebal 5 MM Rangka Aluminium Uk. 60 x M2 575,000.00
120 CM Lengkap dengan Kunci, Engsel dan Hak Angin

23 Jendela Sliding Kaca Tebal 5 MM Rangka Aluminium Uk. 60 x 120 M2 600,000.00


CM Lengkap dengan Kunci

24 Pagar Besi BRC Tinggi 1,50 Meter M1 200,000.00


Tabel Diameter - Berat Besi Beton
Tabel Diameter - Berat Besi Beton Ulir
Polos
Diamete Panjang Berat/M Berat/Ba Diamete Panjang Berat/M Berat/Ba
r (mm) (m) eter(kg) tang(kg) r (mm) (m) eter (kg) tang (kg)

4 12 0.09 1 10 12 0.62 7.4

6 12 0.22 2.66 13 12 1.04 12.5


8 12 0.39 4.74 19 12 2.23 26.8
9 12 0.5 6 22 12 2.98 35.8
10 12 0.62 7.4 25 12 3.85 46.2
11 12 0.75 9 29 12 5.04 60.5
12 12 0.89 10.7 32 12 6.31 75.77
13 12 1.04 12.5 35 12 7.51 90.1
15 12 1.21 14.5 38 12 8.92 107
16 12 1.58 19 41 12 10.5 126
19 12 2.22 26.8
22 12 2.98 35.8
23 12 3.26 39.1
24 12 3.55 42.62
25 12 3.85 46.2
28 12 4.83 58
31 12 5.93 71.1
32 12 6.31 75.72
Pipa Hitam (SGP)

O.D SIZE TEBAL BERAT


Jenis ProdukTebalPanjang / BatangHarga / Batan
Kg/ Kg/6
inch mm mm
meter meter (Rp.)Pipa Besi Medium Hitam
 21/2 = 46.4 2.8  5,08  30,48
 21/2 = 46.4  3,2  5,77  34,62
 3 = 89.1  3,2  6,78  40,68 Pipa Medium Hitam 1/2"2,60 mm6 m155.000,-P
 4 = 114.3  3,5  9,56  57,36 1115000/ 6m = 185833,3
 4 = 114.3  4,5  12,2  73.20 12.2
 5 = 139.8  4,5  15  90 185833.3
 5 = 139.8  6  19,8  118,8 15232.24
 6 = 165.2  4,5  17,8  106,8 15232.24
 6 = 165.2  5  19,8  118,8
 6 = 165.2  6  23,6  141,6
 7 = 190.7  5,3  24,2  145,2
 8 = 216.3  5,8  30,1  180,6
 8 = 216.3  8,2  42,1  252,6
 10 = 267.4  6,6  42,4  254,4
 12 = 318.5  6,9  53  318
 14 = 355.6  7,9  67,70  406,2
njang / BatangHarga / Batang

/2"2,60 mm6 m155.000,-Pipa Medium Hitam 3/4"2,60 mm6 m185.000,-Pipa Medium Hitam 1"3,20 mm6 m250.000,-Pipa Medium Hit

3.8 8615233 46.36


6 13603000
mm6 m250.000,-Pipa Medium Hitam 1 1/4"3,20 mm6 m315.000,-Pipa Medium Hitam 1 1/2"3,20 mm6 m350.000,-Pipa Medium Hitam
m6 m350.000,-Pipa Medium Hitam 2"3,60 mm6 m465.000,-Pipa Medium Hitam 2 1/2"3,60 mm6 m595.000,-Pipa Medium Hitam 3"4,0
95.000,-Pipa Medium Hitam 3"4,00 mm6 m765.000,-Pipa Medium Hitam 4"4,50 mm6 m1.115.000,-Pipa Medium Hitam 6"4,85 mm6 m
Pipa Medium Hitam 6"4,85 mm6 m1.780.000,-Pipa Medium Hitam 8"5,00 mm6 m2.800.000,-
X. PEKERJAAN ATAP

1 Pemasangan 1 m2 Atap Genteng Metal

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)


A TENAGA
Pekerja L.01 OH 0.200 Rp 67,900.00 Rp 13,580.00
Tukang Kayu L.02 OH 0.100 Rp 83,200.00 Rp 8,320.00
Kepala Tukang L.03 OH 0.010 Rp 88,000.00 Rp 880.00
Mandor L.04 OH 0.001 Rp 90,000.00 Rp 90.00
JUMLAH TENAGA KERJA Rp 22,870.00
B BAHAN
Genteng Metal Bh 1.620 Rp 40,300.00 Rp 65,286.00
Paku Skrup Kg 0.200 Rp 40,180.00 Rp 8,036.00
JUMLAH HARGA BAHAN Rp 73,322.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 96,192.00
E Overhead & Proft ( 10 % ) 10% x D Rp 9,619.20
F Harga Satuan Pekerjaan (D+E) Rp 105,811.20

2 Pemasangan 1 m nok genteng metal

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)


A TENAGA
Pekerja L.01 OH 0.250 Rp 67,900.00 Rp 16,975.00
Tukang Kayu L.02 OH 0.150 Rp 83,200.00 Rp 12,480.00
Kepala Tukang L.03 OH 0.015 Rp 88,000.00 Rp 1,320.00
Mandor L.04 OH 0.013 Rp 90,000.00 Rp 1,170.00
JUMLAH TENAGA KERJA Rp 31,945.00
B BAHAN
Nok genteng metal Bh 1.200 Rp 36,200.00 Rp 43,440.00
paku biasa 1/2"-1" Kg 0.050 Rp 15,180.00 Rp 759.00
JUMLAH HARGA BAHAN Rp 44,199.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 76,144.00
E Overhead & Proft ( 10 % ) 10% x D Rp 7,614.40
F Harga Satuan Pekerjaan (D+E) Rp 83,758.40

3 Pemasangan 1 m2 atap seng gelombang

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)

A TENAGA
Pekerja L.01 OH 0.120 Rp 67,900.00 Rp 8,148.00
Tukang Kayu L.02 OH 0.060 Rp 83,200.00 Rp 4,992.00
Kepala Tukang L.03 OH 0.006 Rp 88,000.00 Rp 528.00
Mandor L.04 OH 0.006 Rp 90,000.00 Rp 540.00
JUMLAH TENAGA KERJA Rp 14,208.00
B BAHAN
Seng gelombang Lembar 0.700 Rp 42,300.00 Rp 29,610.00
paku biasa 1/2"-1" Kg 0.020 Rp 15,180.00 Rp 303.60
JUMLAH HARGA BAHAN Rp 29,913.60
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 44,121.60
E Overhead & Proft ( 10 % ) 10% x D Rp 4,412.16
F Harga Satuan Pekerjaan (D+E) Rp 48,533.76

4 Pemasangan 1 m2 nok atap seng

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)

A TENAGA
Pekerja L.01 OH 0.150 Rp 67,900.00 Rp 10,185.00
Tukang Kayu L.02 OH 0.070 Rp 83,200.00 Rp 5,824.00
Kepala Tukang L.03 OH 0.007 Rp 88,000.00 Rp 616.00
Mandor L.04 OH 0.007 Rp 90,000.00 Rp 630.00
JUMLAH TENAGA KERJA Rp 17,255.00
B BAHAN
Seng plat Lembar 0.300 Rp 59,300.00 Rp 17,790.00
paku biasa 1/2"-1" Kg 0.040 Rp 15,180.00 Rp 607.20
JUMLAH HARGA BAHAN Rp 18,397.20
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 35,652.20
E Overhead & Proft ( 10 % ) 10% x D Rp 3,565.22
F Harga Satuan Pekerjaan (D+E) Rp 39,217.42

5 Pemasangan 1 m2 lapisan Aluminium Foil

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)

A TENAGA
Pekerja L.01 OH 0.150 Rp 67,900.00 Rp 10,185.00
Tukang Kayu L.02 OH 0.050 Rp 83,200.00 Rp 4,160.00
Kepala Tukang L.03 OH 0.005 Rp 88,000.00 Rp 440.00
Mandor L.04 OH 0.008 Rp 90,000.00 Rp 720.00
JUMLAH TENAGA KERJA Rp 15,505.00
B BAHAN
Aluminium foil M2 1.050 13,300.00 Rp 13,965.00
JUMLAH HARGA BAHAN Rp 13,965.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 29,470.00
E Overhead & Proft ( 10 % ) 10% x D Rp 2,947.00
F Harga Satuan Pekerjaan (D+E) Rp 32,417.00

6 Pemasangan 1 M' Terpal Pelapis Perabung Atap

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)

A TENAGA
Pekerja L.01 OH 0.250 Rp 67,900.00 Rp 16,975.00
Tukang Kayu L.02 OH 0.150 Rp 83,200.00 Rp 12,480.00
Kepala Tukang L.03 OH 0.015 Rp 88,000.00 Rp 1,320.00
Mandor L.04 OH 0.013 Rp 90,000.00 Rp 1,170.00
JUMLAH TENAGA KERJA Rp 31,945.00
B BAHAN
Terpal Lebar 50 CM M1 1.200 Rp 20,000.00 Rp 24,000.00
paku biasa 1/2"-1" Kg 0.050 Rp 17,000.00 Rp 850.00
JUMLAH HARGA BAHAN Rp 24,850.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 56,795.00
E Overhead & Profit ( 10 % ) 10% x D Rp 5,679.50
F Harga Satuan Pekerjaan (D+E) Rp 62,474.50

7 Pemasangan 1 KG Rangka Kuda - Kuda Baja IWF

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)

A TENAGA
Pekerja L.01 OH 0.060 Rp 67,900.00 Rp 4,074.00
Tukang Las Kontruksi L.03 OH 0.060 Rp 83,200.00 Rp 4,992.00
Kepala Tukang L.03 OH 0.006 Rp 88,000.00 Rp 528.00
Mandor L.04 OH 0.003 Rp 90,000.00 Rp 270.00
JUMLAH TENAGA KERJA Rp 9,864.00
B BAHAN
Besi Baja IWF KG 1.150 Rp 18,220.00 Rp 20,953.00
JUMLAH HARGA BAHAN Rp 20,953.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 30,817.00
E Overhead & Profit ( 10 % ) 10% x D Rp 3,081.70
F Harga Satuan Pekerjaan (D+E) Rp 33,898.70
REKAPITULASI ANALISA PEKERJA

NO. KELOMPOK PEKERJAAN JENIS PEKERJAAN

1 2 3

I. PEKERJAAN PERSIAPAN 1
2
3
4
5
6

II. PEKERJAAN TANAH 1


2
3
4
5
6
7
8
9
10
11

III. PEKERJAAN PONDASI 1


2
3
NO. KELOMPOK PEKERJAAN JENIS PEKERJAAN

1 2 3
4
5
6
7
8

IV. PEKERJAAN BETON 1


2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
NO. KELOMPOK PEKERJAAN JENIS PEKERJAAN

1 2 3
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40

V. PEKERJAAN BESI DAN ALUMINIUM 1


2
3
4
5
6
7
NO. KELOMPOK PEKERJAAN JENIS PEKERJAAN

1 2 3

VI. PEKERJAAN PASANGAN DINDING 1


2
3
4
5
6
7
8
9
10

VII. PEKERJAAN PLESTERAN 1


2
3
4
5
6
7
8
9
10
11
12
13
NO. KELOMPOK PEKERJAAN JENIS PEKERJAAN

1 2 3
14
15
16
17

VIII. PEKERJAAN PENUTUP LANTAI & 1


PENUTUP DINDING
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
NO. KELOMPOK PEKERJAAN JENIS PEKERJAAN

1 2 3
22

IX. PEKERJAAN PLAFOND 1


2
3
4
5

X. PEKERJAAN ATAP 1
2
3
4
5
6
7

XI. HARGA SATUAN PEKERJAAN KAYU 1


2
3
4
5
6
7
8
9
NO. KELOMPOK PEKERJAAN JENIS PEKERJAAN

1 2 3
10
11
12
13
14
15
16
17

XII. PEKERJAAN KUNCI DAN KACA 1


2
3
4
5
6
7
8
9
10
11
12
13
14
15

XIII. PEKERJAAN PENGECATAN 1


NO. KELOMPOK PEKERJAAN JENIS PEKERJAAN

1 2 3
2
3
4
5
6
7
8
9
10

XIV. PEKERJAAN SANITASI DALAM GE 1


2
3
4
5
6
7
8
9
10
11

XV. PEKERJAAN LAIN - LAIN 1


2
3
4
NO. KELOMPOK PEKERJAAN JENIS PEKERJAAN

1 2 3
5
6
REKAPITULASI ANALISA PEKERJAAN

JENIS PEKERJAAN HARGA

3 4

Pembuatan 1 m' pagar sementara dari kayu tinggi 2 meter Rp 253,761.75


Pembuatan 1m2 pagar sementara dari seng gelombang tinggi 2 meter Rp 301,853.75
Pengukuran dan pemasangan 1 M' bouwplank Rp 59,904.46
Pembersihan 1 M2 Lapangan dan Perataan Rp 12,419.00
Pembongkaran 1 M3 beton bertulang Rp 1,061,850.46
Pembongkaran 1 M3 dinding tembok bata Rp 530,925.23

Penggalian 1 M3 tanah biasa sedalam 1 M' Rp 58,492.50


Penggalian 1 M3 tanah biasa sedalam 2 M' Rp 71,676.00
Menggali 1 M3 tanah keras sedalam 1 M3 Rp 77,858.00
Menggali 1 M3 tanah cadas sedalam 1 M3 Rp 117,975.00
Menggali 1 M3 tanah lumpur sedalam 1 M3 Rp 94,083.00
Pembuangan 1 M3 tanah sejauh 30 meter Rp 25,637.70
Pengurugan kembali 1 M3 galian tanah Rp 42,295.00
Pemadatan tanah 1 M3 tanah ( per 20 cm ) Rp 42,295.00
Pengurugan 1 M3 dengan pasir urug Rp 214,797.00
Pemasangan 1 M2 Lapisan Ijuk Tebal 10 CM untuk Bidang Resapan Rp 113,668.50
Mengurug 1 M3 Tanah Urug Rp 109,197.00

Pemasangan 1 M3 pondasi batu belah campuran 1 SP : 3 PP Rp 1,043,509.50


Pemasangan 1 M3 pondasi batu belah campuran 1 SP : 4 PP Rp 990,748.00
Pemasangan 1 M3 pondasi batu belah campuran 1 SP : 5 PP Rp 954,184.00
JENIS PEKERJAAN HARGA

3 4
Pemasangan 1 M2 pondasi batu bata merah camp. 1 SP : 2 Psr Rp 230,560.00
Pemasangan 1 M2 pondasi batu bata merah camp. 1 SP : 4 Psr Rp 207,276.30
Pemasangan 1 M3 pondasi sumuran diameter 100 cm Rp 888,765.24
1 M' Pekerjaan Pemancangan Tiang Pancang Mini Pile Beton Rp 63,132.17
1 Unit Pekerjaan Pemotongan Tiang Pancang Beton Rp 59,730.00

Membuat 1 M3 beton mutu f'c = 7,4 Mpa ( K 100 ), slump ( 12 ± 2 ) cm, w/c = 0,87 Rp 759,515.98
Membuat 1 M3 beton mutu f'c = 9,8 Mpa ( K 125 ), slump ( 12 ± 2 ) cm, w/c = 0,78 Rp 840,119.33
Membuat 1 M3 beton mutu f'c = 12,2 Mpa ( K 150 ), slump ( 12 ± 2 ) cm, w/c = 0,72 Rp 872,087.12
Membuat 1 M3 lantai kerja beton mutu f'c = 7,4 Mpa ( K 100 ), slump ( 3 - 6 ) cm, w/c = 0, Rp 737,558.01
Membuat 1 M3 beton mutu f'c = 14,5 Mpa ( K 175 ), slump ( 12 ± 2 ) cm, w/c = 0,66 Rp 909,979.27
Membuat 1 M3 beton mutu f'c = 16,9 Mpa ( K 200 ), slump ( 12 ± 2 ) cm, w/c = 0,61 Rp 945,787.28
Membuat 1 M3 beton mutu f'c = 19,3 Mpa ( K 225 ), slump ( 12 ± 2 ) cm, w/c = 0,58 Rp 973,042.79
Membuat 1 M3 beton mutu f'c = 21,7 Mpa ( K 250 ), slump ( 12 ± 2 ) cm, w/c = 0,56 Rp 990,511.64
Membuat 1 M3 beton mutu f'c = 24 Mpa ( K 275 ), slump ( 12 ± 2 ) cm, w/c = 0,53 Rp 1,020,568.84
Membuat 1 M3 beton mutu f'c = 26,4 Mpa ( K 300 ), slump ( 12 ± 2 ) cm, w/c = 0,52 Rp 1,029,835.34
Membuat 1 M3 beton mutu f'c = 28,8 Mpa ( K 325 ), slump ( 12 ± 2 ) cm, w/c = 0,49 Rp 1,108,432.99
Membuat 1 M3 beton mutu f'c = 31,2 Mpa ( K 350 ), slump ( 12 ± 2 ) cm, w/c = 0,48 Rp 1,120,475.56
Pembesian 10 Kg dengan besi polos Rp 134,654.85
Pembesian 10 Kg dengan besi ulir Rp 247,844.85
Pemasangan 1 M2 bekisting untuk pondasi Rp 160,610.73
Pemasangan 1 M2 bekisting untuk sloof Rp 171,528.23
Pemasangan 1 M2 bekisting untuk kolom Rp 287,255.65
Pemasangan 1 M2 bekisting untuk Balok Rp 294,136.15
Pemasangan 1 M2 bekisting untuk lantai Rp 318,055.65
Pemasangan 1 M2 bekisting untuk dinding Rp 457,508.15
Pemasangan 1 M2 bekisting untuk Tangga Rp 265,152.39
JENIS PEKERJAAN HARGA

3 4
Pemasangan 1 M2 jembatan Rangka Kayu untuk pengecoran beton Rp 88,568.70
Pemasangan 1 M3 pondasi beton bertulang Camp. 1 PC : 2 Psr : 3 Krk ( 150 Kg besi + bekis Rp 3,744,474.25
Pemasangan 1 M3 pondasi beton Camp. 1 PC : 2 Psr : 3 Krk ( termasuk bekisting ) Rp 1,915,276.00
Membuat 1 M3 sloof beton bertulang Camp. 1 PC : 2 Psr : 3 Krk ( 200 Kg besi + bekisting Rp 4,606,129.55
Membuat 1 M3 sloof beton bertulang Camp. 1 PC : 2 Psr : 3 Krk ( 150 Kg besi + bekisting Rp 3,996,396.80
Membuat 1 M3 kolom beton bertulang Camp. 1 PC : 2 Psr : 3 Krk ( 200 Kg besi + bekisting Rp 6,214,298.20
Membuat 1 M3 kolom beton bertulang Camp. 1 PC : 2 Psr : 3 Krk ( 150 Kg besi + bekisting Rp 5,574,749.95
Membuat 1 M3 balok beton bertulang Camp. 1 PC : 2 Psr : 3 Krk ( 200 Kg besi + bekisting Rp 5,701,170.20
Membuat 1 M3 balok beton bertulang Camp. 1 PC : 2 Psr : 3 Krk ( 150 Kg besi + bekisting Rp 5,091,437.45
Membuat 1 M3 pelat beton bertulang Camp. 1 PC : 2 Psr : 3 Krk ( 150 kg besi + bekisting ) Rp 5,014,449.55
Membuat 1 M3 dinding beton bertulang Camp. 1 PC : 2 Psr : 3 Krk ( 150 kg besi + bekistin Rp 4,869,619.15
Membuat 1 M3 dinding beton bertulang Camp. 1 PC : 2 Psr : 3 Krk ( 200 kg besi + bekistin Rp 5,333,869.20
Membuat 1 M' kolom praktis beton bertulang Camp. 1 PC : 2 Psr : 3 Krk ( 11 cm x 11 cm ) Rp 84,808.08
Membuat 1 M' ring balok beton bertulang Camp. 1 PC : 2 Psr : 3 Krk ( 10 cm x 15 cm ) Rp 103,313.05
Membuat 1 M3 Jalan Beton Mutu K.175 Rp 1,355,704.46
Membuat 1 M3 Dinding dan Lantai Drainase Beton Bertulang Mutu K-175 ( 60 Kg Besi ) Rp 2,647,610.90
Membuat 1 M3 Skor Drainase ( 160 Kg Besi + Bekisting ) Mutu K-175 Rp 4,350,409.36
Membuat Beton Camp. 1 PC : 3 Psr : 5 Krk Rp 753,385.60
Membuat Beton Camp. 1 PC : 2 Psr : 3 Krk Rp 1,047,489.30

Pengerjaan 10 cm pengelasan dengan las listrik Rp 36,317.19


Pemasangan 1 M2 Pintu Rolling Door Besi Rp 778,162.00
Pemasangan 1 M2 Pintu Lipat Besi ( Folding Gate ) Rp 811,069.60
Pemasangan 1 M2 Terali Besi Strip ( 2 x 3 ) mm Rp 498,941.67
Pemasangan 1 M2 Jendela Nako & Tralis Rp 417,604.00
Pemasangan 1 M Kusen Pintu Aluminium Rp 38,850.02
Pemasangan 1 M2 Venetions Blind dan Vertical Blinds Rp 170,758.50
JENIS PEKERJAAN HARGA

3 4

Pemasangan 1 M2 dinding bata merah 1 batu camp. 1PC:2PP Rp 230,560.00


Pemasangan 1 M2 dinding bata merah 1 batu camp. 1PC:3PP Rp 216,531.70
Pemasangan 1 M2 dinding bata merah 1 batu camp. 1PC:4PP Rp 207,276.30
Pemasangan 1 M2 dinding bata merah 1 batu camp. 1PC:5PP Rp 202,204.20
Pemasangan 1 M2 dinding bata merah 1 batu camp. 1PC:6PP Rp 199,859.00
Pemasangan 1 M2 dinding bata merah 1/2 batu camp. 1PC:2PP Rp 110,772.20
Pemasangan 1 M2 dinding bata merah 1/2 batu camp. 1PC:3PP Rp 104,239.52
Pemasangan 1 M2 dinding bata merah 1/2 batu camp. 1PC:4PP Rp 100,424.50
Pemasangan 1 M2 dinding bata merah 1/2 batu camp. 1PC:5PP Rp 98,020.78
Pemasangan 1 M2 dinding bata merah 1/2 batu camp. 1PC:6PP Rp 96,624.22

Pemasangan 1 M2 Plesteran 1 PC : 1 PP Tebal 15 mm Rp 64,817.98


Pemasangan 1 M2 Plesteran 1 PC : 2 PP Tebal 15 mm Rp 57,557.10
Pemasangan 1 M2 Plesteran 1 PC : 3 PP Tebal 15 mm Rp 54,373.40
Pemasangan 1 M2 Plesteran 1 PC : 4 PP Tebal 15 mm Rp 52,235.04
Pemasangan 1 M2 Plesteran 1 PC : 5 PP Tebal 15 mm Rp 50,974.26
Pemasangan 1 M2 Plesteran 1 PC : 6 PP Tebal 15 mm Rp 49,984.84
Pemasangan 1 M2 Plesteran 1 PC : 7 PP Tebal 15 mm Rp 49,426.26
Pemasangan 1 M2 Plesteran 1 PC : 8 PP Tebal 15 mm Rp 48,867.68
Pemasangan 1 M2 Plesteran 1 PC : 1 PP Tebal 20 mm Rp 76,993.97
Pemasangan 1 M2 Plesteran 1 PC : 3 PP Tebal 20 mm Rp 61,401.43
Pemasangan 1 M2 Plesteran 1 PC : 4 PP Tebal 20 mm Rp 69,844.72
Pemasangan 1 M2 Plesteran 1 PC : 5 PP Tebal 20 mm Rp 68,216.85
Pemasangan 1 M2 Plesteran 1 PC : 6 PP Tebal 20 mm Rp 66,844.45
JENIS PEKERJAAN HARGA

3 4
Pemasangan 1 M2 Berapen 1 PC : 5 PP Tebal 15 mm Rp 31,536.16
Pemasangan 1 M2 Plesteran Ciprat 1 PC : 2 PP Rp 41,431.72
Pemasangan 1 M2 Acian Rp 30,910.00
Pemasangan 1 M2 Finishing Siar Pasangan Bata Merah Rp 24,283.47

Pemasangan 1 m2 lantai ubin PC abu-abu ukuran 40x40 Rp 120,497.85

Pemasangan 1 m2 lantai ubin PC abu-abu ukuran 30x30 Rp 114,204.75


Pemasangan 1 m2 lantai ubin PC abu-abu ukuran 20x20 Rp 123,586.10
Pemasangan 1 M2 Lantai Homogenius Uk. 60/60 Rp 261,356.70
Pemasangan 1 M2 Lantai Homogenius Uk. 40/40 Rp 290,574.90
Pemasangan 1 M2 Lantai Homogenius Uk. 30/30 Rp 264,954.80
Pemasangan 1 m2 lantai keramik warna ukuran 40x40 Rp 127,941.00
Pemasangan 1 m2 lantai keramik warna ukuran 30x30 Rp 125,897.75
Pemasangan 1 m2 lantai keramik warna ukuran 20x20 Rp 133,692.90
Pemasangan 1 m' plint keramik warna ukuran 10 x 20 cm Rp 26,935.04
Pemasangan 1 m' plint keramik warna ukuran 10 x 30 cm Rp 28,092.24
Pemasangan 1 m' plint keramik warna ukuran 10 x 40 cm Rp 32,553.29
Pemasangan 1 m' plin Homogenius Uk. 10/60 Rp 41,306.54
Pemasangan 1 m' plint homogenius warna ukuran 10 x 40 cm Rp 43,930.04
Pemasangan 1 m2 dinding keramik warna 20x20 CM Rp 128,031.20
Pemasangan 1 m2 Dinding Keramik ukuran 20x25 Rp 129,123.50
Pemasangan 1 M2 Lantai Karpet Rp 51,120.30
Pemasangan 1 M2 Lantai Parquet Rp 353,155.00
Pemasangan 1 M2 Dinding Batu Tempel Uk. 20 X 20 CM Rp 262,993.50
Pemasangan 1 M2 Dinding Batu Tempel Uk. 20 X 40 CM Rp 301,438.50
Pemasangan 1 M2 Wallpaper Lebar 50 CM Rp 202,084.85
JENIS PEKERJAAN HARGA

3 4
Pemasangan 1 M' Plint Kayu Tebal 2 CM Lebar 10 CM Rp 44,266.20

Pemasangan langit-langit tripleks ukuran (120x240) cm, tebal 4 MM Rp 46,016.19


Pemasangan langit-langit lambrisering kayu, tebal 9mm Rp 179,241.48
Pemasangan langit-langit gypsum board ukuran (120x240x9)mm, tebal 9 mm Rp 52,520.38
Pemasangan 1 M' list langit-langit kayu profil Rp 12,163.31
Pemasangan 1 M2 Piri - Piri Rp 139,780.30

Pemasangan 1 m2 Atap Genteng Metal Rp 105,811.20


Pemasangan 1 m nok genteng metal Rp 83,758.40
Pemasangan 1 m2 atap seng gelombang Rp 48,533.76
Pemasangan 1 m2 nok atap seng Rp 39,217.42
Pemasangan 1 m2 lapisan Aluminium Foil Rp 32,417.00
Pemasangan 1 M' Terpal Pelapis Perabung Atap Rp 62,474.50
Pemasangan 1 KG Rangka Kuda - Kuda Baja IWF Rp 33,898.70

Pembuatan & Pemasangan 1 m3 Kusen Pintu dan Kusen Jendela, Kayu Kelas I Rp 10,699,617.50
Pembuatan & Pemasangan Kusen Kayu Kelas II Rp 5,100,727.50
Pembuatan dan Pemasangan 1 M2 Pintu Klamp Standar, Kayu Kelas II Rp 226,758.40
Pembuatan & Pemasangan 1 M2 Pintu Klamp Sederhana, Kayu Klam Kelas III Rp 222,358.40
Pembuatan & Pemasangan 1 M2 Daun Pintu Panel, Kayu Kelas I Rp 687,087.50
Pembuatan & Pemasangan 1M2 Pintu/Jendela Kaca Kayu Kelas II Rp 460,630.50
Pembuatan & Pemasangan 1 M2 Jalusi Pintu/Jendela Kayu Kelas II Rp 544,131.50
Pembuatan 1 M2 Daun Pintu Plywood Rangkap, Rangka Kayu Kelas II Tertutup ( Lebar samRp 413,363.94
Pembuatan & Pemasangan 1M2 Jalusi Kusen Kayu kelas II Rp 425,722.00
JENIS PEKERJAAN HARGA

3 4
Pembuatan & Pemasangan 1 M2 Teakwood Rangka Ekspos Kayu Kelas I Rp 663,294.94
Pemasangan 1M3 Kuda-kuda Konvensional Kayu Kelas II Rp 4,364,973.80
Pemasangan 1 M3 Konstruksi Gordeng, Kayu Kelas II Rp 5,356,307.00
Pemasangan 1 M2 Rangka Langit-langit 60x60 Kayu Kelas II Rp 87,846.55
Pemasangan 1 M2 Rangka Dinding Pemisah ( 60 x 120 ) CM Kayu Kelas II Rp 122,124.75
Pemasangan 1 M2 Dinding Pemisah Plywood Rangkap Rangka Kayu Kelas II Rp 222,080.10
Pemasangan 1 M' Listplank Ukuran ( 3x20 ) cm , Kayu Kelas II Rp 54,643.60
Pemasangan 1 M' Listplank Ukuran ( 3x30 ) Kayu Kelas II Rp 54,267.40

