Cont Prot
Cont Prot
CONTROL,
PROTECTION &
OPERATION
1
1.0 HVDC CONTROL AND PROTECTION
EQUIPMENT
1.1 General :
This chapter summarizes the control equipment hardware furnished for this
Project. The report is a supplement to the cubicle overview diagrams.
The system is fully computerized and built with the state of the art electronics,
microprocessors and digital signal processors, interconnected by high
performance industry standard busses and fiber optic communication links.
All critical parts of the system are designed with inherent parallel redundancy.
The design employs the same redundancy and switch over principles.
The cubicles are designed for high EMI immunity. This has been verified by
extensive tests according to the IEC EMC requirement.
All control Protection, Monitoring and Interface equipment delivered by M/s.
ABB for this Project are briefly described here.
Fig 1(a) & Fig 1(b) give an overview of the control cubicles and interconnections
which are delivered by M/s. ABB. In these overview diagrams each cubicle is
represented as a square. In total, 34 control cubicles are delivered to each
converter station and in addition a Local Station Mimic Board consisting of 16
panels per converter station are furnished as a backup to the SCADA System
delivered by M/s. BHEL. All control system parts having an impact on the
power transfer of the HVDC link are made redundant.
In the M/s. ABB’s control the Pole Control and Protection cubicles (PCP), the
Valve Control cubicles (VCY, VCD) and the Serial Remote Interface cubicle (SRI)
are provided with parallel redundancy.
The protection system includes protections for the HVDC equipment and HVDC
related AC equipment. The two protection categories both consist of primary
and backup protections. All DC protections excluding the DC filter protection
are located in the PCP cubicles. The DC filter protections are located in the DC
Yard Control (DYC) cubicles. The converter transformer protections (TRP) and
AC filter protections are located in separate protection cubicles (TRP1-2 and
AFP1-4 respectively).
It is important that the control equipment of an HVDC station has a very high
EMI immunity. To verify this a number of EMI tests according to the IEC
requirements have been carried out on the control and protection cubicles. The
EMI tests imposed on the cubicles are:
-IEC 255-4 E5High frequency disturbance test
-IEC 802-2 Electrostatic discharge
-IEC 801-3 Radio interference immunity test (partly)
-IEC 801-4 Electrical fast transient/burst
-IEC 801-5 Surge immunity 1.2/50
2
1.2 Cubicle Overview :
Cubicle overview diagrams Fig 1(a) & Fig 1(b) indicates arrangement at
Chandrapur and Padghe Converter Stations respectively.
1.2.1 Local Station Mimic (LSM) :
The LSM is the local operator interface for control of the HVDC link. The LSM
consists of mosaic panels. From these panels an operator can control the local ac
and dc yards as well as the power flow and control modes of the entire dc link.
1.2.2 Bipole Control and Protection (BCP) :
The cubicle locates equipment for the Electrode Line Impedance Supervision
(ELIS) and the Electrode Line Unbalance Supervision (ELUS). The units are
mounted in a rack with split motherboard and the units have independent power
supplies, power supervision, DCU (Distributed Control Unit) and FALMA (a
bitbus controller) boards. The bitbus repeater for the SCM bus communicates
with both ELIS and ELUS.
The Line Fault Locator (LFL) is also located in the BCP cubicle. Auxiliary power
to the LFL, ELIS and ELUS units is delivered by uninterrupted power sources
(UPS).
1.2.3 Pole Control and Protection (PCPA and PCPB) :
The redundant PCP cubicles include all the functions needed for the closed loop
control of the Pole, sequence control systems and the valve cooling control
(VCC).
Each of the two PCP cubicles also locates a complete primary (set 1) and a
backup (set 2) protection system for the converter Pole including the valve
cooling system protections. The two protection systems are separated with
respect to power supply and measured quantities and both systems in the active
cubicle are simultaneously on line.
Two cubicles, PCPA and PCPB are used to accommodate the redundant Pole
control and protection systems. All control functions are physically placed in a
controller rack, whereas the protections are placed in a protection rack with split
motherboard thus enabling separate power supply to each protection set (1 and
2).
1.2.4 Valve Control (VCY and VCD) :
The main objective of the valve control is to convert electrical control pulses (CP)
generated by the control pulse generator in the PCPA or PCPB cubicle into
optical firing pulses (FP) used to fire the individual thyristors in the valves via
light guides.
The valve control equipment, sometimes also called valve base electronics, may
be considered a fast, remote I/O to the control pulse generator of the firing
control system. The valve control is designed as redundant A and B systems,
hard wired to the higher level PCPA and PCPB systems.
The main functions of the thyristor monitoring system are inherent in the Valve
Control Units (VCU) which constitute an essential part of the valve control
system. These functions are consequently also redundant.
3
The valve control equipment is physically placed in two cubicles, one for the
valves connected to the Y valve windings and one for the valves connected to the
D valve windings of the converter transformers. These cubicles are located
between the PCPA and PCPB cubicles in the control room.
1.2.5 DC Yard Control (DYC) :
The DYC cubicle mainly accommodated the dc filter and smoothing reactor
protections and a switch interface for the disconnectors and grounding switches
in the dc yard.
Like the valve control equipment the dc yard control equipment may be
considered an I/O system for the redundant PCP systems. In this case the switch
interface units for the dc yard apparatuses are interconnected to the sequence
controllers of the PCP systems via a duplicate remote controller in the DYC
cubicle.
1.2.6 Transformer Protection (TRP1, TRP2) :
The transformer protection cubicles accommodate the primary and backup
protection systems for the converter transformers and the converter ac bus
including switch interface for the converter ac circuit breaker. Furthermore,
remote I/O controllers for control of the breakers and the transformer tap
changers are included. The remote I/O is duplicated and controlled from the
controller rack of the PCP cubicles. A two cubicle combination with the primary
protections in one cubicle and the backup protections in the other cubicles is
used.
1.2.7 AC Filter Protection (AFP1, AFP2, AFP3, AFP4) :
In the AFP cubicles the primary and backup ac filter protections are located. The
cubicles also accommodate switch interface for the filter breaker.
