50% found this document useful (2 votes)
1K views

3 - Sample Problem Set - Project Scheduling

The document discusses project scheduling and planning for several hypothetical construction and event planning projects. It provides information on project activities, including descriptions, predecessors, and time estimates. It asks questions about determining critical paths, developing schedules, and calculating completion probabilities. Analyzing the projects allows understanding how to effectively plan and coordinate complex endeavors with multiple interdependent tasks.

Uploaded by

Qila Ila
Copyright
© © All Rights Reserved
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
50% found this document useful (2 votes)
1K views

3 - Sample Problem Set - Project Scheduling

The document discusses project scheduling and planning for several hypothetical construction and event planning projects. It provides information on project activities, including descriptions, predecessors, and time estimates. It asks questions about determining critical paths, developing schedules, and calculating completion probabilities. Analyzing the projects allows understanding how to effectively plan and coordinate complex endeavors with multiple interdependent tasks.

Uploaded by

Qila Ila
Copyright
© © All Rights Reserved
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 4

Project Scheduling

1. Colonial State College is considering building a new multipurpose athletic complex


on campus. The complex would provide a new gymnasium for intercollegiate
basketball games, expended office space, classrooms, and intramural facilities. The
following activities would have to be undertaken before construction can begin.

Activity Description Immediate predecessor Time (weeks)


A Survey building site - 6
B Develop initial design - 8
C Obtain board approval A, B 12
D Select architect C 4
E Establish budget C 6
F Finalize design D, E 15
G Obtain financing E 12
H Hire contractor F, G 8

a. Draw a project network.


b. Identify the critical path (Ans: B-C-E-F-H)
c. Develop the activity schedule for the project.
d. Does it appear reasonable that construction of the athletic complex could begin one
year after the decision to begin the project with the site survey and initial design
plans? What is the expected completion time for the project? (Ans: Yes; 49 weeks)

2. Assume that the activity time estimates (in days) and immediate predecessors for A
swimming pool construction project are as follows:

Activity Optimistic Most probable Pessimistic Immediate


predecessor
A 3 5 6 ----
B 2 4 6 ----
C 5 6 7 A, B
D 7 9 10 A, B
E 2 4 6 B
F 1 2 3 C
G 5 8 10 D
H 6 8 10 D, F
I 3 4 5 E, G, H

a. What are the critical activities? (Ans: A, D, H, I)


b. What is the expected time to complete the project? (Ans: 25.66 days)
c. What is the probability that the project can be completed in 25 or fewer days? (Ans:
0.2578)
3. Davison Construction is building a luxury lakefront home in the Finger Lakes region
of New York. Coordination of the architect and subcontractor will require a major
effort to meet the 44-week (approximately 10-month) completion date requested by
the owner. The Davison project manager prepared the following project network.

B F

Start A C G Finis
h

D E

Estimates of the optimistic, most probable, and pessimistic times (in weeks) for the activities
are as follow.

Activity Optimistic Most probable Pessimistic


A 4 8 12
B 6 7 8
C 6 12 18
D 3 5 7
E 6 9 18
F 5 8 17
G 10 15 20
H 5 6 13

a. Find the critical path.


b. What is the expected project completion time?
c. What is the probability the project can be completed in the 44 weeks as requested by
the owner?
d. What is the probability the building project could run more than 3 months late? Use
57 weeks for this calculation.
e. What should the construction company tell the owner?
4. Doug Casey is in charge of planning and coordinating next spring’s sales
management training program for his company. Doug listed the following activity
information for this project.

Activity Description Immediate Optimistic Time (weeks) Pessimistic


predecessor Most probable
A Plan topic - 1.5 2.0 2.5
B Obtain speakers A 2.0 2.5 6.0
C List meeting locations - 1.0 2.0 3.0
D Select location C 1.5 2.0 2.5
E Finalize speaker travel plans B, D 0.5 1.0 1.5
F Make final check with speakers E 1.0 2.0 3.0
G Prepare and mail brochure B, D 3.0 3.5 7.0
H Take reservations G 3.0 4.0 5.0
I Handle last-minute details F, H 1.5 2.0 2.5

a. Draw a project network.


b. Prepare an activity schedule.
c. What are the critical activities and what is the expected project completion time?
(Ans: A-B-G-H-I; 15 weeks)
d. If Doug wants a 0.99 probability of completing the project on time, how far ahead of
the scheduled meeting date should he begin working on the project? (Ans: 17.4
weeks)

5. The manager of the Oak Hills Swimming Club is planning the club’s swimming team
program. The first team practice is scheduled for May 1. The activities, their
immediate predecessors, and the activity time estimates (in weeks) are as follows.

Activity Description Immediate Optimistic Time (weeks) Pessimistic


predecessor Most probable
A Meet with board - 1 1 2
B Hire coaches A 4 6 8
C Reserve pool A 2 4 6
D Announce program B, C 1 2 3
E Meet with coaches B 2 3 4
F Order team suits A 1 2 3
G Register swimmers D 1 2 3
H Collect fees G 1 2 3
I Plan first practice E, H, F 1 1 1

a. Draw a project network.


b. Develop an activity schedule.
c. What are the critical activities, and what is the project completion time? (Ans: A-B-
D-G-H-I; 14.17 weeks)
d. If the club manager plan to start the project on February 1, what is the probability the
swimming program will be ready by the schedule May 1 date (13 weeks)? Should the
manager begin planning the swimming program before February 1? (Ans: 0.0951;
yes)

You might also like