Pemasangan 1 Buah Kunci Tanam Antik Rp 285,718.40


Pemasangan 1 Buah Kunci Tanam Biasa Rp 195,061.90
Pemasangan 1 Buah Kunci Tanam Kamar Mandi Rp 106,490.45
Pemasangan 1 Buah Kunci Tanam Silinder Rp 106,490.45
Pemasangan 1 Buah Engsel Pintu Rp 24,849.55
Pemasangan 1 Buah Engsel jendela Kupu-kupu Rp 16,636.40
Pemasangan 1 Buah Kait Angin Rp 24,462.35
Pemasangan 1 Buah Handle Jendela Rp 25,562.35
Pemasangan 1 Buah Grendel Jendela Rp 31,402.80
Pemasangan 1 Buah Doorcloser Rp 483,851.50
Pemasangan 1 m2 Kaca Polos tebal 3mm Rp 116,641.80
Pemasangan 1 m2 Kaca Polos tebal 5mm Rp 129,346.80
Pemasangan 1 m2 Kaca Polos tebal 8mm Rp 456,595.06
Pemasangan 1 m2 Kaca Polos tebal 12mm Rp 640,506.90
Pemasangan 1 M2 Kaca Cermin Tebal 5 MM Rp 34,818.85

Pengikisan/Pengerokan 1 m2 Permukaan Cat tembok Lama Rp 12,155.00


JENIS PEKERJAAN HARGA

3 4
Pencucian 1 m2 Bidang Permukaan Dinding Lama yang Pernah dicat Rp 13,205.50
Pengecatan 1 M2 Bidang Kayu Baru ( 1 Lapis Plamir, 1 Lapis Cat Dasar dan 2 Lapis Cat Pe Rp 43,233.91
Pengecatan 1 M2 Bidang Kayu Lama ( 2 Lapis Cat Penutup ) Rp 25,796.93
Pengecatan 1 M2 Tembok Baru ( 1 Lapis Plamuur, 1 Lapis Cat Dasar dan 2 Lapis Cat Penut Rp 19,756.00
Pengecatan 1 M2 Tembok Lama ( 1 Lapis Cat Dasar dan 2 Lapis Cat Penutup ) Rp 12,149.72
Pelaburan 1 M2 Tembok Baru dengan Kapur Sirih Rp 18,671.95
Pelaburan 1 M2 Tembok Lama dengan Kapur Sirih ( Pemeliharaan ) Rp 12,315.60
Pengecatan 1 M2 Permukaan Baja Dengan Menie Besi Rp 24,020.43
Pengecatan 1 M2 Permukaan Baja Galvanis secara semprot Sistem 3 Lapis Cat Mutakhir Rp 86,210.30

Pemasangan 1 Buah Closet Duduk ( Lengkap ) Rp 2,433,607.00


Pemasangan 1 Buah Closet Jongkok Rp 555,401.00
Pemasangan 1 Buah urinoir Rp 2,089,332.30
Pemasangan 1 Buah Wastafel Rp 956,871.52
Pemasangan 1 M' Pipa PVC Diameter 1/2 Inchi Rp 16,354.14
Pemasangan 1 M' Pipa PVC Diameter 3/4 Inchi Rp 20,541.84
Pemasangan 1 M' Pipa PVC Diameter 1 Inchi Rp 25,353.24
Pemasangan 1 M' Pipa PVC Diameter 2 Inchi Rp 40,613.76
Pemasangan 1 M' Pipa PVC Diameter 2,50 Inchi Rp 51,738.39
Pemasangan 1 M' Pipa PVC Diameter 3 Inchi Rp 74,013.39
Pemasangan 1 M' Pipa PVC Diameter 4 Inchi Rp 91,833.39

Memasang 1 M2 Conblock Segi 6 Tebal 6 CM Rp 121,845.90


Memasang 1 M2 Conblok Segi 4 Tebal 8 CM Rp 142,745.90
Memasang 1 M2 Sosotan Aspal Rp 32,092.59
Memasang 1 M2 Taburan Pasir Cor Rp 3,187.80
JENIS PEKERJAAN HARGA

3 4
Pekerjaan 1 M2 Tanam Rumput Gajah Mini Rp 52,993.60
Pemasangan 1 M2 Sunscreen Alluminium Rp 307,331.20
I. PEKERJAAN PERSIAPAN

1 Pembuatan 1 m' pagar sementara dari kayu tinggi 2 meter


No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)
A TENAGA
Pekerja L.01 OH 0.400 Rp 67,900.00 Rp 27,160.00
Tukang Kayu L.02 OH 0.200 Rp 83,200.00 Rp 16,640.00
Kepala Tukang L.03 OH 0.020 Rp 88,000.00 Rp 1,760.00
Mandor L.04 OH 0.020 Rp 90,000.00 Rp 1,800.00
JUMLAH TENAGA KERJA Rp 47,360.00
B BAHAN
Dolken kayu 8-10/400 cm Batang 1.250 Rp 7,000.00 Rp 8,750.00
Semen portland Kg 5.000 Rp 1,360.00 Rp 6,800.00
Pasir beton M3 0.005 Rp 145,000.00 Rp 725.00
Koral beton M3 0.009 Rp 196,300.00 Rp 1,766.70
Balok Kayu Uk. 5/7 CM Kelas II M3 0.072 Rp 2,085,000.00 Rp 150,120.00
Paku biasa 2” – 5” Kg 0.060 Rp 15,180.00 Rp 910.80
Residu Liter 0.400 Rp 35,650.00 Rp 14,260.00
JUMLAH HARGA BAHAN Rp 183,332.50
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 230,692.50
E Overhead & Proft ( 10 % ) 10% x D Rp 23,069.25
F Harga Satuan Pekerjaan (D+E) Rp 253,761.75

2 Pembuatan 1m2 pagar sementara dari seng gelombang tinggi 2 meter


No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)
A TENAGA
Pekerja L.01 OH 0.200 Rp 67,900.00 Rp 13,580.00
Tukang Kayu L.02 OH 0.400 Rp 83,200.00 Rp 33,280.00
Kepala Tukang L.03 OH 0.020 Rp 88,000.00 Rp 1,760.00
Mandor L.04 OH 0.020 Rp 90,000.00 Rp 1,800.00
JUMLAH TENAGA KERJA Rp 50,420.00
B BAHAN
Dolken kayu 8-10/400 cm Batang 1.250 Rp 7,000.00 Rp 8,750.00
Semen portland Kg 2.500 Rp 1,360.00 Rp 3,400.00
Seng Gelombang Lbr 1.200 Rp 42,300.00 Rp 50,760.00
Pasir Beton M3 0.005 Rp 145,000.00 Rp 725.00
Koral Beton M3 0.009 Rp 196,300.00 Rp 1,766.70
Balok Kayu Uk. 5/7 CM Kelas II M3 0.072 Rp 2,085,000.00 Rp 150,120.00
Paku Biasa 2 " - 5 " Kg 0.060 Rp 15,180.00 Rp 910.80
Meni Besi Liter 0.450 Rp 16,800.00 Rp 7,560.00
JUMLAH HARGA BAHAN Rp 223,992.50
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 274,412.50
E Overhead & Proft ( 10 % ) 10% x D Rp 27,441.25
F Harga Satuan Pekerjaan (D+E) Rp 301,853.75
3 Pengukuran dan pemasangan 1 M' bouwplank
No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)
A TENAGA
Pekerja L.01 OH 0.100 Rp 67,900.00 Rp 6,790.00
Tukang Kayu L.02 OH 0.100 Rp 83,200.00 Rp 8,320.00
Kepala Tukang L.03 OH 0.010 Rp 88,000.00 Rp 880.00
Mandor L.04 OH 0.005 Rp 90,000.00 Rp 450.00
JUMLAH TENAGA KERJA Rp 16,440.00
B BAHAN
Kayu Balok Uk. 5/7 CM Kelas III M3 0.012 Rp 1,985,000.00 Rp 23,820.00
Paku 2" - 3" Kg 0.020 Rp 15,180.00 Rp 303.60
Kayu Papan Uk. 3/20 CM Kelas II M3 0.007 Rp 1,985,000.00 Rp 13,895.00
JUMLAH HARGA BAHAN Rp 38,018.60
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 54,458.60
E Overhead & Proft ( 10 % ) 10% x D Rp 5,445.86
F Harga Satuan Pekerjaan (D+E) Rp 59,904.46

4 Pembersihan 1 M2 Lapangan dan Perataan


No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)
A TENAGA
Pekerja L.01 OH 0.100 Rp 67,900.00 Rp 6,790.00
Mandor L.04 OH 0.050 Rp 90,000.00 Rp 4,500.00
JUMLAH TENAGA KERJA Rp 11,290.00
B BAHAN
JUMLAH HARGA BAHAN
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 11,290.00
E Overhead & Proft ( 10 % ) 10% x D Rp 1,129.00
F Harga Satuan Pekerjaan (D+E) Rp 12,419.00

5 Pembongkaran 1 M3 beton bertulang


No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)
A TENAGA
Pekerja L.01 OH 13.334 Rp 67,900.00 Rp 905,378.60
Mandor L.04 OH 0.666 Rp 90,000.00 Rp 59,940.00
JUMLAH TENAGA KERJA Rp 965,318.60
B BAHAN
JUMLAH HARGA BAHAN
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 965,318.60
E Overhead & Proft ( 10 % ) 10% x D Rp 96,531.86
F Harga Satuan Pekerjaan (D+E) Rp 1,061,850.46

6 Pembongkaran 1 M3 dinding tembok bata


No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)
A TENAGA
Pekerja L.01 OH 6.667 Rp 67,900.00 Rp 452,689.30
Mandor L.04 OH 0.333 Rp 90,000.00 Rp 29,970.00
JUMLAH TENAGA KERJA Rp 482,659.30
B BAHAN
JUMLAH HARGA BAHAN
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 482,659.30
E Overhead & Proft ( 10 % ) 10% x D Rp 48,265.93
F Harga Satuan Pekerjaan (D+E) Rp 530,925.23
II. PEKERJAAN TANAH

1 Penggalian 1 M3 tanah biasa sedalam 1 M'


No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)
A TENAGA
Pekerja L.01 OH 0.750 Rp 67,900.00 Rp 50,925.00
Mandor L.04 OH 0.025 Rp 90,000.00 Rp 2,250.00
JUMLAH TENAGA KERJA Rp 53,175.00
B BAHAN
JUMLAH HARGA BAHAN
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 53,175.00
E Overhead & Proft ( 10 % ) 10% x D Rp 5,317.50
F Harga Satuan Pekerjaan (D+E) Rp 58,492.50

2 Penggalian 1 M3 tanah biasa sedalam 2 M'


No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)
A TENAGA
Pekerja L.01 OH 0.900 Rp 67,900.00 Rp 61,110.00
Mandor L.04 OH 0.045 Rp 90,000.00 Rp 4,050.00
JUMLAH TENAGA KERJA Rp 65,160.00
B BAHAN
JUMLAH HARGA BAHAN
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 65,160.00
E Overhead & Proft ( 10 % ) 10% x D Rp 6,516.00
F Harga Satuan Pekerjaan (D+E) Rp 71,676.00

3 Menggali 1 M3 tanah keras sedalam 1 M3


No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)
A TENAGA
Pekerja L.01 OH 1.000 Rp 67,900.00 Rp 67,900.00
Mandor L.04 OH 0.032 Rp 90,000.00 Rp 2,880.00
JUMLAH TENAGA KERJA Rp 70,780.00
B BAHAN
JUMLAH HARGA BAHAN
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 70,780.00
E Overhead & Proft ( 10 % ) 10% x D Rp 7,078.00
F Harga Satuan Pekerjaan (D+E) Rp 77,858.00

4 Menggali 1 M3 tanah cadas sedalam 1 M3


No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)
A TENAGA
Pekerja L.01 OH 1.500 Rp 67,900.00 Rp 101,850.00
Mandor L.04 OH 0.060 Rp 90,000.00 Rp 5,400.00
JUMLAH TENAGA KERJA Rp 107,250.00
B BAHAN
JUMLAH HARGA BAHAN
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 107,250.00
E Overhead & Proft ( 10 % ) 10% x D Rp 10,725.00
F Harga Satuan Pekerjaan (D+E) Rp 117,975.00

5 Menggali 1 M3 tanah lumpur sedalam 1 M3


No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)
A TENAGA
Pekerja L.01 OH 1.200 Rp 67,900.00 Rp 81,480.00
Mandor L.04 OH 0.045 Rp 90,000.00 Rp 4,050.00
JUMLAH TENAGA KERJA Rp 85,530.00
B BAHAN
JUMLAH HARGA BAHAN
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 85,530.00
E Overhead & Proft ( 10 % ) 10% x D Rp 8,553.00
F Harga Satuan Pekerjaan (D+E) Rp 94,083.00

6 Pembuangan 1 M3 tanah sejauh 30 meter


No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)
A TENAGA
Pekerja L.01 OH 0.330 Rp 67,900.00 Rp 22,407.00
Mandor L.04 OH 0.010 Rp 90,000.00 Rp 900.00
JUMLAH TENAGA KERJA Rp 23,307.00
B BAHAN
JUMLAH HARGA BAHAN
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 23,307.00
E Overhead & Proft ( 10 % ) 10% x D Rp 2,330.70
F Harga Satuan Pekerjaan (D+E) Rp 25,637.70

7 Pengurugan kembali 1 M3 galian tanah


No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)
A TENAGA
Pekerja L.01 OH 0.500 Rp 67,900.00 Rp 33,950.00
Mandor L.04 OH 0.050 Rp 90,000.00 Rp 4,500.00
JUMLAH TENAGA KERJA Rp 38,450.00
B BAHAN
JUMLAH HARGA BAHAN
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 38,450.00
E Overhead & Proft ( 10 % ) 10% x D Rp 3,845.00
F Harga Satuan Pekerjaan (D+E) Rp 42,295.00

8 Pemadatan tanah 1 M3 tanah ( per 20 cm )


No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)
A TENAGA
Pekerja L.01 OH 0.500 Rp 67,900.00 Rp 33,950.00
Mandor L.04 OH 0.050 Rp 90,000.00 Rp 4,500.00
JUMLAH TENAGA KERJA Rp 38,450.00
B BAHAN
JUMLAH HARGA BAHAN
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 38,450.00
E Overhead & Proft ( 10 % ) 10% x D Rp 3,845.00
F Harga Satuan Pekerjaan (D+E) Rp 42,295.00

9 Pengurugan 1 M3 dengan pasir urug


No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)
A TENAGA
Pekerja L.01 OH 0.300 Rp 67,900.00 Rp 20,370.00
Mandor L.04 OH 0.010 Rp 90,000.00 Rp 900.00
JUMLAH TENAGA KERJA Rp 21,270.00
B BAHAN
Pasir Urug M3 1.200 145,000.00 Rp 174,000.00
JUMLAH HARGA BAHAN Rp 174,000.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 195,270.00
E Overhead & Proft ( 10 % ) 10% x D Rp 19,527.00
F Harga Satuan Pekerjaan (D+E) Rp 214,797.00

10 Pemasangan 1 M2 Lapisan Ijuk Tebal 10 CM untuk Bidang Resapan


No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)
A TENAGA
Pekerja L.01 OH 0.150 Rp 67,900.00 Rp 10,185.00
Mandor L.04 OH 0.015 Rp 90,000.00 Rp 1,350.00
JUMLAH TENAGA KERJA Rp 11,535.00
B BAHAN
Ijuk Kg 6.000 15,300.00 Rp 91,800.00
JUMLAH HARGA BAHAN Rp 91,800.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 103,335.00
E Overhead & Proft ( 10 % ) 10% x D Rp 10,333.50
F Harga Satuan Pekerjaan (D+E) Rp 113,668.50

11 Mengurug 1 M3 Tanah Urug


No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)
A TENAGA
Pekerja L.01 OH 0.300 Rp 67,900.00 Rp 20,370.00
Mandor L.04 OH 0.010 Rp 90,000.00 Rp 900.00
JUMLAH TENAGA KERJA Rp 21,270.00
B BAHAN
Tanah Urug 1.200 65,000.00 Rp 78,000.00
JUMLAH HARGA BAHAN Rp 78,000.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 99,270.00
E Overhead & Proft ( 10 % ) 10% x D Rp 9,927.00
F Harga Satuan Pekerjaan (D+E) Rp 109,197.00
III. PEKERJAAN PONDASI

1 Pemasangan 1 M3 pondasi batu belah campuran 1 SP : 3 PP


No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)
A TENAGA
Pekerja L.01 OH 1.500 Rp 67,900.00 Rp 101,850.00
Tukang Batu L.02 OH 0.750 Rp 83,200.00 Rp 62,400.00
Kepala Tukang L.03 OH 0.075 Rp 88,000.00 Rp 6,600.00
Mandor L.04 OH 0.075 Rp 90,000.00 Rp 6,750.00
JUMLAH TENAGA KERJA Rp 177,600.00
B BAHAN
Batu Belah M3 1.200 355,000.00 Rp 426,000.00
Semen Portland Kg 202.000 1,360.00 Rp 274,720.00
Pasir Pasang M3 0.485 145,000.00 Rp 70,325.00
JUMLAH HARGA BAHAN Rp 771,045.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 948,645.00
E Overhead & Proft ( 10 % ) 10% x D Rp 94,864.50
F Harga Satuan Pekerjaan (D+E) Rp 1,043,509.50

2 Pemasangan 1 M3 pondasi batu belah campuran 1 SP : 4 PP


No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)
A TENAGA
Pekerja L.01 OH 1.500 Rp 67,900.00 Rp 101,850.00
Tukang Batu L.02 OH 0.750 Rp 83,200.00 Rp 62,400.00
Kepala Tukang L.03 OH 0.075 Rp 88,000.00 Rp 6,600.00
Mandor L.04 OH 0.075 Rp 90,000.00 Rp 6,750.00
JUMLAH TENAGA KERJA Rp 177,600.00
B BAHAN
Batu Belah M3 1.200 355,000.00 Rp 426,000.00
Semen Portland Kg 163.000 1,360.00 Rp 221,680.00
Pasir Pasang M3 0.520 145,000.00 Rp 75,400.00
JUMLAH HARGA BAHAN Rp 723,080.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 900,680.00
E Overhead & Proft ( 10 % ) 10% x D Rp 90,068.00
F Harga Satuan Pekerjaan (D+E) Rp 990,748.00

3 Pemasangan 1 M3 pondasi batu belah campuran 1 SP : 5 PP


No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)
A TENAGA
Pekerja L.01 OH 1.500 Rp 67,900.00 Rp 101,850.00
Tukang Batu L.02 OH 0.750 Rp 83,200.00 Rp 62,400.00
Kepala Tukang L.03 OH 0.075 Rp 88,000.00 Rp 6,600.00
Mandor L.04 OH 0.075 Rp 90,000.00 Rp 6,750.00
JUMLAH TENAGA KERJA Rp 177,600.00
B BAHAN
Batu Belah M3 1.200 355,000.00 Rp 426,000.00
Semen Portland Kg 136.000 1,360.00 Rp 184,960.00
Pasir Pasang M3 0.544 145,000.00 Rp 78,880.00
JUMLAH HARGA BAHAN Rp 689,840.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 867,440.00
E Overhead & Proft ( 10 % ) 10% x D Rp 86,744.00
F Harga Satuan Pekerjaan (D+E) Rp 954,184.00

4 Pemasangan 1 M2 pondasi batu bata merah camp. 1 SP : 2 Psr


No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)
A TENAGA
Pekerja L.01 OH 0.600 Rp 67,900.00 Rp 40,740.00
Tukang Batu L.02 OH 0.200 Rp 83,200.00 Rp 16,640.00
Kepala Tukang L.03 OH 0.020 Rp 88,000.00 Rp 1,760.00
Mandor L.04 OH 0.030 Rp 90,000.00 Rp 2,700.00
JUMLAH TENAGA KERJA Rp 61,840.00
B BAHAN
Bata merah Buah 140.000 Rp 550.00 Rp 77,000.00
Semen Portland Kg 43.500 Rp 1,360.00 Rp 59,160.00
Pasir Pasang M3 0.080 Rp 145,000.00 Rp 11,600.00
JUMLAH HARGA BAHAN Rp 147,760.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 209,600.00
E Overhead & Proft ( 10 % ) 10% x D Rp 20,960.00
F Harga Satuan Pekerjaan (D+E) Rp 230,560.00

5 Pemasangan 1 M2 pondasi batu bata merah camp. 1 SP : 4 Psr


No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)
A TENAGA
Pekerja L.01 OH 0.600 Rp 67,900.00 Rp 40,740.00
Tukang Batu L.02 OH 0.200 Rp 83,200.00 Rp 16,640.00
Kepala Tukang L.03 OH 0.020 Rp 88,000.00 Rp 1,760.00
Mandor L.04 OH 0.030 Rp 90,000.00 Rp 2,700.00
JUMLAH TENAGA KERJA Rp 61,840.00
B BAHAN
Bata merah Buah 140.000 Rp 550.00 Rp 77,000.00
Semen Portland Kg 26.550 Rp 1,360.00 Rp 36,108.00
Pasir Pasang M3 0.093 Rp 145,000.00 Rp 13,485.00
JUMLAH HARGA BAHAN Rp 126,593.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 188,433.00
E Overhead & Proft ( 10 % ) 10% x D Rp 18,843.30
F Harga Satuan Pekerjaan (D+E) Rp 207,276.30
6 Pemasangan 1 M3 pondasi sumuran diameter 100 cm
No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)
A TENAGA
Pekerja L.01 OH 2.400 Rp 67,900.00 Rp 162,960.00
Tukang Batu L.02 OH 0.800 Rp 83,200.00 Rp 66,560.00
Kepala Tukang L.03 OH 0.080 Rp 88,000.00 Rp 7,040.00
Mandor L.04 OH 0.119 Rp 90,000.00 Rp 10,710.00
JUMLAH TENAGA KERJA Rp 247,270.00
B BAHAN
Batu belah M3 0.450 Rp 355,000.00 Rp 159,750.00
Semen Portland Kg 194.000 Rp 1,360.00 Rp 263,840.00
Pasir beton M3 0.312 Rp 145,000.00 Rp 45,240.00
Kerikil M3 0.468 Rp 196,300.00 Rp 91,868.40
JUMLAH HARGA BAHAN Rp 560,698.40
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 807,968.40
E Overhead & Proft ( 10 % ) 10% x D Rp 80,796.84
F Harga Satuan Pekerjaan (D+E) Rp 888,765.24

7 1 M' Pekerjaan Pemancangan Tiang Pancang Mini Pile Beton

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)

A TENAGA
Pekerja L.01 OH 0.1000 Rp 67,900.00 Rp 6,790.00
Operator OH 0.1034 Rp 83,200.00 Rp 8,602.88
Mandor L.04 OH 0.0500 Rp 90,000.00 Rp 4,500.00
JUMLAH TENAGA KERJA Rp 19,892.88
B BAHAN
Jump Piller Driver + Hammer Jam 0.050 750,000.00 Rp 37,500.00
JUMLAH HARGA BAHAN Rp 37,500.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 57,392.88
E Overhead & Profit ( 10 % ) 10% x D Rp 5,739.29
F Harga Satuan Pekerjaan (D+E) Rp 63,132.17

8 1 Unit Pekerjaan Pemotongan Tiang Pancang Beton

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)

A TENAGA
Pekerja L.01 OH 0.7500 Rp 67,900.00 Rp 50,925.00
Mandor L.04 OH 0.0375 Rp 90,000.00 Rp 3,375.00
JUMLAH TENAGA KERJA Rp 54,300.00
B BAHAN
JUMLAH HARGA BAHAN
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 54,300.00
E Overhead & Profit ( 10 % ) 10% x D Rp 5,430.00
F Harga Satuan Pekerjaan (D+E) Rp 59,730.00
IV. PEKERJAAN BETON

1 Membuat 1 M3 beton mutu f'c = 7,4 Mpa ( K 100 ), slump ( 12 ± 2 ) cm, w/c = 0,87
No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)
A TENAGA
Pekerja L.01 OH 1.650 Rp 67,900.00 Rp 112,035.00
Tukang Batu L.02 OH 0.275 Rp 83,200.00 Rp 22,880.00
Kepala Tukang L.03 OH 0.028 Rp 88,000.00 Rp 2,464.00
Mandor L.04 OH 0.083 Rp 90,000.00 Rp 7,470.00
JUMLAH TENAGA KERJA Rp 144,849.00
B BAHAN
Semen Portland Kg 247.000 Rp 1,360.00 Rp 335,920.00
Pasir beton M3 0.621 Rp 145,000.00 Rp 90,003.57
Kerikil ( Maks 30 MM ) Kg 0.555 Rp 196,300.00 Rp 108,946.50
Air Liter 215.000 Rp 50.00 Rp 10,750.00
JUMLAH HARGA BAHAN Rp 545,620.07
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 690,469.07
E Overhead & Proft ( 10 % ) 10% x D Rp 69,046.91
F Harga Satuan Pekerjaan (D+E) Rp 759,515.98

2 Membuat 1 M3 beton mutu f'c = 9,8 Mpa ( K 125 ), slump ( 12 ± 2 ) cm, w/c = 0,78
No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)
A TENAGA
Pekerja L.01 OH 1.650 Rp 67,900.00 Rp 112,035.00
Tukang Batu L.02 OH 0.275 Rp 83,200.00 Rp 22,880.00
Kepala Tukang L.03 OH 0.028 Rp 88,000.00 Rp 2,464.00
Mandor L.04 OH 0.083 Rp 90,000.00 Rp 7,470.00
JUMLAH TENAGA KERJA Rp 144,849.00
B BAHAN
Semen Portland Kg 276.000 Rp 1,360.00 Rp 375,360.00
Pasir beton M3 0.591 Rp 145,000.00 Rp 85,757.14
Kerikil ( Maks 30 MM ) M3 0.749 Rp 196,300.00 Rp 147,028.70
Air Liter 215.000 Rp 50.00 Rp 10,750.00
JUMLAH HARGA BAHAN Rp 618,895.84
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 763,744.84
E Overhead & Proft ( 10 % ) 10% x D Rp 76,374.48
F Harga Satuan Pekerjaan (D+E) Rp 840,119.33

3 Membuat 1 M3 beton mutu f'c = 12,2 Mpa ( K 150 ), slump ( 12 ± 2 ) cm, w/c = 0,72
No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)
A TENAGA
Pekerja L.01 OH 1.650 Rp 67,900.00 Rp 112,035.00
Tukang Batu L.02 OH 0.275 Rp 83,200.00 Rp 22,880.00
Kepala Tukang L.03 OH 0.028 Rp 88,000.00 Rp 2,464.00
Mandor L.04 OH 0.083 Rp 90,000.00 Rp 7,470.00
JUMLAH TENAGA KERJA Rp 144,849.00
B BAHAN
Semen Portland Kg 299.000 Rp 1,360.00 Rp 406,640.00
Pasir beton M3 0.571 Rp 145,000.00 Rp 82,753.57
Kerikil ( Maks 30 MM ) M3 0.753 Rp 196,300.00 Rp 147,813.90
Air Liter 215.000 Rp 50.00 Rp 10,750.00
JUMLAH HARGA BAHAN Rp 647,957.47
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 792,806.47
E Overhead & Proft ( 10 % ) 10% x D Rp 79,280.65
F Harga Satuan Pekerjaan (D+E) Rp 872,087.12

4 Membuat 1 M3 lantai kerja beton mutu f'c = 7,4 Mpa ( K 100 ), slump ( 3 - 6 ) cm, w/c = 0,87
No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)
A TENAGA
Pekerja L.01 OH 1.200 Rp 67,900.00 Rp 81,480.00
Tukang Batu L.02 OH 0.200 Rp 83,200.00 Rp 16,640.00
Kepala Tukang L.03 OH 0.020 Rp 88,000.00 Rp 1,760.00
Mandor L.04 OH 0.060 Rp 90,000.00 Rp 5,400.00
JUMLAH TENAGA KERJA Rp 105,280.00
B BAHAN
Semen Portland Kg 230.000 Rp 1,360.00 Rp 312,800.00
Pasir beton M3 0.638 Rp 145,000.00 Rp 92,489.29
Kerikil ( Maks 30 MM ) M3 0.760 Rp 196,300.00 Rp 149,188.00
Air Liter 215.000 Rp 50.00 Rp 10,750.00
JUMLAH HARGA BAHAN Rp 565,227.29
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 670,507.29
E Overhead & Proft ( 10 % ) 10% x D Rp 67,050.73
F Harga Satuan Pekerjaan (D+E) Rp 737,558.01

5 Membuat 1 M3 beton mutu f'c = 14,5 Mpa ( K 175 ), slump ( 12 ± 2 ) cm, w/c = 0,66
No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)
A TENAGA
Pekerja L.01 OH 1.650 Rp 67,900.00 Rp 112,035.00
Tukang Batu L.02 OH 0.275 Rp 83,200.00 Rp 22,880.00
Kepala Tukang L.03 OH 0.028 Rp 88,000.00 Rp 2,464.00
Mandor L.04 OH 0.083 Rp 90,000.00 Rp 7,470.00
JUMLAH TENAGA KERJA Rp 144,849.00
B BAHAN
Semen Portland Kg 326.000 Rp 1,360.00 Rp 443,360.00
Pasir beton M3 0.543 Rp 145,000.00 Rp 78,714.29
Kerikil ( Maks 30 MM ) M3 0.762 Rp 196,300.00 Rp 149,580.60
Air Liter 215.000 Rp 50.00 Rp 10,750.00
JUMLAH HARGA BAHAN Rp 682,404.89
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 827,253.89
E Overhead & Proft ( 10 % ) 10% x D Rp 82,725.39
F Harga Satuan Pekerjaan (D+E) Rp 909,979.27

