Smart Sourcing Implementation Checklist v3

This document outlines the tasks and timeline for installing and setting up On Time In Full Smart Sourcing software at a dealer. It involves identifying project leaders, setting up IT connectivity, configuring strategy and parameter settings in the test environment, training personnel, and conducting meetings to ensure departments understand the new system and their roles. The on-site portion includes finalizing parameters, training the trainer, analyzing opportunities to preplan service, and holding meetings with dealer leadership and service teams.

Uploaded by

enjoythedocs
Copyright
© © All Rights Reserved
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
179 views

Smart Sourcing Implementation Checklist v3

This document outlines the tasks and timeline for installing and setting up On Time In Full Smart Sourcing software at a dealer. It involves identifying project leaders, setting up IT connectivity, configuring strategy and parameter settings in the test environment, training personnel, and conducting meetings to ensure departments understand the new system and their roles. The on-site portion includes finalizing parameters, training the trainer, analyzing opportunities to preplan service, and holding meetings with dealer leadership and service teams.

Uploaded by

enjoythedocs
Copyright
© © All Rights Reserved
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
You are on page 1/ 6

On Time In Full Smart Sourcing Installation

On-Site Date: Wednesday, March 24, 2010


3
Timeline Week Task # Task Task Description and Key Points Responsibility Date Completed

Identify OTIF & Smart Sourcing Project


Leader/Champion. Recommend someone Dealer Management
Week 1 02/24/10 1.1 Communication
with Parts & Service responsibility or co- Team
leadership.

Announce OTIF & Smart Sourcing strategy Dealer Management


Week 1 02/24/10 1.2 Communication
to Parts & Service at impacted stores Team

Purpose of meeting: To ensure the PSSRs


and Parts Dept understands OTIF and Cat & Dealer
Week 1 02/24/10 1.3 PSSR/Parts meeting
Smart Sourcing rollout plan, and their Management Team
opportunity.

Establish connectivity to Antares


1. Send email to
[email protected]
Week 1 02/24/10 1.4 IT Caterpillar
2. Request connectivity from their dealer
test AS/400 to the ANTARES test system
3. Include Dealer IT contact

Week 1 02/24/10 1.5 Communication Discuss on-site Agenda and Travel Plans Caterpillar

Obtain dealer AS/400 IP address, (test &


Week 2 03/10/10 2.1 IT production, if applicable) DBS user profile Dealer IT Manager
and password for FDC Solutions

DBSi 5.0 Dealers: Successfully install all


service packs (November 2008 and May
2009 and Sept 2009 and Dec 2009)
Week 2 03/10/10 2.2 IT Dealer IT Manager
DBS 2.3.4 Dealers: Ensure Accenture has
latest service packs installed
On Time In Full Smart Sourcing Installation
On-Site Date: Wednesday, March 24, 2010
3
Timeline Week Task # Task Task Description and Key Points Responsibility Date Completed

Strategy and parameter set up for Smart


Sourcing
- List of Dealer Codes and associated
document and inventory stores
- Service ordering practices (Do technicians Dealer Champion and
Week 2 03/10/10 2.3 Strategy
order their own parts? Are they on auto Caterpillar
release? Who manages back orders for the
company?)
Dealer Data:
- Dealer Org Chart

Complete Parameter Setup Form


https://dealer.cat.com/cda/layout?
m=104721&x=7 Dealer Champion and
Week 2 03/10/10 2.4 Strategy
Caterpillar
https://dealer.cat.com/cda/layout?m=104721&x=7

Set up all dealer codes for 555 and 556:


1. Send email to Diane Grosse requesting
Week 2 03/10/10 2.5 Profile profiles for all dealer codes Cat (Tracy K.)
2. Send email to Facility requesting Route-
Stop-Lineups to be udated for new profiles

Install the Smart Sourcing software in Test


Week 2 03/10/10 2.6 Install in Test FDC Solutions
environment

Smart Sourcing Setup Smart Sourcing parameters in


Week 2 03/10/10 2.7 Caterpillar
Parameter Set Up Dealer's Test Environment

Week 2 03/10/10 2.8 Test Environment Turn NEPS 1046 Off Dealer IT Manager
UAT Smart Sourcing
Week 2 03/10/10 2.9 Test Smart Sourcing scenarios remotely Caterpillar
Testing

