Tutorial Microsoft Project: Laboratorium Pengembangan Sistem Dan Manajemen Industri Teknik Industri ITS 2017/2018
Tutorial Microsoft Project: Laboratorium Pengembangan Sistem Dan Manajemen Industri Teknik Industri ITS 2017/2018
Microsoft
Project
Project Views
Gantt Chart
On the View tab, in the Zoom
group, click the down arrow next
to the Timescale box and click
Days.
Project adjusts the timescale to show
individual days. Nonworking days,
such as weekends, are formatted in
light gray.
Resource Sheet
On the View tab, in the Resource Views group, click Resource Sheet. The Resource Sheet view replaces the
Gantt Chart view.
3 Notice to customers of
L.1.2 0.5 2 Customer Services
temporary disconnection
4 L.1.3 Land relinquishment 1 2,3 Field Workers
5 L.1.4 Find operator 0.5 2 Handymen
6 Pre-project phase
L.1.5 Manager
complete!
7 L.2 Pile driving
9 Field
L.2.2 Divide pile 3.5 8
Workers,Handymen
10 L.2.3 Coordinate pile location 0.5 5 Field Workers
11 L.2.4 Drive pile 0.5 10 Field Workers
12 L.2.5 Dig hole 3 11 Field Workers
13 L.2.6 Construct frame and pile 4 9,10 Handymen[200%]
14 L.3 Installation of conductor
16 Field
L.3.2 Pull new conductor tools 2 13,15
Workers[200%]
17 Field
L.3.3 Install conductor equipment 2 16
Workers[200%]
18 L.3.4 Hang conductor tool 2 16 Field Workers
19 L3.5 Cut trees 2 5 Handymen[200%]
Code Work Name Duration Predecessors Assigned Resources
No
23 Field
L.4.1 Cleaning 1 21
Workers[200%]
Change the old conductor
24 L.4.2 1 21 Field Workers
tool
25 L.4.3 Change the old piles 2 24 Field Workers
26 L.4.4 Return materials to store 2 25 Supervisor
th
The project is started at June 11 , 2018. The data will be provided in excel with this tutorial. With note:
1. Work 3 and 4 start at the same time
2. Work 11 and 12 finish at the same time
3. Work 16 finish 100%, but work 17 can only start half week later.
4. Work 16 is ongoing for ½ week, work 18 can be started immediately.
5. Work 24 and 25 finish at the same time
6. Work 25 finish 60%, work 26 can be started.
Project information:
1. Project execution refer to the start date of the project which is June 11, 2018.
2. Work hour is Monday to Saturday at 7.00 – 16.00, except Friday at 7.00 – 17.00.
3. Break time on Monday to Saturday is at 12.00-13.00, except Friday at 11.00 – 13.00.
4. June 19, 2018 is set by the government as holiday.
5. Project duration is in weeks.
Beside the list of works above. PT PLN also has routine works as follow.
1. Morning and Evening Briefing, every time the work is start and finish.
2. Progress Report, that must be collected every Saturday on fourth week of the month.
3. Work Meeting, is organized every July 1.
4. Field Worker Wages, (heavy worker, handyman and supervisor) is payed every Saturday.
th
5. Employee Wages (CS and manager), is payed every 25 of the month.
The following is the availability of the resources on the project.
Table II.2 List of Resources Available
2. Click Options to work hours and assign as in figure II.3 with the following.
- Default start time : change to 07.00 AM to specify the start of the work.
- Default end time : change 5.00 PM to specify the end of the work.
- Hours per day : the time of the work per day. With a setting of 9 hours per day, entering a
two day task duration (2d) is the same as entering 18 hours (16h)
- Hours per week : the time of the work per week. With a setting of 55 hours per week, entering
a three-week task duration (3w) is the same as entering 165 hours (165h)
- Days per month : the amount of working days per month.
You can also change the scheduling in the project. As specified in the case, the duration enter is in weeks,
thus we have to change it in the drop-down menu of Duration is entered in: Weeks
Then, click OK
3. To change the working time, click Work Weeks and click Details.
Figure II.5 Details in Working Time (Except Friday) Figure II.6 Working Time on Friday
Click Set day(s) to these specific working times to manually assign working time. You can click the day in
Select day(s) more than one day by also clicking CTRL. Then write the time as in figure II.4. Do this for the
working time on Friday as well, as shown in figure II.5. Then, click OK.
4. To add information about the holiday that occur at June 19, in the Name field on the Exceptions
tab in the lower portion of the dialog box, type Holiday, and then click in the Start field, type
6/19/18, and then click the Finish field or press the Right Arrow Key.
TIP You can also select the date you
want in the calendar above the
Exceptions tab or from the drop-down
calendar in the Start field.
The date is now scheduled as nonworking time for the project. In the dialog box, the date appears
underlined and color formatting is applied to indicate an exception day.