Remote I/O controllers for the ac filter breakers are also included. The remote
I/O is duplicated and controlled from the controller rack of the PCP cubicles.
A four-cubicle combination with the primary protections in two cubicles and the
backup protections in the other two is used.
1.2.8 Remote Terminal Interface (RTI) :
An RTI cubicle is located in the 400kV control room at each site. The purpose
of the RTI cubicle is to collect indications and measuring values from the
400kV ac switchyard & communicate the signals to the converter control
equipment via. a bus link.
1.2.9 Data Collecting Unit (DCU) :
A DCU cubicle is provided in each station Pole. The cubicle accommodates
data acquisition equipment for the auxiliary power equipment and
communicates commands to and alarms and indications from auxiliary
power equipment on per station Pole basis.
1.2.10 Transient Fault Recorder (TFR) :
One TFR cubicle is provided in each pole control room. The transient fault
recorder provided is a type Hathaway DFR 16/32. The TFR cubicle
accommodates two Data Acquisition Units (DAU) providing the capacity of
recording up to 32 analog and 24 digital quantities per Pole.
4
1.2.11 Master Transient Fault Recorder (MTFR) :
A PC based master TFR is provided at Padghe. The master TFR collects data
from the local TFR:s in each Pole control room and enables study and
comparison of simultaneous records from all TFR locations. Harmonic
analysis, scaling, highlighting etc. can be done by means of the master TFR.
1.2.12 Serial Remote Interface (SRI) and Station Front End (SFE) Cubicles :
The sequence of events recorder function and the alarm system functions are
provided by the SRI and SFE cubicles.
The system is built around three main functional parts :
- Distributed Control Units (DCU)
- Station Front End (SFE)
- Serial Remote Interface (SRI)
1.2.12.1 DCU System :
The data acquisition part, the DCU system, is in most cases integrated with
the HVDC Control System. Normally this is the place where all data enters
the system.
The DCUs time tag the events/alarms with an absolute time and store them
in individual internal queues until they have been collected by the Front End,
(FE). The DCU internal queue is a cyclic buffer and has a capacity of storing
1000 events. The polling speed from the FE is approximately one event per 10
ms.
These queues serve as a backup memory to the FE memory. In the case of an
FE failure the local queues will always keep the last 100 events. Shorter
interruptions in the FE is therefore not a problem.
The DCUs also provide the interface for all types of orders from the operators
to the HVDC control equipment and switchyard equipment.
1.2.12.2 Station Front End (SFE) :
The SFE system collects data and sends operator orders to the DCUs. The
SFE system which is duplicated runs in an active/standby configuration. At
a severe fault in the active system the standby system immediately takes over
all current tasks without loss of information.
1.2.12.3 Serial Remote Interface (SRI) :
The duplicated Gat Way Stations (GWS) in the SRI cubicle provide the
interface between the HVDC control equipment and the SCADA system.
1.2.13 Station LED Annunicator (SLA) and Pole LED Annunciator (PLA) :
The SLA and PLA cubicles contain the backup alarm systems for the SCADA.
Alarms are given by as displays on light emitting diode (LED) units and the
sound of a buzzer (Backup Audible Alarm).
The backup alarm system handles the events classified as “major” or
“warning” alarms. The LED include functions to latch in and display each
alarm until reset, either locally at the LED or from the SCADA or from the
Local Station Mimic (LSM).
5
The SLA cubicle can display the status of 432 alarm signals and is located in
the station control room. The PLA cubicle can display the status of 880 alarm
signals and is located in the Pole control room.
1.2.14 AC Yard Measuring (AYM) :
The cubicle is equipped with two compatible meters for import/export of
active and reactive energy and one tape printer for half hourly recording of
active and reactive energy.
1.2.15 DC Yard Measuring (DYM) :
The electronic units associated with the various DC Current Transducers
(DCCT) are located in the DYM cubicles. One DYM cubicle is provided per
Pole and located in the respective Pole control room. Signals from four dc
current measuring points are routed via. each DYM cubicle. The four signals
are IDNC to PCPB, IDEL, IDGND and IDME to DYC.
The DYM cubicle also locates a backup panel (BUP) containing the necessary
operator controls for operating the Pole such as controls for operating
converter ac breaker, setting Pole current order and bipole power order etc.
Operation from the BUP follows the same procedures as when operating
from the LSM located in the station control room.
1.3 Communication :
The communication inside the converter station uses a hierarchy of serial
busses. In line with the strive for open systems, these all adhere to
international standards.
The communications inside the converter station uses a hierarchy of serial
busses. In line with the strive for open systems, these all adhere to
international standards.
1.3.1 Local Communication :
1.3.1.1 Field Busses :
The field busses used adhere to the standard IEEE 1118 and are run at 375
kbps. For short distances within the control equipment room, electrical
busses are used with screened cables and opto-isolated repeaters in each
cubicle. For longer distances or when passing noisy environments, fibre optic
modems are typically used.
The field bus is used in the three applications as described below.
i) Control bus :
One duplicated bus is used for remote I/O signals for the Pole control
and protection cubicles, tying those cubicles to the AFP1, AFP2, DYC,
RTI, TFR1 and TFR2 cubicles.
ii) Data Collection Bus (SCM bus) :
Another duplicated IEEE 1118 field bus is used to collect the event data
and analogue values for the SCM system. This bus is routed to all
cubicles to provide event and status information to the SCM system.
Together with this bus, a separate pair in the bus cable is used to
distribute the clock synchronizing pulses (once a second) from the
6
master clock to the distributed control units in the control and
protection cubicles.
iii) VCU bus :
Two redundant field buses are used by the cooling control and
protection system, to collect cooling system data from remote I/O.
The main controllers of the cooling control and protection system are
placed in the duplicated Pole control and protection cubicles and are
consequently duplicated. The remote I/O system is also duplicated
and placed close to the main cooling system in the valve cooling room.
1.3.2 Local Area Networks (LAN) :
The LAN used is the well known IEEE 802.3 (Ethernet) and the software used
is OSI compatible with ISO Transport 8073 class 4. This LAN is used to tie the
workstations to master SCM.