6 Membuat 1 M3 beton mutu f'c = 16,9 Mpa ( K 200 ), slump ( 12 ± 2 ) cm, w/c = 0,61
No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)
A TENAGA
Pekerja L.01 OH 1.650 Rp 67,900.00 Rp 112,035.00
Tukang Batu L.02 OH 0.275 Rp 83,200.00 Rp 22,880.00
Kepala Tukang L.03 OH 0.028 Rp 88,000.00 Rp 2,464.00
Mandor L.04 OH 0.083 Rp 90,000.00 Rp 7,470.00
JUMLAH TENAGA KERJA Rp 144,849.00
B BAHAN
Semen Portland Kg 352.000 Rp 1,360.00 Rp 478,720.00
Pasir beton M3 0.522 Rp 145,000.00 Rp 75,710.71
Kerikil ( Maks 30 MM ) M3 0.763 Rp 196,300.00 Rp 149,776.90
Air Liter 215.000 Rp 50.00 Rp 10,750.00
JUMLAH HARGA BAHAN Rp 714,957.61
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 859,806.61
E Overhead & Proft ( 10 % ) 10% x D Rp 85,980.66
F Harga Satuan Pekerjaan (D+E) Rp 945,787.28

7 Membuat 1 M3 beton mutu f'c = 19,3 Mpa ( K 225 ), slump ( 12 ± 2 ) cm, w/c = 0,58
No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)
A TENAGA
Pekerja L.01 OH 1.650 Rp 67,900.00 Rp 112,035.00
Tukang Batu L.02 OH 0.275 Rp 83,200.00 Rp 22,880.00
Kepala Tukang L.03 OH 0.028 Rp 88,000.00 Rp 2,464.00
Mandor L.04 OH 0.083 Rp 90,000.00 Rp 7,470.00
JUMLAH TENAGA KERJA Rp 144,849.00
B BAHAN
Semen Portland Kg 371.000 Rp 1,360.00 Rp 504,560.00
Pasir beton M3 0.499 Rp 145,000.00 Rp 72,292.86
Kerikil ( Maks 30 MM ) M3 0.775 Rp 196,300.00 Rp 152,132.50
Air Liter 215.000 Rp 50.00 Rp 10,750.00
JUMLAH HARGA BAHAN Rp 739,735.36
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 884,584.36
E Overhead & Proft ( 10 % ) 10% x D Rp 88,458.44
F Harga Satuan Pekerjaan (D+E) Rp 973,042.79

8 Membuat 1 M3 beton mutu f'c = 21,7 Mpa ( K 250 ), slump ( 12 ± 2 ) cm, w/c = 0,56
No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)
A TENAGA
Pekerja L.01 OH 1.650 Rp 67,900.00 Rp 112,035.00
Tukang Batu L.02 OH 0.275 Rp 83,200.00 Rp 22,880.00
Kepala Tukang L.03 OH 0.028 Rp 88,000.00 Rp 2,464.00
Mandor L.04 OH 0.083 Rp 90,000.00 Rp 7,470.00
JUMLAH TENAGA KERJA Rp 144,849.00
B BAHAN
Semen Portland Kg 384.000 Rp 1,360.00 Rp 522,240.00
Pasir beton M3 0.494 Rp 145,000.00 Rp 71,671.43
Kerikil ( Maks 30 MM ) M3 0.769 Rp 196,300.00 Rp 150,954.70
Air Liter 215.000 Rp 50.00 Rp 10,750.00
JUMLAH HARGA BAHAN Rp 755,616.13
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 900,465.13
E Overhead & Proft ( 10 % ) 10% x D Rp 90,046.51
F Harga Satuan Pekerjaan (D+E) Rp 990,511.64

9 Membuat 1 M3 beton mutu f'c = 24 Mpa ( K 275 ), slump ( 12 ± 2 ) cm, w/c = 0,53
No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)
A TENAGA
Pekerja L.01 OH 1.650 Rp 67,900.00 Rp 112,035.00
Tukang Batu L.02 OH 0.275 Rp 83,200.00 Rp 22,880.00
Kepala Tukang L.03 OH 0.028 Rp 88,000.00 Rp 2,464.00
Mandor L.04 OH 0.083 Rp 90,000.00 Rp 7,470.00
JUMLAH TENAGA KERJA Rp 144,849.00
B BAHAN
Semen Portland Kg 406.000 Rp 1,360.00 Rp 552,160.00
Pasir beton M3 0.489 Rp 145,000.00 Rp 70,842.86
Kerikil ( Maks 30 MM ) M3 0.760 Rp 196,300.00 Rp 149,188.00
Air Liter 215.000 Rp 50.00 Rp 10,750.00
JUMLAH HARGA BAHAN Rp 782,940.86
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 927,789.86
E Overhead & Proft ( 10 % ) 10% x D Rp 92,778.99
F Harga Satuan Pekerjaan (D+E) Rp 1,020,568.84

10 Membuat 1 M3 beton mutu f'c = 26,4 Mpa ( K 300 ), slump ( 12 ± 2 ) cm, w/c = 0,52
No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)
A TENAGA
Pekerja L.01 OH 1.650 Rp 67,900.00 Rp 112,035.00
Tukang Batu L.02 OH 0.275 Rp 83,200.00 Rp 22,880.00
Kepala Tukang L.03 OH 0.028 Rp 88,000.00 Rp 2,464.00
Mandor L.04 OH 0.083 Rp 90,000.00 Rp 7,470.00
JUMLAH TENAGA KERJA Rp 144,849.00
B BAHAN
Semen Portland Kg 413 Rp 1,360.00 Rp 561,680.00
Pasir beton M3 0.486 Rp 145,000.00 Rp 70,532.14
Kerikil ( Maks 30 MM ) M3 0.756 Rp 196,300.00 Rp 148,402.80
Air Liter 215 Rp 50.00 Rp 10,750.00
JUMLAH HARGA BAHAN Rp 791,364.94
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 936,213.94
E Overhead & Proft ( 10 % ) 10% x D Rp 93,621.39
F Harga Satuan Pekerjaan (D+E) Rp 1,029,835.34

11 Membuat 1 M3 beton mutu f'c = 28,8 Mpa ( K 325 ), slump ( 12 ± 2 ) cm, w/c = 0,49
No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)
A TENAGA
Pekerja L.01 OH 2.100 Rp 67,900.00 Rp 142,590.00
Tukang Batu L.02 OH 0.350 Rp 83,200.00 Rp 29,120.00
Kepala Tukang L.03 OH 0.035 Rp 88,000.00 Rp 3,080.00
Mandor L.04 OH 0.105 Rp 90,000.00 Rp 9,450.00
JUMLAH TENAGA KERJA Rp 184,240.00
B BAHAN
Semen Portland Kg 439.000 Rp 1,360.00 Rp 597,040.00
Pasir beton M3 0.479 Rp 145,000.00 Rp 69,392.86
Kerikil ( Maks 30 MM ) M3 0.745 Rp 196,300.00 Rp 146,243.50
Air Liter 215.000 Rp 50.00 Rp 10,750.00
JUMLAH HARGA BAHAN Rp 823,426.36
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 1,007,666.36
E Overhead & Proft ( 10 % ) 10% x D Rp 100,766.64
F Harga Satuan Pekerjaan (D+E) Rp 1,108,432.99

12 Membuat 1 M3 beton mutu f'c = 31,2 Mpa ( K 350 ), slump ( 12 ± 2 ) cm, w/c = 0,48
No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)
A TENAGA
Pekerja L.01 OH 2.100 Rp 67,900.00 Rp 142,590.00
Tukang Batu L.02 OH 0.350 Rp 83,200.00 Rp 29,120.00
Kepala Tukang L.03 OH 0.035 Rp 88,000.00 Rp 3,080.00
Mandor L.04 OH 0.105 Rp 90,000.00 Rp 9,450.00
JUMLAH TENAGA KERJA Rp 184,240.00
B BAHAN
Semen Portland Kg 448.000 Rp 1,360.00 Rp 609,280.00
Pasir beton M3 0.476 Rp 145,000.00 Rp 69,082.14
Kerikil ( Maks 30 MM ) M3 0.740 Rp 196,300.00 Rp 145,262.00
Air Liter 215.000 Rp 50.00 Rp 10,750.00
JUMLAH HARGA BAHAN Rp 834,374.14
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 1,018,614.14
E Overhead & Proft ( 10 % ) 10% x D Rp 101,861.41
F Harga Satuan Pekerjaan (D+E) Rp 1,120,475.56

13 Pembesian 10 Kg dengan besi polos


No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)
A TENAGA
Pekerja L.01 OH 0.070 Rp 67,900.00 Rp 4,753.00
Tukang Besi L.02 OH 0.070 Rp 83,200.00 Rp 5,824.00
Kepala Tukang L.03 OH 0.007 Rp 88,000.00 Rp 616.00
Mandor L.04 OH 0.004 Rp 90,000.00 Rp 360.00
JUMLAH TENAGA KERJA Rp 11,553.00
B BAHAN
Besi beton Polos U-24 Kg 10.500 Rp 10,300.00 Rp 108,150.00
Kawat Beton Kg 0.150 Rp 18,070.00 Rp 2,710.50
JUMLAH HARGA BAHAN Rp 110,860.50
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 122,413.50
E Overhead & Proft ( 10 % ) 10% x D Rp 12,241.35
F Harga Satuan Pekerjaan (D+E) Rp 134,654.85

14 Pembesian 10 Kg dengan besi ulir

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)

A TENAGA
Pekerja L.01 OH 0.070 Rp 67,900.00 Rp 4,753.00
Tukang Besi L.02 OH 0.070 Rp 83,200.00 Rp 5,824.00
Kepala Tukang L.03 OH 0.007 Rp 88,000.00 Rp 616.00
Mandor L.04 OH 0.004 Rp 90,000.00 Rp 360.00
JUMLAH TENAGA KERJA Rp 11,553.00
B BAHAN
Besi beton Ulir U-39 Kg 10.500 Rp 20,100.00 Rp 211,050.00
Kawat Beton Kg 0.150 Rp 18,070.00 Rp 2,710.50
JUMLAH HARGA BAHAN Rp 213,760.50
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 225,313.50
E Overhead & Profit ( 10 % ) 10% x D Rp 22,531.35
F Harga Satuan Pekerjaan (D+E) Rp 247,844.85

15 Pemasangan 1 M2 bekisting untuk pondasi


No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)
A TENAGA
Pekerja L.01 OH 0.520 Rp 67,900.00 Rp 35,308.00
Tukang Kayu L.02 OH 0.260 Rp 83,200.00 Rp 21,632.00
Kepala Tukang L.03 OH 0.026 Rp 88,000.00 Rp 2,288.00
Mandor L.04 OH 0.026 Rp 90,000.00 Rp 2,340.00
JUMLAH TENAGA KERJA Rp 61,568.00
B BAHAN
Kayu Kelas III M3 0.040 Rp 1,985,000.00 Rp 79,400.00
Paku 5 - 10 Kg 0.300 Rp 15,180.00 Rp 4,554.00
Minyak bekisting Liter 0.100 Rp 4,877.50 Rp 487.75
JUMLAH HARGA BAHAN Rp 84,441.75
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 146,009.75
E Overhead & Proft ( 10 % ) 10% x D Rp 14,600.98
F Harga Satuan Pekerjaan (D+E) Rp 160,610.73

16 Pemasangan 1 M2 bekisting untuk sloof


No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)
A TENAGA
Pekerja L.01 OH 0.520 Rp 67,900.00 Rp 35,308.00
Tukang Kayu L.02 OH 0.260 Rp 83,200.00 Rp 21,632.00
Kepala Tukang L.03 OH 0.026 Rp 88,000.00 Rp 2,288.00
Mandor L.04 OH 0.026 Rp 90,000.00 Rp 2,340.00
JUMLAH TENAGA KERJA Rp 61,568.00
B BAHAN
Kayu Kelas III M3 0.045 Rp 1,985,000.00 Rp 89,325.00
Paku 5 cm - 10 cm Kg 0.300 Rp 15,180.00 Rp 4,554.00
Minyak bekisting Liter 0.100 Rp 4,877.50 Rp 487.75
JUMLAH HARGA BAHAN Rp 94,366.75
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 155,934.75
E Overhead & Proft ( 10 % ) 10% x D Rp 15,593.48
F Harga Satuan Pekerjaan (D+E) Rp 171,528.23

17 Pemasangan 1 M2 bekisting untuk kolom


No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)
A TENAGA
Pekerja L.01 OH 0.660 Rp 67,900.00 Rp 44,814.00
Tukang Kayu L.02 OH 0.330 Rp 83,200.00 Rp 27,456.00
Kepala Tukang L.03 OH 0.033 Rp 88,000.00 Rp 2,904.00
Mandor L.04 OH 0.033 Rp 90,000.00 Rp 2,970.00
JUMLAH TENAGA KERJA Rp 78,144.00
B BAHAN
Kayu Kelas III M3 0.040 Rp 1,985,000.00 Rp 79,400.00
Paku 5 cm - 10 cm Kg 0.400 Rp 15,180.00 Rp 6,072.00
Minyak bekisting Liter 0.200 Rp 4,877.50 Rp 975.50
Balok kayu kelas II M3 0.015 Rp 2,085,000.00 Rp 31,275.00
Plywood tebal 9 mm Lbr 0.350 Rp 146,500.00 Rp 51,275.00
Dolken kayu 8 - 10 cm panjang 4 Batang 2.000 Rp 7,000.00 Rp 14,000.00
m
JUMLAH HARGA BAHAN Rp 182,997.50
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 261,141.50
E Overhead & Proft ( 10 % ) 10% x D Rp 26,114.15
F Harga Satuan Pekerjaan (D+E) Rp 287,255.65

18 Pemasangan 1 M2 bekisting untuk Balok


No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)
A TENAGA
Pekerja L.01 OH 0.660 Rp 67,900.00 Rp 44,814.00
Tukang Kayu L.02 OH 0.330 Rp 83,200.00 Rp 27,456.00
Kepala Tukang L.03 OH 0.033 Rp 88,000.00 Rp 2,904.00
Mandor L.04 OH 0.033 Rp 90,000.00 Rp 2,970.00
JUMLAH TENAGA KERJA Rp 78,144.00
B BAHAN
Kayu Kelas III M3 0.040 Rp 1,985,000.00 Rp 79,400.00
Paku 5 cm - 12 cm Kg 0.400 Rp 15,180.00 Rp 6,072.00
Minyak bekisting Liter 0.200 Rp 4,877.50 Rp 975.50
Balok kayu kelas II M3 0.018 Rp 2,085,000.00 Rp 37,530.00
Plywood tebal 9 mm Lbr 0.350 Rp 146,500.00 Rp 51,275.00
Dolken kayu 8 - 10 cm panjang 4 Batang 2.000 Rp 7,000.00 Rp 14,000.00
m
JUMLAH HARGA BAHAN Rp 189,252.50
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 267,396.50
E Overhead & Proft ( 10 % ) 10% x D Rp 26,739.65
F Harga Satuan Pekerjaan (D+E) Rp 294,136.15

19 Pemasangan 1 M2 bekisting untuk lantai


No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)
A TENAGA
Pekerja L.01 OH 0.660 Rp 67,900.00 Rp 44,814.00
Tukang Kayu L.02 OH 0.330 Rp 83,200.00 Rp 27,456.00
Kepala Tukang L.03 OH 0.033 Rp 88,000.00 Rp 2,904.00
Mandor L.04 OH 0.033 Rp 90,000.00 Rp 2,970.00
JUMLAH TENAGA KERJA Rp 78,144.00
B BAHAN
Kayu Kelas III M3 0.040 Rp 1,985,000.00 Rp 79,400.00
Paku 5 cm - 12 cm Kg 0.400 Rp 15,180.00 Rp 6,072.00
Minyak bekisting Liter 0.200 Rp 4,877.50 Rp 975.50
Balok kayu kelas II M3 0.015 Rp 2,085,000.00 Rp 31,275.00
Plywood tebal 9 mm Lbr 0.350 Rp 146,500.00 Rp 51,275.00
Dolken kayu 8 - 10 cm panjang 4 Batang 6.000 Rp 7,000.00 Rp 42,000.00
m
JUMLAH HARGA BAHAN Rp 210,997.50
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 289,141.50
E Overhead & Proft ( 10 % ) 10% x D Rp 28,914.15
F Harga Satuan Pekerjaan (D+E) Rp 318,055.65

20 Pemasangan 1 M2 bekisting untuk dinding


No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)
A TENAGA
Pekerja L.01 OH 0.660 Rp 67,900.00 Rp 44,814.00
Tukang Kayu L.02 OH 0.330 Rp 83,200.00 Rp 27,456.00
Kepala Tukang L.03 OH 0.033 Rp 88,000.00 Rp 2,904.00
Mandor L.04 OH 0.033 Rp 90,000.00 Rp 2,970.00
JUMLAH TENAGA KERJA Rp 78,144.00
B BAHAN
Kayu Kelas III M3 0.030 Rp 1,985,000.00 Rp 59,550.00
Paku 5 cm - 12 cm Kg 0.400 Rp 15,180.00 Rp 6,072.00
Minyak bekisting Liter 0.200 Rp 4,877.50 Rp 975.50
Balok kayu kelas II M3 0.020 Rp 2,085,000.00 Rp 41,700.00
Plywood tebal 9 mm Lbr 0.350 Rp 146,500.00 Rp 51,275.00
Dolken kayu 8 - 10 cm panjang 4 Rp 21,000.00
m Batang 3.000 Rp 7,000.00

Penjaga jarak bekisting / spacer Buah 4.000 Rp 39,300.00 Rp 157,200.00


JUMLAH HARGA BAHAN Rp 337,772.50
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 415,916.50
E Overhead & Proft ( 10 % ) 10% x D Rp 41,591.65
F Harga Satuan Pekerjaan (D+E) Rp 457,508.15

21 Pemasangan 1 M2 bekisting untuk Tangga


No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)
A TENAGA
Pekerja L.01 OH 0.660 Rp 67,900.00 Rp 44,814.00
Tukang Kayu L.02 OH 0.330 Rp 83,200.00 Rp 27,456.00
Kepala Tukang L.03 OH 0.033 Rp 88,000.00 Rp 2,904.00
Mandor L.04 OH 0.033 Rp 90,000.00 Rp 2,970.00
JUMLAH TENAGA KERJA Rp 78,144.00
B BAHAN
Kayu Kelas III M3 0.030 Rp 1,985,000.00 Rp 59,550.00
Paku 5 cm - 12 cm Kg 0.400 Rp 15,180.00 Rp 6,072.00
Minyak bekisting Liter 0.150 Rp 4,877.50 Rp 731.63
Balok kayu kelas II M3 0.015 Rp 2,085,000.00 Rp 31,275.00
Plywood tebal 9 mm Lbr 0.350 Rp 146,500.00 Rp 51,275.00
Dolken kayu 8 - 10 cm panjang 4 Batang 2.000 Rp 7,000.00 Rp 14,000.00
m
JUMLAH HARGA BAHAN Rp 162,903.63
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 241,047.63
E Overhead & Proft ( 10 % ) 10% x D Rp 24,104.76
F Harga Satuan Pekerjaan (D+E) Rp 265,152.39

22 Pemasangan 1 M2 jembatan Rangka Kayu untuk pengecoran beton


No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)
No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)
A TENAGA
Pekerja L.01 OH 0.150 Rp 67,900.00 Rp 10,185.00
Tukang Kayu L.02 OH 0.050 Rp 83,200.00 Rp 4,160.00
Kepala Tukang L.03 OH 0.005 Rp 88,000.00 Rp 440.00
Mandor L.04 OH 0.008 Rp 90,000.00 Rp 720.00
JUMLAH TENAGA KERJA Rp 15,505.00
B BAHAN
Kayu Kelas III ( papan ) M3 0.026 Rp 1,985,000.00 Rp 52,404.00
Paku 5 cm - 12 cm Kg 0.600 Rp 15,180.00 Rp 9,108.00
Dolken kayu 8 - 10 cm panjang 4 Batang 0.500 Rp 7,000.00 Rp 3,500.00
m
JUMLAH HARGA BAHAN Rp 65,012.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 80,517.00
E Overhead & Proft ( 10 % ) 10% x D Rp 8,051.70
F Harga Satuan Pekerjaan (D+E) Rp 88,568.70

23 Pemasangan 1 M3 pondasi beton bertulang Camp. 1 PC : 2 Psr : 3 Krk ( 150 Kg besi + bekisting )
No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)
A TENAGA
Pekerja L.01 OH 5.300 Rp 67,900.00 Rp 359,870.00
Tukang Batu L.02 OH 0.275 Rp 83,200.00 Rp 22,880.00
Tukang Kayu L.02 OH 1.300 Rp 83,200.00 Rp 108,160.00
Tukang Besi L.02 OH 1.050 Rp 83,200.00 Rp 87,360.00
Kepala Tukang L.03 OH 0.262 Rp 88,000.00 Rp 23,056.00
Mandor L.04 OH 0.265 Rp 90,000.00 Rp 23,850.00
JUMLAH TENAGA KERJA Rp 625,176.00
B BAHAN
Kayu Kelas III ( papan ) M3 0.200 Rp 1,985,000.00 Rp 397,000.00
Paku 5 cm - 12 cm Kg 1.500 Rp 15,180.00 Rp 22,770.00
Minyak Bekisting Liter 0.400 Rp 4,877.50 Rp 1,951.00
Besi Beton Polos Kg 157.500 Rp 10,300.00 Rp 1,622,250.00
Kawat Beton Kg 2.250 Rp 18,070.00 Rp 40,657.50
Semen Portland Kg 336.000 Rp 1,360.00 Rp 456,960.00
Pasir Beton M3 0.540 Rp 145,000.00 Rp 78,300.00
Kerikil M3 0.810 Rp 196,300.00 Rp 159,003.00
JUMLAH HARGA BAHAN Rp 2,778,891.50
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 3,404,067.50
E Overhead & Proft ( 10 % ) 10% x D Rp 340,406.75
F Harga Satuan Pekerjaan (D+E) Rp 3,744,474.25
24 Pemasangan 1 M3 pondasi beton Camp. 1 PC : 2 Psr : 3 Krk ( termasuk bekisting )

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)

A TENAGA
Pekerja L.01 OH 5.300 Rp 67,900.00 Rp 359,870.00
Tukang Batu L.02 OH 0.275 Rp 83,200.00 Rp 22,880.00
Tukang Kayu L.02 OH 1.300 Rp 83,200.00 Rp 108,160.00
Tukang Besi L.02 OH 1.050 Rp 83,200.00 Rp 87,360.00
Kepala Tukang L.03 OH 0.262 Rp 88,000.00 Rp 23,056.00
Mandor L.04 OH 0.265 Rp 90,000.00 Rp 23,850.00
JUMLAH TENAGA KERJA Rp 625,176.00
B BAHAN
Kayu Kelas III ( papan ) M3 0.200 Rp 1,985,000.00 Rp 397,000.00
Paku 5 cm - 12 cm Kg 1.500 Rp 15,180.00 Rp 22,770.00
Minyak Bekisting Liter 0.400 Rp 4,877.50 Rp 1,951.00
Semen Portland Kg 336.000 Rp 1,360.00 Rp 456,960.00
Pasir Beton M3 0.540 Rp 145,000.00 Rp 78,300.00
Kerikil M3 0.810 Rp 196,300.00 Rp 159,003.00
JUMLAH HARGA BAHAN Rp 1,115,984.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 1,741,160.00
E Overhead & Profit ( 10 % ) 10% x D Rp 174,116.00
F Harga Satuan Pekerjaan (D+E) Rp 1,915,276.00

25 Membuat 1 M3 sloof beton bertulang Camp. 1 PC : 2 Psr : 3 Krk ( 200 Kg besi + bekisting )
No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)
A TENAGA
Pekerja L.01 OH 5.650 Rp 67,900.00 Rp 383,635.00
Tukang Batu L.02 OH 0.275 Rp 83,200.00 Rp 22,880.00
Tukang Kayu L.02 OH 1.560 Rp 83,200.00 Rp 129,792.00
Tukang Besi L.02 OH 1.400 Rp 83,200.00 Rp 116,480.00
Kepala Tukang L.03 OH 0.323 Rp 88,000.00 Rp 28,424.00
Mandor L.04 OH 0.283 Rp 90,000.00 Rp 25,470.00
JUMLAH TENAGA KERJA Rp 706,681.00
B BAHAN
Kayu Kelas III ( papan ) M3 0.270 Rp 1,985,000.00 Rp 535,950.00
Paku 5 cm - 12 cm Kg 2.000 Rp 15,180.00 Rp 30,360.00
Minyak Bekisting Liter 0.600 Rp 4,877.50 Rp 2,926.50
Besi Beton Polos Kg 210.000 Rp 10,300.00 Rp 2,163,000.00
Kawat Beton Kg 3.000 Rp 18,070.00 Rp 54,210.00
Semen Portland Kg 336.000 Rp 1,360.00 Rp 456,960.00
Pasir Beton M3 0.540 Rp 145,000.00 Rp 78,300.00
Kerikil M3 0.810 Rp 196,300.00 Rp 159,003.00
JUMLAH HARGA BAHAN Rp 3,480,709.50
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 4,187,390.50
E Overhead & Proft ( 10 % ) 10% x D Rp 418,739.05
F Harga Satuan Pekerjaan (D+E) Rp 4,606,129.55

26 Membuat 1 M3 sloof beton bertulang Camp. 1 PC : 2 Psr : 3 Krk ( 150 Kg besi + bekisting )

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)

A TENAGA
Pekerja L.01 OH 5.650 Rp 67,900.00 Rp 383,635.00
Tukang Batu L.02 OH 0.275 Rp 83,200.00 Rp 22,880.00
Tukang Kayu L.02 OH 1.560 Rp 83,200.00 Rp 129,792.00
Tukang Besi L.02 OH 1.400 Rp 83,200.00 Rp 116,480.00
Kepala Tukang L.03 OH 0.323 Rp 88,000.00 Rp 28,424.00
Mandor L.04 OH 0.283 Rp 90,000.00 Rp 25,470.00
JUMLAH TENAGA KERJA Rp 706,681.00
B BAHAN
Kayu Kelas III ( papan ) M3 0.270 Rp 1,985,000.00 Rp 535,950.00
Paku 5 cm - 12 cm Kg 2.000 Rp 15,180.00 Rp 30,360.00
Minyak Bekisting Liter 0.600 Rp 4,877.50 Rp 2,926.50
Besi Beton Polos Kg 157.500 Rp 10,300.00 Rp 1,622,250.00
Kawat Beton Kg 2.250 Rp 18,070.00 Rp 40,657.50
Semen Portland Kg 336.000 Rp 1,360.00 Rp 456,960.00
Pasir Beton M3 0.540 Rp 145,000.00 Rp 78,300.00
Kerikil M3 0.810 Rp 196,300.00 Rp 159,003.00
JUMLAH HARGA BAHAN Rp 2,926,407.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 3,633,088.00
E Overhead & Proft ( 10 % ) 10% x D Rp 363,308.80
F Harga Satuan Pekerjaan (D+E) Rp 3,996,396.80
27 Membuat 1 M3 kolom beton bertulang Camp. 1 PC : 2 Psr : 3 Krk ( 200 Kg besi + bekisting )
No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)
A TENAGA
Pekerja L.01 OH 7.050 Rp 67,900.00 Rp 478,695.00
Tukang Batu L.02 OH 0.275 Rp 83,200.00 Rp 22,880.00
Tukang Kayu L.02 OH 1.650 Rp 83,200.00 Rp 137,280.00
Tukang Besi L.02 OH 2.100 Rp 83,200.00 Rp 174,720.00
Kepala Tukang L.03 OH 0.403 Rp 88,000.00 Rp 35,464.00
Mandor L.04 OH 0.353 Rp 90,000.00 Rp 31,770.00
JUMLAH TENAGA KERJA Rp 880,809.00
B BAHAN
Kayu Kelas III ( papan ) M3 0.400 Rp 1,985,000.00 Rp 794,000.00
Paku 5 cm - 12 cm Kg 4.000 Rp 15,180.00 Rp 60,720.00
Minyak Bekisting Liter 2.000 Rp 4,877.50 Rp 9,755.00
Besi Beton Polos Kg 210.000 Rp 10,300.00 Rp 2,163,000.00
Kawat Beton Kg 4.500 Rp 18,070.00 Rp 81,315.00
Semen Portland Kg 336.000 Rp 1,360.00 Rp 456,960.00
Pasir Beton M3 0.540 Rp 145,000.00 Rp 78,300.00
Kerikil M3 0.810 Rp 196,300.00 Rp 159,003.00
Kayu Kelas II Balok M3 0.150 Rp 2,085,000.00 Rp 312,750.00
Plywood 9 mm Lbr 3.500 Rp 146,500.00 Rp 512,750.00
Dolken Kayu Ø ( 8 cm - 10 cm ) Batang 20.000 Rp 7,000.00 Rp 140,000.00
panjang 4 meter
JUMLAH HARGA BAHAN Rp 4,768,553.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 5,649,362.00
E Overhead & Proft ( 10 % ) 10% x D Rp 564,936.20
F Harga Satuan Pekerjaan (D+E) Rp 6,214,298.20

