Project Controls
Project Controls
PROJECT CONTROLS
EXECUTIVE SUMMARY
In May 2008, Governor Deval Patrick introduced the $3 billion Accelerated Bridge
Program (ABP) to reduce the Commonwealth’s growing backlog of structurally deficient
bridges. The Accelerated Bridge Program will dramatically improve the health of
Massachusetts bridges and create thousands of jobs. At the same time, taxpayer dollars
will be efficiently spent, eliminating or reducing construction cost inflation and the
expensive deterioration that comes with time. By completing projects sooner, the
Commonwealth will avoid losing critical dollars to inflation. To ensure the goals of the
program are achieved, new program and project controls are being implemented by the
Massachusetts Highway Department (MassHighway), the Department of Conservation
and Recreation (DCR) (collectively, the “Agencies”) and the Oversight Council charged
with coordinating the program. This report describes the state-of-the-art cost, schedule,
and quality management practices that will govern this program. The intense focus on
streamlining project delivery, adoption of innovative design, construction, and project
management techniques promise to make the Accelerated Bridge Program a
transformative initiative that will yield far-reaching improvements extending beyond the
next eight years and across state government.
Central to the mission of the Accelerated Bridge Program is the requirement for
transparency and accountability in all aspects of program management. As a result, cost
and schedule controls will go beyond minimum industry standards for project delivery
and include an ongoing focus on public reporting. Chapter 233 of the Acts of 2008,
which authorizes the Accelerated Bridge Program, specifically requires the
implementation of effective project controls to ensure adequate tracking and reporting of
program progress, cost and schedule. The controls described in this report will
themselves be continuously improved so that over the next eight years, the controls and
reports will evolve to meet the challenges presented. The data and reports generated
through these controls will guide critical program management decisions aimed at
delivering projects on-time and on-budget and provide the public a clear view of the work
performed and the Commonwealth’s return on investment.
The Program Controls described in this report were developed over the past several
weeks and are based on a review of best practices from other state programs, agency
expertise, industry best practices and were prepared with the goal of meeting the public
reporting requirements for the program. MassHighway contracted with Keville
Enterprises, Inc. (KEI), to review current agency internal practices and recommend
i
improvements to such practices with regards to the on-time, on-budget provisions of the
Accelerated Bridge legislation. KEI published dozens of cost and schedule options in a
draft report dated November 1, 2008. In order to address the volume and complexity of
the report, three working groups were assembled to address three categories of
observations and recommendations.
The three working groups were comprised of MassHighway staff that is intimately
knowledgeable in the current operations and procedures of MassHighway. A
representative of DCR participated in each working group and a representative of KEI
served as the facilitator. The ABP management team empowered these individuals to
carefully investigate, assess and debate the options in the draft report. Each working
group was tasked with the development of a list of cost and schedule recommendations or
control measures to adopt.
The cost and schedule recommendations were classified into four categories:
The working groups completed their tasks by November 24, 2008. Final
recommendations were approved by ABP senior management for inclusion in this Project
Controls Report.
It is important to note that the control and reporting requirements contained in the
legislation are extremely aggressive, requiring reporting of detailed project level cost and
schedule information very early in the program, and generally establishing a goal that at
least ninety percent of the bridges in the ABP will be completed on time and on budget.
Every effort has been made to meet these requirements while also delivering the program
in an effective and business-like manner. Best management practices dictate that
successful performance measurement begins with well-structured goals based on accurate
data and assumptions. Inherent to the construction process is the refining of data and
assumptions as projects are scoped and design progresses. Project delivery goals to be
used for performance management are therefore more accurately set at the point of 75%
complete design. Continuous monitoring and reporting throughout the program will
reflect both the progress that is being made and the level of confidence to be accorded
project goals for cost and schedule.
ii
This report is divided into four major sections: 1. Cost Control; 2. Schedule Control; 3.
Construction Quality; and 4. Implementation. Each of these sections contains specific
recommended project control measures for implementation on the ABP. Some of the
measures should be implemented at the project level, and some should be implemented at
the program level. When fully implemented, as a whole, these integrated measures will
provide a project controls system that will allow for effective cost and schedule
monitoring, control, and reporting on the ABP.
COST CONTROL
Section 1 of this Report, Cost Control, provides recommended cost control measures.
These cost control measures are categorized as: Budget and Reporting; Program Cost
Control; Construction Cost Estimating; and Contract Cost Management measures.
Achievement of these measures will provide the Agencies with an effective budget
control and reporting system for the ABP.
iii
• internal monthly program control meetings;
• identifying and monitoring areas of potential cost growth;
• forecasting potential cost growth associated with change orders and claims;
• estimating and monitoring program overhead costs;
• implementing a design-to-cost program;
• incorporating federal agency guidelines for accounting for cost contingencies;
• accounting for cost escalation;
• developing program level cost contingencies;
• developing contract level cost contingencies;
• monitoring and accounting for market price fluctuations; and
• recognizing and avoiding potential schedule delays and their associated costs.
The most effective approach to cost estimating is to develop estimates that are based on
the way that the project will be constructed, otherwise referred to as “bottoms-up” cost
estimating. This involves developing the crews, equipment, and production rates that
would be used to construct the project and developing the estimate based on this
information. This approach to cost estimating results in an estimate that reflects a
buildable approach to the work, while at the same time building in a constructability
check. Another benefit of this approach to cost estimating is that the crew, equipment,
and production rate information that is developed can be easily translated into a project
construction schedule that is integrated with the cost estimate. This early linking of
project cost and project schedule fosters effective cost and schedule control throughout
the life of the project. This bottoms-up approach to cost estimating will be used on all
ABP projects.
iv
SCHEDULE CONTROL
The ABP will also use Design-Build (DB) contracts on ABP projects where appropriate,
in order to minimize project schedules and project costs. Design-Bid-Build (DBB) has
historically been the routine project delivery method used for MassHighway and DCR
projects. It is commonly accepted in the design and construction industry that using the
Design-Build (DB) project delivery method will result in shorter project duration than if
the DBB project delivery method is used, primarily because construction can begin prior
to design completion. Shorter project durations can reduce duration of project overhead
and general condition costs, as well as reduced cost escalation over time. Moreover,
quality improves because the construction company that is actually building the project
can provide direct constructability input during the design process.
v
Construction Schedule Control
Effective schedule control on the nearly $3 Billion Accelerated Bridge Program has
enormous cost ramifications. Prolonged schedule durations translate to increased internal
program costs, increased construction and design overheads, and construction cost
escalation. Accordingly, effective schedule control measures are critical to the success of
the ABP. This report contains recommendations on specific schedule control measures
which, when implemented, will provide an effective schedule control system.
Recommended measures include:
CONSTRUCTION QUALITY
IMPLEMENTATION
vi
from planning, design, construction, operations, finance, or other organizations within the
ABP. The Project Controls organization must be staffed adequately in order to ensure
effective control of program and project costs and schedules.
In addition to establishing the Project Controls Organization, over the next few months,
the Agencies will focus on the following aspects of the Program Controls plan:
All of the control measures implemented will be done with the goal of maintaining
transparency and public access to the status of the ABP program and projects. In light of
this goal, a visual web-based status tool will be created. This tool will provide instant
project status information to Oversight Committee members, community groups,
legislators, municipalities, and the general public. Since this tool will provide an aerial
visualization of each bridge and its surroundings, it can also be used for construction
planning and public outreach.
By law, the Legislature will receive bi-annual reports of the updates to program controls.
vii
SECTION 1 - COST CONTROL
1.A.0 –Introduction
Quality procedures for project control and record keeping are indispensable tools for
Program management and project teams during the planning and execution of a large
project such as the Accelerated Bridge Program. These tools serve the dual purpose of
recording the financial transactions that occur and giving managers an indication of the
progress and problems associated with the project. Cost and schedule management
produce a positive outcome when it effectively aligns the demands of the project
objectives, legislative and public expectations, and fiscal prudence.