1.3.3 Inter-station Communication :
The station to station communication is handled by communication boards
included in the Pole Control and Protection cubicles. The communication is
synchronous and adheres to ISO 3309 (HDLC frames) for high security.
7
1.4 Control System Description :
1.4.1 General :
The control system summary for one pole is illustrated in Figure 1(c). The
primary objective of the control system is to send out firing pulses to the
thyristor valves in order to keep the transmitted DC power or DC current at
the ordered level disregarding AC and DC disturbances. The power order is
set by the operator with possible contributions from various power
modulation functions. The power order goes through the Pole Power
Control, which calculates a current order and coordinates the two stations
through the telecommunication system. The current order is then sent to the
Converter Firing Control (CFC), which calculates the corresponding firing
angle (alpha, ) and sends out firing pulses. The CFC also ensures that the
firing is done within the limits of the thyristor valves.
Alpha (), the extinction angle Gamma () and Ud are also supervised and
controller to be within their respective design limits. This is achieved in the
voltage and Angle Reference Calculation (VARC) function which as outputs
gives a Gamma reference to the CFC and Ud, Alpha and Gamma references
to the Tap Changer Control (TCC). The TCC controls the tap changers on the
converter transformers in order to, within the limits of the design, follow the
Ud, Alpha and Gamma references.
The reactive power balance of the HVDC converter stations is controlled by
the Reactive Power Control (RPC), which switches AC filters in order to keep
the reactive power balance, as well as harmonics generated by the HVDC
stations, within design limits.
Furthermore, the pole sequences which are automatically coordinated
between the two stations are primarily for assisting the operator(s) in :
- Changing control modes.
- ensuring safe switching of DC disconnectors and DC breakers at
connection and disconnection of a pole.
- Changes of modes of operation e.g. Monopolar earth return/metallic
return.
1.4.2 Pole Power Control :
Two different modes exist, either power or current control mode. The main
purpose of the Pole Power control system is to calculate a current order and
thereby keep the transmitted DC power or DC current constant at the ordered
level, independently from AC and DC disturbances, while still maintaining
the stability of the DC system.
1.4.2.1 Power Control Mode :
The power control mode keeps the DC power transmitted equal to the power
order given by the operator. When a new power order is given by the
operator, a ramping rate is also given. The power order and the power ramp
are given to a stepping logic function, which ramps the power order. In order
to keep the power constant, variations in the DC voltage are compensated for
8
by adjusting the current order accordingly. To the power order obtained in
this way, different additional contributions can be added from various power
modulation functions. The current order is obtained by dividing the total
power order by the direct voltage response measured at the DC high voltage
driver. This is the main mode of operation.
9
1.4.2.2 Current Control Mode :
The current control mode keeps the DC current transmitted equal to the
current order given by the operator. The current order and the current ramp
are given to a stepping logic function, which ramps the current order.
1.4.2.3 Back-up Synchronous Control :
In order to avoid the risk for loss of current margin, and consequential trip
during loss of the inter-station telecommunication system a back-up
synchronous control (BSC) is included which automatically synchronizes the
current orders in the two stations.
The BSC is active in both power and current control mode when the
telecommunication is not working or when “separate mode” is selected.
In case of telecommunication failure, BSC will be automatically selected to
handle the synchronization. The BSC serves as a back-up for the
synchronization unit in the Pole Power Control (PPC). In the rectifier the
synchronization is by-passed and the final current order is subject to a slower
rate of change limit. In the inverter the measured direct current is low-pass
filtered and used as the final current order (see figure 1(d) ).
If the current control is transferred from the rectifier to the inverter during
BSC, the current order will be frozen in both stations.
1.4.2.4 Overload Limiter :
The current order will be limited according to the minimum value of the
inherent overload capacity of the two stations. The overload capacity of the
transmission can thereby be fully utilized without risk for unwanted shut-
downs due to high thermal stresses on the equipment. Ambient temperature
measurements are used to determine the maximum allowed transmission
capacity. The power limitations are defined during the main circuit
design.
1.4.3 Power Modulations :
The inherent high speed power control capability of the HVDC transmission
system can be utilized for stabilization and/or frequency control of the
surrounding AC systems. The contribution from power modulation control
functions is therefore superimposed on the normal, operator set power order.
1. The Damping control will normally always be activated. The
Damping Control receives the AC frequency from both stations, and
gives a power contribution to the PPC in order to damp oscillations in
the AC network.
Damping control will be available in power control, normal power
direction but not in islanded operation.
10
Frequency control will be available in power control, normal power
direction and in islanded operation.
4. The Fast stop function will, when manually activated, stop the
HVDC transmission in a fast and safe way.
If the pole is in “joint” control, the DC power will first be ramped down with
a fast ramp rate. Then the Pole sequencing function (PSQ) will coordinate the
blocking of both converters. If the pole is not in joint control then Fast stop
will order a trip.
In case of emergency there is also an “Emergency Stop” provided. It trips the
converter breaker.
1.4.4 Reactive Power Control :
The purpose of the RPC is to control properties in the AC network connected
to the converter station. The quantity to be controlled is either AC bus
voltage or reactive power exchange with the AC system. The system should
also make sure that enough filters of different types are connected to prevent
excessive harmonics to enter into the AC system. The means used to perform
these tasks are switching of the different AC filters.
The task of the controller part of the RPC is to control AC bus voltage (U-
control) or reactive power exchange with the AC system (Q-control). In
Reactive power control the RPC will switch filter to keep the exchange with
the AC network to a set target value within specified limits. In Voltage
control the AC voltage will be controlled directly by the RPC filter switching.
Switch orders will be initiated if the controlled quantity exceeds the limits of
a deadband. The size of the deadband should be coordinated with the size of
the reactive banks and with the response properties of the AC network. The
design will allow for different levels of the deadband with different time
delays for the switching. This could be utilised to give a faster action on
major deviations, for example following on trip of a pole, and a slower
response for minor steady state deviations.
The harmonic filtering properties will be supervised by a Min filter function
in the RPC that monitors the number of different filters connected and
compares that number to the number required for the present operating
situation. To make sure that the filtering performance requirements are met
the amount of filters required of each type will depend on the operation
mode and on the DC power level. To avoid overloading the filters, a higher
priority function (Abs Minfilt) is included (see fig. 1(e) ).