28 Membuat 1 M3 kolom beton bertulang Camp. 1 PC : 2 Psr : 3 Krk ( 150 Kg besi + bekisting )

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)

A TENAGA
Pekerja L.01 OH 7.050 Rp 67,900.00 Rp 478,695.00
Tukang Batu L.02 OH 0.275 Rp 83,200.00 Rp 22,880.00
Tukang Kayu L.02 OH 1.650 Rp 83,200.00 Rp 137,280.00
Tukang Besi L.02 OH 2.100 Rp 83,200.00 Rp 174,720.00
Kepala Tukang L.03 OH 0.403 Rp 88,000.00 Rp 35,464.00
Mandor L.04 OH 0.353 Rp 90,000.00 Rp 31,770.00
JUMLAH TENAGA KERJA Rp 880,809.00
B BAHAN
Kayu Kelas III ( papan ) M3 0.400 Rp 1,985,000.00 Rp 794,000.00
Paku 5 cm - 12 cm Kg 4.000 Rp 15,180.00 Rp 60,720.00
Minyak Bekisting Liter 2.000 Rp 4,877.50 Rp 9,755.00
Besi Beton Polos Kg 157.500 Rp 10,300.00 Rp 1,622,250.00
Kawat Beton Kg 2.250 Rp 18,070.00 Rp 40,657.50
Semen Portland Kg 336.000 Rp 1,360.00 Rp 456,960.00
Pasir Beton M3 0.540 Rp 145,000.00 Rp 78,300.00
Kerikil M3 0.810 Rp 196,300.00 Rp 159,003.00
Kayu Kelas II Balok M3 0.150 Rp 2,085,000.00 Rp 312,750.00
Plywood 9 mm Lbr 3.500 Rp 146,500.00 Rp 512,750.00
Dolken Kayu Ø ( 8 cm - 10 cm ) Batang 20.000 Rp 7,000.00 Rp 140,000.00
panjang 4 meter
JUMLAH HARGA BAHAN Rp 4,187,145.50
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 5,067,954.50
E Overhead & Proft ( 10 % ) 10% x D Rp 506,795.45
F Harga Satuan Pekerjaan (D+E) Rp 5,574,749.95

29 Membuat 1 M3 balok beton bertulang Camp. 1 PC : 2 Psr : 3 Krk ( 200 Kg besi + bekisting )
No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)
A TENAGA
Pekerja L.01 OH 6.350 Rp 67,900.00 Rp 431,165.00
Tukang Batu L.02 OH 0.275 Rp 83,200.00 Rp 22,880.00
Tukang Kayu L.02 OH 1.650 Rp 83,200.00 Rp 137,280.00
Tukang Besi L.02 OH 1.400 Rp 83,200.00 Rp 116,480.00
Kepala Tukang L.03 OH 0.333 Rp 88,000.00 Rp 29,304.00
Mandor L.04 OH 0.318 Rp 90,000.00 Rp 28,620.00
JUMLAH TENAGA KERJA Rp 765,729.00
B BAHAN
Kayu Kelas III M3 0.320 Rp 1,985,000.00 Rp 635,200.00
Paku 5 cm - 12 cm Kg 3.200 Rp 15,180.00 Rp 48,576.00
Minyak Bekisting Liter 1.600 Rp 4,877.50 Rp 7,804.00
Besi Beton Polos Kg 210.000 Rp 10,300.00 Rp 2,163,000.00
Kawat Beton Kg 3.000 Rp 18,070.00 Rp 54,210.00
Semen Portland Kg 336.000 Rp 1,360.00 Rp 456,960.00
Pasir Beton M3 0.540 Rp 145,000.00 Rp 78,300.00
Kerikil M3 0.810 Rp 196,300.00 Rp 159,003.00
Kayu Kelas II Balok M3 0.140 Rp 2,085,000.00 Rp 291,900.00
Plywood 9 mm Lembar 2.800 Rp 146,500.00 Rp 410,200.00

Dolken Kayu Ø ( 8 cm - 10 cm ) Batang 16.000 Rp 7,000.00 Rp 112,000.00


panjang 4 meter
JUMLAH HARGA BAHAN Rp 4,417,153.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 5,182,882.00
E Overhead & Proft ( 10 % ) 10% x D Rp 518,288.20
F Harga Satuan Pekerjaan (D+E) Rp 5,701,170.20

30 Membuat 1 M3 balok beton bertulang Camp. 1 PC : 2 Psr : 3 Krk ( 150 Kg besi + bekisting )

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)

A TENAGA
Pekerja L.01 OH 6.350 Rp 67,900.00 Rp 431,165.00
Tukang Batu L.02 OH 0.275 Rp 83,200.00 Rp 22,880.00
Tukang Kayu L.02 OH 1.650 Rp 83,200.00 Rp 137,280.00
Tukang Besi L.02 OH 1.400 Rp 83,200.00 Rp 116,480.00
Kepala Tukang L.03 OH 0.333 Rp 88,000.00 Rp 29,304.00
Mandor L.04 OH 0.318 Rp 90,000.00 Rp 28,620.00
JUMLAH TENAGA KERJA Rp 765,729.00
B BAHAN
Kayu Kelas III M3 0.320 Rp 1,985,000.00 Rp 635,200.00
Paku 5 cm - 12 cm Kg 3.200 Rp 15,180.00 Rp 48,576.00
Minyak Bekisting Liter 1.600 Rp 4,877.50 Rp 7,804.00
Besi Beton Polos Kg 157.500 Rp 10,300.00 Rp 1,622,250.00
Kawat Beton Kg 2.250 Rp 18,070.00 Rp 40,657.50
Semen Portland Kg 336.000 Rp 1,360.00 Rp 456,960.00
Pasir Beton M3 0.540 Rp 145,000.00 Rp 78,300.00
Kerikil M3 0.810 Rp 196,300.00 Rp 159,003.00
Kayu Kelas II Balok M3 0.140 Rp 2,085,000.00 Rp 291,900.00
Plywood 9 mm Lembar 2.800 Rp 146,500.00 Rp 410,200.00
Dolken Kayu Ø ( 8 cm - 10 cm ) Batang 16.000 Rp 7,000.00 Rp 112,000.00
panjang 4 meter
JUMLAH HARGA BAHAN Rp 3,862,850.50
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 4,628,579.50
E Overhead & Proft ( 10 % ) 10% x D Rp 462,857.95
F Harga Satuan Pekerjaan (D+E) Rp 5,091,437.45

31 Membuat 1 M3 pelat beton bertulang Camp. 1 PC : 2 Psr : 3 Krk ( 150 kg besi + bekisting )
No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)
A TENAGA
Pekerja L.01 OH 5.300 Rp 67,900.00 Rp 359,870.00
Tukang Batu L.02 OH 0.275 Rp 83,200.00 Rp 22,880.00
Tukang Kayu L.02 OH 1.300 Rp 83,200.00 Rp 108,160.00
Tukang Besi L.02 OH 1.050 Rp 83,200.00 Rp 87,360.00
Kepala Tukang L.03 OH 0.265 Rp 88,000.00 Rp 23,320.00
Mandor L.04 OH 0.265 Rp 90,000.00 Rp 23,850.00
JUMLAH TENAGA KERJA Rp 625,440.00
B BAHAN
Kayu Kelas III M3 0.320 Rp 1,985,000.00 Rp 635,200.00
Paku 5 cm - 12 cm Kg 3.200 Rp 15,180.00 Rp 48,576.00
Minyak Bekisting Liter 1.600 Rp 4,877.50 Rp 7,804.00
Besi Beton Polos Kg 157.500 Rp 10,300.00 Rp 1,622,250.00
Kawat Beton Kg 2.250 Rp 18,070.00 Rp 40,657.50
Semen Portland Kg 336.000 Rp 1,360.00 Rp 456,960.00
Pasir Beton M3 0.540 Rp 145,000.00 Rp 78,300.00
Kerikil M3 0.810 Rp 196,300.00 Rp 159,003.00
Kayu Kelas II Balok M3 0.120 Rp 2,085,000.00 Rp 250,200.00
Plywood 9 mm Lembar 2.800 Rp 146,500.00 Rp 410,200.00

Dolken Kayu Ø ( 8 cm - 10 cm ) Batang 32.000 Rp 7,000.00 Rp 224,000.00


panjang 4 meter
JUMLAH HARGA BAHAN Rp 3,933,150.50
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 4,558,590.50
E Overhead & Proft ( 10 % ) 10% x D Rp 455,859.05
F Harga Satuan Pekerjaan (D+E) Rp 5,014,449.55

32 Membuat 1 M3 dinding beton bertulang Camp. 1 PC : 2 Psr : 3 Krk ( 150 kg besi + bekisting )
No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)
A TENAGA
Pekerja L.01 OH 5.300 Rp 67,900.00 Rp 359,870.00
Tukang Batu L.02 OH 0.275 Rp 83,200.00 Rp 22,880.00
Tukang Kayu L.02 OH 1.300 Rp 83,200.00 Rp 108,160.00
Tukang Besi L.02 OH 1.050 Rp 83,200.00 Rp 87,360.00
Kepala Tukang L.03 OH 0.262 Rp 88,000.00 Rp 23,056.00
Mandor L.04 OH 0.265 Rp 90,000.00 Rp 23,850.00
JUMLAH TENAGA KERJA Rp 625,176.00
B BAHAN
Kayu Kelas III M3 0.240 Rp 1,985,000.00 Rp 476,400.00
Paku 5 cm - 12 cm Kg 3.200 Rp 15,180.00 Rp 48,576.00
Minyak Bekisting Liter 1.600 Rp 4,877.50 Rp 7,804.00
Besi Beton Polos Kg 157.500 Rp 10,300.00 Rp 1,622,250.00
Kawat Beton Kg 2.250 Rp 18,070.00 Rp 40,657.50
Semen Portland Kg 336.000 Rp 1,360.00 Rp 456,960.00
Pasir Beton M3 0.540 Rp 145,000.00 Rp 78,300.00
Kerikil M3 0.810 Rp 196,300.00 Rp 159,003.00
Kayu Kelas II Balok M3 0.160 Rp 2,085,000.00 Rp 333,600.00
Plywood 9 mm Lembar 2.800 Rp 146,500.00 Rp 410,200.00

Dolken Kayu Ø ( 8 cm - 10 cm ) Batang 24.000 Rp 7,000.00 Rp 168,000.00


panjang 4 meter
JUMLAH HARGA BAHAN Rp 3,801,750.50
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 4,426,926.50
E Overhead & Proft ( 10 % ) 10% x D Rp 442,692.65
F Harga Satuan Pekerjaan (D+E) Rp 4,869,619.15

33 Membuat 1 M3 dinding beton bertulang Camp. 1 PC : 2 Psr : 3 Krk ( 200 kg besi + bekisting )
No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)
A TENAGA
Pekerja L.01 OH 5.650 Rp 67,900.00 Rp 383,635.00
Tukang Batu L.02 OH 0.275 Rp 83,200.00 Rp 22,880.00
Tukang Kayu L.02 OH 1.560 Rp 83,200.00 Rp 129,792.00
Tukang Besi L.02 OH 1.400 Rp 83,200.00 Rp 116,480.00
Kepala Tukang L.03 OH 0.323 Rp 88,000.00 Rp 28,424.00
Mandor L.04 OH 0.283 Rp 90,000.00 Rp 25,470.00
JUMLAH TENAGA KERJA Rp 706,681.00
B BAHAN
Kayu Kelas III M3 0.250 Rp 1,985,000.00 Rp 496,250.00
Paku 5 cm - 12 cm Kg 3.000 Rp 15,180.00 Rp 45,540.00
Minyak Bekisting Liter 1.200 Rp 4,877.50 Rp 5,853.00
Besi Beton Polos Kg 210.000 Rp 10,300.00 Rp 2,163,000.00
Kawat Beton Kg 3.000 Rp 18,070.00 Rp 54,210.00
Semen Portland Kg 336.000 Rp 1,360.00 Rp 456,960.00
Pasir Beton M3 0.540 Rp 145,000.00 Rp 78,300.00
Kerikil M3 0.810 Rp 196,300.00 Rp 159,003.00
Kayu Kelas II Balok M3 0.105 Rp 2,085,000.00 Rp 218,925.00
Plywood 9 mm Lembar 2.500 Rp 146,500.00 Rp 366,250.00
Dolken Kayu Ø ( 8 cm - 10 cm ) Rp 98,000.00
panjang 4 meter Batang 14.000 Rp 7,000.00

JUMLAH HARGA BAHAN Rp 4,142,291.00


C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 4,848,972.00
E Overhead & Proft ( 10 % ) 10% x D Rp 484,897.20
F Harga Satuan Pekerjaan (D+E) Rp 5,333,869.20

34 Membuat 1 M' kolom praktis beton bertulang Camp. 1 PC : 2 Psr : 3 Krk ( 11 cm x 11 cm )


No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)
A TENAGA
Pekerja L.01 OH 0.180 Rp 67,900.00 Rp 12,222.00
Tukang Batu L.02 OH 0.020 Rp 83,200.00 Rp 1,664.00
Tukang Kayu L.02 OH 0.020 Rp 83,200.00 Rp 1,664.00
Tukang Besi L.02 OH 0.020 Rp 83,200.00 Rp 1,664.00
Kepala Tukang L.03 OH 0.006 Rp 88,000.00 Rp 528.00
Mandor L.04 OH 0.009 Rp 90,000.00 Rp 810.00
JUMLAH TENAGA KERJA Rp 18,552.00
B BAHAN
Kayu Kelas III M3 0.002 Rp 1,985,000.00 Rp 3,970.00
Paku 5 cm - 12 cm Kg 0.010 Rp 15,180.00 Rp 151.80
Minyak Bekisting Liter 1.500 Rp 4,877.50 Rp 7,316.25
Besi Beton Polos Kg 3.000 Rp 10,300.00 Rp 30,900.00
Kawat Beton Kg 0.450 Rp 18,070.00 Rp 8,131.50
Semen Portland Kg 4.000 Rp 1,360.00 Rp 5,440.00
Pasir Beton M3 0.006 Rp 145,000.00 Rp 870.00
Kerikil M3 0.009 Rp 196,300.00 Rp 1,766.70
JUMLAH HARGA BAHAN Rp 58,546.25
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 77,098.25
E Overhead & Proft ( 10 % ) 10% x D Rp 7,709.83
F Harga Satuan Pekerjaan (D+E) Rp 84,808.08

35 Membuat 1 M' ring balok beton bertulang Camp. 1 PC : 2 Psr : 3 Krk ( 10 cm x 15 cm )


No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)
A TENAGA
Pekerja L.01 OH 0.297 Rp 67,900.00 Rp 20,166.30
Tukang Batu L.02 OH 0.033 Rp 83,200.00 Rp 2,745.60
Tukang Kayu L.02 OH 0.033 Rp 83,200.00 Rp 2,745.60
Tukang Besi L.02 OH 0.033 Rp 83,200.00 Rp 2,745.60
Kepala Tukang L.03 OH 0.010 Rp 88,000.00 Rp 880.00
Mandor L.04 OH 0.015 Rp 90,000.00 Rp 1,350.00
JUMLAH TENAGA KERJA Rp 30,633.10
B BAHAN
Kayu Kelas III M3 0.003 Rp 1,985,000.00 Rp 5,955.00
Paku 5 cm - 12 cm Kg 0.020 Rp 15,180.00 Rp 303.60
Minyak Bekisting Liter 1.500 Rp 4,877.50 Rp 7,316.25
Besi Beton Polos Kg 3.600 Rp 10,300.00 Rp 37,080.00
Kawat Beton Kg 0.050 Rp 18,070.00 Rp 903.50
Semen Portland Kg 5.500 Rp 1,360.00 Rp 7,480.00
Pasir Beton M3 0.009 Rp 145,000.00 Rp 1,305.00
Kerikil M3 0.015 Rp 196,300.00 Rp 2,944.50
JUMLAH HARGA BAHAN Rp 63,287.85
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 93,920.95
E Overhead & Proft ( 10 % ) 10% x D Rp 9,392.10
F Harga Satuan Pekerjaan (D+E) Rp 103,313.05

36 Membuat 1 M3 Jalan Beton Mutu K.175

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)

A TENAGA
Pekerja L.01 OH 4.500 Rp 67,900.00 Rp 305,550.00
Tukang Batu L.02 OH 0.275 Rp 83,200.00 Rp 22,880.00
Tukang Kayu L.02 OH 0.260 Rp 83,200.00 Rp 21,632.00
Kepala Tukang L.04 OH 0.423 Rp 88,000.00 Rp 37,224.00
Mandor L.05 OH 0.580 Rp 90,000.00 Rp 52,200.00
JUMLAH TENAGA KERJA Rp 439,486.00
B BAHAN
Balok Kayu Kelas II Uk. 4/6 CM M3 0.019 2,085,000.00 Rp 40,032.00
Paku 5 Cm - 12 Cm KG 0.250 15,180.00 Rp 3,795.00
Papan Kayu Kelas II Uk. 2 x 20 CM M3 0.032 2,085,000.00 Rp 66,720.00
Semen Portland KG 326.000 Rp 1,360.00 Rp 443,360.00
Pasir Beton M3 0.543 Rp 145,000.00 Rp 78,735.00
Kerikil M3 0.762 Rp 196,300.00 Rp 149,580.60
Air LTR 215.000 Rp 50.00 Rp 10,750.00
JUMLAH HARGA BAHAN Rp 792,972.60
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 1,232,458.60
E Overhead & Profit ( 10 % ) 10% x D Rp 123,245.86
F Harga Satuan Pekerjaan (D+E) Rp 1,355,704.46

37 Membuat 1 M3 Dinding dan Lantai Drainase Beton Bertulang Mutu K-175 ( 60 Kg Besi )

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)

A TENAGA
Pekerja L.01 OH 5.300 Rp 67,900.00 Rp 359,870.00
Tukang Batu L.02 OH 0.275 Rp 83,200.00 Rp 22,880.00
Tukang Kayu L.02 OH 1.300 Rp 83,200.00 Rp 108,160.00
Tukang Besi L.02 OH 1.050 Rp 83,200.00 Rp 87,360.00
Kepala Tukang L.03 OH 0.262 Rp 88,000.00 Rp 23,056.00
Mandor L.04 OH 0.265 Rp 90,000.00 Rp 23,850.00
JUMLAH TENAGA KERJA Rp 625,176.00
B BAHAN
Kayu Kelas III M3 0.133 Rp 1,985,000.00 Rp 264,005.00
Paku 5 cm - 12 cm Kg 1.330 Rp 15,180.00 Rp 20,189.40
Minyak Bekisting Liter 1.200 Rp 4,877.50 Rp 5,853.00
Besi Beton Polos Kg 60.000 Rp 10,300.00 Rp 618,000.00
Kawat Beton Kg 1.000 Rp 18,070.00 Rp 18,070.00
Semen Portland Kg 326.000 Rp 1,360.00 Rp 443,360.00
Pasir Beton M3 0.543 Rp 145,000.00 Rp 78,735.00
Kerikil M3 0.762 Rp 196,300.00 Rp 149,580.60
Air Liter 215.000 Rp 50.00 Rp 10,750.00
Plywood 9 mm Lembar 0.800 Rp 146,500.00 Rp 117,200.00
Dolken Kayu Ø ( 8 cm - 10 cm )
Batang 8.000 Rp 7,000.00 Rp 56,000.00
panjang 4 meter
JUMLAH HARGA BAHAN Rp 1,781,743.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 2,406,919.00
E Overhead & Profit ( 10 % ) 10% x D Rp 240,691.90
F Harga Satuan Pekerjaan (D+E) Rp 2,647,610.90

38 Membuat 1 M3 Skor Drainase ( 160 Kg Besi + Bekisting ) Mutu K-175

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)

A TENAGA
Pekerja L.01 OH 5.300 Rp 67,900.00 Rp 359,870.00
Tukang Batu L.02 OH 0.275 Rp 83,200.00 Rp 22,880.00
Tukang Kayu L.02 OH 1.300 Rp 83,200.00 Rp 108,160.00
Tukang Besi L.02 OH 1.050 Rp 83,200.00 Rp 87,360.00
Kepala Tukang L.03 OH 0.262 Rp 88,000.00 Rp 23,056.00
Mandor L.04 OH 0.265 Rp 90,000.00 Rp 23,850.00
JUMLAH TENAGA KERJA Rp 625,176.00
B BAHAN
Kayu Kelas III M3 0.240 Rp 1,985,000.00 Rp 476,400.00
Paku 5 cm - 12 cm Kg 3.200 Rp 15,180.00 Rp 48,576.00
Besi Beton Polos Kg 160.00 Rp 10,300.00 Rp 1,648,000.00
Kawat Beton Kg 2.000 Rp 18,070.00 Rp 36,140.00
Semen Portland Kg 326.000 Rp 1,360.00 Rp 443,360.00
Pasir Beton M3 0.543 Rp 145,000.00 Rp 78,735.00
Kerikil M3 0.762 Rp 196,300.00 Rp 149,580.60
Air Liter 215.000 Rp 50.00 Rp 10,750.00
Plywood 9 mm Lembar 2.800 Rp 146,500.00 Rp 410,200.00
Dolken Kayu Ø ( 8 cm - 10 cm )
panjang 4 meter Batang 4.000 Rp 7,000.00 Rp 28,000.00
JUMLAH HARGA BAHAN Rp 3,329,741.60
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 3,954,917.60
E Overhead & Profit ( 10 % ) 10% x D Rp 395,491.76
F Harga Satuan Pekerjaan (D+E) Rp 4,350,409.36

39 Membuat Beton Camp. 1 PC : 3 Psr : 5 Krk


No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
Pekerja L.01 OH 1.650 Rp 67,900.00 Rp 112,035.00
Tukang Batu L.02 OH 0.250 Rp 83,200.00 Rp 20,800.00
Kepala Tukang L.02 OH 0.025 Rp 88,000.00 Rp 2,200.00
Mandor L.02 OH 0.080 Rp 90,000.00 Rp 7,200.00
JUMLAH TENAGA KERJA Rp 142,235.00
B BAHAN
Semen Portland Kg 218.000 Rp 1,360.00 Rp 296,480.00
Pasir Beton M3 0.520 Rp 145,000.00 Rp 75,400.00
Kerikil M3 0.870 Rp 196,300.00 Rp 170,781.00
JUMLAH HARGA BAHAN Rp 542,661.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 684,896.00
E Overhead & Proft ( 10 % ) 10% x D Rp 68,489.60
F Harga Satuan Pekerjaan (D+E) Rp 753,385.60
40 Membuat Beton Camp. 1 PC : 2 Psr : 3 Krk
No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga(Rp)
A TENAGA
Pekerja L.01 OH 2.000 Rp 67,900.00 Rp 135,800.00
Tukang Batu L.02 OH 0.350 Rp 83,200.00 Rp 29,120.00
Kepala Tukang L.02 OH 0.035 Rp 88,000.00 Rp 3,080.00
Mandor L.02 OH 1.000 Rp 90,000.00 Rp 90,000.00
JUMLAH TENAGA KERJA Rp 258,000.00
B BAHAN
Semen Portland Kg 336.000 Rp 1,360.00 Rp 456,960.00
Pasir Beton M3 0.540 Rp 145,000.00 Rp 78,300.00
Kerikil M3 0.810 Rp 196,300.00 Rp 159,003.00
JUMLAH HARGA BAHAN Rp 694,263.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 952,263.00
E Overhead & Proft ( 10 % ) 10% x D Rp 95,226.30
F Harga Satuan Pekerjaan (D+E) Rp 1,047,489.30
V. PEKERJAAN BESI DAN ALUMINIUM

1 Pengerjaan 10 cm pengelasan dengan las listrik


No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga(Rp)
A TENAGA
Pekerja L.01 OH 0.040 Rp 67,900.00 Rp 2,716.00
Tukang Besi Konstruksi L.03 OH 0.020 Rp 83,200.00 Rp 1,664.00
Kepala Tukang L.03 OH 0.002 Rp 88,000.00 Rp 176.00
Mandor L.04 OH 0.002 Rp 90,000.00 Rp 180.00
JUMLAH TENAGA KERJA Rp 4,736.00
B BAHAN
Kawat Las Listrik Kg 0.400 Rp 20,070.00 Rp 8,028.00
Solar Liter 0.300 Rp 8,700.00 Rp 2,610.00
Minyak Pelumas Liter 0.040 Rp 24,540.65 Rp 981.63
JUMLAH HARGA BAHAN Rp 11,619.63
C PERALATAN
Sewa Alat Mesin Las Jam 0.170 Rp 98,000.00 Rp 16,660.00
JUMLAH HARGA ALAT Rp 16,660.00

D Jumlah (A+B+C) Rp 33,015.63


E Overhead & Proft ( 10 % ) 10% x D Rp 3,301.56
F Harga Satuan Pekerjaan (D+E) Rp 36,317.19

2 Pemasangan 1 M2 Pintu Rolling Door Besi


No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga(Rp)
A TENAGA
Pekerja L.01 OH 1.200 Rp 67,900.00 Rp 81,480.00
Tukang Las Biasa L.03 OH 1.200 Rp 83,200.00 Rp 99,840.00
Kepala Tukang L.03 OH 0.120 Rp 88,000.00 Rp 10,560.00
Mandor L.04 OH 0.006 Rp 90,000.00 Rp 540.00
JUMLAH TENAGA KERJA Rp 192,420.00
B BAHAN
Pintu Gulung Besi M2 1.000 Rp 515,000.00 Rp 515,000.00
JUMLAH HARGA BAHAN Rp 515,000.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 707,420.00
E Overhead & Proft ( 10 % ) 10% x D Rp 70,742.00
F Harga Satuan Pekerjaan (D+E) Rp 778,162.00

3 Pemasangan 1 M2 Pintu Lipat Besi ( Folding Gate )


No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga(Rp)
A TENAGA
Pekerja L.01 OH 0.440 Rp 67,900.00 Rp 29,876.00
Tukang Las Biasa L.03 OH 0.440 Rp 83,200.00 Rp 36,608.00
Kepala Tukang L.03 OH 0.044 Rp 88,000.00 Rp 3,872.00
Mandor L.04 OH 0.022 Rp 90,000.00 Rp 1,980.00
JUMLAH TENAGA KERJA Rp 72,336.00
B BAHAN
Pintu Lipat Besi ( Folding Gate ) M2 1.000 Rp 665,000.00 Rp 665,000.00
JUMLAH HARGA BAHAN Rp 665,000.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 737,336.00
E Overhead & Proft ( 10 % ) 10% x D Rp 73,733.60
F Harga Satuan Pekerjaan (D+E) Rp 811,069.60

4 Pemasangan 1 M2 Terali Besi Strip ( 2 x 3 ) mm


No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga(Rp)
A TENAGA
Pekerja L.01 OH 1.670 Rp 67,900.00 Rp 113,393.00
Tukang Las L.03 OH 1.670 Rp 83,200.00 Rp 138,944.00
Kepala Tukang L.03 OH 0.167 Rp 88,000.00 Rp 14,696.00
Mandor L.04 OH 0.083 Rp 90,000.00 Rp 7,470.00
JUMLAH TENAGA KERJA Rp 274,503.00
B BAHAN
Besi Strip Kg 6.177 13,070.00 Rp 80,733.39
Pengelasan cm 27.080 3,631.72 Rp 98,346.95
JUMLAH HARGA BAHAN Rp 179,080.34
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 453,583.34
E Overhead & Proft ( 10 % ) 10% x D Rp 45,358.33
F Harga Satuan Pekerjaan (D+E) Rp 498,941.67

5 Pemasangan 1 M2 Jendela Nako & Tralis


No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga(Rp)
A TENAGA
Pekerja L.01 OH 0.200 Rp 67,900.00 Rp 13,580.00
Tukang L.03 OH 0.200 Rp 83,200.00 Rp 16,640.00
Kepala Tukang L.03 OH 0.020 Rp 88,000.00 Rp 1,760.00
Mandor L.04 OH 0.001 Rp 90,000.00 Rp 90.00
JUMLAH TENAGA KERJA Rp 32,070.00
B BAHAN
Jendela Nako (Rangka + Kaca 5 mm) M2 1.100 Rp 94,800.00 Rp 104,280.00
Paku Skrup ( 1 cm - 2,5 cm ) Buah 10.000 Rp 15,180.00 Rp 151,800.00
Besi Strip M 7.000 Rp 13,070.00 Rp 91,490.00
JUMLAH HARGA BAHAN Rp 347,570.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 379,640.00
E Overhead & Proft ( 10 % ) 10% x D Rp 37,964.00
F Harga Satuan Pekerjaan (D+E) Rp 417,604.00

6 Pemasangan 1 M Kusen Pintu Aluminium

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga(Rp)

A TENAGA
Pekerja L.01 OH 0.043 Rp 67,900.00 Rp 2,919.70
Tukang Khusus Aluminium L.03 OH 0.043 Rp 83,200.00 Rp 3,577.60
Kepala Tukang L.03 OH 0.0043 Rp 88,000.00 Rp 378.40
Mandor L.04 OH 0.0021 Rp 90,000.00 Rp 189.00
JUMLAH TENAGA KERJA Rp 7,064.70
B BAHAN
Profil Aluminium M2 1.100 Rp 24,375.00 Rp 26,812.50
Skrup Fixer Buah 2.000 Rp 350.00 Rp 700.00
Sealent Tube 0.060 Rp 12,350.00 Rp 741.00
JUMLAH HARGA BAHAN Rp 28,253.50
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 35,318.20
E Overhead & Proft ( 10 % ) 10% x D Rp 3,531.82
F Harga Satuan Pekerjaan (D+E) Rp 38,850.02