In order to implement this Program, the Agencies will set up a multi-tiered reporting
approach. Performance tracking indicators, including but not limited to those identified
in Chapter 233, will be identified and will become the basis for the data presented in ABP
reports. Monthly, quarterly and semi-annual reports generated will be periodically
reviewed with program stakeholders to ensure that all required data is being captured and
presented in a concise and clear format. In addition, the Program will use a web-based
reporting tool that will allow anyone to use the internet to find up-to-date information on
the status of each bridge project as well as the Program as a whole.
Because many of the ABP projects are in the conceptual stage, performance indicators
provided this year (2009) will not be based upon solid advanced designs. For many
projects, not enough scope definition, quantitative information (plans and documents to
provide pricing), or detailed/adequate costs or schedule assessments have yet been
developed. Because of the early stages of design, cost and construction schedule
information is very preliminary and should not be used at this point to control contract
budgets without sufficient contingencies.
2. Designers and Engineers who work for the ABP Program do so as part of a
Designer performance review program that will maintain a high level of
accountability for elements within their control, while promoting a ‘team’
approach (see Section 1.B.10 below).
3. Because of limited scope definition in the early stages of design (i.e.) Structural
submission is not complete until the 75%), internal performance monitoring
will be established after the 75% construction estimate and schedule are
developed and agreed to. This will be the Program definition of “90% on-
time/on-budget.”
4. Allow ample time to properly scope and budget each individual contract – before
budget tracking is fully committed.
5. Reasonably identify program cost components that are within the control of the
Program’s management team while separating all volatile cost components that
are outside of the Agencies’ responsibility, but must be budgeted for as part of
this ABP, and do so in a transparent and auditable manner.
7. Allow for more refined budgeting of unknowns and delays (beyond contingency
and escalation).
8. Allow ample time to take corrective action during the design and/or construction
phase of any one particular/problematic contract.
The following PTIs are expected to be included in the Reporting Program for all projects
involving rehabilitation or replacement of a specific bridge:
Important Note: Because of limited scope definition in the early stages of design (i.e.
Structural submission is not complete until the 75%), performance measurement will
be established after the 75% construction estimate and schedule are developed and
agreed to. This will be the Program definition of “90% on-time/on-budget.”
The following is a sample of the page from web-based information tool being developed:
As part of the program, work will be continuously monitored for new and changing
risks / opportunities. Areas addressed will include safety, cost, schedule and other areas
of concern. This will be done, on a case-by-case basis (on the more critical/larger
aspects of the Program performance), to determine if program assumptions remain
valid, risk levels are changing, policies and procedures are being followed so that
contingencies will be modified accordingly. This analytical technique will be used to
monitor and forecast future outcomes based on both historical data and current project
results to date. The Agencies will analyze variances from either a baseline budget or a
baseline schedule. By using prior progress reporting periods’ data and projecting the
possible variance from baseline at some future point in the program, corrective actions
can be taken and impacts can be mitigated.
SECTION 16 . . . The report shall include, but not be limited to: the total amount
appropriated for each project, the total estimated cost of each project, the amount
expended for the planning and design of each project up to the time the report is filed,
the amount expended on construction of each project up to the time the report is filed,
the timeline from advertisement through contract award and from the start of actual
design and construction by the design build team to project completion, the time saved,
if any, by employing the design build procurement method; and whether, in the opinion
of the council with consultation from the commissioner of highways, design build was an
effective procurement method for each project; the total amount currently expended on
each project, the estimated lifetime maintenance schedule and cost of each project, the
original estimated completion date of each project and the current anticipated
completion date of each project. This report shall also include the total number of
employees and outside contractors and amount expended on salaries and benefits for
employees and outside contractors that are specifically working on projects to be carried
out as part of the accelerated bridge repair program. . . .
Through the use of the existing Agency software, the ABP will create detailed monthly
reports. Separate reports will be prepared for:
• the individual project level
1.B.0 – Summary
Chapter 233 of the Acts of 2008 requires that the Agencies track the Program’s on-time
and on-budget performance for the first three years against a 90% performance goal.
Although both Agencies already implement many of the following measures in their
current programs, the measures vary somewhat between the Agencies in both name and
content. Therefore, to promote transparency for the ABP Program as a whole and to
provide each agency with the benefit of the best practices available, the Agencies intend
to formally adopt the following Program Cost Control measures. This will involve the
adoption of new control measures as well as the upgrade of current practices
3. Peer Reviews
11. Escalation
This program will also be developed with a procedure that promotes accountability at the
contract level and transparency/visibility at the Program Management level.
3. Ensure that program level decisions are based on all critical contract level
considerations;
5. Provide the ability to create multiple levels of reporting for ABP projects within
the larger program. The implementation of a consistent schedule structure will
allow standardized routine reporting within the overall Program, at the most
detailed level.
Control/Accountability Aspects
The Agencies’ Integrated Program Schedule will be generated with a formal procedure to
ensure accountability at the project level. This will be done through the following steps:
1. The construction contractor will provide weekly construction updates during the
weekly construction status meeting held by the Agencies’ Resident Engineer/PM.
The Agencies’ Scheduler will be in attendance and receive meeting minutes.
4. The District Construction Engineer will promptly review the report and provide
direction to the District Scheduler on how to proceed with the monthly update of
the Integrated Program Schedule.
5. The District Scheduler will routinely update the Integrated Program Schedule
that will be utilized for summary level reporting. The Program Controls Group
will be responsible to coordinate the information from the field, ensure
consistency in reporting and prepare the reporting information.
The following steps will be taken by Agencies to provide for successful program
level schedule implementation:
1. Develop the desired program-level reporting for time, cost and resource status;
Organization Requirements
The key to the Integrated Program Schedule is the creation and implementation of a
specified work breakdown structure (WBS) that will become the basic organizational
structure for each project schedule. Program level schedule report formats will also be
developed. Each construction contract will include similar WBS and schedule loading
requirements at bid letting. Once the WBS has been implemented throughout the
program, program status reports will be developed on a monthly basis coinciding with the
monthly updates provided for each project. The program-level reporting can be provided
concurrently with or independently of the individual integrated project schedule update.
10
2. Create a formal cost containment review panel to evaluate cost savings, schedule
savings (design, procurement, and construction), and/or claims avoidance. The
review panel will have one senior cost analyst, designer, construction manager,
and a claims analyst.
3. The panel will log all ideas, evaluate, and report to Program Management on a bi-
monthly basis.
1. Evaluate other potential options that may be cost-effective or may improve the
completion of a bridge contract.
11
The peer review will be conducted periodically to provide a detailed forensic analysis,
claim review, and other audit type exercises. The Peer Review team will evaluate a
variety of project elements including cost reports, construction documents, schedules and
other items.
1. Perform an independent review of the current project scope, budget and schedule
vs. compliance with the originally planned scope, budget and schedule.
2. Evaluate the existing contractual obligations and the extent to which Contractor
and the Agencies have met those obligations.
3. Identify any gaps in responsibilities between the project team members and/or any
disconnects between the Agency’s expectations and each team members’
contracted scope.
4. Evaluate the current budget and the general budget trend/exposure for the
completion of the project.
8. Identify apparent major schedule risks – identify specifics in the schedule and
provide recommendations for mitigation. This will include a brief review of
items that are viewed as aggressively planned.
9. Evaluate remaining top critical paths and provide an adequate measuring tool for
the Contractor’s accountability and evaluation of feasibility of the remaining
schedule.
11. Briefly evaluate any potential schedule recovery steps that should be evaluated
further by the Contractor.
