Preparing and Using Protective Coating Specifications
Preparing and Using Protective Coating Specifications
Protective
Coating
Specifications
SSPC Preparing and Using Protective Coating Specifications Aug. 2011
For many decades, some owners and engineers have considered protective coatings as
“incidental” work not requiring any specialized expertise. With the changes that have
occurred in protective coatings in the past 60+ years, we know that treating coatings as
incidental work can produce costly errors. Up until the designation of hazardous
materials in paint, such as lead, chromium, cadmium, arsenic, it was common for owners
to allow contractors to scrape and paint with primers containing one or more of these
materials, and expect years of good service. Those paints were frequently used for
protection of steel structures because they worked, and they were generally one-part
materials that did not require careful mixing of multiple components, Parts A and B for
instance. Those days are gone, and the replacement coatings are much more complicated
in formulation, in surface preparation requirements, in mixing, and in application and
curing. There is less room for error in using high performance industrial coatings today.
The purpose of this report is to describe some best practices for preparing and
administering a quality specification for application of high performance protective
coatings and linings to industrial structures. This report focuses on developing an
appropriate set of requirements for applying coatings and linings to obtain maximum
coating system performance, service life, and protection of substrates in the prevailing
service environment. A well-prepared and administered specification will help ensure
that the selected contractor performs the work according to the specification requirements
in the allotted time.
The primary audience for this report includes facility owners, both public and private,
coating program managers and engineers, and architecture-engineering firms responsible
for preparing coatings specifications for clients. However, all parties involved in coating
contracts can benefit from the information presented in this report.
1
SSPC Preparing and Using Protective Coating Specifications Aug. 2011
This report does not cover the formatting of the specification document. It instead,
permits specification preparers to use their own formats as long as the requirements are
presented logically and systematically so that its users can readily find them. Also, this
report does not cover contract language intended to manage risk. However, all the
recommendations included in this report should be considered by the designer
(specification writer) based upon knowledge of the project (competent design) and
risk/reward factors dictated by cost and other restrictions imposed by the specific project.
This document does not provide legal advice. It is instead intended to serve as a guide for
the creation of a coating specification. This document and any associated educational
information are only offered as a general discussion of the subject matter and do not
purport to offer legal advice. It is strongly recommended that the designer seek the
assistance of competent local legal counsel prior to final dissemination or use.
.
2
SSPC Preparing and Using Protective Coating Specifications Aug. 2011
To be effective, a well-designed coating specification must take into account the field
conditions in which the specification will function. Thus it is important to consider both
the types of contracts and the roles of contracting parties in the construction contracting
environment.
A coating specification is that part of a coating contract that details the qualitative and
quantitative requirements of the process and finished product. The contractor is required
to provide the specified product and no more without receiving additional compensation.
There are many types and variations of contracts used in the construction industry,
including the coating industry. For purposes of this report, contracts will be divided into
two groups:
• Competitive-bid
• Negotiated
Negotiated. A negotiated contract can have any of a large number of types and options,
generally ranging from direct selection (no competition) through many forms of
competitive negotiation. A negotiated contract permits more of a partnering relationship
between the owner and the contractor. This type of contract is likely to be easier to
administer, and the results are more likely to be closer to full contract conformance. But
this does not diminish the need for proactive contract administration. Actual contract
performance will be a function of the contractor’s quality management system and intent
to satisfy the customer. Such a relationship may be more beneficial to both parties than a
competitive-bid contract, which sometimes becomes adversarial in nature.
There are many types of contracts to address many different purposes and owner
processes. The competitive bidding process is generally thought by public agencies to be
3
SSPC Preparing and Using Protective Coating Specifications Aug. 2011
the most equitable way to distribute public contracting funds. That assumption, however,
is only valid when the entire process is fair to all potential bidders. This fair process
creates the “level playing field.” that nearly every owner desires to find, and most
contractors wish for when bidding on jobs., Such fairness is difficult to develop,
implement, and maintain in the real world; however, designing a good specification can
help work toward achieving a more equitable contracting environment.
A level playing field will exist in any owner’s contracting environment when its contract
requirements are equitably, equally, and totally enforced. All bidders must know and
believe they will be held responsible to meet all contract requirements. Then, contractors
who are fully qualified will be encouraged to bid, and those not fully qualified will be
discouraged from bidding. A level playing field encourages contractors to be more
efficient in all aspects of planning and executing work. It can even result in an improved
owner-contractor relationship by establishing a good working environment.