7 Pemasangan 1 M2 Venetions Blind dan Vertical Blinds

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga(Rp)

A TENAGA
Pekerja L.01 OH 0.350 Rp 67,900.00 Rp 23,765.00
Tukang L.03 OH 0.350 Rp 83,200.00 Rp 29,120.00
Kepala Tukang L.03 OH 0.035 Rp 88,000.00 Rp 3,080.00
Mandor L.04 OH 0.018 Rp 90,000.00 Rp 1,620.00
JUMLAH TENAGA KERJA Rp 57,585.00
B BAHAN
Venetions Blind dan Vertical Blinds
( Tirai ) M 1.000 Rp 97,650.00 Rp 97,650.00
JUMLAH HARGA BAHAN Rp 97,650.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 155,235.00
E Overhead & Proft ( 10 % ) 10% x D Rp 15,523.50
F Harga Satuan Pekerjaan (D+E) Rp 170,758.50
VI. PEKERJAAN PASANGAN DINDING

1 Pemasangan 1 M2 dinding bata merah 1 batu camp. 1PC:2PP


No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)
A TENAGA
Pekerja L.01 OH 0.600 Rp 67,900.00 Rp 40,740.00
Tukang Batu L.02 OH 0.200 Rp 83,200.00 Rp 16,640.00
Kepala Tukang L.03 OH 0.020 Rp 88,000.00 Rp 1,760.00
Mandor L.04 OH 0.030 Rp 90,000.00 Rp 2,700.00
JUMLAH TENAGA KERJA Rp 61,840.00
B BAHAN
Bata Merah Buah 140.000 Rp 550.00 Rp 77,000.00
Semen Protland Kg 43.500 Rp 1,360.00 Rp 59,160.00
Pasir Pasang M3 0.080 Rp 145,000.00 Rp 11,600.00
JUMLAH HARGA BAHAN Rp 147,760.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 209,600.00
E Overhead & Proft ( 10 % ) 10% x D Rp 20,960.00
F Harga Satuan Pekerjaan (D+E) Rp 230,560.00

2 Pemasangan 1 M2 dinding bata merah 1 batu camp. 1PC:3PP

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)

A TENAGA
Pekerja L.01 OH 0.600 Rp 67,900.00 Rp 40,740.00
Tukang Batu L.02 OH 0.200 Rp 83,200.00 Rp 16,640.00
Kepala Tukang L.03 OH 0.020 Rp 88,000.00 Rp 1,760.00
Mandor L.04 OH 0.030 Rp 90,000.00 Rp 2,700.00
JUMLAH TENAGA KERJA Rp 61,840.00
B BAHAN
Bata Merah Buah 140.000 Rp 550.00 Rp 77,000.00
Semen Protland Kg 32.950 Rp 1,360.00 Rp 44,812.00
Pasir Pasang M3 0.091 Rp 145,000.00 Rp 13,195.00
JUMLAH HARGA BAHAN Rp 135,007.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 196,847.00
E Overhead & Proft ( 10 % ) 10% x D Rp 19,684.70
F Harga Satuan Pekerjaan (D+E) Rp 216,531.70
3 Pemasangan 1 M2 dinding bata merah 1 batu camp. 1PC:4PP

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)

A TENAGA
Pekerja L.01 OH 0.600 Rp 67,900.00 Rp 40,740.00
Tukang Batu L.02 OH 0.200 Rp 83,200.00 Rp 16,640.00
Kepala Tukang L.03 OH 0.020 Rp 88,000.00 Rp 1,760.00
Mandor L.04 OH 0.030 Rp 90,000.00 Rp 2,700.00
JUMLAH TENAGA KERJA Rp 61,840.00
B BAHAN
Bata Merah Buah 140.000 Rp 550.00 Rp 77,000.00
Semen Protland Kg 26.550 Rp 1,360.00 Rp 36,108.00
Pasir Pasang M3 0.093 Rp 145,000.00 Rp 13,485.00
JUMLAH HARGA BAHAN Rp 126,593.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 188,433.00
E Overhead & Proft ( 10 % ) 10% x D Rp 18,843.30
F Harga Satuan Pekerjaan (D+E) Rp 207,276.30

4 Pemasangan 1 M2 dinding bata merah 1 batu camp. 1PC:5PP

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)

A TENAGA
Pekerja L.01 OH 0.600 Rp 67,900.00 Rp 40,740.00
Tukang Batu L.02 OH 0.200 Rp 83,200.00 Rp 16,640.00
Kepala Tukang L.03 OH 0.020 Rp 88,000.00 Rp 1,760.00
Mandor L.04 OH 0.030 Rp 90,000.00 Rp 2,700.00
JUMLAH TENAGA KERJA Rp 61,840.00
B BAHAN
Bata Merah Buah 140.000 Rp 550.00 Rp 77,000.00
Semen Protland Kg 22.200 Rp 1,360.00 Rp 30,192.00
Pasir Pasang M3 0.102 Rp 145,000.00 Rp 14,790.00
JUMLAH HARGA BAHAN Rp 121,982.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 183,822.00
E Overhead & Proft ( 10 % ) 10% x D Rp 18,382.20
F Harga Satuan Pekerjaan (D+E) Rp 202,204.20

5 Pemasangan 1 M2 dinding bata merah 1 batu camp. 1PC:6PP

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)

A TENAGA
Pekerja L.01 OH 0.600 Rp 67,900.00 Rp 40,740.00
Tukang Batu L.02 OH 0.200 Rp 83,200.00 Rp 16,640.00
Kepala Tukang L.03 OH 0.020 Rp 88,000.00 Rp 1,760.00
Mandor L.04 OH 0.030 Rp 90,000.00 Rp 2,700.00
JUMLAH TENAGA KERJA Rp 61,840.00
B BAHAN
Bata Merah Buah 140.000 Rp 550.00 Rp 77,000.00
Semen Protland Kg 18.500 Rp 1,360.00 Rp 25,160.00
Pasir Pasang M3 0.122 Rp 145,000.00 Rp 17,690.00
JUMLAH HARGA BAHAN Rp 119,850.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 181,690.00
E Overhead & Proft ( 10 % ) 10% x D Rp 18,169.00
F Harga Satuan Pekerjaan (D+E) Rp 199,859.00

6 Pemasangan 1 M2 dinding bata merah 1/2 batu camp. 1PC:2PP


No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)

A TENAGA
Pekerja L.01 OH 0.300 Rp 67,900.00 Rp 20,370.00
Tukang Batu L.02 OH 0.100 Rp 83,200.00 Rp 8,320.00
Kepala Tukang L.03 OH 0.010 Rp 88,000.00 Rp 880.00
Mandor L.04 OH 0.015 Rp 90,000.00 Rp 1,350.00
JUMLAH TENAGA KERJA Rp 30,920.00
B BAHAN
Bata Merah Buah 70.000 Rp 550.00 Rp 38,500.00
Semen Protland Kg 18.950 Rp 1,360.00 Rp 25,772.00
Pasir Pasang M3 0.038 Rp 145,000.00 Rp 5,510.00
JUMLAH HARGA BAHAN Rp 69,782.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 100,702.00
E Overhead & Proft ( 10 % ) 10% x D Rp 10,070.20
F Harga Satuan Pekerjaan (D+E) Rp 110,772.20

7 Pemasangan 1 M2 dinding bata merah 1/2 batu camp. 1PC:3PP

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)

A TENAGA
Pekerja L.01 OH 0.300 Rp 67,900.00 Rp 20,370.00
Tukang Batu L.02 OH 0.100 Rp 83,200.00 Rp 8,320.00
Kepala Tukang L.03 OH 0.010 Rp 88,000.00 Rp 880.00
Mandor L.04 OH 0.015 Rp 90,000.00 Rp 1,350.00
JUMLAH TENAGA KERJA Rp 30,920.00
B BAHAN
Bata Merah Buah 70.000 Rp 550.00 Rp 38,500.00
Semen Protland Kg 14.370 Rp 1,360.00 Rp 19,543.20
Pasir Pasang M3 0.040 Rp 145,000.00 Rp 5,800.00
JUMLAH HARGA BAHAN Rp 63,843.20
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 94,763.20
E Overhead & Proft ( 10 % ) 10% x D Rp 9,476.32
F Harga Satuan Pekerjaan (D+E) Rp 104,239.52

8 Pemasangan 1 M2 dinding bata merah 1/2 batu camp. 1PC:4PP

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)

A TENAGA
Pekerja L.01 OH 0.300 Rp 67,900.00 Rp 20,370.00
Tukang Batu L.02 OH 0.100 Rp 83,200.00 Rp 8,320.00
Kepala Tukang L.03 OH 0.010 Rp 88,000.00 Rp 880.00
Mandor L.04 OH 0.015 Rp 90,000.00 Rp 1,350.00
JUMLAH TENAGA KERJA Rp 30,920.00
B BAHAN
Bata Merah Buah 70.000 Rp 550.00 Rp 38,500.00
Semen Protland Kg 11.500 Rp 1,360.00 Rp 15,640.00
Pasir Pasang M3 0.043 Rp 145,000.00 Rp 6,235.00
JUMLAH HARGA BAHAN Rp 60,375.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 91,295.00
E Overhead & Proft ( 10 % ) 10% x D Rp 9,129.50
F Harga Satuan Pekerjaan (D+E) Rp 100,424.50
9 Pemasangan 1 M2 dinding bata merah 1/2 batu camp. 1PC:5PP

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)

A TENAGA
Pekerja L.01 OH 0.300 Rp 67,900.00 Rp 20,370.00
Tukang Batu L.02 OH 0.100 Rp 83,200.00 Rp 8,320.00
Kepala Tukang L.03 OH 0.010 Rp 88,000.00 Rp 880.00
Mandor L.04 OH 0.015 Rp 90,000.00 Rp 1,350.00
JUMLAH TENAGA KERJA Rp 30,920.00
B BAHAN
Bata Merah Buah 70.000 Rp 550.00 Rp 38,500.00
Semen Protland Kg 9.680 Rp 1,360.00 Rp 13,164.80
Pasir Pasang M3 0.045 Rp 145,000.00 Rp 6,525.00
JUMLAH HARGA BAHAN Rp 58,189.80
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 89,109.80
E Overhead & Proft ( 10 % ) 10% x D Rp 8,910.98
F Harga Satuan Pekerjaan (D+E) Rp 98,020.78

10 Pemasangan 1 M2 dinding bata merah 1/2 batu camp. 1PC:6PP

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)

A TENAGA
Pekerja L.01 OH 0.300 Rp 67,900.00 Rp 20,370.00
Tukang Batu L.02 OH 0.100 Rp 83,200.00 Rp 8,320.00
Kepala Tukang L.03 OH 0.010 Rp 88,000.00 Rp 880.00
Mandor L.04 OH 0.015 Rp 90,000.00 Rp 1,350.00
JUMLAH TENAGA KERJA Rp 30,920.00
B BAHAN
Bata Merah Buah 70.000 Rp 550.00 Rp 38,500.00
Semen Portland Kg 8.320 Rp 1,360.00 Rp 11,315.20
Pasir Pasang M3 0.049 Rp 145,000.00 Rp 7,105.00
JUMLAH HARGA BAHAN Rp 56,920.20
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 87,840.20
E Overhead & Proft ( 10 % ) 10% x D Rp 8,784.02
F Harga Satuan Pekerjaan (D+E) Rp 96,624.22
VII. PEKERJAAN PLESTERAN

1 Pemasangan 1 M2 Plesteran 1 PC : 1 PP Tebal 15 mm


No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)
A TENAGA
Pekerja L.01 OH 0.300 Rp 67,900.00 Rp 20,370.00
Tukang Batu L.03 OH 0.150 Rp 83,200.00 Rp 12,480.00
Kepala Tukang L.03 OH 0.015 Rp 88,000.00 Rp 1,320.00
Mandor L.04 OH 0.015 Rp 90,000.00 Rp 1,350.00
JUMLAH TENAGA KERJA Rp 35,520.00
B BAHAN
Portland Cement Kg 15.504 Rp 1,360.00 Rp 21,085.44
Pasir Pasang M3 0.016 Rp 145,000.00 Rp 2,320.00
JUMLAH HARGA BAHAN Rp 23,405.44
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 58,925.44
E Overhead & Proft ( 10 % ) 10% x D Rp 5,892.54
F Harga Satuan Pekerjaan (D+E) Rp 64,817.98

2 Pemasangan 1 M2 Plesteran 1 PC : 2 PP Tebal 15 mm


No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)
A TENAGA
Pekerja L.01 OH 0.300 Rp 67,900.00 Rp 20,370.00
Tukang Batu L.03 OH 0.150 Rp 83,200.00 Rp 12,480.00
Kepala Tukang L.03 OH 0.015 Rp 88,000.00 Rp 1,320.00
Mandor L.04 OH 0.015 Rp 90,000.00 Rp 1,350.00
JUMLAH TENAGA KERJA Rp 35,520.00
B BAHAN
Portland Cement Kg 10.224 Rp 1,360.00 Rp 13,904.64
Pasir Pasang M3 0.020 Rp 145,000.00 Rp 2,900.00
JUMLAH HARGA BAHAN Rp 16,804.64
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 52,324.64
E Overhead & Proft ( 10 % ) 10% x D Rp 5,232.46
F Harga Satuan Pekerjaan (D+E) Rp 57,557.10

3 Pemasangan 1 M2 Plesteran 1 PC : 3 PP Tebal 15 mm


No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)
A TENAGA
Pekerja L.01 OH 0.300 Rp 67,900.00 Rp 20,370.00
Tukang Batu L.03 OH 0.150 Rp 83,200.00 Rp 12,480.00
Kepala Tukang L.03 OH 0.015 Rp 88,000.00 Rp 1,320.00
Mandor L.04 OH 0.015 Rp 90,000.00 Rp 1,350.00
JUMLAH TENAGA KERJA Rp 35,520.00
B BAHAN
Portland Cement Kg 7.776 Rp 1,360.00 Rp 10,575.36
Pasir Pasang M3 0.023 Rp 145,000.00 Rp 3,335.00
JUMLAH HARGA BAHAN Rp 13,910.36
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 49,430.36
E Overhead & Proft ( 10 % ) 10% x D Rp 4,943.04
F Harga Satuan Pekerjaan (D+E) Rp 54,373.40

4 Pemasangan 1 M2 Plesteran 1 PC : 4 PP Tebal 15 mm


No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)
A TENAGA
Pekerja L.01 OH 0.300 Rp 67,900.00 Rp 20,370.00
Tukang Batu L.03 OH 0.150 Rp 83,200.00 Rp 12,480.00
Kepala Tukang L.03 OH 0.015 Rp 88,000.00 Rp 1,320.00
Mandor L.04 OH 0.015 Rp 90,000.00 Rp 1,350.00
JUMLAH TENAGA KERJA Rp 35,520.00
B BAHAN
Portland Cement Kg 6.240 Rp 1,360.00 Rp 8,486.40
Pasir Pasang M3 0.024 Rp 145,000.00 Rp 3,480.00
JUMLAH HARGA BAHAN Rp 11,966.40
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 47,486.40
E Overhead & Proft ( 10 % ) 10% x D Rp 4,748.64
F Harga Satuan Pekerjaan (D+E) Rp 52,235.04

5 Pemasangan 1 M2 Plesteran 1 PC : 5 PP Tebal 15 mm


No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)
A TENAGA
Pekerja L.01 OH 0.300 Rp 67,900.00 Rp 20,370.00
Tukang Batu L.03 OH 0.150 Rp 83,200.00 Rp 12,480.00
Kepala Tukang L.03 OH 0.015 Rp 88,000.00 Rp 1,320.00
Mandor L.04 OH 0.015 Rp 90,000.00 Rp 1,350.00
JUMLAH TENAGA KERJA Rp 35,520.00
B BAHAN
Portland Cement Kg 5.184 1,360.00 Rp 7,050.24
Pasir Pasang M3 0.026 145,000.00 Rp 3,770.00
JUMLAH HARGA BAHAN Rp 10,820.24
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 46,340.24
E Overhead & Proft ( 10 % ) 10% x D Rp 4,634.02
F Harga Satuan Pekerjaan (D+E) Rp 50,974.26
6 Pemasangan 1 M2 Plesteran 1 PC : 6 PP Tebal 15 mm
No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)
A TENAGA
Pekerja L.01 OH 0.300 Rp 67,900.00 Rp 20,370.00
Tukang Batu L.03 OH 0.150 Rp 83,200.00 Rp 12,480.00
Kepala Tukang L.03 OH 0.015 Rp 88,000.00 Rp 1,320.00
Mandor L.04 OH 0.015 Rp 90,000.00 Rp 1,350.00
JUMLAH TENAGA KERJA Rp 35,520.00
B BAHAN
Portland Cement Kg 4.416 1,360.00 Rp 6,005.76
Pasir Pasang M3 0.027 145,000.00 Rp 3,915.00
JUMLAH HARGA BAHAN Rp 9,920.76
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 45,440.76
E Overhead & Proft ( 10 % ) 10% x D Rp 4,544.08
F Harga Satuan Pekerjaan (D+E) Rp 49,984.84

7 Pemasangan 1 M2 Plesteran 1 PC : 7 PP Tebal 15 mm


No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)
A TENAGA
Pekerja L.01 OH 0.300 Rp 67,900.00 Rp 20,370.00
Tukang Batu L.03 OH 0.150 Rp 83,200.00 Rp 12,480.00
Kepala Tukang L.03 OH 0.015 Rp 88,000.00 Rp 1,320.00
Mandor L.04 OH 0.015 Rp 90,000.00 Rp 1,350.00
JUMLAH TENAGA KERJA Rp 35,520.00
B BAHAN
Portland Cement Kg 3.936 1,360.00 Rp 5,352.96
Pasir Pasang M3 0.028 145,000.00 Rp 4,060.00
JUMLAH HARGA BAHAN Rp 9,412.96
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 44,932.96
E Overhead & Proft ( 10 % ) 10% x D Rp 4,493.30
F Harga Satuan Pekerjaan (D+E) Rp 49,426.26

8 Pemasangan 1 M2 Plesteran 1 PC : 8 PP Tebal 15 mm


No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)
A TENAGA
Pekerja L.01 OH 0.300 Rp 67,900.00 Rp 20,370.00
Tukang Batu L.03 OH 0.150 Rp 83,200.00 Rp 12,480.00
Kepala Tukang L.03 OH 0.015 Rp 88,000.00 Rp 1,320.00
Mandor L.04 OH 0.015 Rp 90,000.00 Rp 1,350.00
JUMLAH TENAGA KERJA Rp 35,520.00
B BAHAN
Portland Cement Kg 3.456 1,360.00 Rp 4,700.16
Pasir Pasang M3 0.029 145,000.00 Rp 4,205.00
JUMLAH HARGA BAHAN Rp 8,905.16
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 44,425.16
E Overhead & Proft ( 10 % ) 10% x D Rp 4,442.52
F Harga Satuan Pekerjaan (D+E) Rp 48,867.68

9 Pemasangan 1 M2 Plesteran 1 PC : 1 PP Tebal 20 mm


No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)
A TENAGA
Pekerja L.01 OH 0.400 Rp 67,900.00 Rp 27,160.00
Tukang Batu L.03 OH 0.200 Rp 83,200.00 Rp 16,640.00
Kepala Tukang L.03 OH 0.020 Rp 88,000.00 Rp 1,760.00
Mandor L.04 OH 0.022 Rp 90,000.00 Rp 1,980.00
JUMLAH TENAGA KERJA Rp 47,540.00
B BAHAN
Portland Cement Kg 13.632 1,360.00 Rp 18,539.52
Pasir Pasang M3 0.027 145,000.00 Rp 3,915.00
JUMLAH HARGA BAHAN Rp 22,454.52
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 69,994.52
E Overhead & Proft ( 10 % ) 10% x D Rp 6,999.45
F Harga Satuan Pekerjaan (D+E) Rp 76,993.97

10 Pemasangan 1 M2 Plesteran 1 PC : 3 PP Tebal 20 mm


No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)
A TENAGA
Pekerja L.01 OH 0.260 Rp 67,900.00 Rp 17,654.00
Tukang Batu L.03 OH 0.200 Rp 83,200.00 Rp 16,640.00
Kepala Tukang L.03 OH 0.020 Rp 88,000.00 Rp 1,760.00
Mandor L.04 OH 0.013 Rp 90,000.00 Rp 1,170.00
JUMLAH TENAGA KERJA Rp 37,224.00
B BAHAN
Portland Cement Kg 10.368 1,360.00 Rp 14,100.48
Pasir Pasang M3 0.031 145,000.00 Rp 4,495.00
JUMLAH HARGA BAHAN Rp 18,595.48
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 55,819.48
E Overhead & Proft ( 10 % ) 10% x D Rp 5,581.95
F Harga Satuan Pekerjaan (D+E) Rp 61,401.43

11 Pemasangan 1 M2 Plesteran 1 PC : 4 PP Tebal 20 mm


No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)
A TENAGA
Pekerja L.01 OH 0.400 Rp 67,900.00 Rp 27,160.00
Tukang Batu L.03 OH 0.200 Rp 83,200.00 Rp 16,640.00
Kepala Tukang L.03 OH 0.020 Rp 88,000.00 Rp 1,760.00
Mandor L.04 OH 0.022 Rp 90,000.00 Rp 1,980.00
JUMLAH TENAGA KERJA Rp 47,540.00
B BAHAN
Portland Cement Kg 8.320 1,360.00 Rp 11,315.20
Pasir Pasang M3 0.032 145,000.00 Rp 4,640.00
JUMLAH HARGA BAHAN Rp 15,955.20
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 63,495.20
E Overhead & Proft ( 10 % ) 10% x D Rp 6,349.52
F Harga Satuan Pekerjaan (D+E) Rp 69,844.72

12 Pemasangan 1 M2 Plesteran 1 PC : 5 PP Tebal 20 mm


No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)
A TENAGA
Pekerja L.01 OH 0.400 Rp 67,900.00 Rp 27,160.00
Tukang Batu L.03 OH 0.200 Rp 83,200.00 Rp 16,640.00
Kepala Tukang L.03 OH 0.020 Rp 88,000.00 Rp 1,760.00
Mandor L.04 OH 0.022 Rp 90,000.00 Rp 1,980.00
JUMLAH TENAGA KERJA Rp 47,540.00
B BAHAN
Portland Cement Kg 6.912 1,360.00 Rp 9,400.32
Pasir Pasang M3 0.035 145,000.00 Rp 5,075.00
JUMLAH HARGA BAHAN Rp 14,475.32
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 62,015.32
E Overhead & Proft ( 10 % ) 10% x D Rp 6,201.53
F Harga Satuan Pekerjaan (D+E) Rp 68,216.85
13 Pemasangan 1 M2 Plesteran 1 PC : 6 PP Tebal 20 mm
No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)
A TENAGA
Pekerja L.01 OH 0.400 Rp 67,900.00 Rp 27,160.00
Tukang Batu L.03 OH 0.200 Rp 83,200.00 Rp 16,640.00
Kepala Tukang L.03 OH 0.020 Rp 88,000.00 Rp 1,760.00
Mandor L.04 OH 0.022 Rp 90,000.00 Rp 1,980.00
JUMLAH TENAGA KERJA Rp 47,540.00
B BAHAN
Portland Cement Kg 5.888 1,360.00 Rp 8,007.68
Pasir Pasang M3 0.036 145,000.00 Rp 5,220.00
JUMLAH HARGA BAHAN Rp 13,227.68
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 60,767.68
E Overhead & Proft ( 10 % ) 10% x D Rp 6,076.77
F Harga Satuan Pekerjaan (D+E) Rp 66,844.45

14 Pemasangan 1 M2 Berapen 1 PC : 5 PP Tebal 15 mm


No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)
A TENAGA
Pekerja L.01 OH 0.150 Rp 67,900.00 Rp 10,185.00
Tukang Batu L.03 OH 0.075 Rp 83,200.00 Rp 6,240.00
Kepala Tukang L.03 OH 0.008 Rp 88,000.00 Rp 704.00
Mandor L.04 OH 0.008 Rp 90,000.00 Rp 720.00
JUMLAH TENAGA KERJA Rp 17,849.00
B BAHAN
Portland Cement Kg 5.184 1,360.00 Rp 7,050.24
Pasir Pasang M3 0.026 145,000.00 Rp 3,770.00
JUMLAH HARGA BAHAN Rp 10,820.24
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 28,669.24
E Overhead & Proft ( 10 % ) 10% x D Rp 2,866.92
F Harga Satuan Pekerjaan (D+E) Rp 31,536.16

15 Pemasangan 1 M2 Plesteran Ciprat 1 PC : 2 PP


No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)
A TENAGA
Pekerja L.01 OH 0.300 Rp 67,900.00 Rp 20,370.00
Tukang Batu L.03 OH 0.100 Rp 83,200.00 Rp 8,320.00
Kepala Tukang L.03 OH 0.010 Rp 88,000.00 Rp 880.00
Mandor L.04 OH 0.015 Rp 90,000.00 Rp 1,350.00
JUMLAH TENAGA KERJA Rp 30,920.00
B BAHAN
Portland Cement Kg 4.320 1,360.00 Rp 5,875.20
Pasir Pasang M3 0.006 145,000.00 Rp 870.00
JUMLAH HARGA BAHAN Rp 6,745.20
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 37,665.20
E Overhead & Proft ( 10 % ) 10% x D Rp 3,766.52
F Harga Satuan Pekerjaan (D+E) Rp 41,431.72

16 Pemasangan 1 M2 Acian
No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)
A TENAGA
Pekerja L.01 OH 0.200 Rp 67,900.00 Rp 13,580.00
Tukang Batu L.03 OH 0.100 Rp 83,200.00 Rp 8,320.00
Kepala Tukang L.03 OH 0.010 Rp 88,000.00 Rp 880.00
Mandor L.04 OH 0.010 Rp 90,000.00 Rp 900.00
JUMLAH TENAGA KERJA Rp 23,680.00
B BAHAN
Portland Cement Kg 3.250 1,360.00 Rp 4,420.00
JUMLAH HARGA BAHAN Rp 4,420.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 28,100.00
E Overhead & Proft ( 10 % ) 10% x D Rp 2,810.00
F Harga Satuan Pekerjaan (D+E) Rp 30,910.00

17 Pemasangan 1 M2 Finishing Siar Pasangan Bata Merah

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)

A TENAGA
Pekerja L.01 OH 0.150 Rp 67,900.00 Rp 10,185.00
Tukang Batu L.03 OH 0.075 Rp 83,200.00 Rp 6,240.00
Kepala Tukang L.03 OH 0.008 Rp 88,000.00 Rp 704.00
Mandor L.04 OH 0.008 Rp 90,000.00 Rp 720.00
JUMLAH TENAGA KERJA Rp 17,849.00
B BAHAN
Portland Cement Kg 3.108 1,360.00 Rp 4,226.88
JUMLAH HARGA BAHAN Rp 4,226.88
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 22,075.88
E Overhead & Profit ( 10 % ) 10% x D Rp 2,207.59
F Harga Satuan Pekerjaan (D+E) Rp 24,283.47
VIII. PEKERJAAN PENUTUP LANTAI & PENUTUP DINDING

1 Pemasangan 1 m2 lantai ubin PC abu-abu ukuran 40x40

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)


A TENAGA
Pekerja L.01 OH 0.250 Rp 67,900.00 Rp 16,975.00
Tukang Batu L.02 OH 0.125 Rp 83,200.00 Rp 10,400.00
Kepala Tukang L.03 OH 0.013 Rp 88,000.00 Rp 1,144.00
Mandor L.04 OH 0.013 Rp 90,000.00 Rp 1,170.00
JUMLAH TENAGA KERJA Rp 29,689.00
B BAHAN
Ubin abu-abu Uk. 40 x 40 cm Buah 6.630 Rp 9,050.00 Rp 60,001.50
Semen portland Kg 9.800 Rp 1,360.00 Rp 13,328.00
Pasir Pasang M3 0.045 Rp 145,000.00 Rp 6,525.00
JUMLAH HARGA BAHAN Rp 79,854.50
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 109,543.50
E Overhead & Proft ( 10 % ) 10% x D Rp 10,954.35
F Harga Satuan Pekerjaan (D+E) Rp 120,497.85

2 Pemasangan 1 m2 lantai ubin PC abu-abu ukuran 30x30

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)

A TENAGA
Pekerja L.01 OH 0.250 Rp 67,900.00 Rp 16,975.00
Tukang Batu L.02 OH 0.125 Rp 83,200.00 Rp 10,400.00
Kepala Tukang L.03 OH 0.013 Rp 88,000.00 Rp 1,144.00
Mandor L.04 OH 0.013 Rp 90,000.00 Rp 1,170.00
JUMLAH TENAGA KERJA Rp 29,689.00
B BAHAN
Ubin abu-abu Uk. 30 x 30 cm Buah 11.870 4,550.00 Rp 54,008.50
Semen portland Kg 10.000 1,360.00 Rp 13,600.00
Pasir Pasang M 3
0.045 145,000.00 Rp 6,525.00
JUMLAH HARGA BAHAN Rp 74,133.50
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 103,822.50
E Overhead & Proft ( 10 % ) 10% x D Rp 10,382.25
F Harga Satuan Pekerjaan (D+E) Rp 114,204.75
3 Pemasangan 1 m2 lantai ubin PC abu-abu ukuran 20x20

