Cost Accounting
Cost Accounting
C H A P T E R
4
Job Costing
B U S I N E S S M AT T E R S LEARNING OUTCOMES
ferocious force of nature, wildfires cost Canadian taxpay- Apply the decision
ers approximately $417 million per year to suppress. Fires framework in a seven-step
method to assign total
cause evacuations of entire cities, destroy property, create actual costs to a distinct
economic hardship, and kill wildlife and people. In May service.
2011, almost half of Slave Lake in northern Alberta was destroyed by wildfire. But forest fires also renew the
Apply the decision
forests. In its aftermath, the minerals in the soil are revitalized and the sun penetrates to the forest floor. framework in a seven-step
method to assign total
The cost to suppress a forest fire depends on how accessible the fire is. Unfortunately, the most inac- actual costs to a distinct
cessible wildfires are the most destructive and expensive to suppress. These fires are fought primarily using product.
aircraft and fire retardant chemicals. The firefighters are delivered to the site by parachuting in (smoke
Distinguish among three
jumpers) or rapelling in by rope from helicopters. On average, the cost to suppress a Canadian wildfire is methods—actual, budgeted,
approximately $60,000 per fire. Provincial governments use careful job-costing procedures to refine and and normal—to calculate
job-cost allocation rates and
improve their cost estimates for fire suppression. Governments need a reliable job-costing system so they assign indirect costs to a
can account to the taxpayers when asked how money was spent. distinct job.
◆ Quantities of inputs (shared resources used) to complete the job generate all
the cost pools, and these inputs are called cost drivers (also called a cost allocation
base).
◆ The cost driver rate (also called cost allocation rate) is the result of dividing the
indirect cost pool by the total quantity of shared inputs used (the cost driver) to
complete the job.
Direct costs of DM, DLH, and DMH can be readily identified against a job,
either electronically or manually, by giving the job a code and entering the code each
time direct inputs are used for that particular job. Documentation ensures the direct
cost will be traced to one cost object, the finished job. Because we assumed the cost
rate per unit of input is constant, as each unit of direct input is used to complete the
job the direct costs will rise with the quantity used. As we learned in Chapter 2, this
is the distinguishing feature of a variable cost. The accumulation of total variable
DM costs for a job is called a DM cost pool. DLH and DMH cost pools are named
similarly.
Examples of indirect costs include custodial, maintenance, and security costs,
rework, and fringe benefits, all of which vary with the hours worked. Of course the
cost rate to pay for janitorial labour will be different from that paid for maintenance
labour. Both of these different costs are variable and often summed together with
fringe benefit costs in the same indirect cost pool. Fixed costs such as insurance and
property rental fees are also indirect and added to the same cost pool as the variable
indirect costs. The indirect cost pool is a mix of fixed and variable costs from many
sources.
The problem is how to divide up the indirect cost pool among the jobs, know-
ing each job uses inputs common to them all in different quantities. This task is
called cost allocation, and it is a method to estimate the cost of common inputs used
in different quantities by different jobs. Recall from Chapter 2 that managers assign
the direct cost pool by tracing, and the indirect cost pool by allocating the costs to
each job. These relationships are illustrated in Exhibit 4-1.
To assign the single indirect cost pool to jobs, a link needs to be made that can
methodically and consistently explain how a change in the use of one input can explain
changes to the costs assigned to the job. The assumption is that the more of an input
that is used, the higher the benefit or value added to the job will be. The input use is
the reason why one job costs more or less than another. The link is called a cost allo-
cation base (cost driver). The selection of this input is difficult since an MIS usually
records the quantity of direct inputs, not the indirect inputs. Many small businesses
cannot afford to keep track of every quantity of every indirect input, nor would it make
sense to spend the money required to do so. This is a proxy measure of benefit.
EXHIBIT 4-1
Generic Job-Costing System
Cost Assignment
For manufacturing jobs the management team has three choices for a cost
allocation base: quantity of DM, DMLH, or DMH. The goal is to make sure
that the economic fact of how much a job costs is captured in the choice of the
cost allocation base. Managers assume that their choice of a direct input used in
different quantities by different jobs is a good signal of the proportion of com-
mon indirect resources each distinct job consumes. For example, if job 1 con-
sumes more DMH than job 2, then it will also consume more common resources.
If true, then the costing system will represent the real cost of the job completion
process faithfully. Using more machine hours means more of the maintenance
and property insurance costs should be assigned to job 1. The recovery of all
direct and indirect costs for job 1 means the customer will pay more for this job
than for job 2.
Clearly, the use of DMH does not explain how the costs of direct materials
should be assigned to each job because these depend on costs per unit of DM. But
remember that job costing is a GAAP-compliant, inexpensive way to estimate differ-
ences in job costs and assign these costs in a reasonable way. One guideline to help
managers make this choice is whether the conversion of inputs into finished goods is
more machine or labour intensive. If it is more machine intensive, then DMH would
be a better choice as a cost allocation base than DMLH, and vice versa for a job that
is more labour intensive.
In this chapter we will specify the cost allocation base, but in reality this is a dif-
ficult management task. Interestingly, the measurement of a quantity of inputs can
be either non-financial, such as hours of direct labour, or financial, such as total cost
of direct labour used. There is nothing stopping managers from selecting more than
one pair of indirect cost pools and cost allocation bases when it is appropriate to the
business decision that must be made. The larger the number of indirect cost pools,
the more refined the job-costing system will be (which is described further in
Chapter 5).
The cost allocation rate is the result of dividing the indirect cost pool by
the cost allocation base (see Exhibit 4-2). This is the simple average indirect cost
per cost object. Even though the cost allocation base is a direct input quantity,
the indirect cost allocation rate is never the same as any direct cost rate. The rea-
son, of course, is that the indirect cost pool is the result of common use of the
same support resources by all jobs. If the cost object is one customized BMW X5
and the cost allocation base is the total number of direct manufacturing labour
hours (DMLH), then the indirect cost allocation rate is the indirect cost per
DMLH. This is a cost per unit of benefit to the job.
The cost allocation rate and the quantity of DMLH per customized BMW X5
are used to assign the indirect cost per customized BMW X5. Multiplying the indi-
rect cost allocation rate by the quantity of DMLH per customized BMW X5 equals
the total indirect cost per customized BMW X5.
EXHIBIT 4-2
Calculating the Cost Allocation Rate
108 CHAPTER 4
04_horn_ch04.qxd 11/24/11 4:12 PM Page 109
EXHIBIT 4-3
Cost Assignment Systems
2Process
costing is discussed in detail in Chapter 17. Job Costing 109
04_horn_ch04.qxd 11/24/11 4:12 PM Page 110
EXHIBIT 4-4
Examples of Job Costing and Process Costing in the Service, Merchandising, and Manufacturing Sectors
EXHIBIT 4-5
Generic Process Cost Allocation
A B C D
Direct Materials
and Manufacturing
Labour Inputs
Conversion into Conversion into Non-manufacturing
Work-in-Process Finished Goods Costs
Indirect Costs of
Manufacturing
Overhead
110 CHAPTER 4
04_horn_ch04.qxd 11/24/11 4:12 PM Page 111
Step 6: Compute the Indirect Cost Assigned to the Distinct Job The indirect
costs of a distinct type of job are computed by multiplying the indirect cost rate by
the actual quantity of the allocation base used in completing the distinct job.
Step 7: Compute the Total Cost of the Distinct Job by Adding All Direct and
Indirect Costs Assigned to the Job The job cost is the sum of all direct and indi-
rect costs assigned to the distinct job. The direct cost pools have been traced and the
indirect costs have been allocated to each type of job.
EXHIBIT 4-6
Lukach, Sulky, and Associates Actual and Budgeted Operating Income
Step 1: Identify the Distinct Type of Job That Is the Cost Object The job is
the audit of Simpson’s Editorial Services, a very successful professional service. All
costs of this audit must be assigned to the job before its profitability can be ranked
among other types of audit jobs.
Step 2: Identify the Direct Costs of the Distinct Job The direct costs were 800
professional labour hours at $300/DLH for a total of $240,000.
Step 3: Select the Cost Allocation Base to Use for Allocating the Indirect Cost
Pool to a Distinct Job There is only one category of direct costs, professional
labour. LSAL managers assume that changes in professional labour-hours will explain
a sufficient proportion of the change in the total indirect cost pool. The cost alloca-
tion base will be the total professional labour-hours actually consumed by LSAL last
year. Exhibit 4-6 reports that the total professional labour cost at $300/DLH was
$82,260,000, so the total DLH must have been 274,200 hours ($82,260,000 ⫼ $300).
Step 4: Identify and Add All the Indirect Costs into One Indirect Cost Pool
In Exhibit 4-6, the actual total operating expenses have already been calculated as
$147,712,000 ($82,260,000 ⫹ $24,040,000 ⫹ $41,412,000), of which actual direct
professional labour costs were $82,260,000. The indirect cost pool must be
$65,452,000 ($147,712,000 – $82,260,000).
Step 5: Compute the Indirect Cost Allocation Rate Ways to resolve disputes
over what quantity of what input should be in the cost allocation base are discussed
in Chapter 10. Changes in the indirect cost pool should be reasonably explained by
changes in the quantity of inputs in the cost allocation base. In this way, LSAL will
assign costs in a way that reflects the economic facts of completing the job. The cost
allocation rate for the single indirect cost pool using the cost allocation base of quan-
tity of actual professional labour-hours is $65,452,000 ⫼ 274,200 DLH ⫽
$238.7017/DLH (4 decimals). Job Costing 113
04_horn_ch04.qxd 11/24/11 4:12 PM Page 114
EXHIBIT 4-7
Job-Costing Overview for Assigning Actual Total Costs of Three Service Jobs
Research
Customer-
and Service Marketing Distribution
Design Costs Service
Development Costs Costs Costs
Costs
Costs
See Ch. 14 See Ch. 14
÷
Job-Cost Allocation Base (Professional Labour-Hours)
Indirect Indirect
Indirect Cost Pool Cost Pool
Cost Pool Assigned Assigned
Assigned (Allocated) (Allocated)
(Allocated)
Professional
Labour
Professional Actual Cost
Labour Pool Assigned
Actual Cost (Traced) Professional
Pool Assigned Labour
(Traced) Actual Cost
Pool Assigned
(Traced)
Service
Costs
Step 6: Compute the Indirect Cost Assigned to the Distinct Job The Simpson
Editorial Services audit consumed 800 professional labour-hours. The total indirect cost
assigned to this job at the cost allocation rate of $238.7017/DLH is $190,961 (rounded).