To avoid over-voltages, two functions are implemented in the RPC, Q-
maximum and U-maximum. These functions disconnects filters to prevent
protections to act on over-voltages. These parts are active also in manual
mode. The Q-maximum acts to prevent over-voltages to occur at for instance
a pole trip, while the U-maximum disconnects filters to lower an already
exiting high voltage.
11
The highest priority of the RPC functions is the (Abs Minfit) since it protects
from over-loading the filters and consequential filter and pole trips. Of
second and third priority are the U- and Q-maximum functions since they
protect against over-voltages. Fourth priority is (Min filter) and the control
functions have the least priority.
The QPC (Converter Reactive Power Control) will, if necessary increase the
converters consumption of reactive power to absorb the excess of reactive
power at filter switching. This is done by increasing the firing/extinction
angle.
12
1.4.5 Voltage And Angle Reference Calculation (VARC) And Tap Changer
Control (TCC) :
The objective of the VARC is to ensure that the DC voltage, extinction angle
gamma, or firing angle alpha, will be within design limitations during steady
state conditions. This is done by calculating target values in DC voltage,
gamma and alpha reference which are then sent to the TCC. The DC voltage,
alpha and gamma reference target values will also be sent to the CFC (see fig.
1(f) ).
The DC voltage, common in both stations, except for the drop in the DC line
resistance, is controlled by the VARC. Telecommunication is used to
calculate, on line, the resistance. Since the DC voltage is controlled in one
station, the resistance is used to ensure proper voltage control. During
telecommunication outages the resistance value is frozen.
The Tap Changer Control (TCC) system is designed to control the Load Tap
Changer of the converter transformers. The objective of the TCC is to keep
ordered alpha, gamma and DC voltage to the target values determined by the
VARC.
Because of the stepwise character of the tap changers, alpha, gamma and Ud
control are provided with suitable deadbands to avoid hunting. A higher
priority criterion is to ensure that Udi0 is below it’s maximum limitation. The
control of the converter transformer tap changers is fully automatic, however
a manual control possibility, either jointly (three-phase) on or each
transformer separately, is provided.
1.4.6 Converter Firing Control (CFC) :
The CFC, receives a current order from the PPC and sends out firing pulses in
such a way that the ordered current is maintained. The dynamics of the
HVDC transmission system is determined primarily through the settings of
the Voltage Dependent Current Order Limiter, VDCOL, and the Current
Control Amplifier, CCA.
To assist the AC system in recovering from faults, the reactive power
consumed by the converters must often be limited. The Voltage Dependent
Current Order Limiter, VDCOL, accomplishes this by reducing the
transmitted current at low DC voltage.
The Current Control Amplifier, CCA, is principally, a P-I regulator, where the
proportional part executes instantaneous changes, while the integrator part
maintains the value of current during steady state conditions. The current
control amplifier has a high enough gain and suitable dynamics to reach the
demands regarding speed and stability.
The output signal from the current control amplifier is a reference for the
firing angle and used as an input order to the firing control system (see fig.
1(g) ).
1.4.7 Firing Control :
The objective of the firing control is to convert the ordered alpha into
corresponding firing pulses. The allowed changes of the firing angle are
13
dependent upon the operation mode. An alpha rate of change Limiter is
therefore included in order to avoid too fast changes. Especially in regions
where the commutations may become unsuccessful, i.e. low gamma.
One important task of the Firing Control is to secure that the firing instant
does occur within the time limitations which are set with regard to design
limitations of the converter bridge and thyristor valves. This is accomplished
through the following features :
The voltage has to reach a certain level (UMIN), corresponding to
approximately 5 degrees at normal voltages across the thyristor valve to
enable firing. For inverter operation, the value (ALPHA MIN) is set to
around 100 degrees in order to prevent reversed voltage, and thereby
reversed power.
Predictive commutation margin (AMIN) control ensures that the
extinction angle, is kept above the minimum value, normally 17 degrees,
in order to minimize the risk for commutation failures (see fig. 1(g) ).
1.4.8 Conclusion :
The control system described as above gives the operation of the
Chandrapur-Padghe HVDC bipole the necessary flexibility, while permitting
accurate control of the desired quantities automatically. Further, the control
system takes the necessary actions to cope with disturbances in the systems
external to it.
14
DESIGN REQUIREMENTS FOR DC POWER
MODULATION SCHEME IN CHANDRAPUR-PADGHE
HVDC PROJECT
ABSTRACT
MSEB has planned Chandrapur-Padghe HVDC bipolar link rated for 500 kV,
1500 MW with about 750 Km length. This link is for evacuating power from Generation
Complex near Chandrapur to Western part of the state. Apart from other control
features, this HVDC link is being equipped with power modulation controller. For
design of the power modulation controller for DC links, it is necessary to conduct
system studies and evaluate the system performance.
This paper describes the design requirements for DC power modulation scheme.
It is also shown that the active power modulation damps the oscillations in the Western
Region Network and thus helps in improving the system stability.
15
revealed following Dispatch off Peak
1.0 Padghe. Apart
three patterns of (MEDOP),
from evacuation of
INTRODUCTION load/generation. Maximum Western
the power
Dispatch off Peak
In India, the generated at a) Maximum
(MWDOP) and
electrical grid is Chandrapur, this Eastern Dispatch
Maximum Western
divided into five link can also be (MED)
Dispatch off Peak
regions i.e. Eastern used to stabilize b) Maximum Export (MWDOPE)
region, Western 400 kV EHV Western Dispatch conditions.
region, Northern network in the (MWD)
region, North state. EHV Out of the five base
network of MSEB is c) Maximum cases, maximum
Easter and
shown in Exhibit-1. Western Reduced eastern generation,
Southern region.
