Tutorial - Build A Simple Project Plan With Microsoft Project
Tutorial - Build A Simple Project Plan With Microsoft Project
http://techgenix.com/build-project-microsoft-project/ 1/12
٢٠١٨/٤/١٢ Tutorial: Build a simple project plan with Microsoft Project - TechGenix
Email address
SUBSCRIBE
LATEST PODCAST
TechGenix Xtreme
Top Windows 10 …
For this tutorial, I am going to show you how to create tasks and link them
together using constraint-based scheduling.
Constraint-based scheduling
You could probably use a spreadsheet to list out a bunch of tasks and enter
some dates. However, if you change the date of one task and want that to roll
down and adjust the dates of other tasks, you are getting into some
complicated math and scripting. Microsoft Project helps you automatically
calculate the start and finish dates of tasks by using constraints
called predecessors and successors, as shown in the following figure.
http://techgenix.com/build-project-microsoft-project/ 2/12
٢٠١٨/٤/١٢ Tutorial: Build a simple project plan with Microsoft Project - TechGenix
As you can see in that previous figure, task #1 (research models online) starts
before task #2 (test drive cars at various dealers). You represent this by
typing the number 1 in line 2's predecessor column. The graphical chart on
the right is called a Gantt chart. The Gantt chart shows how Microsoft Project
is automatically calculating when one task should start and the other should
finish.
Since the project summary task is not a default option, you need to enable it.
Follow these steps to display the project summary task at the top of your
project:
1. Click the File tab and then select the Options menu item.
2. The project options dialog appears as shown in the following figure.
3. Select the Advanced item.
Locate the Display options for this project section and select All New
projects from the pick list.
Select the Show project summary task.
http://techgenix.com/build-project-microsoft-project/ 4/12
٢٠١٨/٤/١٢ Tutorial: Build a simple project plan with Microsoft Project - TechGenix
The project options dialog with the show project summary task option selected.
From now on, when you create a project, the project summary task will
display (task zero).
1. The blank project should be open as shown in the following figure (the
project name might be different for you).
Click the Task tab and then click the Gantt chart icon.
Verify you can view the project summary task.
Verify all new tasks are auto scheduled by viewing the status bar at the
bottom-left side of the application window.
http://techgenix.com/build-project-microsoft-project/ 5/12
٢٠١٨/٤/١٢ Tutorial: Build a simple project plan with Microsoft Project - TechGenix
1. Click the File tab, select the Save As item, and save the file to a location
of your choosing.
2. Name the file My New House.
http://techgenix.com/build-project-microsoft-project/ 6/12
٢٠١٨/٤/١٢ Tutorial: Build a simple project plan with Microsoft Project - TechGenix
1. Locate the duration field and type the durations as shown in the
following figures.
Note: You do not have to type out the duration completely. You can just
type 30, 20, 10, etc. and Microsoft Project will automatically add the days
text. If there is a problem, type 30d, 20d, 10d, etc.
http://techgenix.com/build-project-microsoft-project/ 7/12
٢٠١٨/٤/١٢ Tutorial: Build a simple project plan with Microsoft Project - TechGenix
Now your project plan should look something like the figure below:
1. Locate the Predecessors column and enter the numbers shown in the
figures below.
Note: You can link one task to multiple tasks by separating each number
with a comma.
http://techgenix.com/build-project-microsoft-project/ 8/12
٢٠١٨/٤/١٢ Tutorial: Build a simple project plan with Microsoft Project - TechGenix
Link all the tasks so Microsoft Project can calculate the start and nish date for your project.
http://techgenix.com/build-project-microsoft-project/ 9/12
٢٠١٨/٤/١٢ Tutorial: Build a simple project plan with Microsoft Project - TechGenix
What's next
In this tutorial, I showed you the basics for configuring scheduling options,
adding tasks, and linking them with predecessors. These are just the first
steps in creating and managing a project schedule.
If a certain task gets delayed, change the duration field, not the start or finish
date. To show task progression, you can insert the % complete field and type
in any percentages. (I recommend you start with 0, 25, 50, 75 and 100%.)
Microsoft Project has many more features, such as the ability to add
resources, create milestones, build reports and much more. If you find this
article interesting and would like to learn more, let us know in the comments.
READ NEXT
AUTHOR
Bill Raymond
http://techgenix.com/build-project-microsoft-project/ 10/12
٢٠١٨/٤/١٢ Tutorial: Build a simple project plan with Microsoft Project - TechGenix
2 COMMENTS
Hi Bill,
Thank you
Your email address will not be published. Required fields are marked
*
POST COMMENT
http://techgenix.com/build-project-microsoft-project/ 11/12
٢٠١٨/٤/١٢ Tutorial: Build a simple project plan with Microsoft Project - TechGenix
Microsoft in 2018:
TechGenix reaches millions of IT
What does Redmond have
Professionals every month, and has
in store?
set the standard for providing free
technical content through its GoScanSSH
growing family of websites, malware targeting
empowering them with the answers public SSH servers
and tools that are needed to set up,
configure, maintain and enhance
their networks.