Step 7: Compute the Total Cost of the Distinct Job by Adding All Direct and
Indirect Costs Assigned to the Job Having spent time choosing a cost allocation
base and calculating the cost allocation rate, managers must not forget to add the direct
costs of the job to the allocated indirect costs to obtain the total job cost. The total cost
of the Simpson Editorial Services audit was $430,961, as summarized in the table below:
Simpson Editorial Services Audit
Step 1: Identify the Distinct Job That Is the Chosen Cost Object The cost
object is job BCPP, manufacturing a paper-making machine for the BC Pulp and
Paper Company in 2012. Throughout the BCPP job, Robinson’s managers and
management accountants gather information from source documents and job-cost
records with the BCPP identification code.
Step 2: Identify the Direct Costs of the Distinct Job Robinson identifies direct
materials and direct manufacturing labour cost pools. As required by the specifica-
tions, Robinson’s manufacturing engineer will issue requisitions for direct materials.
The basic source document, a materials-requisition record, lists the cost of direct
materials used on each specific job in a specific department. The $112 actual total
cost also appears on the BCPP job-cost record in Exhibit 4-8 in the Direct Materials
section. The actual total direct materials cost was $4,606.
The second direct cost pool is direct manufacturing labour. The source docu-
ment is called a labour-time record (time sheet or time card). This record lists the
amount of labour-time in direct manufacturing labour hours (DMLH) for the BCPP
job, the date, the employee identification, the hourly rate in $/DMLH, and the total
cost of each type of labour used. Notice that two different employees worked on this
job for two different time periods and were paid two different hourly rates.
There is collaborating detail about both the direct materials and direct manu-
facturing labour resources consumed by the BCPP job. Panel A of Exhibit 4-9 shows
the materials-requisition record that specifies what quantity of what material was
requisitioned, the cost per unit, and the total direct materials cost. Panel B shows the
labour-time for employee LT232 (the first DMLH record in Exhibit 4-8).
Notice that G.L. Cook worked on two jobs during the week. The 25 DMLH
worked on BCPP is shown in detail day by day. The hourly rate is $18/DMLH
and the total cost assigned to BCPP was $450, as shown in line 18 of Exhibit 4-8
under the heading Direct Manufacturing Labour. G.L. Cook, however, also per-
formed 3 DMLH of maintenance. Maintenance is not traced to either job JL 256
or BCPP. Job Costing 115
04_horn_ch04.qxd 11/24/11 4:12 PM Page 116
EXHIBIT 4-8
Source Documents at Robinson Company: Job-Cost Record BCPP
A B C D E
1 JOB-COST RECORD
2 JOB NO: BCPP CUSTOMER: BC Pulp and Paper
3 Date Started: Feb. 4, 2012 Date Completed: Feb. 28, 2012
4
5
6 DIRECT MATERIALS
7 Date Materials- Quantity Unit Total
8 Received Requisition No. Part No. Used Cost Costs
9 Feb. 4, 2012 2012: 198 MB 468-A 8 $14 $ 112
10 Feb. 4, 2012 2012: 199 TB 267-F 12 63 756
11
12
13 Total $ 4,606
14
15 DIRECT MANUFACTURING LABOUR
16 Period Labour-Time Employee Hours Hourly Total
17 Covered Record No. No. Used Rate Costs
18 Feb. 4-10, 2012 LT 232 551-87-3076 25 $18 $ 450
19 Feb. 4-10, 2012 LT 247 287-31-4671 5 19 95
20
21
22 Total $ 1,579
23
24 MANUFACTURING OVERHEAD*
25 Cost Pool Allocation-Base Allocation- Total
26 Date Category Allocation-Base Quantity Used Base Rate Costs
27 Dec. 31, 2012 Manufacturing Direct Manufacturing 88 hours $45 $ 3,960
28 Labour-Hours
29
30 Total $ 3,960
31 TOTAL MANUFACTURING COST OF JOB $10,145
32
33
34 *The Robinson Company uses a single manufacturing overhead cost pool. The use of multiple overhead cost pools
35 would mean multiple entries in the “Manufacturing Overhead” section of the job-cost record.
36
EXHIBIT 4-9
Source Documents at Robinson Company: Materials-Requisition Record and Labour-Time Record
PANEL A: PANEL B:
MATERIALS-REQUISITION RECORD LABOUR-TIME RECORD
Materials-Requisition Record No. 2012: 198 Labour-Time Record No: LT 232
Job No. BCPP Date: FEB. 4, 2012 Employee Name: G. L. Cook Employee No: 551-873-078
Part Part Unit Total Employee Classification Code: Grade 3 Machinist
No. Description Quantity Cost Cost Hourly Rate: $18
Metal Week Start: Feb. 4, 2012 Week End: Feb. 10, 2012
MB 468-A Brackets 8 $14 $112
Job. No. M T W Th F S Su Total
Issued By: B. Clyde Date: Feb. 4, 2012 BCPP 4 8 3 6 4 0 0 25
Received By: L. Daley Date: Feb. 4, 2012 JL 256 3 0 4 2 3 0 0 12
Maintenance 1 0 1 0 1 0 0 3
Total 8 8 8 8 8 0 0 40
Supervisor: R. Stuart Date: Feb. 4, 2012
116 CHAPTER 4
04_horn_ch04.qxd 11/24/11 4:12 PM Page 117
Step 3: Select the Cost Allocation Base to Use for Allocating the Indirect Cost
Pool to a Distinct Job Indirect manufacturing costs are costs that are necessary to
do a job but cannot be traced to a specific job. Different jobs require different quan-
tities of indirect resources. For example, Exhibit 4-9 shows that Mr. Cook’s mainte-
nance is not the same each day of the week. The objective is to allocate the actual
total costs of indirect resources in a systematic way to their related jobs.
Robinson chooses direct manufacturing labour-hours as the allocation base for
linking all actual indirect MOH to jobs. In its labour-intensive environment,
Robinson believes that when the quantity of direct manufacturing labour-hours con-
sumed changes, it will also explain a sufficient amount of change in the quantity of
indirect costs consumed by each job. Robinson recorded a total of 27,000 actual
direct manufacturing labour-hours for all jobs.
Step 4: Identify and Add All the Indirect Costs into One Indirect Cost Pool
Actual total indirect manufacturing overhead costs have been accumulated as
$1,215,000 for all jobs undertaken in the year.
Step 5: Compute the Indirect Cost Allocation Rate For each cost pool, the
actual indirect cost rate is calculated by dividing actual total indirect costs in the pool
(determined in Step 4 as $1,215,000) by the actual total quantity of the cost
allocation base (determined in Step 3 as 27,000 DMLH). The cost allocation rate is:
Step 6: Compute the Indirect Cost Assigned to the Distinct Job Robinson’s
actual cost records for the year show that the total BCPP direct labour-hours consumed
was 88 DMLH. The total MOH was $3,960 ($45/DMLH × 88 DMLH ⫽ $3,960).
Step 7: Compute the Total Cost of the Distinct Job by Adding All Direct and
Indirect Costs Assigned to the Job From Exhibit 4-8, the actual total of direct
and indirect costs for the BCPP job was $10,145.
Direct manufacturing costs
Direct materials $4,606
Direct manufacturing labour 1,579 $ 6,185
Manufacturing overhead costs
($45 per direct manuf. labour-hour * 88 hours) 3,960
Total manufacturing costs of job BCPP $10,145
Recall that Robinson bid a price of $15,000 for the job. At that revenue, the actual-
costing system shows a gross margin of $4,855 ($15,000 – $10,145) and a gross-
margin percentage of 32.4% ($4,855 ⫼ $15,000 ⫽ 0.324).
Robinson’s manufacturing managers and sales managers can use the gross
margin and gross-margin percentage calculations to compare the profitability of dif-
ferent jobs to understand the reasons why, for example, the BCPP job failed to meet
its expected gross margin of $5,000 ($15,000 ⫺ $10,000) and gross-margin percent-
age of 33.3% ($5,000 ⫼ $15,000). Overall, without a job-costing system, managers
would have a very difficult time determining the profitability of specific jobs and
identifying areas for improvement.
CONCEPTS IN ACTION—GOVERNANCE
Job Costing on the Next-Generation Military Fighter Plane
Northrop Grumman, Inc. is a leading Norway. In December 2006, the F-35
provider of systems and technologies Lightning II successfully completed its first
for the US Department of Defense. test flight; it appears in this photograph
Competitive bidding processes and during subsequent testing at Edwards Air
increased public and congressional Force Base, California, in 2009.
oversight make understanding costs The project team for the F-35
critical in pricing decisions, as well as Lightning II uses a job-costing system.
in winning and retaining government There are two direct cost pools, mate-
contracts. Each job must be estimated rial and manufacturing labour. The
individually because the distinct outputs consume differ- remaining costs are accumulated in one overhead cost
ent amounts of Northrop Grumman’s resources. pool. The cost allocation base is the total budgeted direct
A project team of Northrop Grumman, Lockheed materials cost. This job-costing system allows managers
Martin, and BAE Systems was awarded the System Design to assign costs to processes and projects. Managers use
and Demonstration contract to build the F-35 Lightning II this system to actively manage costs. Program represen-
aircraft—also known as the Joint Strike Fighter—in late 2001. tatives from the Department of Defense and members of
This project, worth over $200 billion, will create a family of Congress have access to clear, concise, and transparent
supersonic, multi-role fighter airplanes designed for the mil- costing data when they complete their audits.
itaries of the United States, United Kingdom, Italy, The Sources: Conversations with Northrop Grumman, Inc. management,
Netherlands, Turkey, Canada, Australia, Denmark, and www.jsf.mil, and various program announcements and press releases.