The back-to-back Dispatch in which maximum
The Western
Region converter station in (MW RD) power transfer in
interconnected Chandrapur is the AC lines from
system is made up being established Under each of the east to west is
of six areas. Gujrat, by Power Grid above dispatch realized, has been
Maharashtra, Corporation of condition generally selected. The
Madhya Pradesh India Ltd. for two types of load maximum possible
and Goa are the connecting Western scenario i.e. peak import from back
provincial Region with load and off peak to back HVDC
networks. The 5th Southern Region. load need to be station i.e. 1100
Zone, NTPC is a considered. MW is also
2.0 considered. This
generating
In each of the stresses the
company owned by OPERATING possible network transmission
the Govt. of India CONDITIONS configuration system to
and does not own
While designing import/export maximum extent,
transmission
the major network through HVDC thus considering
network. Zone 6
for the Region, it is back to back system the worst
consists of
necessary to study between Western conditions in terms
transmission
the behviour of the and Southern of stability.
projects which are
system for all the networks are also
common to 3.0
possible operating needed to be
provincial and/or
conditions. considered.
central power REQUIREMENTS
utilities. However, network OF THE STUDY
The operating
designed
The existing Wester conditions of loads It is well known
considering
Region network has in Western region fact that power
extreme operating
its major generating network are then modulation of DC
conditions can
plants in its eastern defined by five link can be used to
sustain different
area and major base cases e.g. enhance the
operating
loads in Western Maximum Eastern stability of the
conditions. The
area. MSEB has Dispatch Peak power system, and
review of operating
establishing 500 (MEDP), Maximum several HVDC
conditions in
kV, 1500 MW Eastern Dispatch schemes in
western region, in
HVDC link Peak Import operation are
particular in
between (MEDPI), utilized to provide
Maharashtra
Chandrapur to Maximum Eastern additional damping
16
to the power value in response found out. The The frequency
system. Therefore, to AC system time simulations of analysis carried out
the requirements of stabilizing control network behaviour in the frequency
the HVDC link signals. Such at serious network range of 0.1 Hz to
from the point of signals should have disturbances are 3.0 Hz and give the
view of modulation no steady state done to check the frequencies for
controller are first effect i.e. stabilizing performance of the resonance peaks for
decided which are signal should modulation angles at some
as follows : decrease to zero in controller for interesting nodes
the steady state. HVDC converters. and generators in
The HVDC system
Full use of the All these relation to the
would be capable
available short time investigations are reference machine.
of operating in all
overload capability carried out with the
modes and at all It is well
in the converters help of the ABB
transmitted power established that
should be made for network analysis
levels except above eigen value
the purpose of AC digital computer
the five seconds analysis is a
stabilization. program SIMPOW
overload rating (i.e. powerful tool for
(Release 9.3 version
33.3% greater than Small signal analysing
DVSADI Revision
continuous power modulation should oscillatory stability
017).
level) with a power be allowed even for large power
modulation of when HVDC 5.0 LINEAR systems, and in
required value telecontrol facilities ANALYSIS recent years,
above and below are not in service. several programs
The configuration
the mean operated However, in such for computing the
and parameters of
transmitted power event the power eigen structure of
the power
level. modulation large power
modulation
capability should systems have
The equipment for controller can be
be at least 5% of the evolved. The real
AC system determined from
continuous rating. part of the eigen
stabilization analytical studies
modulation will 4.0 using linear value ()
have a feature to analysis. The initial corresponding to
provide positive METHODOLOGY investigation of an interesting mode
damping of AC FOR STUDIES Western Region of oscillation
network Network Stability determines the
To get an stability of the
oscillations over the understanding of has been carried
range 0.1 Hz to 3 out by using linear system, if () is
network behaviour, positive, the system
Hz. linear analysis analysis. This
incorporates is unstable. It is of
The converter (including interest to
frequency analysis, frequency analysis,
controls should investigate how a
eigen value eigen value
utilise fast control control action
analysis and modal calculations and
action to suitably affects the eigen
analysis) is carried modal analysis. In
stabilize the system value. The results
out. From the the linear analysis
by rapidly the eigen value.
system behaviour the system is
increasing or
the frequency of linearised around The results of the
decreasing the
oscillations, mode the operating point eigen value
power flow
of oscillations and at the prevailing analysis are shown
transiently above or
the eigen values are load condition. in Table 1.
below the ordered
17
Modal analysis frequency around frequencies around Power Line Carrier
indicates the 1.1 Hz, the 1.1. – 1.4 Hz, when (PLC) system as
participation of east/west the Chandrapur back-up. The
oscillations with generators oscillate generators are maximum delay in
respect to angle against those in the involved, the the
and amplitude for central area, where frequency telecommunication
each frequency for also the information on the is negligible for the
some interesting Chandrapur converter AC bus fibre optic system
generators. generators are in Chandrapur will and around 90
involved. At be used. Thus the millisecond for the
Thus from the
around 1.4 Hz two signals are PLC system. The
above, we come to
several areas of added (with proper transfer function of
know the buses
generators oscillate polarity) and used the proposed
which are taking
against each other as input signal to modulations
part in oscillations,
in irregular the modulation controller is
their frequencies of
patterns. controller. defined by the
oscillations, the
block diagram in
damping present in 6.0 The Chandrapur-
Fig. 1. The block
the system. From Padghe HVDC
MODULATOR diagram of the
the oscillations of system is designed
DESIGN frequency measure
the buses, the for current (power)
regulator used for
buses/ generators The input signal for control in the
modulation
in various areas an HVDC system rectifier
controller is shown
will follow the modulation (Chandrapur).
in Fig. 2.
