R 12 Migration - Production Cutover Period Activities Details

This document outlines the go-live downtime schedule for upgrading Excel Industries Ltd's EBS system from version 11.5.10.2 to 12.1.3. It includes major milestones, tasks, resources assigned, and estimated timelines. Key steps involve cloning the production database, various pre-upgrade, upgrade, and post-upgrade processes for the application and database, and functional and technical validation activities post go-live. The total estimated effort is 120 hours with the upgrade planned from March 3-6, 2013.

Uploaded by

gopikrishna8843
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
109 views6 pages

R 12 Migration - Production Cutover Period Activities Details

This document outlines the go-live downtime schedule for upgrading Excel Industries Ltd's EBS system from version 11.5.10.2 to 12.1.3. It includes major milestones, tasks, resources assigned, and estimated timelines. Key steps involve cloning the production database, various pre-upgrade, upgrade, and post-upgrade processes for the application and database, and functional and technical validation activities post go-live. The total estimated effort is 120 hours with the upgrade planned from March 3-6, 2013.

Uploaded by

gopikrishna8843
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
You are on page 1/ 6

EXCEL INDUSTRIES LTD -EBS

Go-Live Downtime Schedule EXCEL INDUSTRIES LTD

S.No Areas
1 DBA
2 DBA

3 DBA
5 DBA

6 DBA
7 DBA

8 DBA
9 OPM

10 DBA
11 DBA
12 DBA
13 DBA
14 DBA
15 DBA
16 DBA
EXCEL INDUSTRIES LTD -EBS UPGRADE 12.1.3 FROM 11.5.
e EXCEL INDUSTRIES LTD

Major Milestones Start Date


Clone
Cloning of 11.5.10.2 Production database to identified HP 3-Mar-13
Pre-Upgrade Process
Application of AD.I.7 3-Mar-13
Applying Sub Ledger Patch and pre-req 3-Mar-13
Run Gather Scheme Statistics 3-Mar-13
System for Pre-Upgrade Checkups 3-Mar-13
Application Services Shutdown 3-Mar-13
Take a Backup(APPS & DB) 3-Mar-13
OPM Pre-Migration Process
Applying Pre-Install Patches for OPM 3-Mar-13
Checking OPM Migration Error Log 3-Mar-13
Resolving OPM Migration Log Errors 3-Mar-13
Take a Backup(APPS & DB) 3-Mar-13
Upgrade Process For Application
Upgrading Application from 11.5.10.2 to R12.1.1
R12 Stage move and Install 3-Mar-13
Applying Pre-Install Patches 3-Mar-13
Appling Opatches 4-Mar-13
Apply Main Patch 4-Mar-13
Apps Tech_st and Apps Setup (First Run) 5-Mar-13
System preparation for Autoconfig 6-Mar-13
Enabling Autoconfig on DB Tier 6-Mar-13
Enabling Autoconfig on R12.1.1 6-Mar-13
Take a Backup(APPS & DB) 6-Mar-13
OPM Post-Migration Proces
Applying Post-Migration Patches
Checking OPM Migration Error Log
Resolving OPM Migration Log Errors
Upgrade Process For Database
Upgrading Database from 10.2.0.4 to 11.2.0.3 with Companion
Applying Additional Patches 4-Mar-13
Upgrade Steps 4-Mar-13
Take a Backup(APPS & DB) 4-Mar-13
Upgrade Process For Application
Upgrading Application from R12.1.1 to R12.1.3
Pre-Upgrade Process 5-Mar-13
Apply Maintaince Patch 5-Mar-13
Apply Help Patch 5-Mar-13
Post-Upgrade Process
Post Upgrade -Database 5-Mar-13
Post Upgrade Patches 5-Mar-13
Post Upgrade Functional and Technical activites are below 6-Mar-13
Post Upgrade Technical 6-Mar-13
Post Upgrade Functional
Release 12.1.3
12.1.3 FROM 11.5.10.2

Complete Date Person Time Status

3-Mar-13 Mr.Hemal Shah 4Hours

3-Mar-13 Mr.Adithya/Tajmal 1Hour


3-Mar-13 Mr.Adithya/Tajmal 3Hours
3-Mar-13 Mr.Adithya/Tajmal 4Hours
3-Mar-13 Mr.Adithya/Tajmal 1Hour
3-Mar-13 Mr.Adithya/Tajmal 10mins
3-Mar-13 Mr.Adithya/Tajmal 4Hours

3-Mar-13 Mr.Adithya/Tajmal 3Hours


3-Mar-13 Mr.Vijay/Raman/Senthil 2Hours
3-Mar-13 Mr.Vijay/Raman/Senthil 1Hour
3-Mar-13 Mr.Adithya/Tajmal 4Hours
Total=17Hours

3-Mar-13 Mr.Adithya/Tajmal 1Hour


4-Mar-13 Mr.Adithya/Tajmal 1Hour
4-Mar-13 Mr.Adithya/Tajmal 1Hour
5-Mar-13 Mr.Adithya/Tajmal 25Hours
5-Mar-13 Mr.Adithya/Tajmal 1Hour
6-Mar-13 Mr.Adithya/Tajmal 1Hour
6-Mar-13 Mr.Adithya/Tajmal 30mins
6-Mar-13 Mr.Adithya/Tajmal 30mins
6-Mar-13 Mr.Adithya/Tajmal 4Hours

4Hours
1Hour
2Hour
Total=41Hours

4-Mar-13 Mr.Adithya/Tajmal 5Hours


4-Mar-13 Mr.Adithya/Tajmal 18Hours
5-Mar-13 Mr.Adithya/Tajmal 4Hours
Total=27Hours
Mr.Adithya/Tajmal
5-Mar-13 Mr.Adithya/Tajmal 1Hours
5-Mar-13 Mr.Adithya/Tajmal 18Hours
5-Mar-13 Mr.Adithya/Tajmal 1Hours
Total=24Hours
5-Mar-13 Mr.Adithya/Tajmal 1Hours
6-Mar-13 Mr.Adithya/Tajmal 4Hours
6-Mar-13 Mr.Vijay/Raman/Venkat/Shree Pr 1Hour
6-Mar-13 Mr.Shree Prasanth/Sethu 1Hour
Mr.Vijay/Raman/Ram/Senthil/Ven7Hour
Ready for Business User end Total Hours Taken:120