DMLH spent, but also the indirect costs of fringe benefits and rework for each job.
For fixed cost allocation, when the cost object is a job it is sensible to collect the fixed
costs incurred during the entire time period of the job.
Robinson Company computes indirect cost rates in Step 5 of the job-costing
system (p. 117) on an annual basis. There are two reasons for using longer periods,
such as a year, to calculate indirect cost rates:
◆ Seasonal patterns. The shorter the period is, the greater the influence of sea-
sonal patterns on the amount of costs. For example, if indirect cost rates were
calculated each month, then heating costs would be charged to production only
during the winter months. An annual period incorporates the effects of all four
seasons into one annual indirect cost rate.
◆ Unitized fixed costs. Longer periods to produce jobs mean that the unitized
fixed cost portion of the machine and other fixed cost pools will be spread out
more evenly. Even if output varies from month to month for a single job, the
point is to cost the job, not the time period.
An audit firm has a highly seasonal workload. Tax advice accounts for more than
80% of the workload from January through April. Given the following mix of costs for
a high-output month such as April and a low-output month such as July, actual indirect
cost allocation rates fluctuate by almost 300%. If the low cost allocation rate were
charged in April, then clients would be very pleased. If the high cost allocation rate
were charged in July, then clients would leave. If costs are allocated and charged at the
time they are incurred, then July clients are not paying a fair share of fixed resources
for an identical job in April. July clients are penalized for the time of year the resources
are consumed. Ultimately the firm could not cover its total annual fixed indirect costs.
Allocation Rate
Indirect Costs per Professional
Professional
Variable Fixed Total Labour-Hours Labour-Hour
(1) (2) (3) (4) (5) (3) (4)
High-output month $40,000 $60,000 $100,000 3,200 $31.25
Low-output month 10,000 60,000 70,000 800 87.50
118 CHAPTER 4
04_horn_ch04.qxd 11/24/11 4:12 PM Page 119
ACTUAL COSTING
Actual costing is a costing system that traces direct costs to a distinct type of job by
using the actual direct cost rates. The direct rates are calculated by dividing the
actual direct job cost pools by the actual quantity of direct inputs. The actual indirect
cost pool is divided by the actual quantity of the direct input chosen as the cost allo-
cation base to calculate the actual indirect cost allocation rate. To assign some
amount of the indirect cost pool to one distinct type of job, the actual quantity of the
direct cost allocation base used to complete the job is multiplied by the actual indi-
rect cost allocation rate.
This method looks backwards to historical information as part of Step 5 in the
decision framework. It is best used to provide feedback information to assess the
profitability of each job in comparison to its expected profitability. The benefit of
using an actual cost system is that the job-costing information accurately reflects
economic facts.
However, the accounting cycle produces a lag between when the cost was
incurred and when it was paid. In addition, there is often a wait for the actual infor-
mation to be recorded within the accounting system, and data entry may be inaccu-
rate. Finally, the job has to be finished before the final cost information is known.
Unfortunately for many jobs, such as the construction of the Confederation Bridge,
which links Prince Edward Island to New Brunswick, cost information to assess
profitability was needed long before job-completion at the end of four years.
Timeliness is an important characteristic that defines relevant information.
In addition, historical information may not be the best indicator of future costs.
For example, the worldwide 2007 recession decreased profits in all industries world-
wide. Fixed costs could not be reduced fast enough to keep pace with falling demand.
Unsold inventory built up based on normally expected demand and profit fell
because no one was buying. Managers need better than a 90- to 365-day-old set of
information based on business as usual to adequately respond to these unpredicted
threats to profit. As uncertainty and risk escalate, predictions or budgets need to
EXHIBIT 4-10
Methods to Calculate Cost Rates and Assign Job Costs
Actual indirect cost allocation rate ⫽ Actual indirect cost pool ⫼ Actual Q of direct inputs used
Budgeted indirect cost allocation rate ⫽ Budgeted cost pool ⫼ Budgeted Q of direct inputs used
The Q of direct inputs used to allocate the Indirect Cost Pool was selected by managers as the cost allocation base.
change to reflect the economic reality outside a company. This is at least as impor-
tant as gathering internal cost information from the company itself on the profitabil-
ity of a distinct type of finished job.
BUDGETED COSTING
Budgeted job cost assignment is useful in service industries because bonuses, an
indirect labour cost, are awarded after year-end when all professional billable
hours are known. The indirect cost rate will be mismatched to actual economic
events. Peak-period overtime worked in, for example, an audit company such as
LSAL, is not a predictable amount and, for service companies who are growing
their client base, is not readily budgeted. Nevertheless, overtime services
provided to complete jobs during peak period is an additional input consumed
by some jobs but not others. The customer requiring the overtime should pay
for it; therefore, LSAL must use job costing to allocate indirect labour costs
appropriately.
LSAL accumulates direct professional labour costs in one cost pool and
direct professional labour-hours (DLH) in its MIS. These amounts are used to
calculate the direct labour cost rate. Overtime and bonuses arise from business
growth and are accumulated with other common costs in one indirect cost pool.
In 2012, LSAL budgeted total direct labour costs of $14,400,000, total indirect
costs of $12,960,000, and total DLH of 288,000 for the year. In this case, the
rate is:
$14,400,000
= = $50/DLH
288,000
Assuming only one indirect cost pool and total DLH as the cost allocation base,
the indirect cost allocation rate is:
$12,960,000
= = $45/DLH
288,000 DLH
Suppose an audit of LSAL’s client Tracy Transport, completed during the peak
period in March 2012, uses 800 DLH. LSAL calculates the direct costs of the Tracy
Transport audit by multiplying the budgeted direct cost rate by the actual quantity of
the DLH for the job. LSAL allocates indirect costs to the Tracy Transport audit by
multiplying the budgeted indirect cost allocation rate by the actual quantity of the
cost allocation base used in this job. On this basis, the cost of the Tracy Transport
audit is:
Direct labour costs, $50 × 800 ⫽ $40,000
Indirect costs allocated, $45 × 800 ⫽ $36,000
Total ⫽ $76,000
At the end of the year, the direct costs traced to jobs using budgeted rates will
rarely equal the actual direct costs because the actual and budgeted rates are devel-
oped at different points in time using different information. End-of-period adjust-
ments for underallocated or overallocated direct costs must be made in the same way
that adjustments are made for underallocated or overallocated indirect costs. Three
methods for making these adjustments—adjusted allocation rate, proration, and
write-off—are discussed at the end of this chapter.
120 CHAPTER 4
04_horn_ch04.qxd 11/24/11 4:12 PM Page 121
NORMAL COSTING
Normal costing is more complex than an actual job-costing system. The normal
method differs from the actual method in the way indirect costs are assigned to a dis-
tinct job. A normal job-costing system still traces direct costs to a distinct type of job
by multiplying the actual direct cost rates by the actual quantities of the direct cost
inputs, but indirect costs are allocated based on the budgeted (predetermined) indirect
cost allocation rates multiplied by the actual direct input quantity of the cost alloca-
tion base used by each distinct type of job. The difference is that the indirect cost
allocation rate is calculated using a budgeted indirect cost pool divided by an indirect
quantity of the cost allocation base used for all jobs. Source documents identify the
actual quantities of direct materials, equipment, and labour used as each distinct type
of job is completed.
We illustrate normal costing for the Robinson Company example using the
seven-step procedure presented earlier. The following budgeted data for 2012 are
for its manufacturing operations:
Budget
Total manufacturing overhead costs $1,120,000
Total direct manufacturing labour-hours 28,000
Steps 1 and 2 are exactly as before: Step 1 identifies BCPP as the cost object; Step 2
calculates actual direct material costs of $4,606, and actual direct manufacturing
labour costs of $1,579. Recall from Step 3 that Robinson uses a single cost allocation
base, direct manufacturing labour-hours, to allocate all manufacturing overhead
costs to jobs. The budgeted quantity of direct manufacturing labour-hours for 2012
is 28,000 hours. In Step 4, Robinson groups all the indirect manufacturing costs into
a single manufacturing overhead cost pool. In Step 5, the budgeted manufacturing
overhead rate for 2012 is calculated as:
In Step 6, under a normal costing system, the allocated MOH costs are $3,520:
Manufacturing overhead costs Budgeted manufacturing Actual quantity of direct
= *
allocated to BCPP overhead rate manufacturing labour-hours
$40 per direct manuf. 88 direct manufacturing
= *
labour-hour labour-hours
= $3,520
The manufacturing cost of the BCPP job is $440 lower under normal costing
($9,705) than it is under actual costing ($10,145) because the budgeted indirect cost
rate is $40 per hour, whereas the actual indirect cost rate is $45 per hour. The differ-
ence in rates, ($45 – $40) × 88 actual direct manufacturing labour-hours ⫽ $440.