mode of controller is the Thus in the design
oscillations. These converter AC bus of the modulation 7.0 CASES
oscillating frequency which is controller for the INVESTIGATED
frequencies are easily available HVDC system, To check the proper
slightly different within the telecommunication functioning of
for different converter is required to modulation
operating equipment. transmit the 0.7 Hz
controller for this
conditions. oscillation signal
The conclusion of project, a number
from Padghe to
The frequencies of the linear analysis of cases are studied
Chandrapur. It will
oscillations are is that the with time
then influence the
found as 0.7 Hz, 1.1 dominant stimulation of the
performance of the
Hz and 1.4 Hz. At resonance complete system
stabiliser both at
around 0.7 Hz, the frequency (around behaviour at
transmitting the
generators in 0.7 Hz) can only be certain severe
frequency
western area are damped by disturbances. Some
information (0.7 Hz
oscillating against utilizing the in conjunction with
case) and for the
those in eastern information from line/generator
current order. The
area. In this the oscillation outages. The
telecommunication
oscillation mode, available in the network stability
system for the
the generators in Padghe end, as the without the HVDC
Chandrapur-
the central part, Chandrapur system is done and
Padghe
including the generators are not also with HVDC
transmission is
Chandrapur active in this system withstand
based on a fibre
machines are not oscillation. without
optic system with a
active. At the However, for the modulation
18
controller. The frequencies in the ACKNOWLEDGE
investigations are range of 0.1-3.0 Hz. MENT
tabulated in Table The presence of the The authors wish to
2. HVDC thank management
transmission link
8.0 of MSEB and M/s.
provides a ABB Power
OBSERVATIONS considerable Systems AB for
improvement in
The major task of permission to use
respect of damping
the modulation the results of
of these oscillations
controller is to investigations
by unloading the
control the 0.7 Hz carried out and
AC lines.
oscillations which permission to
are apparent in the The most present this paper.
Padghe end only of predominant of the REFERENCES
Chandrapur- resonance
frequencies, around i) T Smed, G
Padghe HVDC
0.7 Hz, is well Andersson :
transmission. Thus
damped by the “Utilizing
the modulation
action of the HVDC HVDC to
controller of the
link modulation Damp Power
Chandrapur-
controller sensing Oscillations”.
Padghe HVDC
the Padghe bus IEEE
system takes the
frequency. This Transactions
input as the
action depends on on Power
frequency of 400
the presence of at Delivery, Vol. 8
KV bus at Padghe
least the PLC based No. 2 April,
and sends it to the
telecommunication 1993.
controller through
the system. The ii) HVDC Power
telecommunication damping of the Transmission
link. The main remaining higher System by
telecommunication resonance
frequencies of 1.1 K.R. Padiyar.
system is fibre optic
system and if it is Hz and 1.4 Hz even
out of service then if not so
PLC system is to be pronounced is also
used, a slight shown.
decrease in the The back to back
performance can be converters have
observed. negligible impact
9.0 on the oscillations
as they are
CONCLUSION connected to a
point in the
The investigation of network where the
Western Region dominating
Network has oscillation mode
identified three does not appear.
resonance
19
Table 1 : Linear Analysis
1500 0 YES
1500 0 YES
Faults Outages
after fault
MEDPI without 3-ph. to ground fault at None The oscillations in the system can
HVDC link Chandrapur bus for 5 not be damped and the oscillations
cycles. in power flow on the major lines
and Generators are increasing
trend.
MEDPI with HVDC 3-ph. to ground fault at None The oscillations in the systems are
link without Chandrapur bus for 5 reduced slowly up to some extent.
modulation controller cycles.
MEDPI with HVDC 3-ph. to ground fault at The oscillations in the system are
link with modulation Chandrapur bus for 5 reduced fastly and the system
controller (M.C.) cycles. normalised (in @ 15 seconds).
20
MEDPI with HVDC 3-ph. to ground fault at The oscillations in the system are
link with M.C. but no Chandrapur bus for 5 reduced slowly with respect to
fibre optic cycles. Case 3 & the system takes
communication. comparatively more time to get
Delay of 90 ms stabilised.
--do-- DC fault in one Pole One pole The control parameters in HVDC
outage system i.e. dc voltage, current
orders & firing angles are varying
fast as compared to case 3 & get
stabilised after some time.
MEDP 3-ph. to ground fault at None Less oscillations in the system with
Chandrapur bus for 5 respect to Case 3 and system gets
cycles. normalised earlier.
21
INTERACTION BETWEEN HVDC BIPOLE AND HVDC :
BACK-TO-BACK LINKS PLANNED AT CHANDRAPUR
V.D. Ambekar S.M. Mujumdar M. Ahfaz
Supdt. Engineer Exe. Engineer Dy.E.E., (Tr.Plg.)
22
pattern and load growth scenario, the first and 5.0 DESIGN CONSIDERATIONS DUE TO
second modes will be most common modes of MIC SYSTEM
operation. The third mode, though feasible
5.1 Effective Short Circuit Ratio :
may be very rare one. The fourth mode is
infeasible and is practically ruled out. The short circuit MVA at the converter ac bus
gives the idea of ac system strength. An index
4.0 PROBLEMATIC ASPECTS OF
called Effective Short Circuit Ratio (ESCR) is
CHANDRAPUR MIC SYSTEM
used to assess the performance of single-feed
converter at a bus. It is defined as::
4..1 Concurrent Establishment of two Projects :
23
the harmonic current by the bipole and back- recovery periods following faults,
to-back filters. comprehensive Dynamic Performance Studies
(DPS) will be carried out on analogue HVDC
5.3 Design of Lighting Arresters (LAs) :
simulator. The actual controls for Bipole and
For designing the LAs the presence of total back-to-back converters as proposed to be
capacitor quantum at Chandrapur has been used. The aim of this study is to confirm that
considered. Dynamic interaction between there is no adverse interaction between the
filters and ac system may result in the two HVDC links under various operating
amplification of Dynamic Over Voltages conditions/modes, to find solution to the
(DOV) at certain resonant frequencies, giving coordination problem detected during the
rise to the increased energy handling study and to arrive at an optimal operation,
requirement of LAs. control and protection strategy. The
5.4 Control of DOV due to Bipole / BTB equivalent to be used for DPS is shown in fig.
Blocking: 2.
The modulation controls of the two HVDC Normal start-up, ramping of DC power
links need to be properly coordinated so that (separately and simultaneously) and shut
the two links do not modulate power in down to ensure satisfactory stable operation
coordination to the modulation requirements of both HVDC links.
of their respective regions and also the Energisation and de-energisation and also
amount of power to be modulated does not protective tripping of filter banks to verify
cause unnecessary swings in the system which that the reactive power exchange and step
otherwise would have been stable. change in voltage are within specified limit.
