Quality Control Program:: Construction of Adgawan River Flood Control, (Incl. ROW) Limits: Test To Be Performed
Quality Control Program:: Construction of Adgawan River Flood Control, (Incl. ROW) Limits: Test To Be Performed
APPROVED :
MARCELINO M. OPERARIO
District Engineer
s
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
AGUSAN DEL SUR 2ND
DISTRICT ENGINEERING OFFICE
REGIONAL OFFICE XIII
San Francisco, Agusan del Sur
April 8, 2018
Date
We hereby certify that we have conducted an inspection and verification on work accomplished on the above- mentioned
project for the period April 2-7, 2018. We further certify that we have found that the quality of materials in the following
items of work corresponding to the quality accomplished conforms with the Standard Specifications an Special Provisions of
the contract viz :
Quantity Accomplished
ITEM NO.: DESCRIPTION : PROGRAMMED : THIS WEEK : TOTAL : ACCOMPL.
3rd report 16 - 22
We hereby certify that we have conducted an inspection and verification on work accomplished on the above- mentioned
project for the period April 16 - 22, 2018. We further certify that we have found that the quality of materials in the following
items of work corresponding to the quality accomplished conforms with the Standard Specifications an Special Provisions of
the contract viz :
Quantity Accomplished
ITEM NO.: DESCRIPTION : PROGRAMMED : THIS WEEK : TOTAL : ACCOMPL.
3rd report 16 - 22
4th report 23-30/31
We hereby certify that we have conducted an inspection and verification on work accomplished on the above- mentioned
project for the period April 16 - 22, 2018. We further certify that we have found that the quality of materials in the following
items of work corresponding to the quality accomplished conforms with the Standard Specifications an Special Provisions of
the contract viz :
Quantity Accomplished
ITEM NO.: DESCRIPTION : PROGRAMMED : THIS WEEK : TOTAL : ACCOMPL.
3rd report 16 - 22
We hereby certify that we have conducted an inspection and verification on work accomplished on the above- mentioned
project for the period April 23 - 30, 2018. We further certify that we have found that the quality of materials in the following
items of work corresponding to the quality accomplished conforms with the Standard Specifications an Special Provisions of
the contract viz :
Quantity Accomplished
ITEM NO.: DESCRIPTION : PROGRAMMED : THIS WEEK : TOTAL : ACCOMPL.
3rd report 16 - 22
April 2018
Month Year
VENDEY M. GALDIANO
(Project Engineer,Gov't)
22.21% 27.59%
(Current Month) Total to Date
PREPARED BY:
ARVIN D. AYOSO
Materials Engineer - 1
DATREBIL CONSTRUCTION & SUPPLY
SUBMITTED BY:
LEODEGARIO M. MAZO
Engineer III
Chief, Quality Assurance Section
5.38%
STATUS OF TEST
Date: May 2, 201
Project:
Construction of Adgawan River Flood Control, (Incl. ROW)
Location: Veruela, Agusan del Sur
Our records indicate that the status of test in the above project for April 1 - 30, 2018
is as follows.
Actual Medium Number Test
Estimated No. of Test on Balance
Item Materials Quantities Required File
A. FACILITIES FOR THE
Construction ENGINEERS
of Combined Field Office,
A.1.1(1) Laboratory and Livig Quarters Building for the 1.00 ls P.E. Cert-1 0 1
B. Other General
Engineer
Requirements
B.4(1) Construction Survey & Staking 0.23 kms. P.E. Cert-1 0 1
B.4(10) Misc. Survey and Staking 1.00 lumpsum P.E. Cert-1 0 1
B.5 Project Bilboard 4.00 each P.E. Cert-1 0 1
B.7 Occupational Safety and Health Program 7.00 month P.E. Cert-1 0 1
B.8 Traffic Management 7.00 month P.E. Cert-1 0 1
B.9 Mobilization / Demobilization 1.00 lumpsum P.E. Cert-1 0 1
D. Subbase & Base Course
200(1) Aggregate Subbase Course 93.79 cu.m GPC-1 0 1
CBR-1 0 1
E. Surface Courses
311(1)a PCC Pavement (Unreinforced) (0.15m thk) 176.28 sq.m.
a. Cement * 2.35 bags
b. Fine Aggregates ** 0.14 cu.m
c. Coarse Aggregates *** 0.25 cu.m.
