Final SKEE4683 16172
Final SKEE4683 16172
PROGRAMME : SKEE
SECTION : 01
DATE :
ANSWER ONE QUESTION FROM SECTION A
INSTRUCTION TO CANDIDATE :
AND ANSWER ALL QUESTIONS IN SECTION B
Section A.
Q.1 (a) In an overhead transmission line system, the basis of comparison is the
maximum voltage between conductor and ground. Explain why?
[3 Marks]
(b) A d.c. 2-wire system is to be converted into a.c. 3 phase, 3 wire system by
the addition of a third conductor of the same cross-section as the two
existing conductors. Calculate the percentage additional load, which can
now be supplied if the voltage between wires and the percentage loss in the
line remain unchanged. Assume a balanced load of unity power factor.
[7 Marks]
I1
KC i1 C V1
A
I2
KC i2 C V2 V
B
I3
KC i3 C V3
C
Figure Q.1(d)
(4)
SKEE 4683
Q.2 (a) Discuss briefly the rules for selecting an ideal location for substation.
[3 Marks]
(b) A transmission line has a span of 160 m between level supports. The
conductor has an effective diameter of 0.95 cm and weight 0.65 kg/m. The
wind pressure is 40 kg/m2 of projected area and has a breaking stress of
4250 kg/cm2.
Design the overhead lines by calculating:
(i) the sag for a safety factor of 5
(ii) the vertical sag
[8 Marks]
(c) For the area and the loads P1= 4MVA, P2=5 MVA, P3=5 MVA,
P4=6MVA, P5=5 MVA, P6=7 MVA, P7=4 MVA, operating at 13.2 kV as
shown in Figure Q.2(c), design the distribution substation by calculating:
(i) The best location for the substation
[8 Marks]
(ii) The number of substation outgoing feeder (#4/0 AWG copper
conductors). Then, determine whether these feeders are thermally
limited or voltage drop limited. Assume the load is uniformly
distributed on the area with no future loads are expected and the
maximum allowable voltage drop is 6%.
Distribution substation application curves for 6% voltage drop is given in
Appendix A.
[8 Marks]
(13)
SKEE 4683
mi -3 -1 Y 2 3
2
P6
1.5
P1 P2 P7
0 X
P3 P5
-0.5
-1
P4
-1.5
-2
-5 -2.5 0 2.5 5
mi
Figure Q.2(c)
(13)
SKEE 4683
Section B.
(c) Discuss the engineering studies that are recommended to be carried out
when connecting green-energy production plants to power systems.
[4 Marks]
Q.4 (a) State TWO (2) aspects that need to be considered for the designing of power
generating station.
[5 Marks]
(b) Give the comparison of steam power plant and green-energy plant on the
basis of operating cost, initial cost, efficiency and availability of source of
power.
[6 Marks]
(c) A 100 MW steam power station uses coal with calorific value of 5400
kcal/kg. Thermal efficiency of the station is 30% and electrical efficiency is
90%. Assume the heat equivalent of 1 kWh = 860 kcal. Calculate the coal
consumption per hour when the station is delivering its full rated output.
[8 Marks]
Q5) (a) State any TWO (2) types of secondary distribution systems.
[4 Marks]
Distribution
Feeder trnasformer
load
center
Lateral
Feeder
main
a
b
Area
served by
lateral
2/3 I4
c
I4
Figure Q.5(b)
[13 Marks]
(13)
SKEE 4683
(c) A single phase distributor one km long has resistance and reactance per
conductor of 0.1 Ω and 0.15 Ω respectively. At the far end, the voltage VB =
200 V and the current is 100 A at a power factor of 0.8 lagging. At the mid-
point M of the distributor, a current of 100 A is tapped at a power factor of
0.6 lagging with reference to the voltage VM at the mid-point.
(i) Draw the single line diagram of the system
(ii) Design the single phase distributor by finding voltage at mid-point,
sending end voltage VA and phase angle between VA and VB
[10 Marks]
(13)
SKEE 4683
Appendix A
Distribution substation application curves for 6% voltage drop.
(13)
SKEE 4683
Appendix B
Standard transformer and conductor sizes.
(13)
SKEE 4683
(13)
SKEE 4683
The K constant for copper conductors, assuming a lagging-load power factor of 0.9.