Assignment Guidelines - Project Scope and Time Managment
Assignment Guidelines - Project Scope and Time Managment
1.1 Identify and analyse the main project scope and time management issues at
Macon, Inc. (10)
Project scope describes what the project will accomplish, what it will deliver, what it will produce and
where work packages start and finish. So it includes only the work
required to complete the project successfully. Thus, it suffices to say, that project scope management is
primarily about defining and controlling what is and what is not part of a project
Develop test equipment for the tyre industry to meet customer needs. It involved the electrical and
mechanical engineering departments who were the custodians of the product.
Engineering would design a product and then hand it to production to assemble it.
Production ultimately assembled the product and shipped it out to the customer.
Projects were delayed and blame shifted between departments. One project failed
as the result of a project leader who failed to control scope. Each day the project
would fall further behind because work was being added with very little regard for the
project’s completion date. Project estimates were based upon a “gut feel” rather
than upon sound quantitative data. The delay in shipping dates was creating more
and more frustration for the customers. The customers began assigning their own
project managers as “watchdogs” to look out for their companies’ best interests
1.2 What action would you advise the president to take to “achieve some degree of
excellence in project management”? (15)
� Define objectives
The starting point for problem solving is to define the project’s goals and objectives because problems
and opportunities can only be evaluated against these objectives. Objectives at the project level can be
expressed as achieving the project charter and the baseline plan, together with addressing the
stakeholders’ needs and expectations.
o Project charter – this outlines the purpose of the project, its objectives and how it
will be managed.
o Baseline plan – this is the roll up of all the planning and control documents. These
documents include the scope of work, specifications, time planning, procureme nt planning, resource
planning, quality planning, risk planning and communication
planning.
� Identify the problems or opportunities
Sensing and identifying problems is a skill and an art usually gained from experience. Problems and
opportunities can be identified using the following techniques:
o Progress meetings and progress reports – The discussions should identify
potential problems
o Non Conformance Report (NCR) - When the quality control department find
work that does not achieve the required condition as set out in the project quality
plan, they raise a NCR. The NCR initiates a process to correct the problem.
o Situation appraisal – The following questions should be raised- What is wrong
with the current solution? What would happen if we did not address this
problem? In appraising the situation, and with the help of stakeholders, specific
challenges that help shape the problem can be identified.
QUESTION 2 (50)
The table below gives the duration estimates in days for a construction projection.
2.1 Determine the expected completion time for each activity. (10)
a = optimistic time
m = most probable
b = pessimistic
ta = 4 + 4(7) + 10
6
=7
Tb = 2 +4(9) + 10
6
=8
Tc = 2 + 4(5) + 8
6
=5
Td = 16 + 4(19) + 28
6
= 20
Te = 6 + 4(9) + 24
6
= 11
Tf = 1 + 4(7) + 13
6
=7
Tg = 4 + 4(10) + 28
6
= 12
Th = 2 + 4(5) + 14
6
=6
Ti = 5 + 4(8) + 17
6
=9
Tj = 2 + 4(5) + 8
6
=5
2.2 Construct an AON network for the activities of this contract. (10)
2.3 Determine the critical path for the project by calculating the slack for each
activity. (15)
SLACK = LS - ES (or) LF – EF
Activity LS ES Slack
A 1 0 1
B 0 0 0
C 8 8 0
D 14 13 1
E 13 13 0
F 24 24 0
G 19 13 6
H 34 33 1
I 31 31 0
J 40 40 0
Normal Crashed
Activity Duration Cost (Rands) Duration Cost (Rands)
(Days) (Days)
B 3 R1500 2 R2000
C 5 R3500 4 R5000
E 4 R6800 3 R7500
F 5 R2500 3 R6000
I 7 R4200 6 R5400
J 4 R2000 3 R2700
2.4.1 Determine the cost per day to crash each of the activities. (10)
2.4.2 Calculate the total time and the cost involved. (5)
Crashed project cost = normal cost + cost of crashed activities
= R20 500 + (1xR500) + (1xR1500) + (1xR700) + (2xR1750) +
(1xR1200) + (1xR700)
= R20 500 + R6 350
= R26 850
QUESTION 3 (25)
With the aid of an example, critically discuss how making cost and schedule trade-
offs may accelerate project duration.
Crashing (pg 72). – focus on tasks that can complete quickly at little or no cost.
Shorten tasks that are less costly.
The project manager is frequently confronted with having to reduce the scheduled
completion time of a project to meet a deadline. In other words, the manager must
finish the project sooner than indicated by the CPM/PERT network analysis. Project
duration can often be reduced by assigning more labour to project activities, in the
form of overtime, and by assigning more resources (material, equipment, and so on).
However, additional labor and resources increase the project cost. Thus, the
decision to reduce the project duration must be based on an analysis of the trade-off
between time and cost. Project crashing is a method for shortening the project
duration by reducing the time of one (or more) of the critical project activities to less
than its normal activity time. This reduction in the normal activity time is referred to
as crashing. Crashing is achieved by devoting more resources, usually measured in
terms of dollars, to the activities to be crashed.
The General Relationship of Time and Cost
In our discussion of project crashing, we demonstrated how the project critical path
time could be reduced by increasing expenditures for labor and other direct
resources. The objective of crashing was to reduce the scheduled completion time to
reap the results of the project sooner. However, there may be other reasons for
reducing project time. As projects continue over time, they consume indirect costs,
including the cost of facilities, equipment, and machinery, interest on investment,
utilities, labor, personnel costs, and the loss of skills and labor from members of the
project team who are not working at their regular jobs. There also may be direct
financial penalties for not completing a project on time. For example, many
construction contracts and government contracts have penalty clauses for exceeding
the project completion date.
In general, project crashing costs and indirect costs have an inverse relationship;
crashing costs are highest when the project is shortened, whereas indirect costs
increase as the project duration increases.