Job Costing 121
04_horn_ch04.qxd 11/24/11 4:12 PM Page 122
EXHIBIT 4-11
Flow of Costs in Job Costing
Purchases of
Direct Materials Traced When
Direct Manufacturing Labour to Conversion
Conversion Conversion sales
Conversion occur
Inventoriable into into
Costs: into into Cost of Goods Sold
Work-in-Process Finished Goods Cost of Goods Sold
Work-in-Process Finished Goods
Manufacturing Overhead Allocated Inventory Inventory
Inventory Inventory
including Indirect Materials to
and Indirect Manufacturing
Labour
122 CHAPTER 4
04_horn_ch04.qxd 11/24/11 4:12 PM Page 123
assigned to individual jobs. Once assigned to a job, MOH is transferred to the work-
in-process inventory account. But Robinson is using a normal costing method and a
budgeted indirect cost allocation rate, although it is using actual direct manufactur-
ing labour-hours per job to assign the MOH to each job. Normal costing will create
a discrepancy for which an accounting adjustment must be made, between what is
recorded as the job is completed and the actual costs incurred.
Once complete, all assigned BCPP costs are transferred to the finished goods
inventory account on the balance sheet. Only when finished goods are sold is an
expense, cost of goods sold, recognized in the income statement and matched against
revenue earned from sales.
GENERAL LEDGER
You know by this point that a job-costing system has a separate job-cost record for each
job. A summary of the job-cost record is typically found in a subsidiary ledger. The
general ledger account Work-in-Process Control presents the total of these separate
job-cost records pertaining to all unfinished jobs. The job-cost records and Work-in-
Process Control account track job costs from when jobs start until they are complete.
Exhibit 4-12 shows T-account relationships for Robinson Company’s general
ledger. The general ledger gives a “bird’s-eye view” of the costing system. The
amounts shown in Exhibit 4-12 are based on the transactions and journal entries that
EXHIBIT 4-12
Normal Job Costing for BCPP: Diagram of General Ledger Relationships for February 2012
GENERAL LEDGER
1 Purchase of 3 Cash paid for direct 4 Incurrence of other 6 Completion and 8 Incurrence of
direct and indirect manufacturing labour, manufacturing transfer to finished marketing and
materials, $89,000 $39,000, and indirect dept. overhead, goods, $188,800 customer-service
2 Usage of direct manufacturing labour, $75,000 7 Cost of goods sold, costs, $60,000
materials, $81,000, $15,000 5 Allocation of $180,000 9 Sales, $270,000
and indirect manufacturing
materials, $4,000 overhead, $80,000
WORK-IN-PROCESS
MATERIALS CONTROL CONTROL REVENUE
1 89,000 2 85,000 2 81,000 6 188,800 9 270,000
3 39,000
MANUFACTURING 5 80,000
GENERAL LEDGER
The debit balance of $8,800 in the Finished Goods Control account represents
the cost of all jobs that have been completed but not sold as of the end of February 2012.
follow. As you go through each journal entry, use Exhibit 4-12 to see how the various
entries being made come together. General ledger accounts with “Control” in the
titles (for example, Materials Control and Accounts Payable Control) have underly-
ing subsidiary ledgers that contain additional details, such as each type of material in
inventory and individual suppliers that Robinson must pay.
A general ledger should be viewed as only one of many tools that assist man-
agement in planning and control. To control operations, managers rely on not only
the source documents used to record amounts in the subsidiary ledgers, but also
nonfinancial information such as the percentage of jobs requiring rework.
EXPLANATIONS OF TRANSACTIONS
We next look at a summary of Robinson Company’s transactions for February 2012
and the corresponding journal entries for those transactions.
1. Purchases of materials (direct and indirect) on credit, $89,000.
Materials Control 89,000
Accounts Payable Control 89,000
SUBSIDIARY LEDGERS
Exhibits 4-13 and 4-14 present subsidiary ledgers that contain the underlying
details—the “worm’s-eye view” as opposed to the “bird’s-eye view” of the general
ledger—such as each type of materials in inventory and costs accumulated in individ-
ual jobs. The sum of all entries in underlying subsidiary ledgers equals the total
amount in the corresponding general ledger control accounts.
EXHIBIT 4-13
Subsidiary Ledger for Materials, Labour, and Manufacturing Department Overhead 2012*
Total cost of all Total cost of all Total cost of all direct and indirect
Other manufacturing
types of materials types of materials manufacturing labour incurred
overhead costs incurred
received in issued in in February, $54,000 ($39,000 ⫹ $15,000)
in February, $75,000
February, $89,000 February, $81,000
*The arrows show how the supporting documentation (for example, copies of materials-requisition records) results in the
journal entry number shown in circles (for example, journal entry number 2) that corresponds to the entries in Exhibit 4-12.
EXHIBIT 4-14
Subsidiary Ledger for Individual Jobs 2012*
Total cost Total cost Total Total cost of all jobs Total cost Total cost
of direct of direct manuf. completed and of all jobs of all jobs
materials manuf. overhead transferred to finished transferred sold and
issued to labour allocated to goods in Feb., $188,800 to finished invoiced
all jobs used on all jobs goods in Feb.,
in Feb., all jobs in Feb., in Feb., $180,000
$81,000 in Feb., $80,000 $188,800
$39,000
*The arrows show how the supporting documentation (for example, copies of materials-requisition records) results in the journal entry
number shown in circles (for example, journal entry number 2) that corresponds to the entries in Exhibit 4-12.
Materials Records and make all the necessary accounting entries in the subsidiary
and general ledgers.
As direct materials are used, they are recorded as issued in the Materials
Records. Exhibit 4-13, Panel A shows a record of the Metal Brackets issued for
the BCPP machine job. Direct materials are also charged to individual job
records, which are the subsidiary ledger accounts for the Work-in-Process
Control account in the general ledger. For example, the metal brackets used in
the BCPP machine job appear as direct material costs of $112 in the subsidiary
ledger under the job-cost record for BCPP (Exhibit 4-14, Panel A). The cost of
direct materials used across all job-cost records for February 2012 is $81,000
(Exhibit 4-14, Panel A).
As indirect materials (for example, lubricants) are used, they are charged to the
Manufacturing Department overhead records (Exhibit 4-13, Panel C), which com-
prise the subsidiary ledger for Manufacturing Overhead Control. The Manufacturing
Department overhead records accumulate actual costs in individual overhead cate-
gories by each indirect cost pool account in the general ledger. Recall that Robinson
has only one indirect cost pool: Manufacturing Overhead. The cost of indirect
materials used is not added directly to individual job records. Instead, the cost of
these indirect materials is allocated to individual job records as a part of manufac-
turing overhead. Total actual MOH costs of $75,000 were incurred in February.
employee labour records shows the different jobs that G. L. Cook worked on and the
$720 of wages owed to G. L. Cook for the week ending February 10. The sum of
total wages owed to all employees for February 2012 is $54,000. The job-cost record
for BCPP shows direct manufacturing labour costs of $450 for the time G. L. Cook
spent on the BCPP machine job (Exhibit 4-14, Panel A). Total direct manufacturing
labour costs recorded in all job-cost records (the subsidiary ledger for Work-in-
Process Control) for February 2012 is $39,000.
G. L. Cook’s employee record shows $54 for maintenance, which is an indirect
manufacturing labour cost. The total indirect manufacturing labour costs of $15,000
for February 2012 appear in the Manufacturing Department overhead records in the
subsidiary ledger (Exhibit 4-13, Panel C). These costs, by definition, are not traced
to an individual job. Instead, they are allocated to individual jobs as a part of manu-
facturing overhead.
Finished Goods Inventory Records by Jobs Exhibit 4-14, Panel A, shows that
Job BCPP was completed at a cost of $9,705. Job BCPP also simultaneously appears
in the finished goods records of the subsidiary ledger. Given Robinson’s use of nor-
mal costing, cost of goods completed consists of actual direct materials, actual direct
manufacturing labour, and manufacturing overhead allocated to each job based on
the budgeted manufacturing overhead rate multiplied by the actual direct manufac-
turing labour-hours. Exhibit 4-14, Panel B, indicates that Job BCPP was sold and
delivered to the customer on February 28, 2012.
Non-manufacturing Costs and Job Costing Chapter 2 (pp. 46–48) pointed out
that companies use product costs for different purposes. The product costs reported
as inventoriable costs to shareholders may differ from product costs reported for
government contracting and may also differ from product costs reported to
managers for guiding pricing and product-mix decisions. Remember, even though
marketing and customer-service costs are expensed when incurred for financial
Job Costing 127
04_horn_ch04.qxd 11/24/11 4:12 PM Page 128
EXHIBIT 4-15
Robinson Company Income Statement for the Month Ending February 2012
Revenue $270,000
Cost of goods sold ($180,000 + $14,000*) 194,000
Gross margin 76,000
Operating costs
Marketing costs $45,000
Customer-service costs 15,000
Total operating costs 60,000
Operating income $ 16,000
*Cost of goods sold has been increased by $14,000, the difference between the
accounting purposes, companies often trace or allocate these costs to individual jobs
for pricing, product-mix, and cost-management decisions.
To identify marketing and customer-service costs of individual jobs, Robinson
can use the same approach to job costing described earlier in this chapter in the
context of manufacturing. Assume marketing and customer-service costs have the
same cost allocation base, revenues, and are included in a single cost pool. Robinson
can then calculate a budgeted indirect cost rate by dividing budgeted indirect mar-
keting and customer-service costs by budgeted revenues. Robinson can use this rate
to allocate these indirect costs to jobs. For example, if this rate were 15% of rev-
enues, Robinson would allocate $2,250 to Job BCPP (0.15 × $15,000, the revenue
from the job). By assigning both manufacturing costs and non-manufacturing costs
to jobs, Robinson can compare all costs against the revenues that different jobs
generate.