6.0 EXCHANGE OF DESIGN DATA Energisation of converter transformer of one
Exchange of design data have been done pole of each link while the other pole and the
between contractors of the two projects other link are operating at selected power
throughout the engineering and design stages. levels.
But due to almost parallel design activity of Switching of specified 400 kV ac transmission
the two projects, the design data available for lines represented within the equivalent ac
one project at any given point of time have circuit to ensure stable operating of HVDC
been used for engineering and design studies links.
of the other. Hence many studies for both
Single and three phase ac system faults will
projects have been carried out using some of
be applied to ensure satisfactory operation of
the data assumed ones to account for the
both HVDC links.
influence of one HVDC link on another.
Selected load rejection and run back
7.0 DYNAMIC PERFORMANCE STUDY
conditions to verify the satisfactory operation
FOR BIPOLE AND BACK-TO-BACK
of both HVDC links.
CO-ORDINATION
Tripping of one or both poles/blocks on
In order to ensure that the bipole and back-to-
HVDC bipole/BTB link and DC line faults
back ink operate in a stable and logical
on bipole link in monopolar and bipolar
manner during steady state and during
operation and observing the responsible of
24
remaining pole/block on respective HVDC DPS in order to arrive at a coordinated
links. recovery strategy.
9.0 NEED FOR COMMUNICATION 11.0 CONCLUSION
BETWEEN HVDC LINKS
The 1500 MW, ± 500 kV Bipole of MSEB
The details of communication need have not and 2 x 500 MW back-to-back link of PGCIL
been specified in the Technical Specifications planned and under execution at Chandrapur
of the two projects and the coordination would constitute the first MIC HVDC system
between the two links is to be achieved, as far when commissioned.
as possible, without any signal/data transfer
As for these two projects, most of the
between links.
activities related to design and engineering
However, some of the design and engineering were performed in almost identical time frame
studies show the need for communication of the actual data required for taking into
certain signals between the links. In the account the influence of one HVDC link on
proposed joint DPS for coordination of the the other were either not available or partially
projects, the requirement of communication available at the require point of design stage.
channels for exchange of signal/data such as Hence during the design stage, some assumed
power order changes, status of a.c. network data for each others project were required to
etc. in real time mode will be identified and be used.
clearly defined.
A comprehensive Dynamic Performance
10.0 OPERATIONAL STRATEGY FOR MIC Study is proposed to be carried out for
The details of operational strategy, both for verifying the stable and logical operation
steady state and dynamic operation would be of Chandrapur MIC, identifying the
finally worked out on the basis of the results coordination problems of the MIC,
of DPS. At present the broad outline of finding remedial measures and evolving a
operational strategy can be described keeping coordinated steady state and dynamic
in mind the purpose of building the HVDC operating strategy under various ac system
bipole and back-to-back link. conditions and operating modes so that
The MSEB bipole transmission is expected to both HVDC bipole and back-to- back link
play a major role in the East-West power play their envisaged roles without adverse
transfer i.e. from Chandrapur to Mumbai area interaction from each other.
in the Maharashtra integrated AC/DC system.
Hence the strategy should be so evolved that
unnecessary operational constraints are not
inadvertently imposed on the power transfer
capabilities of integrated system due to
proximity of back-to-back link.
The same reasoning is true for the back-to-
back operation as this link is expected to
function as an important asynchronous inter-
regional tie to assist in the economic
integrated operation of the Western and
Southern Regions.
As far as the strategy for the recovery of the
HVDC links after the clearing of the fault at
Chandrapur is concerned, it can be said that
recoveries for both links have to be staggered,
as the simultaneous recovery will not be
possible or very difficult. For the two normal
modes of operation of the MIC system at
Chandrapur as elaborated earlier, the priority
of recovery of one HVDC link over the other
would be clearly defined for different
operating conditions/modes in the proposed
25
26
2.0 HVDC PROTECTION SYSTEM
2.1. General :
The purpose of the HVDC Protection System is to cause the prompt removal
from service of any element of the transmission system, when it suffers a short
circuit or when it starts to operate in any abnormal manner that might cause
damage or otherwise interfere with the effective operation of the rest of the
system. The protective system is aided in this task by the A.C. circuit breaker that
are capable to de-energize the converter transformer and by this action reducing
the direct current and direct voltage. An attempt to keep the system in service in
case of a control failure is made by using the facility of a switch over function
which will change over the control to a redundant control system when
available.
The HVDC Protections are broadly classified as;
- DC Side Protections
- AC Side Protections
- Over Voltage and Surge Protections,
2.2 D.C. Side Protection :
2.2.1 General Protection Philosophy :
The HVDC Control and Protection System is divided into two Redundant
Systems A and B, based on an Active and Standby concept. Both systems include
a complete set of control and protection systems. Each protection system consists
of both set-1 and set-2 protections.
The Protective Scheme is designed to meet the following General requirements.
a. Fault condition or other abnormal conditions that might expose
equipment to hazard as well as conditions that will cause unacceptable
disturbance to operation is detected and the faulty or over-stressed
equipment is taken out of service or relieved of stresses in a controlled
way.
b. The aim of the protection design is to detect every condition according to
above with at least two protections.
c. The protection is arranged in to overlapping zones. For each fault case
there should be fast main protection with a limited protective zone. The
main protection is normally supported with a slower or less sensitive
backup protection. The back-up protection is based on a different
measuring principle and when applicable with a more extended
protective zone.
d. The protection is so arranged that testing and maintenance can be carried
out without affecting the operation of the pole.
e. Auxiliary Power supplies to primary and back up protection are separate
so that outage on one does not affect the function of other.
f. Tripping paths to the breaker are redundant and fed by two different
auxiliary voltage supplies.
Inverter :
- Immediate retarding of the converter.
- Tripping of AC circuit breaker
- Blocking of the converter with by-pass pair when the AC breaker has
opened.
2.2..4.4.2 Type Y-blocking :
Generally used for DC side faults which do not expose the equipment to
serious stresses, AC faults and manual blocking of the pole.
- Immediate retarding of the converter.