Writing a specification that cannot or will not be enforced defeats the purpose of striving
for an equitable contracting environment. Working with competitive-bid contracts can be
challenging but it is possible to overcome the drawbacks by developing a better
awareness of the issues . Identifying and addressing the root causes of competitive
bidding problems and writing your specification to close gaps and potential loopholes
will most likely enhance project success.
The agreement between the facility owner and the contractor is typically one in which the
contractor will perform the specified requirements and the owner will pay the contract
price.
Key Elements for Success. Key elements of the specification that give the owner the
best chance of hiring the lowest responsible bidder who will likely fulfill all contract
requirements are:
4
SSPC Preparing and Using Protective Coating Specifications Aug. 2011
• Requiring performance and payment bonds for the full cost of the project
provided by a rated insurance company
• Establishing comprehensive quality control (QC) requirements (i.e., require the
use of qualified QC personnel, as well as a qualified work force of blasters and
painters or other craft workers) and the means to assure compliance
• Requiring a detailed Work Plan such as that described by Brandon and Damiano
in the Journal of Protective Coatings and Linings (“Work Plan: Use It or Lose It,”
JPCL, June 2011, pp. 14-19)
* Implementing Corrective Action throughout the job, including timely response to
program weaknesses and elimination of the causes of nonconformities
Competent Design. The design must be accurate and complete so that contractors can
properly estimate the cost of full contract conformance. Even so, depending on market
variables, competitive bidding can encourage some level of betting on what estimate will
win the job rather than bidding the cost of full performance. The specification and its
administration must be very strict for competitive bid contracts, because “hungry”
contractors may bid low to obtain the contract and plan to make up differences with add-
ons, or, even worse, by “cutting corners” to be sure to make a profit. Owners should be
wary of estimates that are significantly below their estimated cost of full performance. An
extremely low bid, say 20-25% lower than the second low bidder, will likely indicate that
the contractor failed to take all requirements into account, or that the specification was
vague or incomplete. Another reason for developing a good specification is that it reduces
the chance of getting wildly low bids.
With a well-written and executed specification, the owner is much more likely to receive
the desired product within the established time and price. However, if the specification is
weak, vague, ambiguous or incomplete, the owner may encounter one or more of these
problems:
5
SSPC Preparing and Using Protective Coating Specifications Aug. 2011
Pre-Bid Conference. For large contracts, it is a good practice for owners to hold pre-bid
conferences for potential bidders. Here, the owner presents the specification and
describes the scope of work. The participants may ask for additional information about
the project and specification requirements, and owners should answer questions as
appropriate, and provide those answers to all potential bidders. Participants are frequently
given the opportunity to tour the work site (if available) with the owner to become
familiar with it. Potential bidders are allowed to take measurements and photographs and
ask questions concerning the work. Holding an informative pre-bid conference may result
in more realistic bids with a narrower bidding range. Owners may also require the
contractor who is awarded the contract to inspect the work site and all conditions
affecting the work, review all contract documents, and then submit any errors, omissions,
or other discrepancies within a certain period of time, such as 30 days after award.
Payment for Work Completed. The contractor is responsible for planning, scheduling,
and producing work that conforms to all contract requirements. The contractor is also
required to provide objective evidence of conformity (documentation) of completed work
to project requirements when tendering for work to date. The fact that invoices are
allowed to contain projected work rather than actual work to date seems to confound
many administrators in their attempts to ensure payment for work based on objective
evidence of conformity, but there are ways to handle this. Some owners may choose to
either audit invoices for evidence of conformity a month or two in arrears, or to require
contractors to provide this traceability through logs or other methods. Other owners may
choose to make a one-time extra payment at the beginning of the project to compensate
for the extra delays associated with payment for evidence of conformity. There may be
6
SSPC Preparing and Using Protective Coating Specifications Aug. 2011
other ways as well, but the intent is to keep all parties focused on paying only for
documented conformity.
Subcontractors. Even on large construction contracts, the coating portion may comprise
only a small part of the work. When a subcontractor is used for specialized work such as
coating, the prime contractor must provide documentation that the qualifications of the
coating subcontractor are equal to those of the prime contractor, or as specified. Some
prime contractors may shop around for the cheapest subcontractors available for different
parts of project work without considering their capabilities for providing quality work.
This is a bad practice, because the prime contractor is responsible for all requirements of
the project contract. This practice will likely become less of an issue where bidding is
done in a known environment with a level playing field, as subcontractor bids to prime
contractors will be both responsive to all contract requirements and competitive in price
based on efficiencies.