12. Summarize with a narrative/plan for: making corrective action to, help avoid
additional schedule delays, highlight any positive aspects/outlooks, and provide
12
any specific recovery plans (if possible). This will include a detailed schedule
report.
A similar Peer Review Team will be implemented for selected Design Cost reviews,
Construction Cost Reviews (during design), and Program Management Cost Reviews.
13
Early Risk Task Forces will be comprised of a representative of each of the relevant
major disciplines (land acquisition, permitting, utility, legal, construction, design), a cost
estimator(s) and a construction scheduler. This group will routinely review and present
to Program Management the potential cost and schedule impacts to the project posed by
the types of early project risks delineated above, as well as the potential impacts to early
design priorities and milestones. This group will also be responsible to prepare and
present possible mitigation measures. Depending on the need and personnel assigned,
multiple Task Forces may be established.
14
projection performed as well. Over the next several months, Program Management will
evaluate these costs in much more specific detail, and will do so in a manner that uses
past historical data to generate a defensible budget of these overhead costs.
4. Allow ample time to properly scope and budget for the entire Bridge Program
duration before budget tracking is fully committed.
5. Ensure that program level decisions are made with all contract level
considerations as its basis. This would include using past history to evaluate the
ratio of non-manual workforce (inspectors, resident engineers, designers, office
engineers, etc.) it takes to efficiently manage bridge projects by cost range.
15
maintenance. This evaluation will consider past overhead budgets (comparing the
ratio of $ to design and construction / on an annual basis), and will consider the
Field Management Ratio above.
3. This Program Budget function (i.e. indirect costs) will also be revisited and
adjusted regularly as part of the overall Program Budget evaluation.
1. Create and maintain the accountability and transparency required for the
legislative reporting requirements.
2. Generate a formalized senior management review process that allows for program
level priorities to be evaluated and acted on as efficiently as possible.
16
In the Accelerated Bridge Program, the Agencies will continue the current policy of
Value Engineering.
Develop a comprehensive cost that identifies current scope, cost-to-date, and allowances
for all future potential costs, known or unknown.
1. Assess all contractor claims and change orders and include an estimated cost
where the Program has potential cost exposures.
17
The preferable method is to categorize remaining work into common scopes (i.e.,
utilities, excavation, etc.) and assess potential cost changes. The intent of this
portion of the forecast is to establish a budget contingency for future costs that
will not result in an unexpected contract cost at completion.
3. Review all unit-priced pay item quantities (if any exist within the contract) and
forecast quantities at contract completion.
4. Identify all traffic control costs incurred to date, if any, and include a forecast for
to-go traffic control costs.
5. Obtain input from the designer(s) regarding future design changes being
contemplated by the designer and include estimated costs for potential scope
changes.
Because the ABP is in the conceptual stages, any true performance indicators provided
this year (2008) will be premature and not based upon advanced designs. For many
projects in the Program, at this stage insufficient scope definition, quantitative
information (plan to provide pricing), or detailed/adequate costs assessments of other
significant cost related impacts has been developed.
Therefore, Program Management will implement, for contract specific cost control during
the design stage, a D/E Accountability Program that will maintain a high level of
accountability for elements within the D/E’s control while promoting a ‘team’ approach
– see section 2.A.
18
The following steps will be implemented as the core of the D/E Accountability
Program:
4. The Program’s Estimating Group will review this estimate and the reconciliation.
They will evaluate the categorization of change (i.e. pricing changes, scope
changes, design development, corrective action), and will file a determination of
accountability report to ABP Executive Management.
19
This section defines the recommended use of contract specific escalation during the
evolution of the design phase of a typical ABP contract. In contract specific instances,
escalation factors need to be calculated to include inflation factors for, at a minimum,
construction costs, right-of-way acquisitions, labor costs, and general price inflation. The
construction schedule should be utilized to help determine the budget. The section also
discusses the cost of escalation of the overall Program costs for ‘non-construction’ type
costs.
In light of the many recent financial market fluctuations, and because of the magnitude of
the cost implications to the ABP, the Agencies will initiate a third party study by a
professional local economist to evaluate the current percent cost growth to be expected,
with specific regard to the Commonwealth and to bridge construction commodities,
including labor. Once this study is complete and every year thereafter, an annual
evaluation will be performed and appropriate budget adjustments using program
contingency will be made. This will help to maintain transparency, establish a
standardized approach to be managed by the ABP Cost Control Manager, and separate
this volatile aspect from the accountability of the Designer/Engineer during the design
phase.
Many current economic publications address the cost escalation factor of construction. It
is rare for two publications to agree on what the percentage of escalation should be for
future work. Moreover, each region of the country has varying cost increases. For
example, a 5/13/08 article posted on the ABP website states “A recent report of the
Federal Highway Administration estimated that road and bridge construction costs
increase between 9 percent and 15 percent each year.” The FHWA statement is
consistent with an unverified publication that has looked at the past five years and noted
that the cost of highway and street materials has increased by 70%.
20
This portion of the cost control plan will be implemented in the following manner
and at the applicable estimate stages of design and construction.
2. To ensure consistency and proper forecasting practices, during each stage of the
design, the professional cost estimator will use the Program-directed percentage
of escalation. Based on the estimate generated at current year dollars, the
estimator will then use the construction schedule to escalate to the mid-point of
construction (more advanced approaches - based on year-of-expenditure, will
also be acceptable).
3. This escalation amount will regularly be provided to the Program Cost Control
Manager to report and budget for the escalation at the Program level and as part
of the Performance Tracking Indicators. Again, this will be done at the various
stages of design.
5. Program budget entry will be provided for each contract account for the potential
increase that the Agencies must budget.
21
1. A 9% annual Escalation Rate was added to all cost estimates – and done so in a
manner that attempts to forecast the future bid values by escalating to the mid-
point of construction.
2. A 15% Construction Contingency was also included in the recent estimates. This
is to account for an aggressive (i.e. well managed) cost growth factor that is
anticipated after the Contractor has been awarded a contract.
The ABP Program Budget will monitor the impacts of material pricing.
Anticipated commodities for escalation clauses based on historic increases and current
volatility include:
• Steel
• Cement
• Hot mix asphalt
• Fuel (as it relates to operating construction equipment or providing
temporary heat)
• Fuel (as it relates to material delivery surcharges)
22
Contract-Specific Contingencies
Section 1.C.4 defines the use of contract-specific cost contingencies during the evolution
of the design phase of a typical project in the Accelerated Bridge Program. It is
important to note that the proposed definition of “on-time-on-budget” for the purpose of
the legislative reporting includes a reasonable amount of cost and schedule contingency.
This is a vital component of proper budgeting and cost control that must be a component
of the performance of the Designers, the Contractors, and the ABP management staff.
For bottoms-up estimates, prices at the detail level for material, equipment, and labor
must reflect local/industry pricing to the maximum extent possible. Time and care must
also be taken to develop contingencies, overhead costs, general conditions costs, and
profit rates in a sound, logical manner, rather than by applying blanket percentages.
For all common elements (other than the Lump Sum Bridge item), MassHighway has
recently implemented a “Weighted Average” unit price tracking program. This system
has allowed MassHighway to estimate unit priced items (usually amounting to < 20% of
the contract value) more easily. Because of the consistency noted by MassHighway over
the past year, and to assist in keeping consultant costs lower, the Weighted Average
program will be continued during the early design phases. Designers (and the
independent estimators) will be required to perform a validation of these unit prices as
part the final Engineer’s Estimate (75%).
23
Lump Sum Bridge items (and any other significant lump sum item) will nevertheless be
required to be derived from the “bottoms-up” approach, from an independent cost
estimator, beyond the 25% design stage (part of the 75%, 100%, and PS&E submissions).