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)

A TENAGA
Pekerja L.01 OH 0.270 Rp 67,900.00 Rp 18,333.00
Tukang Batu L.02 OH 0.135 Rp 83,200.00 Rp 11,232.00
Kepala Tukang L.03 OH 0.014 Rp 88,000.00 Rp 1,232.00
Mandor L.04 OH 0.014 Rp 90,000.00 Rp 1,260.00
JUMLAH TENAGA KERJA Rp 32,057.00
B BAHAN
Ubin abu-abu Uk. 20 x 20 cm Bh 26.500 Rp 2,250.00 Rp 59,625.00
Semen portland Kg 10.400 Rp 1,360.00 Rp 14,144.00
Pasir Pasang M3 0.045 Rp 145,000.00 Rp 6,525.00
JUMLAH HARGA BAHAN Rp 80,294.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 112,351.00
E Overhead & Proft ( 10 % ) 10% x D Rp 11,235.10
F Harga Satuan Pekerjaan (D+E) Rp 123,586.10

4 Pemasangan 1 M2 Lantai Homogenius Uk. 60/60

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)

A TENAGA
Pekerja L.01 OH 0.240 Rp 67,900.00 Rp 16,296.00
Tukang Batu L.02 OH 0.120 Rp 83,200.00 Rp 9,984.00
Kepala Tukang L.03 OH 0.012 Rp 88,000.00 Rp 1,056.00
Mandor L.04 OH 0.012 Rp 90,000.00 Rp 1,080.00
JUMLAH TENAGA KERJA Rp 28,416.00
B BAHAN
Homogenius Uk. 60 x 60 cm Bh 3.100 Rp 60,000.00 Rp 186,000.00
Semen portland Kg 9.600 Rp 1,360.00 Rp 13,056.00
Semen warna Kg 1.500 Rp 2,400.00 Rp 3,600.00
Pasir Pasang M3 0.045 Rp 145,000.00 Rp 6,525.00
JUMLAH HARGA BAHAN Rp 209,181.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 237,597.00
E Overhead & Proft ( 10 % ) 10% x D Rp 23,759.70
F Harga Satuan Pekerjaan (D+E) Rp 261,356.70

5 Pemasangan 1 M2 Lantai Homogenius Uk. 40/40

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)

A TENAGA
Pekerja L.01 OH 0.250 Rp 67,900.00 Rp 16,975.00
Tukang Batu L.02 OH 0.125 Rp 83,200.00 Rp 10,400.00
Kepala Tukang L.03 OH 0.013 Rp 88,000.00 Rp 1,144.00
Mandor L.04 OH 0.013 Rp 90,000.00 Rp 1,170.00
JUMLAH TENAGA KERJA Rp 29,689.00
B BAHAN
Homogenius Uk.40 x 40 cm Bh 6.630 Rp 31,900.00 Rp 211,497.00
Semen portland Kg 9.800 Rp 1,360.00 Rp 13,328.00
Semen warna Kg 1.300 Rp 2,400.00 Rp 3,120.00
Pasir Pasang M3 0.045 Rp 145,000.00 Rp 6,525.00
JUMLAH HARGA BAHAN Rp 234,470.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 264,159.00
E Overhead & Profit ( 10 % ) 10% x D Rp 26,415.90
F Harga Satuan Pekerjaan (D+E) Rp 290,574.90

6 Pemasangan 1 M2 Lantai Homogenius Uk. 30/30

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)


No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)

A TENAGA
Pekerja L.01 OH 0.260 Rp 67,900.00 Rp 17,654.00
Tukang Batu L.02 OH 0.130 Rp 83,200.00 Rp 10,816.00
Kepala Tukang L.03 OH 0.013 Rp 88,000.00 Rp 1,144.00
Mandor L.04 OH 0.013 Rp 90,000.00 Rp 1,170.00
JUMLAH TENAGA KERJA Rp 30,784.00
B BAHAN
Homogenius Uk. 30 x 30 cm Bh 11.870 Rp 15,700.00 Rp 186,359.00
Semen portland Kg 10.000 Rp 1,360.00 Rp 13,600.00
Semen warna Kg 1.500 Rp 2,400.00 Rp 3,600.00
Pasir Pasang M3 0.045 Rp 145,000.00 Rp 6,525.00
JUMLAH HARGA BAHAN Rp 210,084.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 240,868.00
E Overhead & Profit ( 10 % ) 10% x D Rp 24,086.80
F Harga Satuan Pekerjaan (D+E) Rp 264,954.80

7 Pemasangan 1 m2 lantai keramik warna ukuran 40x40

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)

A TENAGA
Pekerja L.01 OH 0.250 Rp 67,900.00 Rp 16,975.00
Tukang Batu L.02 OH 0.125 Rp 83,200.00 Rp 10,400.00
Kepala Tukang L.03 OH 0.013 Rp 88,000.00 Rp 1,144.00
Mandor L.04 OH 0.013 Rp 90,000.00 Rp 1,170.00
JUMLAH TENAGA KERJA Rp 29,689.00
B BAHAN
Keramik warna Uk.40 x 40 cm Bh 6.630 Rp 9,600.00 Rp 63,648.00
Semen portland Kg 9.800 Rp 1,360.00 Rp 13,328.00
Semen warna Kg 1.300 Rp 2,400.00 Rp 3,120.00
Pasir Pasang M3 0.045 Rp 145,000.00 Rp 6,525.00
JUMLAH HARGA BAHAN Rp 86,621.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 116,310.00
E Overhead & Proft ( 10 % ) 10% x D Rp 11,631.00
F Harga Satuan Pekerjaan (D+E) Rp 127,941.00

8 Pemasangan 1 m2 lantai keramik warna ukuran 30x30

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)

A TENAGA
Pekerja L.01 OH 0.260 Rp 67,900.00 Rp 17,654.00
Tukang Batu L.02 OH 0.130 Rp 83,200.00 Rp 10,816.00
Kepala Tukang L.03 OH 0.013 Rp 88,000.00 Rp 1,144.00
Mandor L.04 OH 0.013 Rp 90,000.00 Rp 1,170.00
JUMLAH TENAGA KERJA Rp 30,784.00
B BAHAN
Keramik warna Uk. 30 x 30 cm Buah 11.870 Rp 5,050.00 Rp 59,943.50
Semen portland Kg 10.000 Rp 1,360.00 Rp 13,600.00
Semen warna Kg 1.500 Rp 2,400.00 Rp 3,600.00
Pasir Pasang M3 0.045 Rp 145,000.00 Rp 6,525.00
JUMLAH HARGA BAHAN Rp 83,668.50
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 114,452.50
E Overhead & Proft ( 10 % ) 10% x D Rp 11,445.25
F Harga Satuan Pekerjaan (D+E) Rp 125,897.75

9 Pemasangan 1 m2 lantai keramik warna ukuran 20x20

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)


No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)

A TENAGA
Pekerja L.01 OH 0.270 Rp 67,900.00 Rp 18,333.00
Tukang Batu L.02 OH 0.135 Rp 83,200.00 Rp 11,232.00
Kepala Tukang L.03 OH 0.014 Rp 88,000.00 Rp 1,232.00
Mandor L.04 OH 0.014 Rp 90,000.00 Rp 1,260.00
JUMLAH TENAGA KERJA Rp 32,057.00
B BAHAN
Keramik warna Uk. 20 x 20 cm Buah 26.500 Rp 2,450.00 Rp 64,925.00
Semen portland Kg 10.400 Rp 1,360.00 Rp 14,144.00
Semen warna Kg 1.620 Rp 2,400.00 Rp 3,888.00
Pasir Pasang M3 0.045 Rp 145,000.00 Rp 6,525.00
JUMLAH HARGA BAHAN Rp 89,482.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 121,539.00
E Overhead & Proft ( 10 % ) 10% x D Rp 12,153.90
F Harga Satuan Pekerjaan (D+E) Rp 133,692.90

10 Pemasangan 1 m' plint keramik warna ukuran 10 x 20 cm

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)

A TENAGA
Pekerja L.01 OH 0.090 Rp 67,900.00 Rp 6,111.00
Tukang Batu L.02 OH 0.090 Rp 83,200.00 Rp 7,488.00
Kepala Tukang L.03 OH 0.009 Rp 88,000.00 Rp 792.00
Mandor L.04 OH 0.005 Rp 90,000.00 Rp 450.00
JUMLAH TENAGA KERJA Rp 14,841.00
B BAHAN
Plint Keramik Warna Uk. 10 x 20 cm Buah 5.300 Rp 1,400.00 Rp 7,420.00
Semen portland Kg 1.140 Rp 1,360.00 Rp 1,550.40
Semen warna Kg 0.100 Rp 2,400.00 Rp 240.00
Pasir Pasang M3 0.003 Rp 145,000.00 Rp 435.00
JUMLAH HARGA BAHAN Rp 9,645.40
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 24,486.40
E Overhead & Proft ( 10 % ) 10% x D Rp 2,448.64
F Harga Satuan Pekerjaan (D+E) Rp 26,935.04
11 Pemasangan 1 m' plint keramik warna ukuran 10 x 30 cm

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)

A TENAGA
Pekerja L.01 OH 0.090 Rp 67,900.00 Rp 6,111.00
Tukang Batu L.02 OH 0.090 Rp 83,200.00 Rp 7,488.00
Kepala Tukang L.03 OH 0.009 Rp 88,000.00 Rp 792.00
Mandor L.04 OH 0.005 Rp 90,000.00 Rp 450.00
JUMLAH TENAGA KERJA Rp 14,841.00
B BAHAN
Keramik warna Uk. 10 x 30 cm Buah 3.530 Rp 2,400.00 Rp 8,472.00
Semen portland Kg 1.140 Rp 1,360.00 Rp 1,550.40
Semen warna Kg 0.100 Rp 2,400.00 Rp 240.00
Pasir Pasang M3 0.003 Rp 145,000.00 Rp 435.00
JUMLAH HARGA BAHAN Rp 10,697.40
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 25,538.40
E Overhead & Proft ( 10 % ) 10% x D Rp 2,553.84
F Harga Satuan Pekerjaan (D+E) Rp 28,092.24

12 Pemasangan 1 m' plint keramik warna ukuran 10 x 40 cm

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)

A TENAGA
Pekerja L.01 OH 0.090 Rp 67,900.00 Rp 6,111.00
Tukang Batu L.02 OH 0.090 Rp 83,200.00 Rp 7,488.00
Kepala Tukang L.03 OH 0.009 Rp 88,000.00 Rp 792.00
Mandor L.04 OH 0.005 Rp 90,000.00 Rp 450.00
JUMLAH TENAGA KERJA Rp 14,841.00
B BAHAN
Keramik warna Uk. 10 x 40 cm Buah 2.650 Rp 3,250.00 Rp 8,612.50
Semen portland Kg 1.140 Rp 1,360.00 Rp 1,550.40
Semen warna Kg 0.100 Rp 2,400.00 Rp 240.00
Pasir Pasang M3 0.030 Rp 145,000.00 Rp 4,350.00
JUMLAH HARGA BAHAN Rp 14,752.90
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 29,593.90
E Overhead & Proft ( 10 % ) 10% x D Rp 2,959.39
F Harga Satuan Pekerjaan (D+E) Rp 32,553.29

13 Pemasangan 1 m' plin Homogenius Uk. 10/60

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)

A TENAGA
Pekerja L.01 OH 0.090 Rp 67,900.00 Rp 6,111.00
Tukang Batu L.02 OH 0.090 Rp 83,200.00 Rp 7,488.00
Kepala Tukang L.03 OH 0.009 Rp 88,000.00 Rp 792.00
Mandor L.04 OH 0.005 Rp 90,000.00 Rp 450.00
JUMLAH TENAGA KERJA Rp 14,841.00
B BAHAN
Homogenius Uk. 10 x 60 cm M1 1.700 Rp 12,050.00 Rp 20,485.00
Semen portland Kg 1.140 Rp 1,360.00 Rp 1,550.40
Semen warna Kg 0.100 Rp 2,400.00 Rp 240.00
Pasir Pasang M3 0.003 Rp 145,000.00 Rp 435.00
JUMLAH HARGA BAHAN Rp 22,710.40
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 37,551.40
E Overhead & Proft ( 10 % ) 10% x D Rp 3,755.14
F Harga Satuan Pekerjaan (D+E) Rp 41,306.54

14 Pemasangan 1 m' plint homogenius warna ukuran 10 x 40 cm

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)

A TENAGA
Pekerja L.01 OH 0.090 Rp 67,900.00 Rp 6,111.00
Tukang Batu L.02 OH 0.090 Rp 83,200.00 Rp 7,488.00
Kepala Tukang L.03 OH 0.009 Rp 88,000.00 Rp 792.00
Mandor L.04 OH 0.005 Rp 90,000.00 Rp 450.00
JUMLAH TENAGA KERJA Rp 14,841.00
B BAHAN
Homogenius Uk. 10 x 40 cm M1 1.700 Rp 11,150.00 Rp 18,955.00
Semen portland Kg 1.140 Rp 1,360.00 Rp 1,550.40
Semen warna Kg 0.100 Rp 2,400.00 Rp 240.00
Pasir Pasang M3 0.030 Rp 145,000.00 Rp 4,350.00
JUMLAH HARGA BAHAN Rp 25,095.40
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 39,936.40
E Overhead & Profit ( 10 % ) 10% x D Rp 3,993.64
F Harga Satuan Pekerjaan (D+E) Rp 43,930.04

15 Pemasangan 1 m2 dinding keramik warna 20x20 CM

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)

A TENAGA
Pekerja L.01 OH 0.270 Rp 67,900.00 Rp 18,333.00
Tukang Batu L.02 OH 0.130 Rp 83,200.00 Rp 10,816.00
Kepala Tukang L.03 OH 0.013 Rp 88,000.00 Rp 1,144.00
Mandor L.04 OH 0.014 Rp 90,000.00 Rp 1,260.00
JUMLAH TENAGA KERJA Rp 31,553.00
B BAHAN
Keramik warna Uk. 20 x 20 cm Buah 26.500 Rp 2,450.00 Rp 64,925.00
Semen portland Kg 9.300 Rp 1,360.00 Rp 12,648.00
Pasir pasang M3 0.018 Rp 145,000.00 Rp 2,610.00
Semen warna Kg 1.940 Rp 2,400.00 Rp 4,656.00
JUMLAH HARGA BAHAN Rp 84,839.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 116,392.00
E Overhead & Proft ( 10 % ) 10% x D Rp 11,639.20
F Harga Satuan Pekerjaan (D+E) Rp 128,031.20

16 Pemasangan 1 m2 Dinding Keramik ukuran 20x25

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)

A TENAGA
Pekerja L.01 OH 0.270 Rp 67,900.00 Rp 18,333.00
Tukang Batu L.02 OH 0.130 Rp 83,200.00 Rp 10,816.00
Kepala Tukang L.03 OH 0.013 Rp 88,000.00 Rp 1,144.00
Mandor L.04 OH 0.014 Rp 90,000.00 Rp 1,260.00
JUMLAH TENAGA KERJA Rp 31,553.00
B BAHAN
Keramik Uk. 20 x 25 cm Buah 21.500 Rp 2,850.00 Rp 61,275.00
Semen portland Kg 10.400 Rp 1,360.00 Rp 14,144.00
Semen warna Kg 1.620 Rp 2,400.00 Rp 3,888.00
Pasir Pasang M3 0.045 Rp 145,000.00 Rp 6,525.00
JUMLAH HARGA BAHAN Rp 85,832.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 117,385.00
E Overhead & Profit ( 10 % ) 10% x D Rp 11,738.50
F Harga Satuan Pekerjaan (D+E) Rp 129,123.50

17 Pemasangan 1 M2 Lantai Karpet

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)


A TENAGA
Pekerja L.01 OH 0.170 Rp 67,900.00 Rp 11,543.00
Tukang Kayu L.02 OH 0.170 Rp 83,200.00 Rp 14,144.00
Kepala Tukang L.03 OH 0.017 Rp 88,000.00 Rp 1,496.00
Mandor L.04 OH 0.009 Rp 90,000.00 Rp 810.00
JUMLAH TENAGA KERJA Rp 27,993.00
B BAHAN
Karpet M2 1.050 Rp 16,650.00 Rp 17,482.50
Lem Kg 0.350 Rp 2,850.00 Rp 997.50
JUMLAH HARGA BAHAN Rp 18,480.00
C PERALATAN
JUMLAH HARGA ALAT Rp 46,473.00
D Jumlah (A+B+C) Rp 4,647.30
E Overhead & Profit ( 10 % ) 10% x D Rp 51,120.30
F Harga Satuan Pekerjaan (D+E) Rp 51,120.30

18 Pemasangan 1 M2 Lantai Parquet

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)

A TENAGA
Pekerja L.01 OH 0.700 Rp 67,900.00 Rp 47,530.00
Tukang Kayu L.02 OH 0.350 Rp 83,200.00 Rp 29,120.00
Kepala Tukang L.03 OH 0.035 Rp 88,000.00 Rp 3,080.00
Mandor L.04 OH 0.035 Rp 90,000.00 Rp 3,150.00
JUMLAH TENAGA KERJA Rp 82,880.00
B BAHAN
Parquet M2 1.050 Rp 225,200.00 Rp 236,460.00
Lem Kg 0.600 Rp 2,850.00 Rp 1,710.00
JUMLAH HARGA BAHAN Rp 238,170.00
C PERALATAN
JUMLAH HARGA ALAT Rp 321,050.00
D Jumlah (A+B+C) Rp 32,105.00
E Overhead & Profit ( 10 % ) 10% x D Rp 353,155.00
F Harga Satuan Pekerjaan (D+E) Rp 353,155.00
19 Pemasangan 1 M2 Dinding Batu Tempel Uk. 20 X 20 CM

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)

A TENAGA
Pekerja L.01 OH 0.700 Rp 67,900.00 Rp 47,530.00
Tukang Batu L.02 OH 0.350 Rp 83,200.00 Rp 29,120.00
Kepala Tukang L.03 OH 0.035 Rp 88,000.00 Rp 3,080.00
Mandor L.04 OH 0.035 Rp 90,000.00 Rp 3,150.00
JUMLAH TENAGA KERJA Rp 82,880.00
B BAHAN
Batu Tempel Bh 26.500 Rp 5,100.00 Rp 135,150.00
Semen Portland Kg 11.750 Rp 1,360.00 Rp 15,980.00
Pasir Pasang M3 0.035 Rp 145,000.00 Rp 5,075.00
JUMLAH HARGA BAHAN Rp 156,205.00
C PERALATAN
JUMLAH HARGA ALAT Rp 239,085.00
D Jumlah (A+B+C) Rp 23,908.50
E Overhead & Profit ( 10 % ) 10% x D Rp 262,993.50
F Harga Satuan Pekerjaan (D+E) Rp 262,993.50

20 Pemasangan 1 M2 Dinding Batu Tempel Uk. 20 X 40 CM

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)

A TENAGA
Pekerja L.01 OH 0.700 Rp 67,900.00 Rp 47,530.00
Tukang Batu L.02 OH 0.350 Rp 83,200.00 Rp 29,120.00
Kepala Tukang L.03 OH 0.035 Rp 88,000.00 Rp 3,080.00
Mandor L.04 OH 0.035 Rp 90,000.00 Rp 3,150.00
JUMLAH TENAGA KERJA Rp 82,880.00
B BAHAN
Batu Tempel Bh 13.500 Rp 12,600.00 Rp 170,100.00
Semen Portland Kg 11.750 Rp 1,360.00 Rp 15,980.00
Pasir Pasang M3 0.035 Rp 145,000.00 Rp 5,075.00
JUMLAH HARGA BAHAN Rp 191,155.00
C PERALATAN
JUMLAH HARGA ALAT Rp 274,035.00
D Jumlah (A+B+C) Rp 27,403.50
E Overhead & Profit ( 10 % ) 10% x D Rp 301,438.50
F Harga Satuan Pekerjaan (D+E) Rp 301,438.50

21 Pemasangan 1 M2 Wallpaper Lebar 50 CM

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)

A TENAGA
Pekerja L.01 OH 0.350 Rp 67,900.00 Rp 23,765.00
Tukang Batu L.02 OH 0.175 Rp 83,200.00 Rp 14,560.00
Kepala Tukang L.03 OH 0.017 Rp 88,000.00 Rp 1,496.00
Mandor L.04 OH 0.002 Rp 90,000.00 Rp 180.00
JUMLAH TENAGA KERJA Rp 40,001.00
B BAHAN
Wallpaper M 2.200 Rp 65,000.00 Rp 143,000.00
Lem Kg 0.250 Rp 2,850.00 Rp 712.50
JUMLAH HARGA BAHAN Rp 143,712.50
C PERALATAN
JUMLAH HARGA ALAT Rp 183,713.50
D Jumlah (A+B+C) Rp 18,371.35
E Overhead & Profit ( 10 % ) 10% x D Rp 202,084.85
F Harga Satuan Pekerjaan (D+E) Rp 202,084.85

22 Pemasangan 1 M' Plint Kayu Tebal 2 CM Lebar 10 CM

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)

A TENAGA
Pekerja L.01 OH 0.120 Rp 67,900.00 Rp 8,148.00
Tukang Batu L.02 OH 0.120 Rp 83,200.00 Rp 9,984.00
Kepala Tukang L.03 OH 0.012 Rp 88,000.00 Rp 1,056.00
Mandor L.04 OH 0.006 Rp 90,000.00 Rp 540.00
JUMLAH TENAGA KERJA 19,728.000
B BAHAN
Papan Kayu Kelas 1 M3 0.003 Rp 6,585,000.00 Rp 19,755.00
Paku / Skrup 5 CM Kg 0.050 Rp 15,180.00 Rp 759.00
JUMLAH HARGA BAHAN Rp 20,514.00
C PERALATAN
JUMLAH HARGA ALAT Rp 40,242.00
D Jumlah (A+B+C) Rp 4,024.20
E Overhead & Profit ( 10 % ) 10% x D Rp 44,266.20
F Harga Satuan Pekerjaan (D+E) Rp 44,266.20
IX. PEKERJAAN PLAFOND

1 Pemasangan langit-langit tripleks ukuran (120x240) cm, tebal 4 MM


No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)
A TENAGA
Pekerja L.01 OH 0.100 Rp 67,900.00 Rp 6,790.00
Tukang Kayu L.02 OH 0.100 Rp 83,200.00 Rp 8,320.00
Kepala Tukang L.03 OH 0.010 Rp 88,000.00 Rp 880.00
Mandor L.04 OH 0.005 Rp 90,000.00 Rp 450.00
JUMLAH TENAGA KERJA Rp 16,440.00
B BAHAN
Tripleks Tebal 4 MM Lembar 0.375 Rp 66,500.00 Rp 24,937.50
Paku tripleks Kg 0.030 Rp 15,180.00 Rp 455.40
JUMLAH HARGA BAHAN Rp 25,392.90
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 41,832.90
E Overhead & Proft ( 10 % ) 10% x D Rp 4,183.29
F Harga Satuan Pekerjaan (D+E) Rp 46,016.19

2 Pemasangan langit-langit lambrisering kayu, tebal 9mm

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)

A TENAGA
Pekerja L.01 OH 0.800 Rp 67,900.00 Rp 54,320.00
Tukang Kayu L.02 OH 0.800 Rp 83,200.00 Rp 66,560.00
Kepala Tukang L.03 OH 0.080 Rp 88,000.00 Rp 7,040.00
Mandor L.04 OH 0.040 Rp 90,000.00 Rp 3,600.00
JUMLAH TENAGA KERJA Rp 131,520.00
B BAHAN
Kayu papan Kelas II M3 0.015 Rp 2,085,000.00 Rp 31,275.00
Paku tripleks Kg 0.010 Rp 15,180.00 Rp 151.80
JUMLAH HARGA BAHAN Rp 31,426.80
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 162,946.80
E Overhead & Proft ( 10 % ) 10% x D Rp 16,294.68
F Harga Satuan Pekerjaan (D+E) Rp 179,241.48

3 Pemasangan langit-langit gypsum board ukuran (120x240x9)mm, tebal 9 mm

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)

A TENAGA
Pekerja L.01 OH 0.100 Rp 67,900.00 Rp 6,790.00
Tukang Kayu L.02 OH 0.050 Rp 83,200.00 Rp 4,160.00
Kepala Tukang L.03 OH 0.005 Rp 88,000.00 Rp 440.00
Mandor L.04 OH 0.005 Rp 90,000.00 Rp 450.00
JUMLAH TENAGA KERJA Rp 11,840.00
B BAHAN
Gypsum board Lembar 0.364 Rp 86,500.00 Rp 31,486.00
Paku skrup Kg 0.110 Rp 40,180.00 Rp 4,419.80
JUMLAH HARGA BAHAN Rp 35,905.80
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 47,745.80
E Overhead & Proft ( 10 % ) 10% x D Rp 4,774.58
F Harga Satuan Pekerjaan (D+E) Rp 52,520.38

4 Pemasangan 1 M' list langit-langit kayu profil

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)

A TENAGA
Pekerja L.01 OH 0.050 Rp 67,900.00 Rp 3,395.00
Tukang Kayu L.02 OH 0.050 Rp 83,200.00 Rp 4,160.00
Kepala Tukang L.03 OH 0.005 Rp 88,000.00 Rp 440.00
Mandor L.04 OH 0.003 Rp 90,000.00 Rp 270.00
JUMLAH TENAGA KERJA Rp 8,265.00
B BAHAN
List kayu profil M 1.050 Rp 2,515.00 Rp 2,640.75
Paku Kg 0.010 Rp 15,180.00 Rp 151.80
JUMLAH HARGA BAHAN Rp 2,792.55
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 11,057.55
E Overhead & Proft ( 10 % ) 10% x D Rp 1,105.76
F Harga Satuan Pekerjaan (D+E) Rp 12,163.31

5 Pemasangan 1 M2 Piri - Piri

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)

A TENAGA
Pekerja L.01 OH 0.230 Rp 67,900.00 Rp 15,617.00
Tukang Kayu L.02 OH 0.670 Rp 83,200.00 Rp 55,744.00
Kepala Tukang L.03 OH 0.067 Rp 88,000.00 Rp 5,896.00
Mandor L.04 OH 0.012 Rp 90,000.00 Rp 1,080.00
JUMLAH TENAGA KERJA Rp 78,337.00
B BAHAN
Papan Piri - Piri ( Siap Ketam ) M3 0.020 Rp 2,285,000.00 Rp 45,700.00
Paku Kg 0.200 Rp 15,180.00 Rp 3,036.00
JUMLAH HARGA BAHAN Rp 48,736.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 127,073.00
E Overhead & Proft ( 10 % ) 10% x D Rp 12,707.30
F Harga Satuan Pekerjaan (D+E) Rp 139,780.30
XI. HARGA SATUAN PEKERJAAN KAYU

1 Pembuatan & Pemasangan 1 m3 Kusen Pintu dan Kusen Jendela, Kayu Kelas I
No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)
A TENAGA
Pekerja L.01 OH 7.000 Rp 67,900.00 Rp 475,300.00
Tukang Kayu L.02 OH 21.000 Rp 83,200.00 Rp 1,747,200.00
Kepala Tukang L.03 OH 2.100 Rp 88,000.00 Rp 184,800.00
Mandor L.04 OH 0.350 Rp 90,000.00 Rp 31,500.00
JUMLAH TENAGA KERJA Rp 2,438,800.00
B BAHAN
Balok Kayu Kelas I M3 1.100 Rp 6,585,000.00 Rp 7,243,500.00
Paku 10 cm Kg 1.250 Rp 15,180.00 Rp 18,975.00
Lem Kayu Kg 1.000 Rp 25,650.00 Rp 25,650.00
JUMLAH HARGA BAHAN Rp 7,288,125.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 9,726,925.00
E Overhead & Proft ( 10 % ) 10% x D Rp 972,692.50
F Harga Satuan Pekerjaan (D+E) Rp 10,699,617.50

2 Pembuatan & Pemasangan Kusen Kayu Kelas II

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)

A TENAGA
Pekerja L.01 OH 6.000 Rp 67,900.00 Rp 407,400.00
Tukang Kayu L.02 OH 18.000 Rp 83,200.00 Rp 1,497,600.00
Kepala Tukang L.03 OH 1.800 Rp 88,000.00 Rp 158,400.00
Mandor L.04 OH 0.300 Rp 90,000.00 Rp 27,000.00
JUMLAH TENAGA KERJA Rp 2,090,400.00
B BAHAN
Balok Kayu Kelas II M3 1.200 Rp 2,085,000.00 Rp 2,502,000.00
Paku 10 cm Kg 1.250 Rp 15,180.00 Rp 18,975.00
Lem Kayu Kg 1.000 25,650.00 Rp 25,650.00
JUMLAH HARGA BAHAN Rp 2,546,625.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 4,637,025.00
E Overhead & Proft ( 10 % ) 10% x D Rp 463,702.50
F Harga Satuan Pekerjaan (D+E) Rp 5,100,727.50
3 Pembuatan dan Pemasangan 1 M2 Pintu Klamp Standar, Kayu Kelas II

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)