The prime contractor should also have a separate contract containing appropriate
submittals with the subcontractor that will ensure that all project requirements will be
met. In the event that there is a conflict between the requirements of the owner’s contract
and the subcontractor’s contract, a dispute is likely to arise. Thus, both the contractor and
subcontractor should be familiar with the terms of the contract between the owner and the
prime contractor and that between the prime contractor and subcontractor.
Requests for Information (RFI). There are often contract clauses that require
contractors to review plans and specifications and request clarification where necessary,
and advise the owner of errors, omissions, or other contract deficiencies where
appropriate, before work begins. A request for information (RFI) may be used to ask for
clarification of vagueness in requirements or apparent work conflicts or discrepancies.
Contractors should include procedures for the RFI process in their QC plans. RFIs should
never be used for requesting contract deviations.
7
SSPC Preparing and Using Protective Coating Specifications Aug. 2011
Requirements for inspection come in many variations, and inspectors may be hired by the
owner, the contractor, the engineer, or some combination of these. The owner may or
may not specify qualifications for the contractor’s inspectors (referred to as QC
inspectors hereafter), and may or may not hire Quality Assurance (QA) inspectors to
monitor the contractor’s Quality Control (QC)/QA inspection and documentation.
Regardless of the QC and QA inspection functions, the owner should specify
requirements for inspection and documentation. If the contractor is to document
conformity to all requirements, this should be clear in the specification. It is
recommended that the owner base payment obligations on objective quality evidence
(OQE) of conformity to all requirements. This must be coordinated with procedures for
payment.
Inspectors should not be responsible for final acceptance or rejection of work unless
specifically assigned this responsibility and qualified for this task. Quite often, the final
accept/reject function requires knowledge and experience beyond that required of
inspector certification programs. Making accept/reject decisions are more suited to
Protective Coating Specialists (PCS) certifications, or other qualifications.
To assume that a certified coating inspector has the capability to properly represent the
owner’s interests may be unfair to both the inspector and the owner. A final accept/reject
decision by unqualified personnel can do more harm than good in terms of incentivizing
appropriate contractor behavior, or in providing the desired work product.
8
SSPC Preparing and Using Protective Coating Specifications Aug. 2011
Because coating contracts are legal documents, it is important to consider various legal
concerns when writing the specification and drawing up the contract. A contracts attorney
should review the final contract with special attention to:
(4) Claims - Assertions for a right, such as money or property, as part of a legal
obligation.
(5) Mechanics liens - Security interests in the title to property for the benefit of
those who have supplied labor or materials that improve the property.
Requests for deviation (DFS) should be made by the contractor in the production phase
only when unforeseen conditions are discovered that could not have been identified prior
to production.
Differing Site Conditions (Site Variation). Owners should inform potential contractors
of all site conditions that may affect the project cost or production before bidding begins
9
SSPC Preparing and Using Protective Coating Specifications Aug. 2011
or provide for a full and unfettered site investigation. Thus, it can be critical to provide all
bidders the opportunity to inspect the work site, where feasible, before submitting their
bids.
After production begins, the contractor may discover work site conditions that differ
materially from those indicated in the specification and could not have been identified
during the planning process. The contractor should be required to inform the owner of
this within a reasonable time frame, so that these conditions may be promptly addressed.
Differing site conditions are often a cause of contract disputes and litigation.
CA identifies the root cause of a nonconformity, takes steps to eliminate it, and then
follows up to ensure that the nonconformity does not recur. Corrective Action is initiated
through a Corrective Action Request (CAR) which may be prepared by the inspector or
other individual involved in the project QC or QA process. It is tracked on a
Nonconforming Work Log, or similar document, and on a Corrective Action Log, to
ensure that the problem is satisfactorily resolved and that appropriate action is taken. The
correction and repair procedures taken by the contractor should be those prescribed in the
specification or as recommended by the coating manufacturer and/or an established
industry practice, and documented.
CA/PA clauses can be specified in the project specification or in the QMS standard. For
instance, SSPC QP series contractor certifications require project-specific Work Plans,
10
SSPC Preparing and Using Protective Coating Specifications Aug. 2011
Corrective Action, and other requirements that are pertinent to the contract administrator.
If an owner has specific requirements that tend to overlap QP series requirements, it is the
contractor’s responsibility to harmonize the requirements to avoid any conflicting
requirements. The ideal place to do this is in the Work Plan.