PRORATION APPROACH
Proration spreads underallocated overhead or overallocated overhead among ending
work-in-process inventory, finished goods inventory, and cost of goods sold. Materials Job Costing 129
04_horn_ch04.qxd 11/24/11 4:12 PM Page 130
A B C
Allocated
Manufacturing
Overhead
Included in Each
Account Balance Account Balance
1 Account (Before Proration) (Before Proration)
2 Work-in-process control $ 50,000 $ 16,200
3 Finished goods control 75,000 31,320
4 Cost of goods sold 2,375,000 1,032,480
5 $2,500,000 $1,080,000
A B C D E F G
Allocated Allocated
Manufacturing Manufacturing
Overhead Overhead Included
Included in Each in Each Account Proration of $135,000 of Account
Account Balance Account Balance Balance as a Underallocated Balance
10 (Before Proration) (Before Proration) Percent of Total Manufacturing Overhead (After Proration)
11 Account (1) (2) (3) = (2) / $1,080,000 (4) = (3) x $135,000 (5) = (1) + (4)
12 Work-in-process control $ 50,000 $ 16,200 1.5% 0.015 x $135,000 = $ 2,025 $ 52,025
13 Finished goods control 75,000 31,320 2.9% 0.029 x 135,000 = 3,915 78,915
14 Cost of goods sold 2,375,000 1,032,480 95.6% 0.956 x 135,000 = 129,060 2,504,060
15 Total $2,500,000 $1,080,000 100.0% $135,000 $2,635,000
Robinson’s two Manufacturing Overhead accounts are closed with the differ-
ence between them included in cost of goods sold. The Cost of Goods Sold account
after the write-off equals $2,510,000, the balance before the write-off of $2,375,000
plus the underallocated manufacturing overhead amount of $135,000.
(Try to solve this problem before examining the solution that follows.)
PROBLEM
You are asked to bring the following incomplete accounts of Endeavour Printing,
Inc., up to date through January 31, 2013. Consider the data that appear in the
T-accounts as well as the following information in items (a) through (j).
Endeavour’s normal costing system has two direct cost categories (direct
material costs and direct manufacturing labour costs) and one indirect cost pool
(manufacturing overhead costs, which are allocated using direct manufacturing
labour costs).
ADDITIONAL INFORMATION
a. Manufacturing overhead is allocated using a budgeted rate that is set every
December. Management forecasts next year’s manufacturing overhead costs and
next year’s direct manufacturing labour costs. The budget for 2013 is $600,000 for
manufacturing overhead costs and $400,000 for direct manufacturing labour costs.
b. The only job unfinished on January 31, 2013, is No. 419, on which direct manu-
facturing labour costs are $2,000 (125 direct manufacturing labour-hours) and
direct material costs are $8,000.
c. Total direct materials issued to production during January 2013 are $90,000.
d. Cost of goods completed during January is $180,000.
e. Materials inventory as of January 31, 2013, is $20,000.
f. Finished goods inventory as of January 31, 2013, is $15,000.
g. All plant workers earn the same wage rate. Direct manufacturing labour-hours
used for January total 2,500 hours. Other labour costs total $10,000.
h. The gross plant payroll paid in January equals $52,000. Ignore withholdings.
i. All “actual” manufacturing overhead incurred during January has already been
posted.
j. All materials are direct materials.
REQUIRED
Calculate the following:
1. Materials purchased during January.
2. Cost of Goods Sold during January.
3. Direct manufacturing labour costs incurred during January.
4. Manufacturing Overhead Allocated during January.
5. Balance, Wages Payable Control, December 31, 2012.
6. Balance, Work-in-Process Control, January 31, 2013.
7. Balance, Work-in-Process Control, December 31, 2012.
8. Manufacturing Overhead Underallocated or Overallocated for January 2013.
SOLUTION
Letters alongside entries and in T-accounts correspond to letters in the preceding
additional information. Numbers alongside entries in T-accounts correspond to
numbers in the requirements above. Amounts from the T-accounts are labelled
“(T).”
1. From Materials Control T-account, Materials purchased: $90,000 (c) ⫹ $20,000 (e) ⫺
$15,000 (T) ⫽ $95,000
2. From Finished Goods Control T-account, Cost of Goods Sold: $20,000 (T) ⫹
$180,000 (d) ⫺ $15,000 (f) = $185,000
3. Direct manufacturing wage rate: $2,000 (b) ⫼ 125 direct manufacturing labour-
hours (b) ⫽ $16 per direct manufacturing labour-hour
Direct manufacturing labour costs: 2,500 direct manufacturing labour-hours (g) ⫻
$16 per hour ⫽ $40,000
4. Manufacturing overhead rate: $600,000 (a) ⫼ $400,000 (a) ⫽ 150%
Manufacturing Overhead Allocated: 150% of $40,000 ⫽ 1.50 ⫻ $40,000 (see 3) ⫽
$60,000
5. From Wages Payable Control T-account, Wages Payable Control, December 31,
2012: $52,000 (h) ⫹ $3,000 (T) ⫺ $40,000 (see 3) ⫺ $10,000 (g) ⫽ $5,000
6. Work-in-Process Control, January 31, 2013: $8,000 (b) ⫹ $2,000 (b) ⫹ 150% of
132 CHAPTER 4 $2,000 (b) ⫽ $13,000 (This answer is used in item 7.)
04_horn_ch04.qxd 11/24/11 4:12 PM Page 133
Work-in-Process Control
December 31, 2012 Bal. (7) 3,000 (d) 180,000
Direct materials (c) 90,000
Direct manufacturing labour (b) (g) (3) 40,000
Manufacturing overhead
allocated (3) (a) (4) 60,000
January 31, 2013 Bal. (b) (6) 13,000
SUMMARY POINTS
The following question-and-answer format summarizes the chapter’s learning outcomes. Each point
presents a key question, and the guidelines are the answer to that question.
3. How does the decision framework Manufacturing industries are usually machine or capital intensive. The decision framework
apply to product job costing? applies in the same way to product job costing as it does to service job costing. Many manu-
facturing processes are machine or capital intensive rather than labour intensive. This affects
the identification of cost pools and cost allocation bases. The assignment of costs in a product
job-costing system requires the same seven steps.
4. How do you distinguish actual, The difference among these three is in how the cost allocation rate is calculated and the quan-
budgeted, and normal costing tity of the cost allocation base (actual or budgeted) used to assign the indirect cost to each
methods? distinct job.
5. When are transactions recorded A job-costing system records the flow of inventoriable costs: (a) acquisition of all inputs,
in a job-costing system and what (b) their conversion into work-in-process, (c) their conversion into finished goods or services,
methods are available to adjust and (d) the sale of finished goods or services. Year-end adjustments are made to over- or
for over- and underallocation of under-allocated support costs. The over- or underallocation is either prorated or if the
indirect costs? difference is not significant, written off to cost of goods sold.
T E R M S T O L E A R N
This chapter and the Glossary at the end of the book contain definitions of the following
important terms:
actual costing (p. 119) indirect cost allocation rate (p. 106) materials-requisition record (p. 115)
actual indirect cost allocation rate job (p. 109) normal costing (p. 121)
(p. 111) job-cost record (p. 111) opportunity cost (p. 112)
adjusted allocation-rate approach job-cost sheet (p. 111) overallocated indirect costs (p. 128)
(p. 129) job-costing system (p. 109) process-costing system (p. 109)
cost allocation (p. 107) labour intensive (p. 111) proration (p. 129)
cost allocation base (p. 107) labour-time record (p. 115) source document (p. 111)
cost allocation rate (p. 108) manufacturing overhead allocated underallocated indirect costs (p. 128)
cost driver (p. 107) (p. 124)
cost pool (p. 107) manufacturing overhead applied (p. 124)
A S S I G N M E N T M AT E R I A L
MyAccountingLab Make the grade with MyAccountingLab: The questions, exercises, and problems
marked in red can be found on MyAccountingLab at www.myaccountinglab.com. You
can practise them as often as you want, and most feature step-by-step guided
instructions to help you find the right answer. Exercises and problems with an Excel
icon in the margin have an accompanying Excel template on MyAccountingLab.
SHORT-ANSWER QUESTIONS
4-1 How does a job-costing system differ from a process-costing system?
4-2 What is the benefit of creating more than one manufacturing overhead cost pool?
4-3 Why might an advertising agency use job costing for an advertising campaign by Pepsi,
whereas a bank might use process costing to determine the cost of chequing account deposits?
4-4 Describe the seven steps in job costing.
4-5 What are the two major cost objects that managers focus on in companies using job costing?
4-6 Describe the three major source documents used in job-costing systems.
4-7 What is the main concern about source documents used to prepare job-cost records?
134 CHAPTER 4
04_horn_ch04.qxd 11/24/11 4:12 PM Page 135
4-8 Give two reasons why most organizations use an annual period rather than a weekly or
monthly period to compute budgeted indirect cost allocation rates.
4-9 How does actual costing differ from normal costing?
4-10 Describe two ways in which a house-construction company may use job-cost information.
4-11 Comment on the following statement: “In a normal costing system, the amounts in
the Manufacturing Overhead Control account will always equal the amounts in the
Manufacturing Overhead Allocated account.”
4-12 Describe three different debit entries in the Work-in-Process Control general ledger
T-account.
4-13 Describe three alternative ways to dispose of underallocated or overallocated indirect costs.
4-14 When might a company use budgeted costs rather than actual costs to compute direct labour
rates?
4-15 Describe briefly why modern technology such as Electronic Data Interchange (EDI) is help-
ful to managers.
EXERCISES
4-16 Terminology. A number of terms are listed below:
REQUIRED
Select the terms from the above list to complete the following sentences.
1. __________ spreads underallocated overhead or overallocated overhead among ending
work-in-process inventory, finished goods inventory, and cost of goods sold.
2. The benefits of using a(n) __________ cost system is that your costing information is very
accurate.
3. The __________ is the result of dividing the indirect cost pool by the cost allocation base.
4. A __________ is an original record that supports journal entries in an accounting system.
5. A(n) __________ is the contribution to income lost or forgone by not using a limited
resource in its next-best alternative use.