A TENAGA
Pekerja L.01 OH 0.350 Rp 67,900.00 Rp 23,765.000
Tukang Kayu L.02 OH 1.050 Rp 83,200.00 Rp 87,360.000
Kepala Tukang L.03 OH 0.105 Rp 88,000.00 Rp 9,240.000
Mandor L.04 OH 0.018 Rp 90,000.00 Rp 1,620.000
JUMLAH TENAGA KERJA Rp 121,985.00
B BAHAN
Papan Kayu Kelas II M3 0.040 Rp 2,085,000.00 Rp 83,400.00
Paku 5-7 cm Kg 0.050 Rp 15,180.00 Rp 759.00
JUMLAH HARGA BAHAN Rp 84,159.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 206,144.00
E Overhead & Proft ( 10 % ) 10% x D Rp 20,614.40
F Harga Satuan Pekerjaan (D+E) Rp 226,758.40

4 Pembuatan & Pemasangan 1 M2 Pintu Klamp Sederhana, Kayu Klam Kelas III

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)

A TENAGA
Pekerja L.01 OH 0.350 Rp 67,900.00 Rp 23,765.000
Tukang Kayu L.02 OH 1.050 Rp 83,200.00 Rp 87,360.000
Kepala Tukang L.03 OH 0.105 Rp 88,000.00 Rp 9,240.000
Mandor L.04 OH 0.018 Rp 90,000.00 Rp 1,620.000
JUMLAH TENAGA KERJA Rp 121,985.00
B BAHAN
Papan Kayu Kayu Kelas III M3 0.040 Rp 1,985,000.00 Rp 79,400.00
Paku 5 - 7 cm Kg 0.050 Rp 15,180.00 Rp 759.00
JUMLAH HARGA BAHAN Rp 80,159.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 202,144.00
E Overhead & Proft ( 10 % ) 10% x D Rp 20,214.40
F Harga Satuan Pekerjaan (D+E) Rp 222,358.40

5 Pembuatan & Pemasangan 1 M2 Daun Pintu Panel, Kayu Kelas I

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)

A TENAGA
Pekerja L.01 OH 1.000 Rp 67,900.00 Rp 67,900.00
Tukang Kayu L.02 OH 3.000 Rp 83,200.00 Rp 249,600.00
Kepala Tukang L.03 OH 0.300 Rp 88,000.00 Rp 26,400.00
Mandor L.04 OH 0.050 Rp 90,000.00 Rp 4,500.00
JUMLAH TENAGA KERJA Rp 348,400.00
B BAHAN
Papan Kayu Kelas I M3 0.040 Rp 6,585,000.00 Rp 263,400.00
Lem Kayu Kg 0.500 Rp 25,650.00 Rp 12,825.00
JUMLAH HARGA BAHAN Rp 276,225.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 624,625.00
E Overhead & Proft ( 10 % ) 10% x D Rp 62,462.50
F Harga Satuan Pekerjaan (D+E) Rp 687,087.50

6 Pembuatan & Pemasangan 1M2 Pintu/Jendela Kaca Kayu Kelas II

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)

A TENAGA
Pekerja L.01 OH 0.800 Rp 67,900.00 Rp 54,320.000
Tukang Kayu L.02 OH 2.400 Rp 83,200.00 Rp 199,680.000
Kepala Tukang L.03 OH 0.240 Rp 88,000.00 Rp 21,120.000
Mandor L.04 OH 0.040 Rp 90,000.00 Rp 3,600.000
JUMLAH TENAGA KERJA Rp 278,720.00
B BAHAN
Papan Kayu Kelas II M3 0.024 Rp 2,085,000.00 Rp 50,040.00
Kaca Tebal 3 MM M2 1.000 Rp 82,300.00 Rp 82,300.00
Lem Kayu Kg 0.300 Rp 25,650.00 Rp 7,695.00
JUMLAH HARGA BAHAN Rp 140,035.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 418,755.00
E Overhead & Proft ( 10 % ) 10% x D Rp 41,875.50
F Harga Satuan Pekerjaan (D+E) Rp 460,630.50
7 Pembuatan & Pemasangan 1 M2 Jalusi Pintu/Jendela Kayu Kelas II

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)

A TENAGA
Pekerja L.01 OH 1.000 Rp 67,900.00 Rp 67,900.00
Tukang Kayu L.02 OH 3.000 Rp 83,200.00 Rp 249,600.00
Kepala Tukang L.03 OH 0.300 Rp 88,000.00 Rp 26,400.00
Mandor L.04 OH 0.050 Rp 90,000.00 Rp 4,500.00
JUMLAH TENAGA KERJA Rp 348,400.00
B BAHAN
Papan Kayu Kelas II M3 0.064 Rp 2,085,000.00 Rp 133,440.00
Lem Kayu Kg 0.500 Rp 25,650.00 Rp 12,825.00
JUMLAH HARGA BAHAN Rp 146,265.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 494,665.00
E Overhead & Proft ( 10 % ) 10% x D Rp 49,466.50
F Harga Satuan Pekerjaan (D+E) Rp 544,131.50

8 Pembuatan 1 M2 Daun Pintu Plywood Rangkap, Rangka Kayu Kelas II Tertutup ( Lebar sampai 90 cm )

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)

A TENAGA
Pekerja L.01 OH 0.700 Rp 67,900.00 Rp 47,530.000
Tukang Kayu L.02 OH 2.100 Rp 83,200.00 Rp 174,720.000
Kepala Tukang L.03 OH 0.210 Rp 88,000.00 Rp 18,480.000
Mandor L.04 OH 0.035 Rp 90,000.00 Rp 3,150.000
JUMLAH TENAGA KERJA Rp 243,880.00
B BAHAN
Papan Kayu Kelas II M3 0.025 Rp 2,085,000.00 Rp 52,125.00
Paku 1 cm - 2,5cm Kg 0.030 Rp 15,180.00 Rp 455.40
Lem Kayu Kg 0.500 Rp 25,650.00 Rp 12,825.00
Plywood tebal 4 mm Ukuran Lembar 1.000 Rp 66,500.00 Rp 66,500.00
JUMLAH HARGA BAHAN Rp 131,905.40
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 375,785.40
E Overhead & Proft ( 10 % ) 10% x D Rp 37,578.54
F Harga Satuan Pekerjaan (D+E) Rp 413,363.94

9 Pembuatan & Pemasangan 1M2 Jalusi Kusen Kayu kelas II

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)

A TENAGA
Pekerja L.01 OH 0.670 Rp 67,900.00 Rp 45,493.000
Tukang Kayu L.02 OH 2.000 Rp 83,200.00 Rp 166,400.000
Kepala Tukang L.03 OH 0.200 Rp 88,000.00 Rp 17,600.000
Mandor L.04 OH 0.335 Rp 90,000.00 Rp 30,150.000
JUMLAH TENAGA KERJA Rp 259,643.00
B BAHAN
Papan Kayu Kelas II M3 0.060 Rp 2,085,000.00 Rp 125,100.00
Paku 1 cm - 2,5cm Kg 0.150 Rp 15,180.00 Rp 2,277.00
JUMLAH HARGA BAHAN Rp 127,377.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 387,020.00
E Overhead & Proft ( 10 % ) 10% x D Rp 38,702.00
F Harga Satuan Pekerjaan (D+E) Rp 425,722.00
10 Pembuatan & Pemasangan 1 M2 Teakwood Rangka Ekspos Kayu Kelas I

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)

A TENAGA
Pekerja L.01 OH 0.800 Rp 67,900.00 Rp 54,320.000
Tukang Kayu L.02 OH 2.400 Rp 83,200.00 Rp 199,680.000
Kepala Tukang L.03 OH 0.240 Rp 88,000.00 Rp 21,120.000
Mandor L.04 OH 0.040 Rp 90,000.00 Rp 3,600.000
JUMLAH TENAGA KERJA Rp 278,720.00
B BAHAN
Papan Kayu Kelas I M3 0.025 Rp 6,585,000.00 Rp 164,625.00
Paku 1 cm - 2,5cm Kg 0.030 Rp 15,180.00 Rp 455.40
Lem Kayu Kg 0.300 Rp 25,650.00 Rp 7,695.00
Teakwood 3,60 mm Lembar 1.000 Rp 151,500.00 Rp 151,500.00
JUMLAH HARGA BAHAN Rp 324,275.40
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 602,995.40
E Overhead & Proft ( 10 % ) 10% x D Rp 60,299.54
F Harga Satuan Pekerjaan (D+E) Rp 663,294.94

11 Pemasangan 1M3 Kuda-kuda Konvensional Kayu Kelas II

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)

A TENAGA
Pekerja L.01 OH 4.000 Rp 67,900.00 Rp 271,600.00
Tukang Kayu L.02 OH 12.000 Rp 83,200.00 Rp 998,400.00
Kepala Tukang L.03 OH 1.200 Rp 88,000.00 Rp 105,600.00
Mandor L.04 OH 0.200 Rp 90,000.00 Rp 18,000.00
JUMLAH TENAGA KERJA Rp 1,393,600.00
B BAHAN
Balok Kayu Kelas II M3 1.100 Rp 2,085,000.00 Rp 2,293,500.00
Besi strip tebal 5mm Kg 15.000 Rp 13,070.00 Rp 196,050.00
Paku 12 cm Kg 5.600 Rp 15,180.00 Rp 85,008.00
JUMLAH HARGA BAHAN Rp 2,574,558.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 3,968,158.00
E Overhead & Proft ( 10 % ) 10% x D Rp 396,815.80
F Harga Satuan Pekerjaan (D+E) Rp 4,364,973.80
12 Pemasangan 1 M3 Konstruksi Gordeng, Kayu Kelas II

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)

A TENAGA
Pekerja L.01 OH 6.700 Rp 67,900.00 Rp 454,930.000
Tukang Kayu L.02 OH 20.100 Rp 83,200.00 Rp 1,672,320.000
Kepala Tukang L.03 OH 2.010 Rp 88,000.00 Rp 176,880.000
Mandor L.04 OH 0.335 Rp 90,000.00 Rp 30,150.000
JUMLAH TENAGA KERJA Rp 2,334,280.000
B BAHAN
Balok Kayu Kelas II M3 1.100 Rp 2,085,000.00 Rp 2,293,500.00
Besi strip tebal 5mm Kg 15.000 Rp 13,070.00 Rp 196,050.00
Paku 12 cm Kg 3.000 Rp 15,180.00 Rp 45,540.00
JUMLAH HARGA BAHAN Rp 2,535,090.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 4,869,370.00
E Overhead & Proft ( 10 % ) 10% x D Rp 486,937.00
F Harga Satuan Pekerjaan (D+E) Rp 5,356,307.00

13 Pemasangan 1 M2 Rangka Langit-langit 60x60 Kayu Kelas II

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)

A TENAGA
Pekerja L.01 OH 0.200 Rp 67,900.00 Rp 13,580.000
Tukang Kayu L.02 OH 0.300 Rp 83,200.00 Rp 24,960.000
Kepala Tukang L.03 OH 0.030 Rp 88,000.00 Rp 2,640.000
Mandor L.04 OH 0.010 Rp 90,000.00 Rp 900.000
JUMLAH TENAGA KERJA Rp 42,080.00
B BAHAN
Balok Kayu 4 x 6 cm Kayu Kelas II M3 0.0163 Rp 2,085,000.00 Rp 33,985.50
Paku 7 – 10 cm Kg 0.250 Rp 15,180.00 Rp 3,795.00
JUMLAH HARGA BAHAN Rp 37,780.50
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 79,860.50
E Overhead & Proft ( 10 % ) 10% x D Rp 7,986.05
F Harga Satuan Pekerjaan (D+E) Rp 87,846.55

14 Pemasangan 1 M2 Rangka Dinding Pemisah ( 60 x 120 ) CM Kayu Kelas II

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)

A TENAGA
Pekerja L.01 OH 0.150 Rp 67,900.00 Rp 10,185.000
Tukang Kayu L.02 OH 0.450 Rp 83,200.00 Rp 37,440.000
Kepala Tukang L.03 OH 0.045 Rp 88,000.00 Rp 3,960.000
Mandor L.04 OH 0.008 Rp 90,000.00 Rp 720.000
JUMLAH TENAGA KERJA Rp 52,305.00
B BAHAN
Balok Kayu Kelas II M3 0.028 Rp 2,085,000.00 Rp 58,380.00
Paku 7 – 10 cm Kg 0.150 Rp 2,250.00 Rp 337.50
JUMLAH HARGA BAHAN Rp 58,717.50
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 111,022.50
E Overhead & Proft ( 10 % ) 10% x D Rp 11,102.25
F Harga Satuan Pekerjaan (D+E) Rp 122,124.75
15 Pemasangan 1 M2 Dinding Pemisah Plywood Rangkap Rangka Kayu Kelas II

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)

A TENAGA
Pekerja L.01 OH 0.200 Rp 67,900.00 Rp 13,580.000
Tukang Kayu L.03 OH 0.600 Rp 83,200.00 Rp 49,920.000
Kepala Tukang L.03 OH 0.060 Rp 88,000.00 Rp 5,280.000
Mandor L.04 OH 0.010 Rp 90,000.00 Rp 900.000
JUMLAH TENAGA KERJA Rp 69,680.00
B BAHAN
Balok Kayu Kelas II M3 0.028 Rp 2,085,000.00 Rp 58,380.00
Paku 7 – 10 cm Kg 0.150 Rp 15,180.00 Rp 2,277.00
Plywood 4 MM, 120 x 240 Lembar 0.860 Rp 66,500.00 Rp 57,190.00
Lem Kayu Kg 0.560 Rp 25,650.00 Rp 14,364.00
JUMLAH HARGA BAHAN Rp 132,211.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 201,891.00
E Overhead & Proft ( 10 % ) 10% x D Rp 20,189.10
F Harga Satuan Pekerjaan (D+E) Rp 222,080.10

16 Pemasangan 1 M' Listplank Ukuran ( 3x20 ) cm , Kayu Kelas II

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)

A TENAGA
Pekerja L.01 OH 0.100 Rp 67,900.00 Rp 6,790.000
Tukang Kayu L.02 OH 0.200 Rp 83,200.00 Rp 16,640.000
Kepala Tukang L.03 OH 0.020 Rp 88,000.00 Rp 1,760.000
Mandor L.04 OH 0.005 Rp 90,000.00 Rp 450.000
JUMLAH TENAGA KERJA Rp 25,640.00
B BAHAN
Papan Kayu Kelas II M3 0.0108 Rp 2,085,000.00 Rp 22,518.00
Paku 5 dan 7 cm Kg 0.100 Rp 15,180.00 Rp 1,518.00
JUMLAH HARGA BAHAN Rp 24,036.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 49,676.00
E Overhead & Proft ( 10 % ) 10% x D Rp 4,967.60
F Harga Satuan Pekerjaan (D+E) Rp 54,643.60

17 Pemasangan 1 M' Listplank Ukuran ( 3x30 ) Kayu Kelas II

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)

A TENAGA
Pekerja L.01 OH 0.100 Rp 67,900.00 Rp 6,790.000
Tukang Kayu L.02 OH 0.200 Rp 83,200.00 Rp 16,640.000
Kepala Tukang L.03 OH 0.020 Rp 88,000.00 Rp 1,760.000
Mandor L.04 OH 0.005 Rp 90,000.00 Rp 450.000
JUMLAH TENAGA KERJA Rp 25,640.00
B BAHAN
Papan Kayu Kelas II M3 0.011 Rp 2,085,000.00 Rp 22,935.00
Paku 5 dan 7 cm Kg 0.050 Rp 15,180.00 Rp 759.00
JUMLAH HARGA BAHAN Rp 23,694.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 49,334.00
E Overhead & Proft ( 10 % ) 10% x D Rp 4,933.40
F Harga Satuan Pekerjaan (D+E) Rp 54,267.40
XII. PEKERJAAN KUNCI DAN KACA

1 Pemasangan 1 Buah Kunci Tanam Antik

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)

A TENAGA
Pekerja L.01 OH 0.060 Rp 67,900.00 Rp 4,074.00
Tukang Kayu L.02 OH 0.600 Rp 83,200.00 Rp 49,920.00
Kepala Tukang L.03 OH 0.060 Rp 88,000.00 Rp 5,280.00
Mandor L.04 OH 0.003 Rp 90,000.00 Rp 270.00
JUMLAH TENAGA KERJA Rp 59,544.00
B BAHAN
Kunci Tanam Antik Buah 1.000 Rp 200,200.00 Rp 200,200.00
JUMLAH HARGA BAHAN Rp 200,200.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 259,744.00
E Overhead & Proft ( 10 % ) 10% x D Rp 25,974.40
F Harga Satuan Pekerjaan (D+E) Rp 285,718.40

2 Pemasangan 1 Buah Kunci Tanam Biasa

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)

A TENAGA
Pekerja L.01 OH 0.010 Rp 67,900.00 Rp 679.00
Tukang Kayu L.02 OH 0.500 Rp 83,200.00 Rp 41,600.00
Kepala Tukang L.03 OH 0.050 Rp 88,000.00 Rp 4,400.00
Mandor L.04 OH 0.005 Rp 90,000.00 Rp 450.00
JUMLAH TENAGA KERJA Rp 47,129.00
B BAHAN
Kunci Tanam Biasa Bh 1.000 130,200.00 Rp 130,200.00
JUMLAH HARGA BAHAN Rp 130,200.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 177,329.00
E Overhead & Proft ( 10 % ) 10% x D Rp 17,732.90
F Harga Satuan Pekerjaan (D+E) Rp 195,061.90

3 Pemasangan 1 Buah Kunci Tanam Kamar Mandi

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)

A TENAGA
Pekerja L.01 OH 0.005 Rp 67,900.00 Rp 339.50
Tukang Kayu L.02 OH 0.500 Rp 83,200.00 Rp 41,600.00
Kepala Tukang L.03 OH 0.050 Rp 88,000.00 Rp 4,400.00
Mandor L.04 OH 0.003 Rp 90,000.00 Rp 270.00
JUMLAH TENAGA KERJA Rp 46,609.50
B BAHAN
Kunci Tanam KM Bh 1.000 Rp 50,200.00 Rp 50,200.00
JUMLAH HARGA BAHAN Rp 50,200.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 96,809.50
E Overhead & Proft ( 10 % ) 10% x D Rp 9,680.95
F Harga Satuan Pekerjaan (D+E) Rp 106,490.45

4 Pemasangan 1 Buah Kunci Tanam Silinder

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)

A TENAGA
Pekerja L.01 OH 0.005 Rp 67,900.00 Rp 339.50
Tukang Kayu L.02 OH 0.500 Rp 83,200.00 Rp 41,600.00
Kepala Tukang L.03 OH 0.050 Rp 88,000.00 Rp 4,400.00
Mandor L.04 OH 0.003 Rp 90,000.00 Rp 270.00
JUMLAH TENAGA KERJA Rp 46,609.50
B BAHAN
Kunci Silinder Buah 1.000 50,200.00 Rp 50,200.00
JUMLAH HARGA BAHAN Rp 50,200.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 96,809.50
E Overhead & Proft ( 10 % ) 10% x D Rp 9,680.95
F Harga Satuan Pekerjaan (D+E) Rp 106,490.45

5 Pemasangan 1 Buah Engsel Pintu

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)

A TENAGA
Pekerja L.01 OH 0.015 Rp 67,900.00 Rp 1,018.50
Tukang Kayu L.02 OH 0.150 Rp 83,200.00 Rp 12,480.00
Kepala Tukang L.03 OH 0.015 Rp 88,000.00 Rp 1,320.00
Mandor L.04 OH 0.0008 Rp 90,000.00 Rp 72.00
JUMLAH TENAGA KERJA Rp 14,890.50
B BAHAN
Engsel pintu Buah 1.000 Rp 7,700.00 Rp 7,700.00
JUMLAH HARGA BAHAN Rp 7,700.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 22,590.50
E Overhead & Proft ( 10 % ) 10% x D Rp 2,259.05
F Harga Satuan Pekerjaan (D+E) Rp 24,849.55

6 Pemasangan 1 Buah Engsel jendela Kupu-kupu

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)

A TENAGA
Pekerja L.01 OH 0.010 Rp 67,900.00 Rp 679.00
Tukang Kayu L.02 OH 0.100 Rp 83,200.00 Rp 8,320.00
Kepala Tukang L.03 OH 0.010 Rp 88,000.00 Rp 880.00
Mandor L.04 OH 0.0005 Rp 90,000.00 Rp 45.00
JUMLAH TENAGA KERJA Rp 9,924.00
B BAHAN
Engsel kupu-kupu Buah 1.000 Rp 5,200.00 Rp 5,200.00
JUMLAH HARGA BAHAN Rp 5,200.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 15,124.00
E Overhead & Proft ( 10 % ) 10% x D Rp 1,512.40
F Harga Satuan Pekerjaan (D+E) Rp 16,636.40

7 Pemasangan 1 Buah Kait Angin

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)

A TENAGA
Pekerja L.01 OH 0.015 Rp 67,900.00 Rp 1,018.50
Tukang Kayu L.02 OH 0.150 Rp 83,200.00 Rp 12,480.00
Kepala Tukang L.03 OH 0.015 Rp 88,000.00 Rp 1,320.00
Mandor L.04 OH 0.008 Rp 90,000.00 Rp 720.00
JUMLAH TENAGA KERJA Rp 15,538.50
B BAHAN
Kait angin Buah 1.000 Rp 6,700.00 Rp 6,700.00
JUMLAH HARGA BAHAN Rp 6,700.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 22,238.50
E Overhead & Proft ( 10 % ) 10% x D Rp 2,223.85
F Harga Satuan Pekerjaan (D+E) Rp 24,462.35

8 Pemasangan 1 Buah Handle Jendela

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)


No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)

A TENAGA
Pekerja L.01 OH 0.015 Rp 67,900.00 Rp 1,018.50
Tukang Kayu L.02 OH 0.150 Rp 83,200.00 Rp 12,480.00
Kepala Tukang L.03 OH 0.015 Rp 88,000.00 Rp 1,320.00
Mandor L.04 OH 0.008 Rp 90,000.00 Rp 720.00
JUMLAH TENAGA KERJA Rp 15,538.50
B BAHAN
Handle Jendela Buah 1.000 Rp 7,700.00 Rp 7,700.00
JUMLAH HARGA BAHAN Rp 7,700.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 23,238.50
E Overhead & Profit ( 10 % ) 10% x D Rp 2,323.85
F Harga Satuan Pekerjaan (D+E) Rp 25,562.35

9 Pemasangan 1 Buah Grendel Jendela

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)

A TENAGA
Pekerja L.01 OH 0.020 Rp 67,900.00 Rp 1,358.00
Tukang Kayu L.02 OH 0.200 Rp 83,200.00 Rp 16,640.00
Kepala Tukang L.03 OH 0.020 Rp 88,000.00 Rp 1,760.00
Mandor L.04 OH 0.001 Rp 90,000.00 Rp 90.00
JUMLAH TENAGA KERJA Rp 19,848.00
B BAHAN
Grendel Jendela Buah 1.000 Rp 8,700.00 Rp 8,700.00
JUMLAH HARGA BAHAN Rp 8,700.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 28,548.00
E Overhead & Profit ( 10 % ) 10% x D Rp 2,854.80
F Harga Satuan Pekerjaan (D+E) Rp 31,402.80

10 Pemasangan 1 Buah Doorcloser

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)

A TENAGA
Pekerja L.01 OH 0.050 Rp 67,900.00 Rp 3,395.00
Tukang Kayu L.02 OH 0.500 Rp 83,200.00 Rp 41,600.00
Kepala Tukang L.03 OH 0.050 Rp 88,000.00 Rp 4,400.00
Mandor L.04 OH 0.003 Rp 90,000.00 Rp 270.00
JUMLAH TENAGA KERJA Rp 49,665.00
B BAHAN
Door Closer Buah 1.000 Rp 390,200.00 Rp 390,200.00
JUMLAH HARGA BAHAN Rp 390,200.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 439,865.00
E Overhead & Proft ( 10 % ) 10% x D Rp 43,986.50
F Harga Satuan Pekerjaan (D+E) Rp 483,851.50

11 Pemasangan 1 m2 Kaca Polos tebal 3mm

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)

A TENAGA
Pekerja L.01 OH 0.015 Rp 67,900.00 Rp 1,018.50
Tukang Kayu L.02 OH 0.150 Rp 83,200.00 Rp 12,480.00
Kepala Tukang L.03 OH 0.015 Rp 88,000.00 Rp 1,320.00
Mandor L.04 OH 0.0008 Rp 90,000.00 Rp 72.00
JUMLAH TENAGA KERJA Rp 14,890.50
B BAHAN
Kaca tebal 3mm m2 1.100 Rp 82,300.00 Rp 90,530.00
Sealant Kg 0.050 Rp 12,350.00 Rp 617.50
JUMLAH HARGA BAHAN Rp 91,147.50
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 106,038.00
E Overhead & Proft ( 10 % ) 10% x D Rp 10,603.80
F Harga Satuan Pekerjaan (D+E) Rp 116,641.80
12 Pemasangan 1 m2 Kaca Polos tebal 5mm

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)

A TENAGA
Pekerja L.01 OH 0.015 Rp 67,900.00 Rp 1,018.50
Tukang Kayu L.02 OH 0.150 Rp 83,200.00 Rp 12,480.00
Kepala Tukang L.03 OH 0.015 Rp 88,000.00 Rp 1,320.00
Mandor L.04 OH 0.0008 Rp 90,000.00 Rp 72.00
JUMLAH TENAGA KERJA Rp 14,890.50
B BAHAN
Kaca tebal 5 mm m2 1.100 Rp 92,800.00 Rp 102,080.00
Sealant Kg 0.050 Rp 12,350.00 Rp 617.50
JUMLAH HARGA BAHAN Rp 102,697.50
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 117,588.00
E Overhead & Proft ( 10 % ) 10% x D Rp 11,758.80
F Harga Satuan Pekerjaan (D+E) Rp 129,346.80

13 Pemasangan 1 m2 Kaca Polos tebal 8mm

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)

A TENAGA
Pekerja L.01 OH 0.017 Rp 67,900.00 Rp 1,154.30
Tukang Kayu L.02 OH 0.170 Rp 83,200.00 Rp 14,144.00
Kepala Tukang L.03 OH 0.017 Rp 88,000.00 Rp 1,496.00
Mandor L.04 OH 0.0009 Rp 90,000.00 Rp 81.00
JUMLAH TENAGA KERJA Rp 16,875.30
B BAHAN
Kaca tebal 8 mm m2 1.100 Rp 362,000.00 Rp 398,200.00
Sealant Kg 0.0009 Rp 12,350.00 Rp 11.12
JUMLAH HARGA BAHAN Rp 398,211.12
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 415,086.42
E Overhead & Proft ( 10 % ) 10% x D Rp 41,508.64
F Harga Satuan Pekerjaan (D+E) Rp 456,595.06
14 Pemasangan 1 m2 Kaca Polos tebal 12mm

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)

A TENAGA
Pekerja L.01 OH 0.025 Rp 67,900.00 Rp 1,697.50
Tukang Kayu L.02 OH 0.250 Rp 83,200.00 Rp 20,800.00
Kepala Tukang L.03 OH 0.025 Rp 88,000.00 Rp 2,200.00
Mandor L.04 OH 0.0013 Rp 90,000.00 Rp 117.00
JUMLAH TENAGA KERJA Rp 24,814.50
B BAHAN
Kaca tebal 12 mm m2 1.100 Rp 506,000.00 Rp 556,600.00
Sealant Kg 0.070 Rp 12,350.00 Rp 864.50
JUMLAH HARGA BAHAN Rp 557,464.50
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 582,279.00
E Overhead & Proft ( 10 % ) 10% x D Rp 58,227.90
F Harga Satuan Pekerjaan (D+E) Rp 640,506.90

15 Pemasangan 1 M2 Kaca Cermin Tebal 5 MM

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)

A TENAGA
Pekerja L.01 OH 0.015 Rp 67,900.00 Rp 1,018.50
Tukang Kayu L.02 OH 0.150 Rp 83,200.00 Rp 12,480.00
Kepala Tukang L.03 OH 0.015 Rp 88,000.00 Rp 1,320.00
Mandor L.04 OH 0.008 Rp 90,000.00 Rp 720.00
JUMLAH TENAGA KERJA Rp 15,538.50
B BAHAN
Kaca Cermin Tebal 5 MM m2 1.100 Rp 14,650.00 Rp 16,115.00
JUMLAH HARGA BAHAN Rp 16,115.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 31,653.50
E Overhead & Proft ( 10 % ) 10% x D Rp 3,165.35
F Harga Satuan Pekerjaan (D+E) Rp 34,818.85
XIII. PEKERJAAN PENGECATAN

1 Pengikisan/Pengerokan 1 m2 Permukaan Cat tembok Lama

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)

A TENAGA
Pekerja L.01 OH 0.150 Rp 67,900.00 Rp 10,185.00
Mandor L.04 OH 0.003 Rp 90,000.00 Rp 270.00
JUMLAH TENAGA KERJA Rp 10,455.00
B BAHAN
Soda api Kg 0.050 Rp 11,900.00 Rp 595.00
JUMLAH HARGA BAHAN Rp 595.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 11,050.00
E Overhead & Proft ( 10 % ) 10% x D Rp 1,105.00
F Harga Satuan Pekerjaan (D+E) Rp 12,155.00

2 Pencucian 1 m2 Bidang Permukaan Dinding Lama yang Pernah dicat

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)