As part of the 75% design submission, all construction cost estimates will begin with a
detailed quantity take-off. The independent estimator will then develop a logical work
breakdown structure for the project, followed by the crews, equipment, and production
rates that will be used in constructing each element of the work. Once this information is
developed, the estimator will then develop pricing information (again using weighted
averages for normal unit prices and the “bottoms-up” approach for lump sum and/non-
routine elements).
Pricing of overtime and shift work shall reflect appropriate local (union) labor wage
premiums and appropriate calculation of payroll taxes and burdens above. This will be
evaluated as part of the 100% submission, following the completion of a detailed
Contract Time Determination study (i.e. detailed construction schedule) that utilizes
information from the 100% construction cost estimate.
All estimates will contain an appropriate level of contingency to account for: stage of
design; level of scope definition; difficulty level of construction; chance of scope creep
24
during design; chance of scope creep during construction; construction risk factors
(subsurface conditions, hidden conditions, hazardous materials, form of construction
contract, construction contract pay item structure, market price trends); bid climate; etc.
The estimate contingency should be applied below the bottom line of the cost estimate
and not included in quantities or unit pricing.
All estimates will contain appropriate markups for indirect costs including home office
overhead, profit and insurance (special coverage such as pollution, marine, and other
unique job requirements) and bonds.
All estimates will include escalation to the midpoint of construction, calculated monthly
or yearly. Useful indices to determine the applicable escalation rate may include
Engineering News Record, Consumer Price Index for materials, Metals Weekly, various
D.O.T. and FTA escalation materials indices, and local sources. However, because of its
size, the Accelerated Bridge Program will develop a standard escalation factor, to be used
by all estimators, that is generated by a professional economist.
1. All site-specific Construction Cost estimates (greater than $1M) will include an
Executive Summary of costs by the ABP Work Breakdown Structure.
2. All estimates will be developed into appropriate summary level Unit Costs at total
and Systems cost levels, to allow for cost benchmarking, (e.g. cost per Bridge
Foot, cost per Lane Foot, cost per LF of vertical foundation; cost per CY of
concrete or earth; etc).
3. Each estimate at the 75% submission for all site specific construction contracts
greater than $1 Million shall be accompanied by a Basis of Estimate narrative.
The Basis of Estimate shall may include the following:
• List the specific project documents and source documents forming the basis
of estimated scopes and assumptions. Identify sources and dates.
• Identify all scopes, quantities, and costs, provided by sources other than the
estimating team (e.g. ‘pass-through’ Allowances provided by the Agencies,
Designer, or end-user.)
• Reconcile major scope changes from prior estimates, as identified by the
design team.
• Reconcile summary level cost variances from prior estimate, in tabular or
narrative form.
• Reference, and explain, detailed estimate ‘backup’ such that third party
readers can correlate summary level information with the backup.
• Outline unresolved scope or cost issues.
• Describe estimate departures from project documents, and why they are
included (e.g. constructability).
• Describe estimate assumptions regarding site access restraints.
• Describe estimate assumptions regarding sequence of work and labor
shifts.
25
QA Review Guidelines
Scope Review
Review the scope of the work for which the estimate was developed. Documents to be
Check to see that all scope elements are included in the estimate.
Estimate Format
Review correspondence and other documentation provided by the estimator which
identifies the required format that the estimate is to be presented in, e.g. CSI, bid item
numbers, Uniformat, etc., and check to see that the estimate is in the required format.
26
Quantity Take-Offs
Check line item quantities. Review the estimator’s take-off files to ensure the accuracy
of quantities derived by the estimator. At a minimum, check quantities of major scope
items comprising the majority of the cost of the project. Ensure that quantity take-off
documentation is included in the estimate file prepared by the estimator.
Material Pricing
Check pricing of materials. Ensure that backup documentation is included in the estimate
file prepared by the estimator for all items of material. Backup documentation may
include vendor quotes, historic pricing from other recent estimates, photocopies of pages
from estimating manuals, copies of recent invoices, or other pertinent substantiation.
Equipment Pricing
Check pricing of equipment. Ensure that backup documentation is included in the
estimate file prepared by the estimator for all equipment. Backup documentation may
include vendor quotes, historic pricing from other recent estimates, photocopies of pages
from estimating manuals, copies of recent invoices or lease agreements, or other pertinent
substantiation.
Labor Pricing
Check pricing of labor. Ensure that backup documentation is included in the estimate file
prepared by the estimator for all labor. Backup documentation should include prevailing
wage agreements in the vicinity of the project and other pertinent information. If
appropriate, check to see that the backup includes a workup of the elements comprising
the fully burdened wage rate.
Contingency
Check to see that the estimate contains an appropriate level of contingency, taking into
account the following factors: stage of design; level of scope definition; difficulty level of
27
construction; chance of scope creep during design; chance of scope creep during
construction; construction risk factors (subsurface conditions, hidden conditions, form of
construction contract, construction contract pay item structure, market price trends, etc.);
bid climate; etc. Check to see that contingencies are applied in appropriate locations
within the estimate (below the bottom line, spread through line items, etc.). Ensure that
the estimate file prepared by the estimator contains a discussion/workup of contingency
rates used.
4. Generate Estimate Reconciliation sheets to show why the estimates have changed
from one stage to the next.
5. Identify and monitor those aspects that the Designer is accountable for – alerting
Program Management and design managers of discrepancies with
recommendation to mitigate.
28
3. Allow ample time to make corrective action during the design phase.
The Agencies will apply a contract specific Cost Contingency during the evolution of the
design phase of an ABP contract that follows the process outlined below. It is important
to note that the proposed definition of “on-time-on-budget,” for the purposes of the
legislative reporting, includes a reasonable amount of cost and schedule contingency; the
section below is specific to the cost contingency.
29
It important to note however, that it is not proposed that a 10% Cost contingency be
included in the final Engineer’s Estimate (for advertisement). The Engineer’s
Estimate is to be developed to provide for a reasonable cost projection of the contract
documents provided (and not a prediction of the low bid). Cost contingencies to be
added to the Engineer’s Estimate at this stage, will be discussed/evaluated, on a
contract-by-contract basis, as part of the risk/exposure discussion of the Estimate
Review Briefing with Senior ABP Management staff. The overall ABP Program
Control Budget that will include a proposed 10-15% Cost Contingency (again, such
contingency will not be part of the Engineer’s Estimate).
5. Construction Phase
Once in construction, the same 10%-15% Cost contingency will be utilized and
budgeted for within the Program Control Budget to account for cost growth during
construction.
An ABP Program Budget exposure has been identified to monitor a budgetary risk
associated with the potential cost increases normally associated with highway/bridge
construction in the Northeast (winter impacts and common delay issues).
30
have completed over the past 3 years and will compare the bid value vs. the actual Cost-
at-Completion to determine a reasonable percentage for which to budget. This study may
be commissioned within the coming months. If the findings conclude that there needs to
be a budget allotment of much greater than the 15% previously added, then the Agencies
will adjust the program and Budget Control in a reasonable manner.
31
possible;
32
The key elements of effective design schedule control are: accurate schedules; reporting;
transparency; accountability; and change order management. The following three
documents will be used to support these key elements.
1.) Project Design Schedule – a detailed CPM schedule which shows how the
designer plans to execute the design, planned resources (designer hours), design
activities and their durations, and the logical relationship of each of the design
activities.
2.) Design Consultant’s Monthly Report - a monthly summary report which includes
the following information:
• Overview
• Accomplishments for the month
• Upcoming key deliverables
• Critical action items (listing person responsible and need date)
• Summary financial report
• Project Meetings – past and future
• Community meetings
3.) Scope Statement – a descriptive statement of the project scope developed and
managed by the Agencies’ Design Manager. The scope statement will be revised
and updated as the design progresses. A reconciliation statement that clearly
describes scope changes will also be developed at each stage of the design. The
reconciliation statement will also include the specific reasons for all scope
changes.