6. _________ is the assigning of direct costs to the chosen cost object.
7. A _________ is a grouping of individual cost items.
4-17 Job costing, process costing. In each of the following situations, determine whether job
costing or process costing would be more appropriate.
4-18 Actual costing, normal costing, manufacturing overhead. Destin Products uses a job-
costing system with two direct cost categories (direct materials and direct manufacturing 1. Budget is 85% of direct
labour) and one manufacturing overhead cost pool. Destin allocates manufacturing overhead labour costs.
costs using direct manufacturing labour costs. Destin provides the following information:
REQUIRED
1. Compute the actual and budgeted manufacturing overhead rates for 2013.
2. During March, the cost record for Job 626 contained the following:
Direct materials used $38,000
Direct manufacturing labour costs $27,000
Compute the cost of Job 626 using (a) an actual costing system and (b) a normal costing system.
3. At the end of 2013, compute the underallocated or overallocated manufacturing overhead
under Destin’s normal costing system. Why is there no underallocated or overallocated
overhead under Destin’s actual costing system?
4. Comment briefly on the advantages and disadvantages of actual costing systems and nor-
mal costing systems.
4-19 Job costing; actual, normal, and variation of normal costing. Chirac & Partners is a
1a. Direct cost rate, $58 per Quebec-based public accounting partnership specializing in audit services. Its job-costing sys-
professional labour-hour; tem has a single direct cost category (professional labour) and a single indirect cost pool (audit
Indirect cost rate, $48 per support, which contains all the costs in the Audit Support Department). Audit support costs
professional labour-hour are allocated to individual jobs using actual professional labour-hours. Chirac & Partners
employs ten professionals who are involved in their auditing services.
Budgeted and actual amounts for 2013 are as follows:
Budget for 2013
Professional labour compensation $960,000
Audit support department costs $720,000
Professional labour-hours billed to clients 16,000 hours
Actual results for 2013
Audit support department costs $744,000
Professional labour-hours billed to clients 15,500 hours
Actual professional labour cost rate $58 per hour
REQUIRED
1. Identify the direct cost rate per professional labour-hour and the indirect cost rate per pro-
fessional labour-hour for 2013 under (a) actual costing, (b) normal costing, and (c) variation
of normal costing that uses budgeted rates for direct costs.
2. The audit of Pierre & Company done in 2013 was budgeted to take 110 hours of profes-
sional labour time. The actual professional labour time on the audit was 120 hours.
Compute the 2013 job cost using (a) actual costing, (b) normal costing, and (c) variation of
normal costing that uses budgeted rates for direct costs. Explain any differences in the job
cost.
4-20 Job costing; actual, normal, and variation from normal costing. Thanatos & Hades
1a. Direct cost rate, $60 per (T&H) is a law firm that specializes in writing wills. Its job-costing system has one direct cost
professional labour-hour; pool, professional labour, and a single indirect cost pool that includes all supporting costs of
Indirect cost rate, $109.09 per running the law office. The support costs are allocated to clients on the basis of professional
professional labour-hour labour-hours. In addition to the two senior partners at T&H, there are six associates who
work directly with clients. Each of the eight lawyers is expected to work for approximately
2,500 hours per year.
Budgeted and actual costs for 2012 were:
Budgeted professional labour costs $1,100,000
Budgeted support costs $2,000,000
Actual professional labour costs $1,320,000
Actual support costs $2,400,000
Actual total professional hours 22,000 hours
136 CHAPTER 4
04_horn_ch04.qxd 11/24/11 4:12 PM Page 137
REQUIRED
1. Compute the direct cost rate and the indirect cost rate per professional labour-hour under:
a. Actual costing.
b. Normal costing.
c. Variation from normal costing that uses budgeted rates for direct costs.
2. The will for a rich tycoon, Ari Roos, was very complex and took four lawyers at the firm
1,000 hours each to prepare. What would be the cost of writing this will under each of the
costing methods in requirement 1?
4-21 Job costing, normal, and actual costing. Anderson Construction assembles residential
homes. It uses a job-costing system with two direct cost categories (direct materials and direct 1a. $50 per direct labour-hour;
labour) and one indirect cost pool (assembly support). The allocation base for assembly b. $42 per direct labour-hour
support costs is direct labour-hours. In December 2012, Anderson budgets 2013 assembly sup-
port costs to be $8,000,000 and 2013 direct labour-hours to be 160,000.
At the end of 2013, Anderson is comparing the costs of several jobs that were started
and completed in 2013. Information for a couple of jobs follows.
Direct materials and direct labour are paid for on a contract basis. The costs of each are
known when direct materials are used or direct labour-hours are worked. The 2013 actual
assembly support costs were $6,888,000, while the actual direct labour-hours were 164,000.
REQUIRED
1. Compute the (a) budgeted and (b) actual indirect cost rate. Why do they differ?
2. What is the job cost of the Laguna Model and the Mission Model using (a) normal costing
and (b) actual costing?
3. Why might Anderson Construction prefer normal costing over actual costing?
4-22 Normal costing, manufacturing overhead. (J. Watson) Trenton Ltd. uses a normal job-
costing system and applies manufacturing overhead to products on the basis of machine hours. 1. $31.25 per machine hour
At the beginning of 2012, the company controller budgeted annual overhead at $1,500,000.
She also forecast that machine hours would total 48,000. Actual costs were as follows:
Machining Assembly
Department Department
The company uses a budgeted overhead rate for allocating overhead to production
orders on a machine-hour basis in Machining and on a direct-manufacturing-labour-cost
basis in Assembly.
REQUIRED
1. During February, the cost record for Job 494 contained the following:
Machining Assembly
Department Department
Rotundo pays all tax professionals employed by Tax Assist on an hourly basis ($36 per hour,
including all fringe benefits).
Tax Assist’s job-costing system has a single direct cost category (professional labour at
$36 per hour) and a single indirect cost pool (office support that is allocated using profes-
sional labour-hours).
Tax Assist charges clients $78 per professional labour-hour.
REQUIRED
1. Compute budgeted indirect cost rates per professional labour-hour using
a. Quarterly budgeted billable hours as the denominator.
b. Annual budgeted billable hours as the denominator.
2. Compute the operating income for the following four customers using
a. Quarterly based indirect cost rates.
b. An annual indirect cost rate.
◆ Stan Hansen: 10 hours in February.
138 CHAPTER 4 ◆ Lelani Kai: 6 hours in March and 4 hours in April.
04_horn_ch04.qxd 11/24/11 4:12 PM Page 139
*The term manufacturing overhead is not used uniformly. Other terms that are often encountered in printing
companies include job overhead and shop overhead.
REQUIRED
1. Prepare general journal entries to summarize 2013 transactions. As your final entry, dispose
of the year-end overallocated or underallocated manufacturing overhead as a direct write-off
to Cost of Goods Sold. Number your entries. Explanations for each entry may be omitted.
2. Show posted T-accounts for all inventories, Cost of Goods Sold, Manufacturing Overhead
Control, and Manufacturing Overhead Allocated.
4-27 Job costing, journal entries. Duchess Ltd. manufactures and installs kitchen cabinetry. It
uses normal job costing with two direct cost categories (direct materials and direct manufac- 1. WIP ending balance, $17.40
turing labour) and one indirect cost pool for manufacturing overhead (MOH), applied on the
basis of machine hours (MH). At the beginning of the year, the company estimated that
it would work 980,000 MH and had budgeted $73,500,000 for MOH. The following data
(in $ millions) pertain to operations for the year 2013:
REQUIRED
1. Prepare general journal entries. Number your entries. Post to T-accounts. What is the
ending balance of Work-in-Process Control?
2. Show the journal entry for disposing of overallocated or underallocated manufacturing
overhead directly as a year-end write-off to Cost of Goods Sold. Post the entry to
T-accounts.
4-28 Job costing, unit cost, ending work-in-process. Coakwell Company worked on only two
1. $551,500 jobs during May. Information on the jobs is given below:
At the beginning of the year, annual manufacturing overhead (MOH) was budgeted at
$3,780,000 and Coakwell budgeted 35,000 DMLH per month. Job A701 was completed in
May.
REQUIRED
1. Compute the total cost of Job A701.
2. Calculate per unit cost for Job A701 assuming it has 2,500 units.
3. Make this journal entry transferring Job A701 to Finished Goods.
4. Determine the ending balance in the Work-in-Process account.
4-29 Job costing, various cost drivers. (J. Watson) Rochester Ltd. has budgeted $435,000 for
1a. $25 per direct manufacturing overhead for the upcoming year. It forecast that 72,500 machine hours will be
labour-hour used in the factory, and budgeted direct labour-hours were 17,400. The average direct labour
rate is budgeted to be $20. Actual data for the year were:
REQUIRED
1. Compute the budgeted manufacturing overhead rate under each of the following cost
drivers:
a. Direct labour-hours
b. Direct labour cost
c. Machine hours
2. Compute the amount of underallocated or overallocated manufacturing overhead under
each of the cost drivers listed in requirement 1.
4-30 Job costing, journal entries, T-accounts, source documents. Production Company
2. Overallocation, $16,000 produces gadgets for the coveted small appliance market. The following data reflect activity
for the most recent year, 2012:
Costs incurred
Purchases of direct materials (net) on account $124,000
Direct manufacturing labour cost 80,000
Indirect labour 54,500
Amortization, factory equipment 30,000
Amortization, office equipment 7,000
Maintenance, factory equipment 20,000
Miscellaneous factory overhead 9,500
Rent, factory building 70,000
Advertising expense 90,000
Sales commissions 30,000
140 CHAPTER 4
04_horn_ch04.qxd 11/24/11 4:12 PM Page 141
Production Company uses a normal job-costing system and allocates overhead to work-in-
process at a rate of $2.50 per direct manufacturing labour dollar. Indirect materials are
insignificant, so there is no inventory account for indirect materials.