A TENAGA
Pekerja L.01 OH 0.150 Rp 67,900.00 Rp 10,185.00
Mandor L.04 OH 0.003 Rp 90,000.00 Rp 270.00
JUMLAH TENAGA KERJA Rp 10,455.00
B BAHAN
Sabun Kg 0.050 Rp 31,000.00 Rp 1,550.00
JUMLAH HARGA BAHAN Rp 1,550.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 12,005.00
E Overhead & Proft ( 10 % ) 10% x D Rp 1,200.50
F Harga Satuan Pekerjaan (D+E) Rp 13,205.50
3 Pengecatan 1 M2 Bidang Kayu Baru ( 1 Lapis Plamir, 1 Lapis Cat Dasar dan 2 Lapis Cat Penutup )

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)

A TENAGA
Pekerja L.01 OH 0.070 Rp 67,900.00 Rp 4,753.00
Tukang Cat L. 02 OH 0.009 Rp 83,200.00 Rp 748.80
Kepala Tukang L.03 OH 0.006 Rp 88,000.00 Rp 528.00
Mandor L.04 OH 0.003 Rp 90,000.00 Rp 270.00
JUMLAH TENAGA KERJA Rp 6,299.80
B BAHAN
Cat menie Kg 0.200 Rp 30,300.00 Rp 6,060.00
Plamir Kg 0.150 Rp 27,500.00 Rp 4,125.00
Cat dasar Kg 0.170 Rp 30,300.00 Rp 5,151.00
Cat penutup Kg 0.260 Rp 58,300.00 Rp 15,158.00
Kuas Buah 0.010 Rp 17,375.00 Rp 173.75
Pengencer Kg 0.030 Rp 36,700.00 Rp 1,101.00
Ampelas Lbr 0.200 Rp 6,175.00 Rp 1,235.00
JUMLAH HARGA BAHAN Rp 33,003.75
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 39,303.55
E Overhead & Proft ( 10 % ) 10% x D Rp 3,930.36
F Harga Satuan Pekerjaan (D+E) Rp 43,233.91

4 Pengecatan 1 M2 Bidang Kayu Lama ( 2 Lapis Cat Penutup )

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)

A TENAGA
Pekerja L.01 OH 0.070 Rp 63,000.00 Rp 4,410.00
Tukang Cat L. 02 OH 0.009 Rp 75,000.00 Rp 675.00
Kepala Tukang L.03 OH 0.006 Rp 76,000.00 Rp 456.00
Mandor L.04 OH 0.003 Rp 81,000.00 Rp 243.00
JUMLAH TENAGA KERJA Rp 5,784.00
B BAHAN
Cat penutup Kg 0.260 Rp 58,300.00 Rp 15,158.00
Kuas Buah 0.010 Rp 17,375.00 Rp 173.75
Pengencer Kg 0.030 Rp 36,700.00 Rp 1,101.00
Ampelas Lbr 0.200 Rp 6,175.00 Rp 1,235.00
JUMLAH HARGA BAHAN Rp 17,667.75
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 23,451.75
E Overhead & Profit ( 10 % ) 10% x D Rp 2,345.18
F Harga Satuan Pekerjaan (D+E) Rp 25,796.93

5 Pengecatan 1 M2 Tembok Baru ( 1 Lapis Plamuur, 1 Lapis Cat Dasar dan 2 Lapis Cat Penutup )

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)

A TENAGA
Pekerja L.01 OH 0.020 Rp 67,900.00 Rp 1,358.00
Tukang Cat L.02 OH 0.063 Rp 83,200.00 Rp 5,241.60
Kepala Tukang L.03 OH 0.0063 Rp 88,000.00 Rp 554.40
Mandor L.04 OH 0.003 Rp 90,000.00 Rp 270.00
JUMLAH TENAGA KERJA Rp 7,424.00
B BAHAN
Plamuur Kg 0.200 Rp 27,500.00 Rp 5,500.00
Cat dasar Kg 0.150 Rp 8,300.00 Rp 1,245.00
Cat Penutup Kg 0.170 Rp 22,300.00 Rp 3,791.00
JUMLAH HARGA BAHAN Rp 10,536.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 17,960.00
E Overhead & Proft ( 10 % ) 10% x D Rp 1,796.00
F Harga Satuan Pekerjaan (D+E) Rp 19,756.00
6 Pengecatan 1 M2 Tembok Lama ( 1 Lapis Cat Dasar dan 2 Lapis Cat Penutup )

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)

A TENAGA
Pekerja L.01 OH 0.028 Rp 67,900.00 Rp 1,901.20
Tukang Cat L.02 OH 0.042 Rp 83,200.00 Rp 3,494.40
Kepala Tukang L.03 OH 0.0042 Rp 88,000.00 Rp 369.60
Mandor L.04 OH 0.003 Rp 90,000.00 Rp 270.00
JUMLAH TENAGA KERJA Rp 6,035.20
B BAHAN
Cat dasar Kg 0.120 Rp 8,300.00 Rp 996.00
Cat Penutup Kg 0.180 Rp 22,300.00 Rp 4,014.00
JUMLAH HARGA BAHAN Rp 5,010.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 11,045.20
E Overhead & Proft ( 10 % ) 10% x D Rp 1,104.52
F Harga Satuan Pekerjaan (D+E) Rp 12,149.72

7 Pelaburan 1 M2 Tembok Baru dengan Kapur Sirih

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)

A TENAGA
Pekerja L.01 OH 0.150 Rp 67,900.00 Rp 10,185.00
Tukang Cat L.02 OH 0.001 Rp 83,200.00 Rp 83.20
Kepala Tukang L.03 OH 0.0001 Rp 88,000.00 Rp 8.80
Mandor L.04 OH 0.0025 Rp 90,000.00 Rp 225.00
JUMLAH TENAGA KERJA Rp 10,502.00
B BAHAN
Kapur Sirih Kg 0.150 Rp 4,700.00 Rp 705.00
Ampelas Lbr 0.100 Rp 6,175.00 Rp 617.50
Alang - Alang Ikat 0.250 Rp 20,600.00 Rp 5,150.00
JUMLAH HARGA BAHAN Rp 6,472.50
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 16,974.50
E Overhead & Proft ( 10 % ) 10% x D Rp 1,697.45
F Harga Satuan Pekerjaan (D+E) Rp 18,671.95

8 Pelaburan 1 M2 Tembok Lama dengan Kapur Sirih ( Pemeliharaan )

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)

A TENAGA
Pekerja L.01 OH 0.040 Rp 67,900.00 Rp 2,716.00
Tukang Cat L.02 OH 0.005 Rp 83,200.00 Rp 416.00
Kepala Tukang L.03 OH 0.0005 Rp 88,000.00 Rp 44.00
Mandor L.04 OH 0.0025 Rp 90,000.00 Rp 225.00
JUMLAH TENAGA KERJA Rp 3,401.00
B BAHAN
Kapur Sirih Kg 0.300 Rp 4,700.00 Rp 1,410.00
Ampelas Lbr 0.200 Rp 6,175.00 Rp 1,235.00
Alang - Alang Ikat 0.250 Rp 20,600.00 Rp 5,150.00
JUMLAH HARGA BAHAN Rp 7,795.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 11,196.00
E Overhead & Proft ( 10 % ) 10% x D Rp 1,119.60
F Harga Satuan Pekerjaan (D+E) Rp 12,315.60
9 Pengecatan 1 M2 Permukaan Baja Dengan Menie Besi

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)

A TENAGA
Pekerja L.01 OH 0.020 Rp 67,900.00 Rp 1,358.00
Tukang Cat L. 02 OH 0.200 Rp 83,200.00 Rp 16,640.00
Kepala Tukang L.03 OH 0.020 Rp 88,000.00 Rp 1,760.00
Mandor L.04 OH 0.0025 Rp 90,000.00 Rp 225.00
JUMLAH TENAGA KERJA Rp 19,983.00
B BAHAN
Menie besi Kg 0.100 Rp 16,800.00 Rp 1,680.00
Kuas Buah 0.010 Rp 17,375.00 Rp 173.75
JUMLAH HARGA BAHAN Rp 1,853.75
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 21,836.75
E Overhead & Proft ( 10 % ) 10% x D Rp 2,183.68
F Harga Satuan Pekerjaan (D+E) Rp 24,020.43

10 Pengecatan 1 M2 Permukaan Baja Galvanis secara semprot Sistem 3 Lapis Cat Mutakhir

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)

A TENAGA
Pekerja L.01 OH 0.040 Rp 67,900.00 Rp 2,716.00
Tukang Cat L. 02 OH 0.700 Rp 83,200.00 Rp 58,240.00
Kepala Tukang L.03 OH 0.070 Rp 88,000.00 Rp 6,160.00
Mandor L.04 OH 0.020 Rp 90,000.00 Rp 1,800.00
JUMLAH TENAGA KERJA Rp 68,916.00
B BAHAN
Cat Dasar Kg 0.30 Rp 30,300.00 Rp 9,090.00
Pengencer Liter 0.01 Rp 36,700.00 Rp 367.00
JUMLAH HARGA BAHAN Rp 9,457.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 78,373.00
E Overhead & Proft ( 15 % ) 15% x D Rp 7,837.30
F Harga Satuan Pekerjaan (D+E) Rp 86,210.30
XIV. PEKERJAAN SANITASI DALAM GEDUNG

1 Pemasangan 1 Buah Closet Duduk ( Lengkap )

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)

A TENAGA
Pekerja L.01 OH 3.30 Rp 67,900.00 Rp 224,070.00
Tukang Batu L.02 OH 1.10 Rp 83,200.00 Rp 91,520.00
Kepala Tukang L.03 OH 0.01 Rp 88,000.00 Rp 880.00
Mandor L.04 OH 0.16 Rp 90,000.00 Rp 14,400.00
JUMLAH TENAGA KERJA Rp 330,870.00
B BAHAN
Closet duduk Unit 1.00 Rp 1,775,000.00 Rp 1,775,000.00
6%x
Perlengkapan LS Rp 106,500.00 Rp 106,500.00
Closet
JUMLAH HARGA BAHAN Rp 1,881,500.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 2,212,370.00
E Overhead & Proft ( 10 % ) 10% x D Rp 221,237.00
F Harga Satuan Pekerjaan (D+E) Rp 2,433,607.00

2 Pemasangan 1 Buah Closet Jongkok

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)

A TENAGA
Pekerja L.01 OH 1.00 Rp 67,900.00 Rp 67,900.00
Tukang Batu L.02 OH 1.50 Rp 83,200.00 Rp 124,800.00
Kepala Tukang L.03 OH 0.15 Rp 88,000.00 Rp 13,200.00
Mandor L.04 OH 0.16 Rp 90,000.00 Rp 14,400.00
JUMLAH TENAGA KERJA Rp 220,300.00
B BAHAN
Closet jongkok Unit 1.00 Rp 275,000.00 Rp 275,000.00
Semen Portland Kg 6.00 Rp 1,360.00 Rp 8,160.00
Pasir Pasang M3 0.01 Rp 145,000.00 Rp 1,450.00
JUMLAH HARGA BAHAN Rp 284,610.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 504,910.00
E Overhead & Profit ( 10 % ) 10% x D Rp 50,491.00
F Harga Satuan Pekerjaan (D+E) Rp 555,401.00
3 Pemasangan 1 Buah urinoir

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)

A TENAGA
Pekerja L.01 OH 1.000 Rp 67,900.00 Rp 67,900.00
Tukang Batu L.02 OH 1.000 Rp 83,200.00 Rp 83,200.00
Kepala Tukang L.03 OH 0.100 Rp 88,000.00 Rp 8,800.00
Mandor L.04 OH 0.050 Rp 90,000.00 Rp 4,500.00
JUMLAH TENAGA KERJA Rp 164,400.00
B BAHAN
Urinoir Unit 1.000 Rp 1,325,000.00 Rp 1,325,000.00
Semen Portland Kg 6.000 Rp 1,360.00 Rp 8,160.00
Pasir pasang M3 0.010 Rp 145,000.00 Rp 1,450.00
Perlengkapan % 30.000 Rp 400,383.00 Rp 400,383.00
JUMLAH HARGA BAHAN Rp 1,734,993.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 1,899,393.00
E Overhead & Proft ( 10 % ) 10% x D Rp 189,939.30
F Harga Satuan Pekerjaan (D+E) Rp 2,089,332.30

4 Pemasangan 1 Buah Wastafel

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)

A TENAGA
Pekerja L.01 OH 1.200 Rp 67,900.00 Rp 81,480.00
Tukang Batu L.02 OH 1.450 Rp 83,200.00 Rp 120,640.00
Kepala Tukang L.03 OH 0.150 Rp 88,000.00 Rp 13,200.00
Mandor L.04 OH 0.060 Rp 90,000.00 Rp 5,400.00
JUMLAH TENAGA KERJA Rp 220,720.00
B BAHAN
Wastafel Unit 1.200 Rp 475,000.00 Rp 570,000.00
Semen Portland Kg 6.000 Rp 1,360.00 Rp 8,160.00
Pasir pasang M3 0.010 Rp 145,000.00 Rp 1,450.00
Perlengkapan % 12.000 Rp 69,553.20 Rp 69,553.20
JUMLAH HARGA BAHAN Rp 649,163.20
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 869,883.20
E Overhead & Proft ( 10 % ) 10% x D Rp 86,988.32
F Harga Satuan Pekerjaan (D+E) Rp 956,871.52

5 Pemasangan 1 M' Pipa PVC Diameter 1/2 Inchi

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)

A TENAGA
Pekerja L.01 OH 0.036 Rp 67,900.00 Rp 2,444.40
Tukang Batu L.02 OH 0.060 Rp 83,200.00 Rp 4,992.00
Kepala Tukang L.03 OH 0.006 Rp 88,000.00 Rp 528.00
Mandor L.04 OH 0.002 Rp 90,000.00 Rp 180.00
JUMLAH TENAGA KERJA Rp 8,144.40
B BAHAN
Pipa PVC Diameter 1/2 Inchi M1 1.200 Rp 4,150.00 Rp 4,980.00
Perlengkapan % 35.000 Rp 1,743.00 Rp 1,743.00
JUMLAH HARGA BAHAN Rp 6,723.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 14,867.40
E Overhead & Profit ( 10 % ) 10% x D Rp 1,486.74
F Harga Satuan Pekerjaan (D+E) Rp 16,354.14

6 Pemasangan 1 M' Pipa PVC Diameter 3/4 Inchi

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)


No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)

A TENAGA
Pekerja L.01 OH 0.036 Rp 67,900.00 Rp 2,444.40
Tukang Batu L.02 OH 0.060 Rp 83,200.00 Rp 4,992.00
Kepala Tukang L.03 OH 0.006 Rp 88,000.00 Rp 528.00
Mandor L.04 OH 0.002 Rp 90,000.00 Rp 180.00
JUMLAH TENAGA KERJA Rp 8,144.40
B BAHAN
Pipa PVC Diameter 3/4 Inchi M1 1.200 Rp 6,500.00 Rp 7,800.00
Perlengkapan % 35.000 Rp 2,730.00 Rp 2,730.00
JUMLAH HARGA BAHAN Rp 10,530.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 18,674.40
E Overhead & Profit ( 10 % ) 10% x D Rp 1,867.44
F Harga Satuan Pekerjaan (D+E) Rp 20,541.84

7 Pemasangan 1 M' Pipa PVC Diameter 1 Inchi

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)

A TENAGA
Pekerja L.01 OH 0.036 Rp 67,900.00 Rp 2,444.40
Tukang Batu L.02 OH 0.060 Rp 83,200.00 Rp 4,992.00
Kepala Tukang L.03 OH 0.006 Rp 88,000.00 Rp 528.00
Mandor L.04 OH 0.002 Rp 90,000.00 Rp 180.00
JUMLAH TENAGA KERJA Rp 8,144.40
B BAHAN
Pipa PVC Diameter 1 Inchi M1 1.200 Rp 9,200.00 Rp 11,040.00
Perlengkapan % 35.000 Rp 3,864.00 Rp 3,864.00
JUMLAH HARGA BAHAN Rp 14,904.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 23,048.40
E Overhead & Profit ( 10 % ) 10% x D Rp 2,304.84
F Harga Satuan Pekerjaan (D+E) Rp 25,353.24

8 Pemasangan 1 M' Pipa PVC Diameter 2 Inchi

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)

A TENAGA
Pekerja L.01 OH 0.054 Rp 67,900.00 Rp 3,666.60
Tukang Batu L.02 OH 0.090 Rp 83,200.00 Rp 7,488.00
Kepala Tukang L.03 OH 0.009 Rp 88,000.00 Rp 792.00
Mandor L.04 OH 0.003 Rp 90,000.00 Rp 270.00
JUMLAH TENAGA KERJA Rp 12,216.60
B BAHAN
Pipa PVC Diameter 2 Inchi M1 1.200 Rp 15,250.00 Rp 18,300.00
Perlengkapan % 35.000 Rp 6,405.00 Rp 6,405.00
JUMLAH HARGA BAHAN Rp 24,705.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 36,921.60
E Overhead & Profit ( 10 % ) 10% x D Rp 3,692.16
F Harga Satuan Pekerjaan (D+E) Rp 40,613.76

9 Pemasangan 1 M' Pipa PVC Diameter 2,50 Inchi

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)

A TENAGA
Pekerja L.01 OH 0.081 Rp 67,900.00 Rp 5,499.90
Tukang Batu L.02 OH 0.135 Rp 83,200.00 Rp 11,232.00
Kepala Tukang L.03 OH 0.0135 Rp 88,000.00 Rp 1,188.00
Mandor L.04 OH 0.004 Rp 90,000.00 Rp 360.00
JUMLAH TENAGA KERJA Rp 18,279.90
B BAHAN
Pipa PVC Diameter 2,50 Inchi M1 1.200 Rp 17,750.00 Rp 21,300.00
Perlengkapan % 35.000 Rp 7,455.00 Rp 7,455.00
JUMLAH HARGA BAHAN Rp 28,755.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 47,034.90
E Overhead & Profit ( 10 % ) 10% x D Rp 4,703.49
F Harga Satuan Pekerjaan (D+E) Rp 51,738.39
10 Pemasangan 1 M' Pipa PVC Diameter 3 Inchi

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)

A TENAGA
Pekerja L.01 OH 0.081 Rp 67,900.00 Rp 5,499.90
Tukang Batu L.02 OH 0.135 Rp 83,200.00 Rp 11,232.00
Kepala Tukang L.03 OH 0.0135 Rp 88,000.00 Rp 1,188.00
Mandor L.04 OH 0.004 Rp 90,000.00 Rp 360.00
JUMLAH TENAGA KERJA Rp 18,279.90
B BAHAN
Pipa PVC Diameter 3,0 Inchi M1 1.200 Rp 30,250.00 Rp 36,300.00
Perlengkapan % 35.000 Rp 12,705.00 Rp 12,705.00
JUMLAH HARGA BAHAN Rp 49,005.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 67,284.90
E Overhead & Profit ( 10 % ) 10% x D Rp 6,728.49
F Harga Satuan Pekerjaan (D+E) Rp 74,013.39

11 Pemasangan 1 M' Pipa PVC Diameter 4 Inchi

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)

A TENAGA
Pekerja L.01 OH 0.081 Rp 67,900.00 Rp 5,499.90
Tukang Batu L.02 OH 0.135 Rp 83,200.00 Rp 11,232.00
Kepala Tukang L.03 OH 0.0135 Rp 88,000.00 Rp 1,188.00
Mandor L.04 OH 0.004 Rp 90,000.00 Rp 360.00
JUMLAH TENAGA KERJA Rp 18,279.90
B BAHAN
Pipa PVC Diameter 4,0 Inchi M1 1.200 Rp 40,250.00 Rp 48,300.00
Perlengkapan % 35.000 Rp 16,905.00 Rp 16,905.00
JUMLAH HARGA BAHAN Rp 65,205.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 83,484.90
E Overhead & Profit ( 10 % ) 10% x D Rp 8,348.49
F Harga Satuan Pekerjaan (D+E) Rp 91,833.39
XV. PEKERJAAN LAIN - LAIN

1 Memasang 1 M2 Conblock Segi 6 Tebal 6 CM


No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)
A TENAGA
Pekerja L.01 OH 0.500 Rp 67,900.00 Rp 33,950.00
Tukang Batu L.03 OH 0.020 Rp 83,200.00 Rp 1,664.00
Kepala Tukang L.03 OH 0.020 Rp 88,000.00 Rp 1,760.00
Mandor L.04 OH 0.002 Rp 90,000.00 Rp 180.00
JUMLAH TENAGA KERJA Rp 37,554.00
B BAHAN
Paving Blok Tebal = 8 cm Buah 38.000 Rp 1,900.00 Rp 72,200.00
Pasir Urug M3 0.007 Rp 145,000.00 Rp 1,015.00
JUMLAH HARGA BAHAN Rp 73,215.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 110,769.00
E Overhead & Proft ( 10 % ) 10% x D Rp 11,076.90
F Harga Satuan Pekerjaan (D+E) Rp 121,845.90

2 Memasang 1 M2 Conblok Segi 4 Tebal 8 CM


No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)
A TENAGA
Pekerja L.01 OH 0.500 Rp 67,900.00 Rp 33,950.00
Tukang Batu L.03 OH 0.020 Rp 83,200.00 Rp 1,664.00
Kepala Tukang L.03 OH 0.020 Rp 88,000.00 Rp 1,760.00
Mandor L.04 OH 0.002 Rp 90,000.00 Rp 180.00
JUMLAH TENAGA KERJA Rp 37,554.00
B BAHAN
Conblok Segi 4 Tebal = 8 cm Buah 48.000 Rp 1,900.00 Rp 91,200.00
Pasir Urug M3 0.007 Rp 145,000.00 Rp 1,015.00
JUMLAH HARGA BAHAN Rp 92,215.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 129,769.00
E Overhead & Proft ( 10 % ) 10% x D Rp 12,976.90
F Harga Satuan Pekerjaan (D+E) Rp 142,745.90

3 Memasang 1 M2 Sosotan Aspal


No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)
A TENAGA
Pekerja L.01 OH 0.020 Rp 67,900.00 Rp 1,358.00
Tukang Batu L.03 OH 0.002 Rp 83,200.00 Rp 166.40
Mandor L.04 OH 0.001 Rp 90,000.00 Rp 90.00
JUMLAH TENAGA KERJA Rp 1,614.40
B BAHAN
Aspal Kg 1.500 Rp 14,475.00 Rp 21,712.50
Tempat Masak Aspal Bh 0.003 Rp 49,392.50 Rp 148.18
Kayu Bakar M3 0.020 Rp 285,000.00 Rp 5,700.00
JUMLAH HARGA BAHAN Rp 27,560.68
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 29,175.08
E Overhead & Proft ( 10 % ) 10% x D Rp 2,917.51
F Harga Satuan Pekerjaan (D+E) Rp 32,092.59

4 Memasang 1 M2 Taburan Pasir Cor

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)

A TENAGA
Pekerja L.01 OH 0.020 Rp 67,900.00 Rp 1,358.00
Mandor L.02 OH 0.001 Rp 90,000.00 Rp 90.00
JUMLAH TENAGA KERJA Rp 1,448.00
B BAHAN
Pasir Beton (PB) M3 0.010 Rp 145,000.00 Rp 1,450.00
JUMLAH HARGA BAHAN Rp 1,450.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 2,898.00
E Overhead & Profit ( 10 % ) 10% x D Rp 289.80
F Harga Satuan Pekerjaan (D+E) Rp 3,187.80

5 Pekerjaan 1 M2 Tanam Rumput Gajah Mini

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)

A TENAGA
Pekerja L.01 OH 0.040 Rp 67,900.00 Rp 2,716.00
Mandor L.04 OH 0.004 Rp 90,000.00 Rp 360.00
JUMLAH TENAGA KERJA Rp 3,076.00
B BAHAN
Pupuk Kandang Krg 0.040 25,000.00 Rp 1,000.00
Rumput Gajah Mini M2 1.050 42,000.00 Rp 44,100.00
JUMLAH HARGA BAHAN Rp 45,100.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 48,176.00
E Overhead & Profit ( 10 % ) 10% x D Rp 4,817.60
F Harga Satuan Pekerjaan (D+E) Rp 52,993.60

6 Pemasangan 1 M2 Sunscreen Alluminium

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) JumlahHarga(Rp)

A TENAGA
Pekerja L.01 OH 0.080 Rp 67,900.00 Rp 5,432.00
Tukang L.03 OH 0.800 Rp 83,200.00 Rp 66,560.00
Kepala Tukang L.03 OH 0.080 Rp 88,000.00 Rp 7,040.00
Mandor L.04 OH 0.004 Rp 90,000.00 Rp 360.00
JUMLAH TENAGA KERJA Rp 79,392.00
B BAHAN
Sunscreeen Alluminium M2 1.000 200,000.00 Rp 200,000.00
JUMLAH HARGA BAHAN Rp 200,000.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) Rp 279,392.00
E Overhead & Profit ( 10 % ) 10% x D Rp 27,939.20
F Harga Satuan Pekerjaan (D+E) Rp 307,331.20
Rencana Anggaran Biaya
( RAB )
Kegiatan : Pengembangan Objek Pariwisata Unggulan
Pekerjaan : Perencanaan Pengembangan Objek Wisata Danau Rusa
Tahun Anggaran : 2018

PEKERJAAN BANGUNAN FLYING FOX


Harga
No. Uraian Pekerjaan Volume Sat. Jumlah Harga (Rp)
Satuan (Rp)
1 2 3 4 5 6
1 PEKERJAAN PERSIAPAN
1 Mobilisasi dan demobilisasi (tentatif) 1 lot 9,000,000.00 9,000,000.00
2 Safety cost 1 lot 2,500,000.00 2,500,000.00
3 Sewa alat
- Truck 1 lot 4,000,000.00 4,000,000.00

Jumlah pekerjaan persiapan 15,500,000.00


2 PEKERJAAN PONDASI
1 Pek. Galian pondasi 6 m3 58,492.50 350,955.00
2 Pek. Cor pondasi (k=225 Mpa) 15 m3 973,042.79 14,595,641.89
Jumlah pekerjaan pondasi 14,946,596.89
3 PEKERJAAN STRUKTUR
1 Pem. Base plate + angkur 8 bh 100,000.00 800,000.00
2 Pek. Rangka besi siku (joint welding) 798 kg 32,228.90 25,718,662.20
3 Pek. Tangga besi 1 lot ### 15,000,000.00
- Besi pipa
- Plate bordes
4 Pek. Atap 16 m2 175,000.00 2,800,000.00
- zinclaum + rangka hollow
5 Treetop
- Pipa steel 6 inch 6 bh 2,500,000.00 15,000,000.00
Jumlah pekerjaan struktur 59,318,662.20
4 PEKERJAAN FINISHING
Pengecatan rangka besi 202 m2 24,020.43 4,852,125.85
Peralatan treetop + install 1 lot -
Peralatan flying fox + intall 1 lot -
Jumlah pekerjaan finishing 4,852,125.85
Uraian Pekerjaan Pere

A. Pekerjaan Gazebo

No

1
I.

1
2

II.
1
2
3
4
5
6
7
###
###
###
###
###
###
###
###
Uraian Pekerjaan Perencanaan Objek Wisata Danau Rusa

A. Pekerjaan Gazebo
Harga Satuan
Uraian Jumlah Volume Satuan (Rp)

2 3 4 5
PEKERJAAN PERSIAPAN

Pembersihan lapangan (luas total area) 4 LS Rp 12,419.00


Pekerjaan bowplank (sekeliling area) 4 m2 Rp 59,904.46

PEKERJAAN PONDASI
Galian tanah pondasi m2 Rp 58,492.50
Urugan pasir bawah pondasi m2 109197
Cor Lantai kerja 1 : 3 : 5
Cor Pondasi plat setempat 60 x 60 x 15
Pek. Besi beton plat setempat 60 x 60 x 15
Pas. Bekisting pondasi plat setempat 60 x 60 x 15
Cor Pondasi Plat Setempat 120 x 60 x 15
Pek. Besi beton kolom pedestal 15 x 35
Pas. Bekisting kolom pedestal 15 x 35
Cor Kolom Pedestal 11 x 11
Pek. Besi beton kolom pedestal 11 x 11
Pas. Bekisting kolom pedestal 11 x 11
Pondasi batu bata 1 bt 1 : 2
Raben pondasi 1 : 3
Urugan tanah bekas galian
Jumlah Harga (Rp)

Rp -
Rp -
Rp -
Rekapitulasi
Kegiatan : Pengembangan Objek Pariwisata Unggulan
Pekerjaan : Perencanaan Pengembangan Objek Wisata Danau Rusa
Tahun Anggaran : 2018

PEKERJAAN BANGUNAN FLYING FOX

No. Uraian Pekerjaan Jumlah Harga (Rp)


1 PEKERJAAN PERSIAPAN 15,500,000.00
2 PEKERJAAN PONDASI 14,946,596.89
3 PEKERJAAN STRUKTUR 59,318,662.20
4 PEKERJAAN FINISHING 4,852,125.85
Jumlah harga 94,617,384.94
Ppn (10%) 9,461,738.49
Total jumlah 104,079,123.44

Terbilang :
Err:511

Bangkinang, Desember 2018

Diperiksa oleh : Dibuat oleh :


Pejabat Pelaksana Teknis Kegiatan PT. METAFORMA CONSULTANT
(PPTK)

DHESY ELYANTI Ir. ADE IWAN HERMANA


NIP. 19811224 200605 2 001 Direktur Utama

Disetujui oleh :
Kuasa Pengguna Anggaran/ Kuasa
Pengguna Barang

SURYADI, S.Sos
NIP. 19661704 198803 1 003