33
This portion of the program control plan will consist of the following elements:
This will allow the Agencies’ Design managers to quickly identify areas of
concern. Any task with a performance ratio above 1.0 indicates a possible delay
in completing the design task.
• The Project Management Plan shall establish the framework for the
project, including the organization of participants, responsibilities,
decision structure, channels of communication and procedures to be
followed in developing the design within the required timeframe.
34
The Project Design Schedule shall be developed and maintained using MS Project
or Primavera Scheduling software (or approved equivalent), and shall include
such information as required in the standard bridge schedule template (as
amended), or other schedule guidance issued by Agencies for the project. Design
services shall be undertaken and completed in accordance with the Project Design
Schedule as approved by the Agencies, and as revised and updated from time to
time by Design Consultant. The Project Design Schedule shall be used by the
Design Consultant and the Agencies for planning and monitoring the progress of
the design work.
35
This list is currently being finalized by the design schedule review team and is
subject to change.
The Design Consultant shall update and submit the monthly Project Design
Schedule. The monthly update shall: describe work completed during the
reporting period; describe work planned for the next reporting period; explain and
comment on schedule delays; provide costs-to-date and a statement of the
adequacy of the remaining design budget; indicate MBE/WBE/DBE activities;
and indicate anticipated problems with recommended solutions.
As part of the monthly requisition for payment, the Design Consultant shall also
prepare a monthly summary report to include the following aspects:
• Overview
• Accomplishments for the month
• Key deliverables upcoming
• Critical action items (listing person responsible and need date)
• Summary financial report
• Project Meetings – past and future
• Community meetings
The Agencies’ design managers will develop a scope statement for each ABP project at
initial project inception. The scope statement will be revised and updated at each stage of
the design. A reconciliation statement that clearly describes scope changes will also be
developed at each stage of the design. The reconciliation statement will also include the
specific reasons for all scope changes and all associated cost and schedule changes.
36
3. Allow ample time to take corrective action during the design phase.
Initial Implementation
A standard form will be developed (by Feb-09) to utilize on a future ABP projects. This
form will be filed at each design phase and identify when each significant scope change
is made. This will document the history of the scope changes over the life of the project.
In order to minimize costly delays during construction, it is vital that a Critical Path
Method (CPM) Schedule be developed during the planning stages of every ABP project.
This CPM schedule needs to be founded upon the critical elements of the contract
documents (including limitations of operations), the corresponding construction cost
estimate data, and a reasonable determination of the possible construction means-and-
methods.
During the design phase, the Agencies will ensure that professional construction
schedulers are utilized to prepare construction schedules that will determine the overall
Contract Time (duration) of each ABP construction contract. This will be referred to as
the Contract Time Determination schedule (a.k.a. pre-bid construction schedule), and will
be utilized throughout the design phases.
37
The Agencies will also ensure that the critical information (crews, equipment, production
rates, quantities, construction sequence) from the construction cost estimate (section 1.C)
is integrated with the basis of the Contract Time Determination schedule. This will also
assure that contract documents have been planned with efficient construction planning
practices.
Once the construction contract has been awarded, this Contract Time Determination
schedule will be compared with the construction contractor’s Baseline Schedule
submission. This will ensure that the Contactor has incorporated all scope elements in its
schedule, is not positioning for a schedule claim, is utilizing the schedule to logically plan
the work, and has planned the work properly to avoid major surprises or delays.
This schedule also contains a quality control review plan for Contract Time
Determination schedules that will be used on ABP projects.
These types of schedules will not be submitted until after the construction cost estimate is
complete, in order to provide adequate time for the professional scheduler to utilize the
data generated in the construction cost estimate. In general, these schedule submissions
will be due to the Agencies no sooner than 3 weeks and no later than 5 weeks, after the
construction cost estimate has been completed.
38
Access Restraints are also contractual dates. However, these are included in the contract
to serve as a contractual means to control the start the contractor’s work. (Example: “the
contractor will receive access to parcel 45 no sooner than 60 days from the Contract
Notice-to-Proceed date.”)
The Designer’s Professional Scheduler will be responsible to work with the Agencies to
determine which Contract Milestones and Access Restraints should be included in the
contract provisions and to include them in the Contract Time Determination schedule.
39
“The Contractor will not be allowed to perform any work after 6:00PM”). In order to
minimize construction claims, ensure quality bidding, and avoid major discrepancies with
the Engineer’s Estimates, it is vital that these Limitations of Operations be clearly defined
in the construction contract. The Designer’s Cost Estimator and scheduler will be
required to communicate regarding the implications of these constraints.
Open Ends
A CPM schedule relies on the logically tied relationship of each activity. “Open Ends”
are created when an activity does not have a successor (i.e. an activity that depends upon
the completion of a predecessor activity). The professional construction scheduler will
ensure that all of the activities in the overall schedule have been adequately tied and that
there are no open ends in the schedule.
* The Agencies will have a standard submittal review duration of 30 calendar days
– with the exception of more complicated submittals (to be defined). These will
have durations of 60 calendar days. This clause will help to properly plan the
work and avoid a dispute (claim) for delays at the inception of the project.
The Agencies will initiate a formalized study of all bridges to be constructed near term to
ensure that accomplishment of these elements has been accounted for properly.
Commensurate changes will be made to the Program Budget and Program schedule, if
necessary.
40
Schedule Format
The Reviewer shall make sure that the schedule has been developed in accordance with
the requirements of the Agencies’ contract scope and specifications describing the
schedule requirements. The final Contract Time Determination Schedule will be
provided to the Agencies in hard-copy form (plots or 11x17). The Reviewer shall also
ensure that the schedule is developed in the format required by Agencies. The Reviewer
shall make sure that:
41
Critical Path
The Reviewer will perform a random “spot check” of 3 of the top 10 critical paths. The
Reviewer will:
• follow the logic/sequence (to validate reasonableness of the
successor/predecessor activities);
• check 50% of the durations on each these paths (to ensure that there is an
adequate basis for them – crews/manhours, etc.);
• validate the reasonableness/basis of any significant lags that are used;
• ensure that calendars have been used properly; and
• ensure that the top critical path is a logical critical path for the project.
If there are significant problems with this spot check, or the checks in the two paragraphs
that follow, the Reviewer will meet with the Scheduler to resolve findings and will
continue to evaluate other paths and other aspects of the schedule.
42
that contain more than 10 Milestones/Access Restraints, the Reviewer will validate no
less than 10% of the Milestones/Access Restraints, in a similar fashion described above.
The Reviewer will also ensure that the Milestones/Access Restraints have been inserted
into the schedule software properly (i.e. activity type and zero duration).
Open Ends
The Reviewer will ensure the schedule submission contains no open ends. These are
activities that are not assigned a successor and therefore contain excessive float values.
The one exception to this is the final contract Milestone.
Contingency
The Reviewer will check to see that the pre-bid construction schedule contains an
appropriate level of schedule contingency taking into account the stage of design, level of
scope definition, and/or difficulty level of construction. The Reviewer will also ensure
that the pre-bid construction basis statement contains a discussion/workup of any Time
contingency used.
43
shall make adjustments to the pre-bid construction schedule based on the comments
provided by the Reviewer, and shall provide a copy of the adjusted pre-bid construction
schedule to the Reviewer. The Reviewer shall perform a final QC review of the pre-bid
construction schedule to ensure that all adjustments have been incorporated into the final
bid documents to be advertised.
Final QC Approval
Completion of the Schedule QC Review will be required prior to approving the contract
documents for bid advertisement.