REQUIRED
1. Prepare journal entries to record the 2012 transactions including an entry to close out over-
allocated or underallocated overhead to cost of goods sold. For each journal entry, indicate
the source document that would be used to authorize each entry. Also note which subsidiary
ledger, if any, should be referenced as backup for the entry.
2. Post the journal entries to T-accounts for all of the inventories, Cost of Goods Sold,
Manufacturing Overhead Control, and Manufacturing Overhead Allocated accounts.
4-31 Accounting for manufacturing overhead. Consider the following selected cost data for
KYM Inc. for 2013.
1. $22 per MH
KYM’s job-costing system has a single manufacturing overhead cost pool (allocated using a
budgeted rate based on actual MH). Any amount of underallocation or overallocation is
immediately written off to cost of goods sold.
REQUIRED
1. Compute the budgeted manufacturing overhead (MOH) rate.
2. Journalize the allocation of manufacturing overhead (MOH).
3. Compute the amount of underallocation or overallocation of MOH. Is the amount signif-
icant? Journalize the disposition of this amount based on the ending balances in the rele-
vant accounts.
4-32 Proration of overhead. The Ride-On-Water (ROW) Company produces a line of non-
motorized boats. ROW uses a normal job-costing system and allocates manufacturing over- 1. 50% of direct
head costs using direct manufacturing labour cost. The following data are available for 2012: manufacturing labour costs
Budgeted manufacturing overhead costs $100,000
Budgeted direct manufacturing labour cost $200,000
Actual manufacturing overhead costs $106,000
Actual direct manufacturing labour cost $220,000
4-33 Job costing, solving for unknowns. (J. Watson) Osprey Ltd. manufactures designer purses.
a. $653,000 During the year, it recorded direct materials used of $684,000. Total manufacturing costs of
$1,482,000 were incurred during the year. Osprey uses one indirect cost pool for all overhead
costs and allocates overhead at a rate of 60% of direct labour dollars.
January 1 December 31
REQUIRED
Prepare a Schedule of Cost of Goods Manufactured and Sold for the year. You will need to
solve for the following unknowns:
a. Direct materials purchased.
b. Direct labour costs.
c. Manufacturing overhead allocated.
d. Cost of goods manufactured.
e. Cost of goods sold.
PROBLEMS
4-34 Job-costing procedures. Broadway Printers operates a printing press with a monthly cap-
1. Taylor operating acity of 2,000 machine hours (MH). Broadway has two main customers, Taylor Corporation
margin, 2.5% and Kelly Corporation. Data on each customer for January follow:
Taylor Kelly
Corporation Corporation Total
Each of the following requirements refers only to the preceding data; there is no connection
between the requirements.
REQUIRED
1. Fixed costs arise because equipment and other capacity have been purchased. What would
the allocation of fixed costs and what would be the operating income and operating margin
for each job if the fixed MOH cost allocation base were machine hours instead of revenue?
2. Should Broadway drop the Kelly Corporation business? If Broadway drops the Kelly
Corporation business, its total fixed costs will decrease by 20%.
3. Kelly Corporation indicates that it wants Broadway to do an additional $88,000 worth of
printing jobs during February. These jobs are identical to the existing business Broadway did
for Kelly in January in terms of variable costs and machine hours required. Broadway
anticipates that the business from Taylor Corporation in February will be the same as that
in January. Broadway can choose to accept as much of the Taylor and Kelly business for
February as it wants. Assume that total fixed costs for February will be the same as the
fixed costs in January. What should Broadway do? What will Broadway’s operating income
be in February?
4-35 Disposition of underallocated or overallocated overhead. ( J. Watson) Princeton
1. Underallocated, $35,000 Manufacturing budgeted $325,000 and incurred $337,000 of overhead costs in the past year.
During the year, it allocated $302,000 to its production. An extract from the company’s finan-
cial records showed the following account balances:
Work-in-Process Inventory $26,000
Finished Goods Inventory $37,625
Cost of Goods Sold $86,375
142 CHAPTER 4
04_horn_ch04.qxd 11/24/11 4:12 PM Page 143
REQUIRED
1. Calculate the amount of underallocated or overallocated manufacturing overhead for the
year.
2. Prepare the journal entry to dispose of this underallocated or overallocated overhead
amount using
a. Immediate write-off to Cost of Goods Sold.
b. Proration based on ending balances (before proration) in Work-in-Process Inventory,
Finished Goods Inventory, and Cost of Goods Sold.
3. Which method do you recommend for this company?
4-36 Job costing, law firm. Keating & Partners is a law firm specializing in labour relations and
employee-related work. It employs 25 professionals (5 partners and 20 managers) who work 1. $65 per professional
directly with its clients. The average budgeted total compensation per professional for 2013 is labour-hour
$104,000. Each professional is budgeted to have 1,600 billable hours to clients in 2013.
Keating is a highly respected firm, and all professionals work for clients to their maximum
1,600 billable hours available. All professional labour costs are included in a single direct cost
category and are traced to jobs on a per-hour basis.
All costs of Keating & Partners other than professional labour costs are included in a
single indirect cost pool (legal support) and are allocated to jobs using professional labour-
hours as the allocation base. The budgeted level of indirect costs in 2013 is $2.2 million.
REQUIRED
1. Compute the 2013 budgeted professional labour-hour direct cost rate.
2. Compute the 2013 budgeted indirect cost rate per hour of professional labour.
3. Keating & Partners is considering bidding on two jobs:
a. Litigation work for Richardson Inc. that requires 100 budgeted hours of professional
labour.
b. Labour contract work for Punch Inc. that requires 150 budgeted hours of professional
labour.
Prepare a cost estimate for each job.
4-37 Job costing with two direct cost and two indirect cost categories, law firm (continua-
tion of 4-36). Keating has just completed a review of its job-costing system. This review 1a. $125 per hour
included a detailed analysis of how past jobs used the firm’s resources and interviews with per- b. $50 per hour
sonnel about what factors drive the level of indirect costs. Management concluded that a sys-
tem with two direct cost categories (professional partner labour and professional manager
labour) and two indirect cost categories (general support and administration support) would
yield more accurate job costs. Budgeted information for 2013 related to the two direct cost
categories is as follows:
Professional Professional
Partner Labour Manager Labour
Number of professionals 5 20
Hours of billable time per professional 1,600 per year 1,600 per year
Total compensation (average per professional) $200,000 $80,000
Budgeted information for 2013 relating to the two indirect cost categories is
General Administration
Support Support
REQUIRED
1. Compute the 2013 budgeted direct cost rates for (a) professional partners and (b) profes-
sional managers.
2. Compute the 2013 budgeted indirect cost rates for (a) general support and (b) administra-
tion support.
3. Compute the budgeted job costs for the Richardson and Punch jobs, given the following
information:
4. Comment on the results in requirement 3. Why are the job costs different from those
computed in Problem 4-36?
4-38 Normal costing, overhead allocation, working backwards. Gaston Ltd. uses a normal job-
1. $2,875,000 costing system with two direct cost categories—direct materials and direct manufacturing
labour—and one indirect cost category—manufacturing overhead. At the beginning of 2013,
Gaston had $236,000 in work-in-process inventory. The company allocates manufacturing
overhead at the rate of 180% of direct manufacturing labour costs. Total allocated manufac-
turing overhead for the year was $5,175,000. Manufacturing costs incurred for the year were
$9,732,500 and the cost of goods manufactured for the year totalled $9,612,200.
REQUIRED
1. What was the total direct labour cost in 2013?
2. What was the total cost of direct materials used in 2013?
3. What was the dollar amount of work-in-process inventory on December 31, 2013?
4-39 Disposition of overhead overallocation or underallocation, two indirect cost pools.
2. Machining Department: Glavine Corporation manufactures precision equipment made to order for the semiconduc-
Overallocation, $510,000; tor industry. Glavine uses two manufacturing overhead cost pools—one for the overhead
Assembly Department: costs incurred in its highly automated Machining Department and another for overhead costs
Underallocation, $170,000 incurred in its labour-based Assembly Department. Glavine uses a normal costing system. It
allocates Machining Department overhead costs to jobs based on actual machine hours using
a budgeted machine hour overhead rate. It allocates Assembly Department overhead costs to
jobs based on actual direct manufacturing labour-hours using a budgeted direct manufactur-
ing labour-hour rate.
The following data are for the year 2013:
Machining Assembly
Department Department
Machine hours and direct manufacturing labour-hours and the ending balances (before
proration of underallocated overhead) are as follows:
REQUIRED
1. Compute the budgeted overhead rates for the year in the Machining and Assembly
Departments.
2. Compute the underallocated or overallocated overhead in each department for the year.
Dispose of the underallocated or overallocated amount in each department using:
a. Immediate write-off to Cost of Goods Sold.
b. Proration based on ending balances (before proration) in Cost of Goods Sold, Finished
Goods, and Work-in-Process.
144 CHAPTER 4
04_horn_ch04.qxd 11/24/11 4:12 PM Page 145
c. Proration based on the allocated overhead amount (before proration) in the ending
balances of Cost of Goods Sold, Finished Goods, and Work-in-Process.
3. Which disposition method do you prefer in requirement 2? Explain.
4-40 Job costing, normal versus actual under/over applied overhead. ( J. Watson) The
following information relates to the activities of King Ltd. for the year 2013: 1. Underallocated, $21,100
The company uses normal costing and applies overhead on the basis of machine hours (MH).
The company had calculated its overhead rate to be $4.25 per MH on the basis of 60,000
budgeted MH. Actual MH worked in the plant were 63,200.
REQUIRED
1. Compute the amount of overallocated or underallocated overhead for the year.
2. Prepare the journal entry to record the disposition of the amount of overallocated or
underallocated overhead assuming the company writes off the difference to Cost of Goods
Sold.