A quality management system addresses the principles and processes surrounding the
design, development, and delivery of a general product or service. Specifying a QMS
standard as a preliminary requirement of the contractor sets up a process of organized
activities to meet established goals.
The owner should have expectations from the contractor concerning the work to be
accomplished. The most important expectation is that only work conforming to the
specification will be tendered. More specific expectations of contractors obligated to a
QMS include but are not be limited to:
(2) Performing complete project planning and submitting a Work Plan or series of
process control procedures (PCPs) to the owner.
The QMS concept is based on proven relationships between planning processes and
satisfactory results and promotes continual improvement to build on the planning process.
The intent of the QMS is to ensure that the contractor’s initial planning and preparation
and its verification efforts are designed to achieve conforming work.
11
SSPC Preparing and Using Protective Coating Specifications Aug. 2011
(1) The designer must prepare a specification that describes all requirements in a
readily understandable manner that is realistic and achievable.
(2) The owner must provide complete information for potential bidders to
estimate costs, ensure fairness in the bidding and the contract administration
processes.
(3) The contractor must collect all contract requirements from the contract
documents, referenced documents, secondary references in referenced
documents, and any other pertinent documents, such as best practices. From
this information the contractor must develop a Work Plan that describes all
processes that will be used to create conforming product, and all inspection
and documentation requirements.
(4) The contractor must use the Work Plan as a continuous working document, all
work must be inspected to the Work Plan requirements.
(5) Supervisors and production workers must understand all requirements and
have the ability, equipment, and incentive to meet all requirements for
processes in each phase of the work.
(6) Inspectors must verify that the work meets all specification requirements. All
nonconformities must be documented, tracked, and either corrected or
resolved through contract change order. A Nonconformity Log can facilitate
tracking.
(7) Owner quality assurance (QA) personnel should audit the documentation
prepared by the inspectors and periodically conduct observations, as deemed
necessary, to ensure that documentation of all work is complete. If the latter is
not the case, use the Corrective Action system to address the documentation
deficiencies and any other identified issues. A Corrective Action Request
(CAR) Log can facilitate tracking.
12
SSPC Preparing and Using Protective Coating Specifications Aug. 2011
Coordination Requirements
To be fully effective, the technical specifications must be coordinated with the owner’s
“front-end” documents, as well as the general requirements for each project. The front-
end documents, such as General Conditions, Additional General Conditions, Special
Conditions, etc., establish the legal contracting environment, and the general
requirements, designated as Division I requirements by the Construction Specification
Institute (CSI), apply to all technical specifications. Division I specification Sections
include such requirements as Submittals, Payment Procedures, Site Conditions, Quality
Control, Environmental Protection Requirements, and many more.
Coating specifications, as with most technical specifications for construction work, can
be very complex documents, even without considering the thousands of seemingly
mundane issues that are encountered on every project. Many specifications do not try to
cover all of the routine issues, but most industries have developed standards for these
routine issues. The coating industry, for instance, has covered many of these issues for
coating of industrial steel structures in SSPC PA 1 Shop, Field, and Maintenance Printing
of Steel. Each coating specification for steel structures should start with SSPC PA 1 as
the foundation, and modify as needed or add to it as necessary to create a complete
specification that gives both the contract administrator and the contractor a complete
description of requirements. SSPC PA 7 should be similarly used for concrete structures.
Key Elements
Scope of Project. Specifications should have introductions that describe the general
scope of the project to prospective bidders. It should cover requirements for furnishing all
of the required materials, labor, equipment, and tools for the surface preparation,
application, and inspection work for the project. It should also provide a description of
the project location and may include a map or plan of the work area. No project
requirements should be included in the scope. Each project requirement should be located
in its appropriate area of the specification and nowhere else. This minimizes confusion to
persons using the specification. Enough information should be presented in the scope
section to permit potential bidders to determine whether they are interested in
investigating the proposed project further.
13
SSPC Preparing and Using Protective Coating Specifications Aug. 2011
Areas to be Coated and Not to be Coated. The specification must define all of the areas
that are to be coated and all of the areas that are not to be coated in order for the
contractor to understand the full scope of the project. Areas not to be coated may have to
be masked, and, if other areas are added after start of the production, the owner may be
required to provide additional funding.
Site Access and Storage Area. The owner must provide contractor personnel with
access to the work site. Work areas often have limited access because of security or
safety concerns or the presence of other conditions such as vehicular traffic, close
proximity to the public, or the presence of other trades. Also, sufficient area must be
provided for the contractor to store required equipment and materials.
Site Investigation Clause. When the contract documents fully describe the project’s
existing conditions, the importance of site investigation prior to submitting bids can be
diminished, because bids are more likely to be representative of costs of performing the
work and it is less likely that differing site condition claims will arise. It is reasonable to
require qualified bidders to identify errors, omissions, and other contract discrepancies
they find prior to submitting bids, but this is difficult to administer. A reasonable
alternative is to require the contractor to advise the contract administrator of any errors,
omissions, and other contract discrepancies, other than those that cannot be anticipated or
identified without special access, within a reasonable time after submission of bids, such
as 30 days.
Technical organizations that provide standards and other guidance relevant to coating
projects include but are not limited to:
• ASTM (American Society for Testing and Materials) for test procedures
• API (American Petroleum Institute) for fuel tanks and appurtenances
• AWWA (American Water Works Association) for water tanks and appurtenances
• FHWA (Federal Highway Administration) for bridge and highway structures
• NACE International for metal corrosion
• NSF (National Sanitation Foundation) for potable water tank interiors
• SSPC (The Society for Protective Coatings) for guidance in coating operations
14
SSPC Preparing and Using Protective Coating Specifications Aug. 2011
A submittal section of the specification requires the contractor to regulate the timely flow
of materials and documents used on the project and ensure their compliance with
specification requirements. Some of the submittals require submission in time for owner
review in time for procurement, delivery, and contractor QC of materials and equipment
before initiating the production. Other submittals document the progress and quality of
the production work to date.
Typical coating project submittals required prior to initiation of production include but
are not limited to:
15
SSPC Preparing and Using Protective Coating Specifications Aug. 2011
Typical coating project submittals required after initiation of production include but are
not limited to:
Safety and Health Plans. SSPC PA Guide 10 Guide to Safety and Health Requirements
for Industrial Painting Projects provides guidance, including sample contract language,
for specifying safety and health requirements for contractors. SSPC Guide 17 Guide to
Developing a Corporate Safety Program for Industrial Painting and Coating Contractors
is also usable by owners to evaluate contractors’ safety programs. Again, these
documents should be reviewed by the owner or designer to ensure they are appropriate
for inclusion in the contract documents.
Work Plan and Process Control Procedures (PCPs). A Work Plan is a written
document containing a list of all actions and procedures, assembled in logical sequence
that describes all steps necessary for the contractor to produce a finished product
conforming to all specification requirements. It translates the requirements of the
specification into a series of steps for field implementation. It provides to the contractor’s
staff the ability to plan and prepare to accomplish cost effective production within the
schedule and in accordance with project requirements. It also provides the owner’s staff
with the ability to review submittals and understand the contractor’s intended processes.
The Work Plan also permits but is not limited to scheduling such project procedures as:
16
SSPC Preparing and Using Protective Coating Specifications Aug. 2011
Coating work typically involves multiple processes, each of which will have to be
documented. Sometimes the owner prefers to use PCPs instead of a Work Plan to
facilitate routine coordination of work between the contractor’s forces and the owner’s
forces. PCPs are commonly used in refineries and shipyards. In such locations, work is
usually done “piecemeal” and must be coordinated with that of other trades. All of the
PCPs, when combined, should contain the same basic information as in a Work Plan.
When PCPs are used individually, a separate schedule is required to show the order in
which each process is to be used. When using a Work Plan or a series of PCPs, hold or
check points may be placed in the specification to permit inspection for conformance of
work to date before proceeding further.
Work Plans are more commonly used where the entire site is turned over to the contractor
to complete work on the contractor’s schedule. The format, i.e. Work Plan vs. a series of
PCPs, is the contractor’s choice, unless specified otherwise in the contract documents.
Good planning will result in more efficient work production, and thus a savings to the
contractor. It will also help to avoid disputes by identifying conflicts, discrepancies, etc.
at an early time in the process.
17
SSPC Preparing and Using Protective Coating Specifications Aug. 2011
The coating industry is fortunate to have multiple certification programs for coating
inspection personnel and coating inspection companies. It is recommended that these
certifications be used to the maximum extent on coating projects (e.g. NACE CIP or
SSPC equivalent for inspectors or SSPC QP 5 for coating inspection companies).
While qualifications for contract planners, administrators, and workers are often
undefined, it may be desirable to identify more specific qualifications, such as those
listed above, to help reduce the number of discrepancies between the owner and the
contractor and permit easier resolution.
Delivery and Storage of Materials and Equipment. A delivery and storage section of
the specification should contain special requirements for packing and shipping products,
equipment and their components. Conditions for acceptance of these items at the project
site should also be included, along with special storage, handling, and disposal
requirements necessary to prevent contamination or damage.
It may be desirable to have a clause permitting the owner’s representative to obtain from
the contractor at any time a sample of the coating being applied. Local air pollution
personnel usually have this authority.
Description of Project Site Conditions. It is important that the project site condition be
fully described. Information on any environmental limitations or other conditions at the
project site that might affect project work should be presented. These may include
prevailing temperature, humidity, or ventilation. This section may also describe where the
contractor can locate work equipment, trailers, lunchrooms, or shower facilities.
18
SSPC Preparing and Using Protective Coating Specifications Aug. 2011
Specified Type and Size Range of Abrasives. The specified abrasives should be tested
for particle size distribution, oil content, crystalline silica, and soluble contaminants by
the referenced test methods, e.g., SSPC-AB 1, for conformance to specification before
use. This presumes the specification contains specific requirements for the abrasive. If
there are no abrasive requirements specified then the choice of abrasive is left to the
contractor.
Kits and Equipment for Testing for Surface Cleanliness and Profile and Film
Thickness. QC kits and other equipment necessary for testing for surface cleanliness and
profile and for coating thickness must be available at the work site. Production workers
must be able to monitor the quality of their own work, and QC personnel must be able to
verify that the specification requirements are being met. Wet film gages are commonly
used by applicators to verify that the wet coating thickness at application time will meet
the final dry film thickness specification requirements once the coating dries. The
specific parameters and test requirements must be included in the specification if the
owner/designer expects those tests to be performed.
The VOC (volatile organic compound) content of coating materials is required in most
U.S. geographical locations. If commercial products are specified, their colors should be
selected from the manufacturer’s list of available colors. It is always best to procure all
products of a multiple coat system from the same supplier and make sure that they are
suitable for the intended use. Where multiple suppliers of a single system must be used,
rules for determining all requirements of the coating system must be specified to avoid
conflict among suppliers.
Upon delivery, the coating materials must be identified as those specified and as having
sufficient shelf life to complete the project. It is a good practice to check both the
condition of the containers, including the seals, and the condition of the coating by
laboratory testing of one or more samples and record the batch numbers. The volume of
coating materials required can be calculated from their spreading rates and the surface
areas to be covered. This will ensure that there is sufficient coating at the job site to
complete the work.
19
SSPC Preparing and Using Protective Coating Specifications Aug. 2011
• Air temperature
• Surface temperature
• Dew point/relative humidity
• Wind speed
• Lighting for all work areas (as prescribed in SSPC-Guide 12)
Blast Cleaning of Surfaces for Coating Application. Abrasive blast cleaning is the
most commonly specified surface preparation method for cleaning industrial steel
surfaces for coating. Waterjetting is sometimes used to prepare previously blasted and
coated steel surfaces. Any required special equipment or procedures should be specified
along with the required level of cleaning and profiling. Some recommended methods for
surface preparation of concrete and concrete masonry unit (CMU) for coating are
described in ASTM D4258, “Practice for Surface Cleaning Concrete for Coating”, and
ASTM D4261, “Practice for Surface Cleaning of Concrete Unit Masonry for Coating.”
Other requirements that may be included are field checking for cleanliness of abrasives
and air supply used in abrasive blasting and blow down and the quality of the water used
in waterjetting (usually potable water can be specified).
• Condition in container
• The ratio by volume of the components to combine *
• Instruction for mixing components
• Amounts of thinner, if any, permitted
• Ambient conditions for application
• Induction time at different temperatures *
• Pot life at different temperatures *
• Recoat window *
• Contrasting colors for multiple coat systems
• Stripe coating requirements
20
SSPC Preparing and Using Protective Coating Specifications Aug. 2011
The dry film thickness range should have minimum and maximum limits necessary for
optimum coating performance. If appearance is important the appearance of cured films
can be required to be in accordance with SSPC-PA 1 for steel surfaces and in accordance
with SSPC-PA 7 for concrete surfaces.
Accepting Project Work and Clean-Up of all Equipment, Materials, and Waste
Products. A punch list of action items needing completion is prepared prior to a final
inspection to ensure that all work is complete and ready for the final acceptance by the
owner.
At all times, the contractor must keep the premises and surrounding area free from
accumulation of waste materials and rubbish created by project work. Following
completion and acceptance of the work, the contractor must remove all debris,
equipment, and materials from the site. Materials and equipment may have to be
decontaminated if exposed to hazardous materials such as lead-based paint before being
removed from the work site. The existing facilities must be restored to their original
condition.
It is important that a warranty section of the specification clearly states any special or
extended warranty or bonding for conformance to specification.
Warranties for coating work are typically for one year after acceptance of the work.
Arrangements should be made to have completed projects re-inspected for deficiencies
prior to the termination of the warranty period, so that a written legal claim can be made
21
SSPC Preparing and Using Protective Coating Specifications Aug. 2011
within this time frame. Some owners withhold 5 to 10% of the total payment until the end
of the warranty period to ensure that deficiencies found within this period are addressed.
A prudent owner or designer should consider defining the conditions that would
constitute a breach of warranty at the end of the warranty period. If desired, a scheduled
warranty inspection and list of attending parties can be included in the specification.
22
SSPC Preparing and Using Protective Coating Specifications Aug. 2011
Contract specifications (using CSI three-part Section format – see Appendix C))
GENERAL
Scope of Project
Areas to be coated and not to be coated
Site Access and Storage Area
Site Investigation Clause
References (sometimes called “Applicable Documents”)
• SSPC PA 1 Shop, Field, and Maintenance Painting of Steel
• For coating concrete surfaces:
• SSPC-PA 7, Applying Thin Film Coatings to Concrete
• SSPC-TU 10, Procedures for Applying Thick Film Coatings and
Surfacings Over Concrete Floors
• Surface preparation
• Others
Precedence of Documents
Definitions
Submittals (pre-work)(Many of these continue during work)
• Contract errors, omissions, and other discrepancies, including conflicting
requirements, ambiguous requirements
• Procedures for Corrective Action
• Project-specific Work Plan or Process Control Procedures (PCPs)
• Project-specific Health, safety, and environmental compliance plans
• Site access/security requirements
• Project-specific Confined space entry plans (permit required and non-
permit required)
• Procurement of necessary materials
• Procurement of necessary job site and support equipment
• Assigning the management team to the project
23
SSPC Preparing and Using Protective Coating Specifications Aug. 2011
24
SSPC Preparing and Using Protective Coating Specifications Aug. 2011
PRODUCTS
Coating materials and thinners (other than as specified by mfg.)
• Contrasting colors for multi-coat systems
Abrasives
Test Kits
• Amine blush testing
• Salt testing
EXECUTION
Deliver, Store, Mix, Apply, and Cure Coatings According to SSPC-PA 1 (for steel
surfaces) or SSPC PA 7 or TU 10 for concrete surfaces)
Equipment for Surface Preparation and Coating Application
Kits and Equipment for Testing for Surface Cleanliness and Profile and Film
Thickness
Specified Types of Coating Materials Delivered and Their Verification
Field mock-up (as part of verifying procedures during start-up – particularly for
coating of concrete)
Acceptable Ambient Conditions
• Periods of control
• During surface preparation
• During coating application and initial curing (specify initial cure time)
• During other operation
• Parameters of control
• Air temperature
• Surface temperature
• Dew point/relative humidity
• Wind speed
• Surface contaminants
• Lighting for all work areas (as prescribed in SSPC-Guide 12)
Blast Cleaning of Surfaces for Coating Application
• Desired results
• Allowable methods
• Ambient conditions for surface preparation
25
SSPC Preparing and Using Protective Coating Specifications Aug. 2011
26
SSPC Preparing and Using Protective Coating Specifications Aug. 2011
27
SSPC Preparing and Using Protective Coating Specifications Aug. 2011
28
SSPC Preparing and Using Protective Coating Specifications Aug. 2011
29
SSPC Preparing and Using Protective Coating Specifications Aug. 2011
30
SSPC Preparing and Using Protective Coating Specifications Aug. 2011
Division Structure
31
SSPC Preparing and Using Protective Coating Specifications Aug. 2011
32
SSPC Preparing and Using Protective Coating Specifications Aug. 2011
33 10 00 Water Utilities
33 50 00 Fuel Distribution Utilities
33 51 00 Natural-Gas Distribution
33 52 00 Liquid Fuel Distribution
33 56 00 Fuel-Storage Tanks
45 00 00 Industry-Specific Manufacturing Equipment
46 00 00 Water and Wastewater Equipment
48 00 00 Electrical Power Generation
*The miscellaneous examples of sections are intended to show the layout of the
CSI/CSC Masterformat. The entire system is available through the CSI web site:
http://www.csinet.org/ . CSC – Construction Specifications Canada:
http://www.csc-dcc.ca/
Section Format
Each Section concerns a particular portion of the work, and has a three-part structure that
interfaces with the Division 01 general sections. The format is as follows:
Section xx xx xx xx
Part 1 – General
Part 2 – Products
Part 3 – Execution
Sections in Division 01 contain requirements only under Part 1 – General while Sections
in Divisions 02 – 48 generally have requirements in all three Parts. The Part 1
requirements in Divisions 02 – 48 supplement the general requirements of Division 01
Sections. For instance, it is common for there to be requirements in many Divisions 02 –
48 Sections specific submittals, and these submittals would be subject to the general
submittal requirements in Section 01 33 00 Submittal Procedures.
33
SSPC Preparing and Using Protective Coating Specifications Aug. 2011
The CCS should be accomplished by personnel from a business that routinely performs
coating evaluations, and the individual investigator should be Certified by SSPC or
NACE as a Protective Coatings Specialist (PCS). The CCS should be sufficiently detailed
to provide all technical information about the coatings, and structures to be coated,in
order to properly design the project. At a minimum, the CCS should provide a detailed
report of:
1. Existing coating conditions, including condition of coating film, and the existence
of potentially hazardous substances that may impact coating management (i.e.
lead, cadmium, chromium, etc.);
4. Any other information of interest to the coating system management that should
be identifiable by an individual trained and experienced in the field of coating
analysis, coating failure analysis, and coating design.
The scope of the CCS should be tailored to the specific project, and it should be
recognized that while multiple coating failures or deficiencies may look similar to the
untrained eye, the risks of generalizing to save evaluation costs are potentially very high.
The cost of large-scale failure of the overcoating, and complete replacement of the
coating system, is far more than the cost of a CCS for all but the smallest projects.
The risks of overcoating can usually be avoided by designing the project to remove all
existing coatings to bare metal, then providing appropriate surface preparation and
coating application. However, the extra costs of the coating removal, especially if
containing hazardous material, may be exorbitant compared to the costs of maintenance
overcoating where the existing coating system is in fair-to-good condition.
34
SSPC Preparing and Using Protective Coating Specifications Aug. 2011
The fact that lead was highly used as a primer is indicative of its value to the corrosion
control industry. Premature removal of sound lead primer is not considered to be a good
coating management practice, but it must be coordinated with the owner’s overall
facilities management plan.
Owners should consider an annual CCS to survey all structures to be authorized for
design in the coming year or two. When accomplished for multiple projects, the per-
structure cost will decrease. By accomplishing this survey prior to design, the basis for
budgeting and design is fully identified.
The CCS can also be a very useful tool when used to screen structures for maintenance
painting requirements. A CCS can be scoped to provide a general inspection of many
structures to screen for near-term overcoating or recoating requirements, and subsequent
investigation can be made to provide appropriate details for project planning and design.
It should be pointed out that the aesthetic features of a coating do not define the coating
condition; they only describe how the coating looks. Many coating systems have been
replaced when only the topcoat is in need of "refurbishment." Likewise, many structures
such as water tanks and fuel tanks have had complete coating replacement when only the
roof coating needed replacement. A CCS can identify the weak components as well as the
satisfactory components, and propose solutions to make maximum use of existing
resources.
35
SSPC Preparing and Using Protective Coating Specifications Aug. 2011
SSPC – http://www.sspc.org
CSI – http://www.csinet.org/
Articles on Contracting
J. H. Brandon and M. P. Damiano, “Contract Expectations,” JPCL, August 2007, pp. 50-
60
http://www.paintsquare.com/library/article_download.cfm?articleid=2898&pub=1
J. H. Brandon and M. P. Damiano, “Contracting Issues: Are Owners Getting What They
Ask For,” JPCL, March 2008, pp. 27-37
http://www.paintsquare.com/library/article_download.cfm?articleid=3073&pub=1
J. H. Brandon and M. P. Damiano, “Work Plan: Use It or Lose It,” JPCL, June 2011, pp.
14-19
http://www.paintsquare.com/archive/?fuseaction=view&articleid=4483
36
SSPC Preparing and Using Protective Coating Specifications Aug. 2011
Brandon, J.H.; Hames, B; Gorrell, P.G. Use of Work (Quality) Plans on Coatings
Projects. SSPC:The Society for Protective Coatings 2003, New Orleans.
37