In the sections that follow, the specifications, types of schedules, quality of the
Contractor’s Schedule Submittals, and other schedule-enhancement tools to be used on
the Program will be explained. These requirements, concepts, and best practices, will be
implemented in the project management procedures of the ABP.
Heavy/highway contractors may generate claims that are founded on the construction
schedule of record (official schedule submittal). However, the construction schedule may
not be maintained and the schedule requirements of the construction contract may not be
enforced, and as a result, the Owner is left with little to present in defense of the claim.
The Accelerated Bridge Program will implement several steps in the sections that follow
to ensure that cases like this are minimized.
44
1. Provide the Agencies’ project managers with training sessions on best practices of
construction schedule control (including Primavera or equivalent, CPM, Work-
Session, Schedule Recovery, Critical Issues Reporting, Documentation, and Field
Verification).
3. Provide the Agencies’ Schedule Control Manager with the necessary tools and
resources to ensure that contractors are progressing diligently.
4. Ensure that the proper critical information flows from the field to the program
level to ensure that informed program level decisions are made efficiently and
effectively.
5. Ensure that proper documentation is provided to build the necessary audit trail in
defense of time-related delay claims.
45
3. ABP Project Managers and Schedulers will review critical information in the
Contractor’s Monthly Schedule and will routinely review, comment, and
document the reason and basis for schedule changes.
4. The Agencies will update the current Schedule Specifications and internal
procedures to promote the transparency and accountability required as part of the
ABP Legislation.
5. The Agencies will also provide guidance and training to the ABP Project
Managers/Resident Engineers on developing CPM schedule reviews, with
Program integration (reporting and standardization) in mind. The Resident
Engineers will continue to have a major responsibility of providing the primary
review of each of the Contractor’s monthly schedule updates.
Preservation Contracts
1. Contractor NTP
2. Mobilization
3. 25% complete
4. 50% complete
5. 75% complete
6. Substantial Completion
7. Final acceptance
8. DHD Certificate of Completion
Replacement Contracts
1. Contractor N.T.P.
2. Complete Structural Steel Shop Submittal & Drawings Submitted
3. Bridge Deck Demolition Complete
4. Substructure Replacement/Repair Complete (if applicable)
5. Structural Steel Replacement Complete
6. Final Bridge Deck Restored
7. Substantial Completion
8. Final Acceptance
46
Repair Contracts
1. Contractor N.T.P.
2. Complete Structural Steel Shop Submittal & Drawings Submitted
3. Complete Concrete Repair Submittal & Drawings Submitted
4. Bridge Deck Repair Complete (if applicable)
5. Structural Steel Repair Complete (if applicable)
6. Substructure Repair Complete (if applicable)
7. Substantial Completion
8. Final Acceptance
9. DHD Certificate of Completion
The actual schedule submittal requirements will be detailed in the contract documents in
terms of frequency and items to be submitted. The typical project will include:
Depending on how the project progresses, there may also be revised schedules or even
time-impact schedules on a case-by-case basis. The typical schedule submittal includes
an electronic file, hardcopy plots and a schedule narrative. The electronic schedule file is
the most important part of the schedule submittal as all information necessary to
complete the schedule review can be found in the electronic file. A hard copy submittal
(or even a PDF plot) should never be accepted in lieu of the electronic file as changes in
the schedule may not be apparent when reviewing only a static print.
Schedule Narrative
A schedule narrative will be required for every schedule update the construction
Contractor submits. This will detail the current status of the project, work performed in
the past update period, and all changes to the schedule being proposed in the schedule
submittal.
Preliminary Schedule
Review of the Preliminary Schedule Submittal typically is based on activities expected to
be performed in the initial 90 days. The focus of this review is to see the general phasing
of the project, planned performance on major contract milestones and overall time, initial
47
cost and resource loading. Generally a preliminary schedule review is not considered
comprehensive but will provide an overview of the Contractor’s approach to the project.
Baseline Schedule
The review of the Baseline Schedule submittal is the starting point against which all
delay and production issues are measured. It is the comprehensive review of the
Contractor’s initial work plan to complete the project within the specified contract
Time/duration. To assist in the review of the Baseline, the Agencies’ Scheduler(s) will
utilize the valuable information that is developed as part of the Contract Time
Determination schedule (done by a professional scheduler during design). The Baseline
Schedule will be compared against this document to see how the Contractor’s planned
approach to the project varies in planned production, sequencing and milestone
completion. This will help to quickly identify problems (related to scope, intent,
production, restrictions, etc.), and will be part of the documented review comments that
the Agencies’ Scheduler will develop.
All work scope contained in the Plans, Contract, Specifications and Special Provisions
should be included in the Baseline Schedule along with a verification of the planned
durations, schedule logic, and cost and resource loading as required. Once the Baseline
Schedule is accepted, this submittal becomes the ‘schedule of record’ for the project until
superseded. The Agencies’ Specifications and Special Provisions will indicate the
process for receiving a schedule submittal and the time allowed for review and response.
Revised Schedule
Revised Schedule Submittals require careful examination because the Contractor is
proposing modifications to the approved work plan that may not be in accordance with
the Contract documents. Revised Schedules used to validate alleged delay claims require
a comprehensive review in addition to the normal Schedule Update. In this process, the
Contractor is often seeking approval for work/delays that have not yet occurred The
Agencies’ procedure will validate the proposed changes with a detailed review of the
48
Contractor’s planned resources, sequencing, production rates, and potential impact to the
contract substantial completion date.
This program will also be developed with a procedure that promotes accountability at the
contract level and transparency/visibility at the Agencies’ executive level.
The objective of this portion of the Construction Schedule Control program will be
to:
3. Ensure that program level decisions are made based on critical contract level
considerations and status as a basis;
5. Provide the ability to create multiple levels of reporting for ABP projects within
the larger Program. The implementation of a consistent schedule structure will
allow standardized routine reporting within the overall program, at the most
detailed level.
Control/Accountability Aspects
The Agencies’ Integrated Program Schedule will be generated with a formal procedure to
ensure accountability at the project level. This will be done with the following steps:
1. The Contractor will provide weekly construction updates during the weekly
construction status meeting held by the Agencies Resident Engineer/PM. The
Agencies’ Scheduler may attend and receive meeting minutes.
49
3. Upon receiving the Contractor’s schedule, the Resident Engineers (and/or District
Schedulers) will review the schedule and provide comments in a written report to
the ABP District Construction Engineer in a timely manner.
4. The ABP District Construction Engineer will promptly review the report and
direct the District Scheduler on how to proceed with the monthly update of the
Integrated Program Schedule.
5. The District Scheduler will routinely update the Integrated Program Schedule that
will be utilized for summary level reporting. The Program Controls Group will
be responsible to coordinate the information from the field, ensure consistency in
reporting, and prepare the reporting information.
The following steps will be taken by Agencies to provide for successful Program
level schedule implementation:
1. Develop Agencies‘ desired Program-level reporting for time, cost and resource
status;
Organizational Requirements
The key to the Integrated Program Schedule is the creation and implementation of a
specified work breakdown structure (WBS) that will become the basic organizational
structure for each project schedule. Program level schedule report formats will also be
developed. Each construction contract will include similar WBS and schedule loading
requirements at bid advertising. Once the WBS has been implemented throughout the
program, program status reports will be developed on a monthly basis coinciding with the
monthly updates provided for each project. The Program-level reporting can be provided
concurrently with or independently of the individual integrated project schedule update.
50
The schedules submitted by typical highway construction contractors are only as detailed
as required by the contract specifications, and are often times diluted by the lack of
enforcement of scheduling specification requirements. This has historically complicated
the determination of delay causation, and has hindered the owner’s ability to implement
effective schedule control and recovery measures.
