Lecture 3 - Project Management
Lecture 3 - Project Management
Lecture 2 (continued)
CPM and PERT
Critical Path Method (CPM)
• Sequence of scheduled activities that determines the duration of the project.
• If there is any delay in any tasks on the critical path, then your whole project
will be delayed.
• Although many projects have only one critical path, some projects may have
multiple critical paths.
1. Best-Guess Estimates
a 4m b
2. 3-Point Estimates E
6
3. Triangular Distribution E a m b
3
• If you have multiple critical path, you will run into network
sensitivity. A project schedule is sensitive if the critical path is
likely to change once the project begins.
Payam Rahimi, PhD., P.Eng.
APS1032H: Introduction to Energy Project Management 12
Key Steps in the CPM
• Step 6: Update the critical path diagram to show progress
• While fast tracking reduces your project timeframe, it also involves risk
because you are performing parallel activities that were originally
planned to be performed in sequence.
• CPM and PERT are often used in the same context and scenario.
• Perhaps pouring the concrete foundation (Activity A-B), happens at the same
time as the assembly of the roof trusses (Activity A-D). However, the
finalization of the roof (Activity D-E) cannot begin until both A-D and B-D
(assembly of the building frame) are done.
• B-D cannot start until the concrete foundation has been poured (A-B).
• Step 2: Make a backward pass through the diagram, calculating the latest
time (TL) for each event (node). TL is the earliest of the leaving times for the
existing arcs.
• Step 3: Calculate node slack time (SN) for each node. This the amount of time
by which an event could be adjusted later than its TE without causing
problems downstream.
• Step 4: Calculate the total arc slack time (SA) for each arc (activity). This is
the amount of time by which an activity could be adjusted later than the TE of
the node at its tail without causing problem later.
• Step 5: The critical path connects the nodes at which SN = 0 via the arcs at
which SA= 0
Payam Rahimi, PhD., P.Eng.
APS1032H: Introduction to Energy Project Management 30
Class Exercise (2)
• Find the critical path for the PERT diagram below
• Given the above assumptions, the expected value of each activity duration
is given in exactly the same way as for the three-estimate approach.
• Variances of the project duration is the sum of the variances of the activity
durations for the activities in the critical path.
Payam Rahimi, PhD., P.Eng.
APS1032H: Introduction to Energy Project Management 37
Resource Leveling
• The PERT method assumes that you have all the resources that
you need.