Authority Matrix Dov

The document is an authority matrix that outlines the planned and revised planned start and finish dates for various activities related to obtaining approvals and inspections from utility authorities like SEWA, Civil Defence Authority, Etisalat for the transformer room, low voltage, firefighting, gas, and water connections of a building project. It provides the schedule for submitting drawings and documents, inspections, addressing comments, deposit payments, and obtaining necessary sign-offs for energization and commissioning.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
215 views

Authority Matrix Dov

The document is an authority matrix that outlines the planned and revised planned start and finish dates for various activities related to obtaining approvals and inspections from utility authorities like SEWA, Civil Defence Authority, Etisalat for the transformer room, low voltage, firefighting, gas, and water connections of a building project. It provides the schedule for submitting drawings and documents, inspections, addressing comments, deposit payments, and obtaining necessary sign-offs for energization and commissioning.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 3

AUTHORITY MATRIX

PLANNED Revised Planned


Activity ID Activity Name Remarks
Start Finish Start Finish
HT / TRANSFORMER ROOM
AUT-HT-1000 SEWA Approval of Transformer Room Dwg 25-Sep-16
AUT-HT-1010 HT and Transformer Room Civil Works Readiness 6-Nov-17
AUT-HT-1020 Application / Inspection of HT & Transformer Room by SEWA 12-Nov-17
20-Nov-
AUT-HT-1030 SEWA Comments for HT & Transformer Room 21-Nov-17
17

NOT IN GECO SCOPE


21-Nov-
AUT-HT-1040 Incorporation of Comments for HT & Transformer Room 25-Nov-17
17
AUT-HT-1050 2nd Inspection and approval by SEWA 5-Dec-17
AUT-HT-1060 HT / Transformer Application Submission to SEWA 6-Dec-17
AUT-HT-1070 Installation of Transformer 5-Dec-17 30-Dec-17
AUT-HT-1080 Installation of HT Panel 7-Dec-17 1-Jan-18
AUT-HT-1090 Installation of 1C 630mm2 Cables b/w Transformer & MDB 7-Dec-17 1-Jan-18
AUT-HT-1100 Cable Pulling b/w Transformer & HT Panel 7-Dec-17 1-Jan-18
AUT-HT-1110 Glanding & Termination of Cables to HT Panels / Transformers 25-Jan-18
AUT-HT-1120 Testing & Commissioining of HT Panels / Transformers 27-Jan-18 28-Jan-18
AUT-HT-1130 Energization of HT Panel / Transformer by SEWA 16-Jan-19 17-Jan-19

LV
LV Drawings Approval
AUT-LV-1000 Electrical Load Application Form Submission to SEWA 13-Apr-17 20-Apr-17 31-Dec-17 7-Jan-18
AUT-LV-1010 Acceptance of application form by SEWA 21-Apr-17 8-Jan-18
AUT-LV-1020 Electrical SLD / Load Sch / Dwg Submission to SEWA 22-Apr-17 6-May-17 9-Jan-18 20-Jan-18
27-May-
AUT-LV-1100 Receipt of Approval of Dwg Stamped from SEWA 6-May-17 21-Jan-18 8-Feb-18
17
LV Material Approval / Inspection
AUT-LV-1180 Delivery of LV Switchgear to Site 7-Dec-17 3-Sep-18
14-Aug- 24-Aug-
AUT-LV-1190 Opening ot Permanent Connection File in SEWA 14-Dec-18 24-Dec-18
19 19
25-Aug- 25-Aug-
AUT-LV-1200 SEWA 1st LV Inspection 25-Dec-18 1-Jan-19
19 19
26-Aug- 29-Aug-
AUT-LV-1210 Incorporating SEWA Comments 1-Jan-19 5-Jan-19
19 19
29-Aug-
AUT-LV-1220 SEWA 2nd Inspection for LV 6-Jan-19 6-Jan-19 1-Sep-19
19
AUT-LV-1260 Power ON 16-Jan-19 17-Jan-19 2-Sep-19 3-Sep-19

CIVIL DEFENCE
AUT-CD-1010 Submission to CDA for Approval of Dwg FF/ FA/ EM 1st Time 19-Jun-17 9-Jan-18
AUT-CD-1070 CDA Approval of Drawings 19-Jun-17 10-Jul-17 9-Jan-18 27-Jan-18
AUT-CD-1090 Substantial Completion of FF/FA/EM Works for CDA Inspection 15-Dec-18
AUT-CD-1080 Application & CD 1st Inspection 16-Dec-18 23-Dec-18 4-Sep-19 15-Sep-19
AUT-CD-1100 CDA comments rectification 23-Dec-18 25-Dec-18 15-Sep-19 17-Sep-19
AUT-CD-1110 Re Submission for CDA Inspection 25-Dec-18 17-Sep-19
AUT-CD-1120 CD Final Inspection and Approval 25-Dec-18 1-Jan-19 17-Sep-19 24-Sep-19
AUT-CD-1130 Getting Civil Defense Cerificate/NOC 1-Jan-19 9-Jan-19 24-Sep-19 3-Oct-19
SEWA WATER SUPPLY
25-Aug-
AUT-WS-1040 Application for SEWA Inspection for Water supply 25-Oct-18 12-Nov-18 5-Aug-19
19
12-Nov- 26-Aug-
AUT-WS-1070 Pay Water Meter Deposit to SEWA 28-Nov-18 10-Sep-19
18 19
28-Nov-
AUT-WS-1080 Issuance of Water Meter & Installations(By SEWA) 16-Dec-18 11-Sep-19 26-Sep-19
18

AUT-WS-1090 Issuance of Water NOC's 16-Dec-18 23-Dec-18 27-Sep-19 3-Oct-19


SEWA NATURAL GAS
26-Aug-
AUT-NG-1090 Pay GAS Meter Deposit to SEWA 8-Nov-18 7-Sep-19
19
AUT-NG-1100 Application for SEWA Inspection 14-Oct-18 8-Aug-19
11-Nov-
AUT-NG-1140 Issuance of GAS Meter & Installations(By SEWA) 22-Nov-18 8-Sep-19 20-Sep-19
18
25-Nov-
AUT-NG-1150 Issuance of GAS NOC 3-Dec-18 21-Sep-19 29-Sep-19
18

ETISALAT
AUT-ET-1000 Submission of Drawings to Etisalat 14-Jul-17 27-Jul-17 17-Jan-18 30-Jan-18
AUT-ET-1010 Approval of Drawings from Etisalat 27-Jul-17 17-Aug-17 30-Jan-18 16-Feb-18
12-Aug-
AUT-ET-1020 Submission of Wiring Completion Report to ETISALAT 25-Nov-18
19
25-Nov- 13-Aug-
AUT-ET-1030 Application for Etisalat Inspection 8-Nov-18
18 19
13-Aug- 28-Aug-
AUT-ET-1040 ETISALAT 1st Inspection
19 19
29-Aug-
AUT-ET-1070 Issuance of NOC 8-Nov-18 19-Nov-18 6-Sep-19
19
19-Nov-
AUT-ET-1080 Payment & Connections 28-Nov-18 7-Sep-19 15-Sep-19
18