Accordingly, the Agencies will supplement the existing construction contract schedule
specifications to require more comprehensive construction schedule submittals from
construction contractors. The Agencies will require that all construction contractor
schedules, for all site specific ABP projects greater than $1 Million, be generated using
the Critical Path Method (CPM), and Primavera Scheduling Software (or approved
equivalent). This requirement will assure the foundation for adequate/defendable delay
analysis, schedule control, and efficient reporting processes.
The Agencies’ schedule specifications will be broken down into general, technical, and
project-specific requirements. There will also be another level of schedule specification
for sub-projects within larger projects.
General specifications will govern the basic information to be included in the CPM
schedule. These will include, but not be limited to:
51
• activity coding.
Project-specific specifications will vary among projects. These include, but are not
limited to:
• weather considerations,
• work limitations and working periods,
• construction sequence, and
• contract milestones.
The Agencies will mandate that all Contractors of site specific contracts greater than $1
Million utilize Primavera scheduling software (or equivalent) to control both cost and
schedule of the Accelerated Bridge Program in the most effective manner and to provide
the a uniform reporting platform. This type of software is endorsed by many state
departments of transportation, is the software most commonly used by the local
Contractors, and is the preferred choice of local claims consultants that work for state
agencies.
4. Provide the most efficient and effective mechanism to summarize program status
(project “roll-up”) and manage multiple projects in an accelerated fashion.
5. Implement a schedule control system that is most commonly accepted for civil
construction projects by local contractors, claims consultants, professional
schedulers, and other DOTs alike.
52
In order to implement this control measure, the following steps will be taken:
3. There will be a period of training for all Agency staff working with project
schedules. The training course typically includes:
• Basic terminology and scheduling techniques;
• Effective operation of the software scheduling application;
• Development of a baseline schedule;
• Schedule review techniques for baseline and updated schedules; and
• Basic time impact analysis for claims issues.
4. The Implementation Plan and training course will be coordinated with any
changes in Schedule Specifications so that the most current schedule requirements
will be reinforced with the Agencies’ staff.
The Agencies will amend their construction scheduling specifications to require a cost
and resource loaded construction schedule for every site specific construction contract
that is valued at over $1 Million. This specification adjustment will be made in early
2009.
The main goal of this portion of the program control will be to develop a more
effective and industry accepted method to:
The following measures will be part of the construction schedule control program:
Cost & Resource Loaded Schedules (for all site specific contracts > $1Million):
• Each schedule activity will have an assigned cost consistent with the value of
work to be installed and will accurately reflect the bid value of the activity
payment item. Example: Lump Sum Bridge Structure 999.000, one payment
53
• Each schedule activity will also have an assigned crew composition by man-hour
consistent with the value of work to be installed and reflective of the bid value of
the payment item.
• Unless approved by the Agencies’ Project Managers, each activity will not be
more than 20 days duration or less than 5 days duration. This will help to ensure
the proper cost break-down.
2. To identify Work items and paths that are critical to the timely completion
of the Work.
54
6. As the basis for analyzing the Time impact of changes in the Work.
11. To aid in integrating the Work with the operational requirements of the
Agencies.
5 day duration
5 days x 24 laborer hours/day = 120 laborer hours for the planned activity to demo the invert.
If, the Contractors “actual” are 80 hours, and the activity is on the critical path, questions
55
Activity DR121 shows, the same activity in the resource loaded example above shows, the
budgeted cost to be $28,334.
d. Schedule Narrative
1. Each narrative shall list the Activities on each Critical Path and compare
Early Dates and Late Dates.
2. Each narrative shall include (a) the Contractor's site management plan
(e.g., lay down, staging, traffic, parking, etc.), (b) the use of construction
equipment and resources, (c) basis and assumptions for critical activity
durations and logic, (d) compliance with winter weather requirements, and
(e) any shifts, non-Business Days and multiple calendars applied to the
Activities.
3. For each Progress Schedule Submittal, the narrative shall recap progress
and days gained or lost versus the previous Progress Schedule, describe
changes in resources to be used on remaining Work and identify Delays,
their extent and causes. For Progress Schedule Submittals, each narrative
56
shall also itemize changes in Activities and logic ties caused by each
Change Order, schedule recovery plans and grouping of related
Contractor-initiated revisions.
4. Each narrative shall certify that the Contractor has not been delayed, as of
the closing date, by any act, error or omission of the Agencies, or their
Designer/Engineer, except as otherwise specifically stated in the narrative
or identified in a claim submitted in accordance with the general
conditions of the Contract. Any determination by the Agencies will be
binding on the Contractor if the Contractor fails to do so.
e. Delay Provisions
In order to assist the Agencies with the management of delays, the schedule specification
will include a clear, detailed description of what the Contractor needs to provide in order
to prove delay and receive a Time extension.
The extension of Contract Time will be considered only if the Contractor demonstrates
via the timely submittal of a detailed schedule analysis by using the Contemporaneous
Window Analysis methodology or other similar methodology acceptable to the Agencies.
The analysis shall include: a) a detailed narrative which clearly describes the events
causing the delay and the resulting impacts to the project schedule; b) documentation
substantiating and supporting the delay; c) a detailed CPM schedule (both electronic and
hard copies) clearly delineating the delay; d) a matrix showing delays caused by the
Authority, delays caused by the Contractor, delays caused by any third party and any
force majeure delays; and e) any additional information reasonably requested by
Agencies, including the Contractor’s daily reports, in order to enable the Agencies to
perform a timely and informed analysis of the request for extension of Contract Time.
The following or similar language will also be added to the end of the scheduling
specification to ensure that proper attention to the scheduling requirements is provided by
the Contractor.
A. MEASUREMENT
1. A fixed price not to exceed $_______.00 will be made to reimburse the
contractor for CPM Scheduling. Payment will be made under Item No.
_______, CPM Scheduling, to the Contractor.
B. PAYMENT
1. Fifteen percent (15%) of the fixed price for CPM Scheduling will be made
upon return to the Contractor of the CPM Construction Plan Baseline
Schedule Submittal as "Re-submittal Not Required" (As-Planned
Schedule).
57
The Agencies will require every Contractor on site specific contracts greater than $1
Million to comply with an Earned Value Management Program for payment of all Lump
Sum Payment items. This specification requirement will be included in all ABP
construction contracts that are planned to be bid in early 2009 and those thereafter.
The following measure will be part of the construction schedule control program:
Shows a planned cost of $28,334 for the demolition of the invert. It also shows that it is
part of bid item 0211.000 DEMOLITION LUMP SUM.
Using the Agencies Earned Value payment procedure, if the contractor has completed 3
days of the 5 day demolition activity, and has 2 days of work remaining (verified by an
Agencies inspector) at the time of the payment requisition closing date, the Contractor
would be entitled to receive $17,000 ((28,334 x (3/5)).
58
Note: Unit Priced Payment items will be paid in accordance with the procedures already
in place (prior to Nov-08).
1. Generate a formalized senior management review process that allows for program
level priorities to be evaluated and acted on as efficiently as possible.
2. Evaluate cost and schedule controls – these meetings will be primarily focused on
identifying schedule related concerns and working out a swift course of action
(see section 1.B for Internal Control Meetings).
59
3. Develop action items to recover delays (and/or costs) and monitor status at
subsequent meetings.
6. Action items to recover costs and/or delays will be generated and statused at
subsequent meetings.
60
The main goal of this program is to help explore options to RECOVER LOST TIME
FOR DELAYS.