Week 3 03/17/10 3.1 Hot Stock Review start date with facing facility Cat (Tracy K.)
On Time In Full Smart Sourcing Installation
On-Site Date: Wednesday, March 24, 2010
3
Timeline Week Task # Task Task Description and Key Points Responsibility Date Completed

Week 3 03/17/10 3.2 Training Prep Identify dealer Trainer Dealer Champion

Week 3 03/17/10 3.3 Training Prep Identify personnel to be trained by store Dealer Champion

Week 3 03/17/10 3.4 Strategy Run a min type analysis on Dealer inventroy Caterpillar

Purpose of meeting: To ensure the Dealer


Management and Team Leaders
understand OTIF and Smart Sourcing
rollout plan, as well as each others' roles
and responsibilities. Establish branch
goals.
Week 4 - Onsite 03/24/10 4.1 Leader Meeting Cat and Dealer
Facilitator: Cat
Attendees: Dealer Champion, Parts VP,
Service VP, Product Support Manager,
Inventory Control Manager, Branch
Managers

Parameter Review parameters and initial set up


Week 4 - Onsite 03/24/10 4.2 strategy/Smart Strategy Cat Team and Dealer
Sourcing Testing Run test scenarios

Smart Sourcing team on site for training


Week 4 - Onsite 03/24/10 4.3 Train the Trainer Review training materials & user aids Cat & Dealer Trainer
*CAT resources available to assist

Cat, Dealer Champion,


Smart Sourcing team conducts work flow
Service Opportunity Service Manager, Parts
Week 4 - Onsite 03/24/10 4.4 analysis to determine high opportunities to
Analysis Manager, Cat
preplan and challenges
PSOR/SOR
Purpose of meeting: To ensure the Service
Week 4 - Onsite 03/24/10 4.5 Service Meeting Dept understands OTIF and Smart Sourcing Cat and Dealer
rollout plan, and their opportunity.
On Time In Full Smart Sourcing Installation
On-Site Date: Wednesday, March 24, 2010
3
Timeline Week Task # Task Task Description and Key Points Responsibility Date Completed
Train impacted stores and personnel
Training Product
Week 4 - Onsite 03/24/10 4.6 (Service Dept., Order Entry, Backorder Cat Team
Support Personnel
Analysts, Warehouse Personnel, etc.)
Finalize and agree on metrics to track OTIF
Week 4 - Onsite 03/24/10 4.7 Metrics Cat and Dealer Team
success. Discuss reporting available.
Send communication letter to entire
dealership
OTIF Announcement Letter:
Week 4 - Onsite 3/24/2010 4.8 Communication https://dealer.cat.com/cda/layout? Dealer Champion
m=104721&x=7

https://dealer.cat.com/cda/layout?m=104721&x=7

Smart Sourcing logic moved to production Dealer IT Manager and


Week 5 03/31/10 5.1 Install in Production
system FDC Solutions
Turn on delivery date capture - See link
Turn on Delivery below Dealer
Week 5 03/31/10 5.2 Date for DBSi 5.0 Trainer/Parameter
dealers Owner/IT
https://dealer.cat.com/cda/files/368852/7/Delivery%20Date%20Performance%20Setup%20with%20Screenshots.doc?m=104

Go live with OTIF & Smart Sourcing


Week 5 03/31/10 5.3 Go Live Dealer
processes and systems
Track and measure performance. Plan
Cat and Dealer
Week 9 04/28/10 9.1 Follow up monthly touch base meetings with Cat
Champion
team.
Update non-working days. Similar to the
Year End Annual Maintenance Dealer
month end processing (Source Schedule)
Complete Change Readiness
Change
Optional Assessment/Document questions and Dealer
Management
concerns to gain buy-in
Smart Sourcing On-Site Agenda
Review parameters and initial set up
2 Hours
Strategy

4 Hours Run test scenarios


Day 1
Service Analysis to identify high
2 Hours opportunities/challenges to pre ordering
parts

1 Hour Session Present Service Opportunities

1 Hour Sessions
Train Dealer Counter and Shop Personnel
(Qty TBD)
Day 2

1 Hour Metric Discussion

1 Hour Wrap-up
Agenda

Cat Team and Dealer Team

Cat Team and Dealer Team

Cat Team & Dealer Service


Manager

Cat Team and Dealer Service


Team

Cat Team

Cat Team and Dealer Team

Cat Team and Dealer Team