William Clark Partnership LTD V Dock ST PCT LTD Case Analysis
The court determined a contractual dispute between a construction company and a company providing quantity surveying and project management services. While the quantity surveying company had substantially performed its pre-construction services, it failed to provide monthly cost reports during construction, so the construction company was entitled to a deduction for that breach. However, the construction company did not prove that deficiencies by the quantity surveying company caused the entire cost overrun on the project.
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0 ratings0% found this document useful (0 votes)
106 views3 pages
William Clark Partnership LTD V Dock ST PCT LTD Case Analysis
The court determined a contractual dispute between a construction company and a company providing quantity surveying and project management services. While the quantity surveying company had substantially performed its pre-construction services, it failed to provide monthly cost reports during construction, so the construction company was entitled to a deduction for that breach. However, the construction company did not prove that deficiencies by the quantity surveying company caused the entire cost overrun on the project.
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 3
William Clark Partnership Ltd v Dock St Pct Ltd
Queen's Bench Division (Technology & Construction Court)
16 October 2015 Case Analysis Where Reported [2015] EWHC 2923 (TCC); 163 Con. L.R. 117; Official Transcript; Case Digest Subject: Construction law Other related subjects: Contracts; Damages Keywords: Breach of contract; Causation; Causation; Construction contracts; Deductions; Loss; Professional negligence; Project managers; Quantity surveyors Summary: The court determined issues arising from a contractual dispute between a construction company and a company providing quantity surveying and project management services. Abstract: The claimant company sought the balance of professional fees due under a deed of appointment with the defendant construction company.
The claimant had provided quantity surveying and project
management services for the defendant's development project. The deed entitled the claimant to invoice 65 per cent of the total fees at completion of the tender stage, with the balance due in instalments. The defendant was dissatisfied with the services provided, stating that there had been considerable overspend on the project. The claimant contended that it had provided the services required and was entitled to payment. The defendant counter-claimed for repayment of a sum already paid, or a deduction, by abatement or otherwise, from any sum payable, and for damages for breach of contract and/or professional negligence. It also claimed that unnecessary variations had been made to the works by the claimant. The issues were (i) in respect of breach, causation and loss in relation to the pre-construction, construction and post-construction phase services, and the unnecessary variations claim; (ii) whether the contractual trigger point for payment under the deed of appointment had been satisfied; and (iii) the defendant's entitlement to a deduction in relation to any non-performed or defectively performed services. Held: Judgment accordingly. (1) The pre-construction phase was from project inception through to entry into a contract. The services included preparation of specification documents and an estimate of construction costs for the chosen design scheme, and advice on any design scheme change cost implications. The claimant was alleged to have failed to ascertain the defendant's budget, to provide a final cost plan or to advise regarding a competitive tendering process. However, the defendant had not made out a case regarding any relevant loss or damage as a result of any breach in relation to that phase (see paras 3.1 to 3.27 of judgment). The heart of the defendant's case was in the context of the construction phase. The claimant's performance of its obligations was seriously deficient. It failed to give appropriate advice regarding the design process costs implications and to properly analyse or report on the final account. However, the allegations were not fully particularised by the defendant and it was not appropriate to make any finding of widespread breach. The defendant's case, albeit a claim for damages for professional negligence, had the essential characteristics of a global claim, in that it identified numerous breaches by the claimant which were said to be potential or actual causes of cost overrun, without any detailed particularisation of the causal connection between the individual breaches and the whole or part of the overrun, Walter Lilly & Co Ltd v Mackay [2012] EWHC 1773 (TCC), [2012] B.L.R. 503 considered. The defendant's fundamental difficulty was that it had failed to prove, on the balance of probabilities, that no substantial part of the overrun would have been incurred in any event. It was not self-evident that a substantial overrun could only have been caused by failings attributed to the quantity surveying and project management operations. The defendant had not, therefore, made out its case on causation in respect of the total cost overrun, Walter Lilly applied (paras 6.1 to 6.33). The defendant's unnecessary variationsclaim succeeded, but only to a limited extent (paras 7.1-7.39). It had also suffered real loss as a result of the claimant's breach in relation to post-construction phase services, but again only to a limited extent (paras 9.1 to 9.10). (2) Completion of the tender stage was to be equated with completion of the pre- construction services, which the claimant had substantially performed. It was therefore entitled to payment of the balance of its fees, subject to a deduction in relation to the variations and post-construction phase services. The defendant had failed on the most substantial allegation of non-performance, the failure to undertake a competitive tender, and the claimant's established failures were not so significant so as to justify a finding that it had not substantially performed the pre-construction phase services. In those circumstances, and subject to the defences of deduction by abatement or otherwise and/or set off, the claimant had established its entitlement to its remaining fees and there was no basis for repayment of sums already paid (paras 4.1 to 4.5). (3) In respect of pre-construction phase services, it was only necessary to consider deduction in relation to the failure to prepare a cost plan. It was open to the defendant to contend that the services were not properly performed, but it could not defend itself by contending that all, or some specific part, of the services were performed, but not properly in every material respect, so as to seek a reduction in the price payable for the whole or specific part, Multiplex Constructions (UK) Ltd v Cleveland Bridge UK Ltd [2006] EWHC 1341 (TCC), 107 Con. L.R. 1 applied. The defendant's claim to entitlement to deduct the costs of the failure to prepare a costs plan had to fail. It was entitled to make a deduction in relation to the construction phase services, for the claimant's breach of its obligations to provide monthly cost reports. That was a serious failure of a basic obligation any professional quantity surveyor would be expected to provide. It was not appropriate to make any further deduction in relation to post-construction phase services (paras 5.1 to 5.11, 9.1 to 8.5, 10.1 to 10.2).
Judge: Judge Stephen Davies
Counsel: For the claimant: Lucy Colter. For the defendant: Justin Mort QC. Solicitor: For the claimant: Kennedys Law LLP (Manchester). For the defendant: Harrison Drury (Preston).
In Conclusion Following The Above Said The Best Advice For The Contractor Is: To Give Notice Timeously, in Writing, and in Terms and Condition of The Contract To Keep Adequate Records