- The converter is blocked directly with by-pass pair in the inverter and
resembles therefore a category Z-blocking. In the rectifier the order to
block is delayed to bring about extinction of the current before
blocking. The blocking is made without by-pass pairs in the rectifier if
the DC current is below a voltage dependent limit. Otherwise the
converter is blocked with by-pass pairs.
2.2.4.4.3 Type Z-blocking :
The Z-blocking is generally used for ground faults or over-currents related to
the DC side.
The Z-blocking always implies a blocking with simultaneous firing of by
pass pairs.
2.2.4.5 AC Circuit Breaker Trip :
This disconnects the AC side of the converter transformers from the AC
power source. By doing this the AC system, which primarily is a constant
voltage source, is prevented from feeding a fault on the valve side of the
converter transformer. Also removing AC voltages from the valves avoids
unnecessary voltage stresses especially when the valves have performed
severe current stresses.
All protective trip orders to the AC circuit breakers will energize both trip
coils in the breakers via two different trip devices. The redundant trip orders
will also be fed by two redundant auxiliary power suppliers.
Fig. 2(k) indicates the trip circuit overviews.
2.2.4.6 Start Breaker failure protection :
When a trip order to the AC-breaker is sent, at the same time an order to
start the breaker failure protection is generated. If the breaker doesn't
succeed with the opening, the breaker failure protection trips the next
breaker further out.
2.2.4.7 Set lockout relay for AC circuit breaker :
If a protection trip order is sent to the AC breaker, an order to the lockout
relay is sent to prevent the breaker to close before the operator has checked
the cause of the trip. The lockout relay is manually reset by the operator.
2.2.5 System Supervision :
The HVDC Control and Protection System is primarily designed to minimize
the need for a periodic maintenance.
For the protection system this means, that all parts of the protection system
are continuously supervised and the need for the manual checks is
completely eliminated.
All computing elements incorporated are well proven supervisory techniques,
such as :
“ Program execution control ” (stall alarm or watch dog alarms), which will
check that calculations are executed normally. In combination with the
predictable cyclic execution and the HiDraw function block programme
development tool, it gives an excellent supervision of the individual
microprocessors that makes up the HVDC Control and Protection System.
“Memory checks”
Flash PROM memories are checked by a checksum calculation. This makes it
possible to check that both the program code and all protection settings remain
unchanged.
Static RAMs are checked at regular intervals by writing and reading special test
patterns to each memory cell.
Dynamic RAM memories are checked by either continuous parity check or by
ECC (Error Correction Code) techniques.
These techniques ensure that all computers used for protections will behave
correctly and that the setting are intact.
To ensure that the measuring elements are not faulty, all measurements are made
with two electronic measuring circuits (aux. CTs or OCTs, input amplifiers, S &
H circuits, A/D converters etc.) Although, only one of these measurements is
used for a particular protection, both measurements should always show
reasonably similar values, if no part of the system is faulty. When applicable, an
additional comparison is made with the results from other locations measuring
the same parameter. The control and protection system is automatically
monitoring all measurement and an alarm is generated if an error is detected and
an alarm is generated on detecting an error.
Indication from breakers and disconnectors are supervised with the normal
double point technique (one closing and one opening contact) but those are also
read by two independent switch control units.
All indications and trip signals are transferred by redundant field busses, where
all units on the bus and all segments are continuously monitored with "alive
messages".
To verify that a tripping signal is able to trip the breaker, the corresponding
switch control unit will perform an automatic check of the output circuitry and
the breaker tripping coil by energizing one side of the trip coil at a time.
When a manual opening of the breaker is performed the protection system
alternates between the two trip coils every other time. This means, that as long as
a breaker is opened a separate trip test from the protections is not needed and in
the rare case where a breaker is never operated, a "trip test" is easily performed
by twice opening and closing the breaker from the SCM system.
In conclusion, the supervision of the control and protection system is thus
regarded as completely automatic. This means not only a remarkable
improvement of the overall reliability of the system but also a total elimination of
both the test switches and handles.
To achieve this, the current in each phase of the HP12 filter branches is
measured and a QHLA 510 computer is operating as a minimum current
detection. When two out of three phases indicate low current level, the
filter is indicated as out of service. If no HP12 filter branch is available,
the converter station is blocked via the station sequence control.
2.4 OVER VOLTAGE AND SURGE PROTECTIONS :
Insulation levels comprises selection of the electrical strength of
equipment and its application in relation to the voltages which can appear
on the system taking into account the characteristics of the protective
devices.
This section summarizes the requirements on the insulation for
Chandrapur and Padghe converter stations.
The Protective devices employed for over voltage protections are ZnO
arresters of non-gaped type. In this section, the selection of arrester
protective levels and its base are explained.
Arrester stresses are caused either by external sources such as AC
transient voltages lighting surges or by internal sources such as ground
faults. Ground faults within the valve hall are averted by the shielded
(indoors) design and the controlled atmosphere.
The base for insulation co-ordination is the arrester protection scheme
shown in fig. 2(n).
The arrester protective levels indicated in this section are used for
determination of insulation levels of equipment.
Arrester data are based on the transient over-voltage studies for the DC
and AC sides.
2.4.2 DC Side Over-Voltage Protection :
2.4.2.1 General :
A DC bus can be directly protected by an arrester connected between the
point to be protected and ground. A DC bus can also be protected by two
or more arresters connected in series, where the individual arrester also
gives protection for converter unit, e.g. a valve.
When protective levels for buses, protected by series connected arresters
are determined, the normal design procedure is to add the protective
levels of the series connected arresters. The individual arresters are rated
for the surge currents and energy stresses occurring at the worst fault
events or disturbances. The maximum surge currents for each of the
series connected arresters in general do not occur at the same instants or
fault events. Therefore the used procedure for definition of protective
levels is conservative and introduces extra margins to the insulation
design.
2.4.2.2 The Insulation Across The Thyrister Valves :
The insulation across each thyristor valve is protected by an arrester
connected in parallel with it.
2.4.2.2.1 Switching Surges :
The valve arresters may be exposed to switching surges entering from the
AC system through the transformer. These stresses depend upon the
operating conditions, the AC system characteristics and the AC filter
configuration.