• The Contractor is informed that cooperation in this matter will help to expedite
resolution;
• Posturing, from all parties, is to be put aside;
• The Contractor’s latest schedule is to be analyzed and tested for “what-if”
options;
• The session must be attended by “the people that are actually doing the work,”
• Requires Commitment from Senior Members of the Agencies, the Contractor, and
the Designer;
• If multiple contractors and sub-contractors are involved, they all need to be
represented;
• A log will be created of all of the schedule changes to validate the recovery plan
and in any future Time Entitlement Analysis; and
• “Commercial issues” are to be sorted out at a later date.
The Quality Control Plan (QCP) defines the goals for meeting the Agencies’ expectations
regarding the analysis and reporting of CPM schedule submittals. These goals fall into
three categories: (1) agency goals for the project; (2) quality assurance for schedule
review and (3) quality control of the schedule review.
The agency goals for the project include providing a quality deliverable, within budget
and within the time considerations determined by the Contract or Specifications. The
process for determining these goals is a collaborative effort between the Agencies’
Project Managers and the Schedule Reviewer. It provides transparency among Agencies’
expectations, the review process, and production of the schedule deliverable.
Quality assurance for the schedule review process focuses on the process of producing
the deliverable. Quality control of the schedule review involves review of the work
being performed. Quality control involves the Agencies’ management and scheduler staff
61
and includes oversight of the process, completion of review checklists, external reporting,
and internal approvals.
During the Agencies’ schedule review, the quality control process will be enforced as
prescribed in the QCP through completion of the final deliverable for each schedule
submittal. Quality assurance will occur over the length of the Program with review
cycles also as determined by the QCP.
As an initial step toward implementing this program, the ABP schedule managers will
review the following checklist for Baseline Schedule Reviews:
62
Logic review
• Are there open ended activities?
• Are the activity relationships logical? (Foundations after excavation)
• Are seasonal impacts addressed?
• Can the activity durations be supported by reasonable production rates?
• Are relationships other than a FS, 0 lag reasonable? Review to ensure that logic is
modeled not to promote sequestered float.
Float Review
• Are lag relationships and lag durations reasonable?
• Are activity durations inflated?
• Are all logic ties dependent on one another?
• Review the logic and analyze to determine if the critical path is flowing through
the higher probable problem areas of the project. If it is, is there a work around to
eliminate this work plan?
• Is the percentage of critical and near critical activities reasonable? Generally 15 –
25% should be expected.
Narrative Review
• Does the narrative describe in detail how the contractor plans on utilizing its
resources, including subcontractor crews and equipment, to support its approach
to constructing the project?
Resource Review (For projects that are resource loaded or used with narrative info.)
• Are labor and equipment resources adequate for the work planned?
• Relative to durations, are crew sizes and production rates too high or too low?
• Will the resources be adequate to support production rates? (Cross check with
narrative)
• Are the resources specified unrealistic?
63
• Are there too many resources identified for the work being planned at that time
frame, due to: confined space limitations or other work being done concurrently,
posing adjacent contractor problems or subcontractor conflict (coordination may
or may not be a reasonable plan)?
• If logic ties are used to represent planned resource usage, but are not necessarily
dependent on one another, convince the contractor to resource load these
activities. If the logic is not due to means and methods but is based on a
preferential logical work approach, any delay claims emanating there from should
be rejected.
64
The objective of this portion of the construction schedule control program will be as
follows:
2. The Agencies recognize that another critical aspect is the planning of right-of-way
acquisitions, permitting, and environmental approval process. The Agencies will
initiate a formalized study to evaluate the near term bridges in order to confirm
the duration for these three critical approvals. If it is later determined that the
current planning duration assumptions are inadequate, necessary changes will be
made to the Program Budget and Program schedule.
Additional Examples that will be incorporated into the Agencies’ guidance for
schedule management: The following is a list of common schedule review comments
that can adversely impact project schedules and/or costs. The Agencies will provide
guidance to the project management team members that will help to ensure that these
critical aspects are dealt with consistently and efficiently.
2. Comments that have the potential to change the Contractor’s accepted work
operations (Means and Methods)
65
A methodology which has been proven effective over time is to include construction
quality control requirements (construction contractor inspection and testing parameters)
in the construction contract documents, and require the contractor to submit a formal
construction quality control (QC) plan which delineates the detailed inspection and
testing measures it will implement for each element of the work, to ensure that all work
installed conforms to the requirements of the contract documents. This is treated as a
formal submittal which gives the owner the opportunity to review and comment on the
plan to ensure that it is comprehensive and effective.
The owner then develops and implements its own internal quality assurance (QA)
oversight plan to ensure that the contractor is complying with the inspection and testing
requirements contained in its approved QC plan. Owner QA oversight measures
typically include performing its own inspections and tests at appropriate frequencies to
verify that the contractor is properly and effectively implementing its QC plan, and that
the plan is in fact ensuring that the work of the project conforms to the requirements of
the contract documents. Frequencies and levels of QA oversight inspections and tests
will vary from project to project, depending on the complexity of the project and the
observed effectiveness of the contractor’s QC plan and efforts.
66
To achieve these objectives, the following steps will be implemented as the core
guideline:
1. The Agencies will review their existing Contractor Quality Control specifications
for construction contracts, make warranted improvements, and tailor the
specifications to specifically address the requirements of Accelerated Bridge
Program. These specifications will be included in all ABP construction contracts.
2. The Agencies will hold Contractor Quality Control refresher training sessions
with all ABP construction personnel, to ensure that all construction personnel are
intimately familiar with the requirements of the ABP Contractor Quality Control
construction contract specifications.
3. The Agencies will hold construction Contractor Quality Control training sessions
with all construction contractors prior to their performing work on ABP
construction Contracts. The purpose of this training will be to ensure that all
construction contractors performing work on ABP construction contracts
understand the requirements of the Contractor Quality Control specifications.
67
SECTION 4 – IMPLEMENTATION
Mission
This organizational arrangement will allow Project Controls Group to focus its efforts
solely on its control and reporting functions, and report project and Program status in an
objective and factual manner.
Organizational Structure
68
developing, monitoring, reviewing, analyzing, and reporting on project level (design and
construction) schedules, as well as the overall program level schedule. It is anticipated
that schedule analysts will be assigned both in MassHighway Boston, MassHighway
District Offices and the DCR Office and Field Offices.
The number of Schedule Analysts will be determined in conjunction with the finalization
of each individual project’s schedule review. It is expected that during Years One and
Two of the program, the Schedule Control Group will consist of the Schedule Control
Supervisor and three Schedule Analysts. The Schedule team will develop and implement
the schedule control and reporting system. This will require a program level schedule,
project level schedule templates, and early project level schedules and reports. As more
ABP projects become active, additional Schedule Analysts will be added on an as needed
basis. As the volume of Program contracts escalate, the number of Schedule Analysts
will be commensurate with the level of effort required to maintain effective control of
and reporting on all project schedules and the Program level schedule. Early estimations
on staffing needs will be completed following the acceptance of the Project Controls
Report. Neither Agency currently supports a program controls effort that is
commensurate with the level of effort proposed for the Accelerated Bridge Program.
Throughout the early years of the Program, the Project Controls Plan will be augmented
with a staff of contract employees or consultants with the requisite expertise in schedule
and cost management. However, the Agencies intend to transition over time that labor
intensive effort, from consultants to an “in-house” staffing capability.
The number of Cost Analysts will be determined in conjunction with the finalization of
each individual project’s schedule review. It is envisioned that at the beginning of the
program, the Cost Control Organization will consist of the Cost Control Supervisor and
two Cost Analysts who will together develop and implement the program level cost
control and reporting system. Additional duties will include cost control and reporting
templates, and early project cost control reports. As more ABP projects become active,
additional Cost Analysts will be added on an as needed basis. The number of Cost
Analysts will be commensurate with the level of effort required to maintain effective
control of and reporting on all project costs and program level costs.
69