Test Project: Earned Value Analysis Report
Test Project: Earned Value Analysis Report
BAC $1,000,000.00
PV $500,000.00
AC $510,000.00
EV $420,000.00
In this example,
the project is
over budget
Cost Variance (CV = EV - AC) -$90,000.00
and behind
Cost Performance Index (CPI = EV/AC) 0.82 schedule
Schedule Variance (SV = EV - PV) -$80,000.00
Schedule Performance Index (SPI = EV/PV) 0.84