H. Miscellaneous Structures
603(3)a1 Metal Guardrail (Metal Beam Including Post) 70.00 l.m. Q-1 0 1
603(4)a Metal Beam End Piece 2.00 ea P.E. Cert. - 1 0 1
A.1 Earthworks
101(6) Removal of Structures and Obstruction 67.48 cu.m. P.E. Cert. - 1 1 0
104(1)a Embankment from Roadway Excavation 78.77 sq.m. P.E. Cert. - 1 0 1
105(1)a Subgrade Preparation, Common Material 176.28 mts P.E. Cert. - 1 0 1
1700(1) Clearing & Grubbing 1,400.00 sq.m. P.E. Cert. - 1 1 0
1702(1)a Structure Excavation 801.04 cu.m. P.E. Cert. - 1 0 1
1704(1) Embankment 6,860.26 cu.m. P.E. Cert. - 1 1 0
. Bank & Slope Protection Structures
404(1)b Reinforcing Steel Grade 60 23,831.58 kgs. Q-1/size/10,000kg 0 2/size
405(1)a3 Structural Concrete Class A 539.25 cu.m.
a. Cement * 3,659.19 bags
b. Fine Aggregates ** 192.59 cu.m
c. Coarse Aggregates *** 385.18 cu.m
407(8) Lean Concrete 147.57 cu.m.
a. Cement * 848.53 bags
b. Fine Aggregates ** 52.70 cu.m
c. Coarse Aggregates *** 105.41 cu.m
1710(2)a Grouted Riprap, Class A 362.62 cu.m.
a. Cement * 870.29 bags
b. Fine Aggregates ** 72.52 cu.m.
c. Coarse Aggregates *** 4.35 cu.m
1714(1) Gabions 20.00 cu.m. Q-1 1 0
a. Boulders 1.05 cu.m. Sp. Gr. - 1 1 0
1714(2) Mattresses 195.00 cu.m. Q-1 1 0
a. Boulders Sp. Gr. - 1 1 0
1716(6) Structural Steel sheet Piles (Furnished) 3,900.00 lm Q-1 1 0
1716(12) Structural Steel sheet Piles (Driven) 3,835.00 lm IR-1 1 0
Summary:
a. Cement * 5,380.36 bags Q-1 0 1
b. Fine Aggregates ** 317.95 cu.m. Q-1 0 1
G-5 0 5
c. Coarse Aggregates *** 495.19 cu.m. Q-1 0 1
G-7 0 7
Work
Accom.
0.00%
50.00%
0.00%
50.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
100.00%
0.00%
0.00%
100.00%
0.00%
100.00%
0.00%
100.00%
100.00%
0.00%
0.00%
100.00%
100.00%
0.00%
0.00%
0.00%
0.00%
0.00%
27.59%
M. GALDIANO
gineer II
Engineer I
Project :
Construction of Adgawan River Flood Control, (Incl. ROW) For the period: April 1 - 30, 2018
Location : Veruela, Agusan del Sur
Note:
Project on-going…
CONCERN REMARKS
* Accreditation of PE/PI A
VENDEY M. GALDIANO PE I
Accreditation No.
* Accreditation of Contractors'/Consultants'
ME B
ARVIN D. AYOSO ME-I
Project on going…
Acreditation No.
* Limits of Assignment of PE/ME C
None
None
REMARKS
Project on going…
The minimum testing requirement were performed by the
contractor.
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
AGUSAN DEL SUR 2ND
DISTRICT ENGINEERING OFFICE
REGIONAL OFFICE XIII
San Francisco, Agusan del Sur
CERTIFICATION
Construction of Adgawan River Flood Control, (Incl. ROW)
Name of Project :
I hereby certify that Item 1714(1) which represents the Gabions of the above named projec
a total quantity of Twenty (20) cubic meter was done in accordance to the approved plans &
specifications.
VENDEY M. GALDIAN
Project Engineer I
R.13.11.6/qas/ads II/fconolIIIfiles
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
AGUSAN DEL SUR 2ND
DISTRICT ENGINEERING OFFICE
REGIONAL OFFICE XIII
San Francisco, Agusan del Sur
CERTIFICATION
Construction of Adgawan River Flood Control, (Incl. ROW)
Name of Project :
I hereby certify that Item 1713(2) which represents the Mattresses of the above named pro
with a total quantity of One-Hundred Ninety five (195) cubic meter was done in accordance to the
approved plans & specifications.
VENDEY M. GALDIAN
Project Engineer I
R.13.11.6/qas/ads II/fconolIIIfiles
Republic of the Philippines
NT OF PUBLIC WORKS AND HIGHWAYS
AGUSAN DEL SUR 2ND
TRICT ENGINEERING OFFICE
REGIONAL OFFICE XIII
San Francisco, Agusan del Sur
IFICATION
n River Flood Control, (Incl. ROW)
VENDEY M. GALDIANO
Project Engineer I
Republic of the Philippines
NT OF PUBLIC WORKS AND HIGHWAYS
AGUSAN DEL SUR 2ND
TRICT ENGINEERING OFFICE
REGIONAL OFFICE XIII
San Francisco, Agusan del Sur
IFICATION
n River Flood Control, (Incl. ROW)
VENDEY M. GALDIANO
Project Engineer I