3. Identify and briefly outline an alternative treatment (from requirement 2) for disposing of
overallocated or underallocated overhead.
4. Prepare a Schedule of Cost of Goods Manufactured for the year.
5. Briefly explain the differences between actual and normal costing, and state how the
Schedule of Cost of Goods Manufactured would differ under actual costing.
4-41 Job costing and governance. Jack Halpern is the owner and CEO of Aerospace Comfort, a
firm specializing in the manufacture of seats for air transport. He has just received a copy of a 1. $820.30 per seat
letter written to the Auditor General of the Canadian government. He believes it is from an
ex-employee of Aerospace.
Dear Sir,
Aerospace Comfort in 2013 manufactured 100 X7 seats for the Canadian Forces. You may
be interested to know the following:
1. Direct materials cost billed for the 100 X7 seats was $40,000.
2. Direct manufacturing labour cost billed for 100 X7 seats was $8,400. This cost includes
16 hours of setup labour at $50 per hour, an amount included in the manufacturing over-
head cost pool as well. The $8,400 also includes 15 hours of design time at $120 an hour.
Design time was explicitly identified as a cost the Canadian Forces was not to reimburse.
3. Manufacturing overhead cost billed for 100 X7 seats was $14,700 (175% of direct manu-
facturing labour costs). This amount includes the 16 hours of setup labour at $50 per
hour that is incorrectly included as part of direct manufacturing labour costs.
You may also want to know that over 40% of the direct materials is purchased from
Frontier Technology, a company that is 51% owned by Jack Halpern’s brother.
For obvious reasons, this letter will not be signed.
c.c.: The Globe and Mail
Jack Halpern, CEO of Aerospace Comfort
Aerospace Comfort’s contract states that the Canadian Forces reimburses Aerospace
at 130% of manufacturing costs.
REQUIRED
Assume that the facts in the letter are correct as you answer the following questions.
1. What is the cost amount per X7 seat that Aerospace Comfort billed the Canadian Forces?
Assume that the actual direct materials costs are $40,000.
2. What is the amount per X7 seat that Aerospace Comfort should have billed the Canadian
Forces? Assume that the actual direct materials costs are $40,000.
3. Based on the problems highlighted in the letter, what should the Canadian Forces do to
tighten its procurement procedures to reduce the likelihood of such situations recurring?
Job Costing 145
04_horn_ch04.qxd 11/24/11 4:12 PM Page 146
At the end of 2013, two jobs were incomplete: No. 1768B (total direct manufacturing labour
costs were $15,000) and No. 1819C (total direct manufacturing labour costs were $48,000).
Machine time totalled 318 hours for No. 1768B and 654 hours for No. 1819C. Direct mate-
rials issued to No. 1768B amounted to $30,600. Direct materials for No. 1819C came to
$56,800.
Total charges to the Manufacturing Overhead Control account for the year were
$406,200. Direct manufacturing labour charges made to all jobs were $650,000, representing
25,000 direct manufacturing labour-hours (DMLH).
There were no beginning inventories. In addition to the ending work-in-process, the
ending finished goods showed a balance of $204,500 (including a direct manufacturing labour
cost component of $60,000). Sales for 2013 totalled $3,124,000, cost of goods sold was
$2,200,000, and marketing costs were $523,900.
Nicole prices on a cost-plus basis. It currently uses a guideline of cost plus 40% of cost.
REQUIRED
1. Prepare a detailed schedule showing the ending balances in the inventories and cost of goods
sold (before considering any underallocated or overallocated manufacturing overhead).
Show also the manufacturing overhead allocated to these ending balances.
2. Compute the underallocated or overallocated manufacturing overhead for 2013.
3. Prorate the amount computed in requirement 2 on the basis of:
a. The ending balances (before proration) of work-in-process, finished goods, and cost of
goods sold.
b. The allocated overhead amount (before proration) in the ending balances of work-
in-process, finished goods, and cost of goods sold.
4. Assume that Nicole decides to immediately write off to Cost of Goods Sold any underallo-
cated or overallocated manufacturing overhead. Will operating income be higher or lower
than the operating income that would have resulted from the proration in requirements 3(a)
and 3(b)?
5. Calculate the cost of job No. 1819C if Nicole Limited had used the adjusted allocation
rate approach to disposing of underallocated or overallocated manufacturing overhead
in 2013.
4-43 General ledger relationships, underallocation and overallocation. (S. Sridhar, adapted)
1. $403,000 Northley Industries is a manufacturer of sailboats. The following partial information for 2013
is available:
543,000
146 CHAPTER 4
04_horn_ch04.qxd 11/24/11 4:12 PM Page 147
ADDITIONAL INFORMATION
1. Direct manufacturing labour wage rate was $16 per hour.
2. Manufacturing overhead (MOH) is allocated at $25 per direct manufacturing labour-hour
(DMLH).
3. During the year, sales revenues were $1,664,000, and marketing and distribution expenses
were $199,700.
REQUIRED
1.
What was the amount of direct materials issued to manufacturing during the year?
2.
What was the amount of manufacturing overhead allocated to jobs during the year?
3.
What was the cost of jobs completed during the year?
4.
What was the balance in work-in-process inventory on December 31, 2013?
5.
What was the cost of goods sold before any proration of underallocated or overallocated
overhead?
6. What was the underallocated or overallocated manufacturing overhead for the year?
7. Dispose of the underallocated or overallocated manufacturing overhead using:
a. Immediate write-off to Cost of Goods Sold.
b. Proration based on ending balances (before proration) in Work-in-Process, Finished
Goods, and Cost of Goods Sold.
8. Using each of the disposition methods in requirement 7, calculate operating income for the
year.
9. Which disposition method in requirement 7 do you recommend Northley use? Explain
your answer briefly.
4-44 Normal costing, departments. ( J. Watson) Kalor Ltd. uses a normal job-costing system
with two direct cost categories, direct materials and direct labour, and one indirect cost pool. 1. $17,829,625
Manufacturing overhead is allocated based on direct labour costs. Any overallocated or
underallocated overhead is written off to Cost of Goods Sold. Each product goes through two
departments, Fabrication and Assembly. The Fabrication process is automated whereas the
Assembly Department is highly labour intensive. Kalor’s budget for 2013 was as follows:
Kalor started the year without any work-in-process. During the year it had the
following results:
At December 31, 2013, the company had only two jobs still in process, #Z438 and
#Q917. Job #Z438 had $7,000 of direct materials and $1,500 of direct labour and had used
3,400 MH in fabrication. It had not yet been transferred to the Assembly Department. Job
#Q917 had incurred $4,000 and $6,000 of direct materials costs in Fabrication and Assembly,
respectively. It had used 1,800 MH in Fabrication and 800 MH in Assembly. Labour charges
in the two departments were $9,000 and $18,000 for Fabrication and Assembly, respectively.
REQUIRED
1. Calculate Cost of Goods Manufactured for the year ended December 31, 2013, assuming
the company uses its current overhead costing method.
2. Under the current costing system, what is the amount of overallocated or underallocated
overhead?
3. What would be the amount of overallocated or underallocated overhead at the end of the
year if the company had used departmental overhead rates with the most appropriate base
for each department?
Machine-hours data and the ending balances (before proration of underallocated or overallo-
cated overhead) are as follows:
REQUIRED
1. Compute the budgeted manufacturing overhead rate for 2013.
2. Compute the underallocated or overallocated manufacturing overhead of Naf Radiator in
2013. Dispose of this underallocated or overallocated amount using:
a. Write-off to Cost of Goods Sold.
b. Proration based on ending balances (before proration) in Work-in-Process Control,
Finished Goods Control, and Cost of Goods Sold.
c. Proration based on the allocated overhead amount (before proration) in the ending bal-
ances of Work-in-Process Control, Finished Goods Control, and Cost of Goods Sold.
3. Which method do you prefer in requirement 2? Explain.
Work-in-Process at December 1
During the month of December the following costs were incurred by job:
148 CHAPTER 4
04_horn_ch04.qxd 11/24/11 4:12 PM Page 149
In addition, the company incurred the following costs during the month of December
(these costs have not yet been recorded in the books):
ADDITIONAL INFORMATION
1. The balance in the Overhead Control account on December 1 was $195,010.
2. There were no jobs in Finished Goods as of December 1.
3. Jobs # 815, 822, 823, and 824 were completed during December.
4. Job 824 is the only job in Finished Goods as of December 31.
5. The company’s pricing policy is 200% of total manufacturing cost.
REQUIRED
1. Calculate the budgeted overhead rate used by Pearson.
2. Calculate the unit cost of ending work-in-process inventory assuming that the number of
units in the job(s) total 250 units.
3. Calculate the cost of goods manufactured and the unadjusted gross margin for the month
of December.
4. Calculate the amount of overallocated or underallocated overhead for the year.
4-47 Job costing, service industry. Michael Scott books tours for new bands, and arranges to
print T-shirts and produce demo CDs to sell on the tour. Scott’s agency uses a normal costing 1. $2,100
system with two direct cost pools, labour and materials, and one indirect cost pool, general
overhead. General overhead is allocated to each tour at 150% of labour cost. The following
information relates to the agency for 2013:
1. As of June 1, there were tours in progress for two bands: Grunge Express and Different
Strokes.
2. During June, both bands finished their tours.
3. New tours were started for three bands, As I Lay Dying, Ask Me Later, and Maybe
Tomorrow. Of these bands, only Maybe Tomorrow finished its tour by the end of June.
All costs incurred during the planning stage for a tour are gathered in a balance sheet account
called “Tours In Process (TIP)”. When a tour is completed, the costs are transferred to an
income statement account called “Cost of Completed Tours (CCT).”
The following cost information is for June: