Method Statement of GE Module Installation
Method Statement of GE Module Installation
09929
EPC Contractor's name
PROJECT
RE-POWERING PROJECT OF GHORASAL 3RD UNIT
Revision history
Rev. Revision Created by Checked by Approved by description
A Gu Heng Yan Guohua Zhu Zuoyu
Participant
施工方案审核页
Name Method Statement of GE Module Installation
文件名称 GE 模块安装方案
The First Northeast Electric Power
Established
Engineering Co,. Ltd of China Energy Date
by 2018 年 02 月 10 日
Engineering Group 编制日期
编制单位
中国能源建设集团东北电力第一工程有限公司
Establishme
Chief Engineer/person
nt
in charge
Personnel
编制单位总工或专责
编制人员
Department Comments
参与审核部门 审核意见
Technical
Management
Dpt.
技术管理部门
Examination and Approval personnel:
审核人员: 年 月 日
QC Dpt.
质量管理部门
项 Examination and Approval personnel:
目 审核人员: 年 月 日
审
核
EHS Dpt.
安全管理部门
Examination and Approval personnel:
审核人员: 年 月 日
Chief
Engineer
项目总工程师
Signature:
签字: 年 月 日
NEPC Ghorasal 3# Unit Re-powering Project Site Management Department Electric Automation Branch 电自专业公司
fTable of Content
目 录
1 BASIS 编制依据..................................................................................................................................................... 1
1 Basis 编制依据
● Tools and machinery are all prepared for use and meet demand of safety operation after check.
施工用的工器具及机械准备齐全并经过检查维修满足安全施工需要。
● Method statement has been established and approved. Technical disclosure has
been conducted with confirmed signature.
施工方案编制完毕并经过审批合格并对所有施工人员进行技术交底,双方签字确认。
After placement of module, check cargo list and inspect for complete and damage.
And then measure auxiliary dimension for matching with reserved location on the
top, and then use 25t vehicle crane to lift auxiliary in position and align for
correctness and fasten the bolts to fix components. Prior to installation, check
the amount of tools; after finishing, inspect for complete and clean waste.(set
up platform and install auxiliary around module as mentioned above as per
manufacture drawing, if any doubt, contact the representative and follow the
instructions.)
模块吊装到位后,----清点到货清单,检查附件是否齐全,检查附件有无损伤----检查无
误后,测量附件尺寸,是否与顶部预留位置相符合----确认无误后利用 25t 汽车吊将顶部
附件吊装到位,进行调整找正,确认尺寸无误后,拧紧螺栓固定部件。安装前清点工器具
数目,安装完毕后校对工器具数目是否有遗漏,并清理现场垃圾。(搭建走台,9 安装模块
周围附件同上,安装时根据厂家图的示意安装,如有疑惑,请与厂代沟通,在厂代指导下
进行安装)
4.2 Installation procedure 安装方法
●Follow the drawing for installation. Remove cover plate on the top and then
measure dimension to ensure conformance with auxiliary; paste sealant and then lift
auxiliary in place and align and fasten bolts tightly and check seal. (set up
platform and install auxiliary around module as mentioned above as per manufacture
drawing, if any doubt, contact the representative and follow the instructions.)
根据厂家图的示意安装,将模块顶部盖板拆除,测量尺寸是否与附件相符,确认无误后并
粘贴密封胶,而后将附件吊装就位,进行找正,确认尺寸无误,拧紧螺栓并检查密封是否
良好。(搭建走台,9 安装模块周围附件同上,安装时根据厂家图的示意安装,如有疑惑,
请与厂代沟通,在厂代指导下进行安装)
● After completion of installation for all auxiliary, repaint the abrasion ones.
所有附件安装完毕后,需对有磨损的部位进行补漆处理。
●Check dismantled parts for complete and intact as per installation drawing and
packing list.
按厂家安装图以及装箱单校对拆卸运输件是否齐全,有无损伤。
5.1Device parts and individual tools should be complete with no rust and damage.
设备的零件及专用工器具应齐全,无锈蚀和损伤变形。
5.2 Assembly of auxiliary should follow sequence. For auxiliary without number,
follow the representative’s direction.
附件应按照编号顺序组装,严禁混装,无编号的附件请在厂代指导下安装。
5.3 Installation of GE module and auxiliary should follow the design and instruction,
if any doubt, contact the representative before installation.
GE 模块及附件安装符合设计及厂家说明书的要求,安装时如有疑惑请与厂代沟通,确认无
误后方可安装。
● When conducting crane, supporting blocking should be steady and hanging tools
be fastened tightly;slip rope should be used on hanging tools; no people is allowed
standing below the hanging materials; no overload is allowed for crane and hoisting
machine.
吊装作业时吊车应支垫平稳,吊物捆绑牢固,在吊件上拴以牢固的溜绳,吊物下方严禁站
人及通过,吊车及卷扬机严禁超载工作。
Content 交底内容:
1、 Construction workers entered into site must do physical check and hold valid documentation and receive
safety induction with exam.
进入施工现场的施工人员,全部经过本工程安全文明施工规定与要求的专项培训,考试合格,体检合格。
2、 Workers on site must wear PPE that meet safety regulations and be uniform. Work of height must wear
safety harness hanging on upper liable place. Double harness is needed if worker on height needs to mobile
from place to place with one of them fastened on safety rope.
进入现场的人员带好安全帽,系好帽带。进入现场的人员穿符合安全要求的工作服,着装整齐统一高处
作业人员必须正确扎好安全带,并挂在上方牢固可靠处。
3、 Goggles are needed for work on grinding machine,fire welding,cutting(toothless saw,grinding
wheel),exposed to chemical articles(paint,diluter). Leakage protector must be installed on electrical
devices. No electric wire is allowed directly hanging on switch blade or plugging into socket.
使用砂轮机、火焊、切割、高速切削、接触化学危险品时佩戴防护镜。施工人员必须严格遵守有关工器
具使用方法及要求。施工用配电箱必须装设漏电保护器,做到一机一闸一保。严禁将电线直接购挂在闸
刀上或者直接插入插座内使用。
4、 Secondary wire for electric welding uses soft rubber cable with neatly arrangement and timely take back
after completion.
电焊二次线使用软橡套电缆,布设整齐、规划合理,完工后及时回收。
5、 Keep tools and machinery clean and complete safety regulation; safety apparatus meets standard with intact
certificate and inspect and maintain termly; no bad machines can be allowed operating.
施工机械完好清洁,安全规程齐全,安全装置符合标准、齐全有效,定期检查与保养,严禁带病运行。
6、 Rubbish should be disposed separably and cleared regularly to designated places. Storage spots should be
set up for solid waste with different and recognizable dustbins. Waste materials like discarded iron, tools
and electrode should be disposed timely.
施工现场设置分类垃圾箱,现场施工垃圾分类排放,定期清理,确保文明施工;施工现场禁止吸烟,施
工区域必须消灭焊条头、木头、铁线头、废料头、砂轮片等杂物。
Given by:安全交底人
Superior Safety Officers 上级安全人员
Received by
交底对象
Total
人
共计
Content 交底内容:
1. Installation of GE module and auxiliary should follow the design and instruction, if any doubt, contact the
representative before installation.
GE 模块附件安装,安装时根据厂家图的示意安装,如有疑惑,请与厂代沟通,在厂代指导下进行安装
2. The main part is top auxiliary, side auxiliary and building of platform.
附件主要分为顶部附件,侧部附件以及走台搭建
3. After placement of equipment, check dimension before installation and alignment.
在设备就位后,请认真核对尺寸,确认无误后,再进行安装找正
4. If any problem, contact the representative and follow his instruction.
如果附件有问题请及时与厂代沟通,在厂家指导下进行安装
Given by:技术交底人
Received by
交底对象
Total
人
共计