Preliminaries
Preliminaries
1. Preliminaries section of the bills of quantities contains items that are of a general nature
that may affect the contractor’s tender.
2. SMM7 requires that items referred to as Employers Requirements (A30–A37) and
General Cost Items (A40–A44) shall be split into:
• Fixed charges, the cost of which is considered to be independent of duration,
that is to say charges that are not proportional either to the quantity of the work or
its duration, for example:
o The Site/Existing buildings (A12)
o The Contract/Subcontract (A20)
• Time-related charges, the cost of which is considered to be dependent on
duration, that is to say charges that are directly proportional to either the quantity
of the work or its duration (SMM7 – Section A D1 and D2), for example:
o Employer’s requirements (A30–A37)
o Contractor’s general cost items (A40–A44).
3. Although the preliminaries section of bills of quantities tends to contain many items,
several of them are difficult to quantify and price and for this reason it is usually only the
major items such as accommodation, staffing and mechanical plant that are priced.
Preliminaries items
Employer’s requirements – Facilities/Temporary Work/Services – A36
Example – Temporary Accommodation
The contractor shall provide suitable accommodation for the clerk of works, with a minimum
floor area of 20 m2 including desk, four chairs, filing cabinet and all necessary heating, lighting
and cleaning.
Data
Contract period: 144 weeks, Transport to and from site: £150 per trip, Hire of hut: £70 per week,
Hire of furniture and heaters, etc.: £30 per week
Fixed charges
Transport to and from site 2 trips × £150 = 300.00
Erection 10 hours
Dismantle 5 hours
15 hours labourer @ £13.20 = 198.00
Total of fixed charges = 498.00