5. Click OK to close the Change Working Time dialog box. To verify the change to the project calendar,
note in the chart portion of the Gantt Chart view that Thursday, June 19, is now formatted as gray
to indicate nonwork-ing time (just like the weekends).
In this section, you made just one specific day a nonworking day for the entire plan. Other common
examples of working time adjustments include:
▪ Recurring holidays or other times off that follow a known pattern, such as weekly, monthly, or
annually. To set up recurring nonworking times, click the Details button on the Exceptions tab in the
Change Working Time dialog box.
▪ Vary working times per week, for example, to address seasonal changes in working times. To set up
custom work weeks, on the Work Weeks tab of the Change Working Time dialog box, enter the date
range you want, click the Details button, and then set the working time adjustments you want.
1. Click the cell below the Duration column heading for task 1.1, Project review. The Duration
field for task 1.1 or task no. 2 is selected.
2. Type 1, and then press Enter. The duration will automatically show like the following, as the
durations enter has been changed to weeks.
TIP You can also click the up and down arrows to enter or change the value in the Duration field
The value 1 wk appears in the Duration field. Project draws a Gantt bar for the task, starting at the
project start date you previously set. Complete all the durations as specified in the table II.1.
Note: you can also specify duration by entering start and finish dates, and project will calculate the duration.
For instance:
3. In the Start field of Project review, type 6/11/18, and press the Tab key.
TIP You can also select the date you want in the Start field. Click the down arrow button, and in
the calendar that appears, navigate to the month you want. Then click the date you want.
4. In the Finish field for the same task, type or select 6/19/18, and then press Enter.
Project calculates the duration as 1.04 week. Note that this is seven working days: Monday through
Saturday, Tuesday and Wednesday. As Monday is a holiday. However, for this case just input the duration
directly first.
TIP You can mark a task of any duration as a milestone. Double-click the task name to display
the Task Information dialog box, and then click Advanced and select the Mark Task as
Milestone option.
Sub Tasks
TIP If you want to demote a summary task back to a subtask, you must change the outline structure of the
subtasks below the summary task. Select all subtasks, and then click the Outdent command.
Next, you’ll create another summary task in a different way.
3. Firstly, delete the task Pre-Project Phase. Then, select the names of tasks 1 through 3.
4. On the Task tab, in the Insert group, click Summary.
Project inserts a row for a new task, indents the task directly below it, and renumbers the
subsequent tasks. Project names the new task <New Summary Task>.
▪ With <New Summary Task> selected, type Pre-Project Phase and press Enter. Now the plan is
organized into two phases of work. Do either method on the rest of the phases.
9. Click OK to create the recurring task. Project inserts the recurring task. Initially, the recurring
task is expanded. A recurring task icon appears in the Indicators column. Each occurrence of the
recurring task is sequentially numbered.
The following is the setting for progress report. Do the same to the given case.
Figure II.17 Setting progress report
In Project, the first task is called the predecessor because it precedes tasks that depend on it. The second
task is called the successor because it succeeds, or follows, tasks on which it is dependent. Any task can be
a predecessor for one or more successor tasks. Likewise, any task can be a successor to one or more
predecessor tasks. The following is different type of task relationships.
Tasks 2 and 3 are linked with a finish-to-start relationship. This also automatically update the start and finish
date. If you want to link all the subtasks with finish-to-start relationships, you can do it in one action by
select the task name from 2 to 6, and click Link the Selected Tasks again.
Have you noticed the light blue highlighting of some of the Duration, Start, and Finish fields as you linked
tasks? Project highlights the values that are affected after each scheduling change you make in a plan.
TIP To unlink tasks, select the tasks you want to unlink and then click Unlink Tasks in the Schedule group
on the Task tab.
Another technique on linking tasks.
3. Select the name of task 3 Notice to customers of temporary disconnection.
4. On the Task tab, in the Properties group, click Information. The Task Information dialog box appears.
5. Click the Predecessors tab.
6. Click the empty cell below the Task Name column heading, and then click the down arrow that
appears
7. In the Task Name list, click Project review.
8. Click OK to close the Task Information dialog box.
There are several notes on the link of the tasks, which are:
7. Work 3 and 4 start at the same time: SS
8. Work 11 and 12 finish at the same time: FF
9. Work 16 finish 100%, but work 17 can only start half week later: +0.5 wks lag
10. Work 16 is ongoing for ½ week, work 18 can be started immediately: -1.5 wks lags
11. Work 24 and 25 finish at the same time: FF
12. Work 25 finish 60%, work 26 can be started: - 0.8 wks lag or -40%
These tasks can be linked by directly write the linking type in the predecessor.
1. In the predecessor column of task 4, type 2,3SS. This shows that task 4 and 3 have Start to start
relationship. The link can be looked in the Gantt chart
2. For task 11 and 12 as well as task 24 and 25, both has same linking type, which is Finish to finish
relationship. To show the link in Gantt chart, type FF in predecessor column of task 11 and task 24,
directly after the predecessor number.
Figure II.22 Finish to Finish Relationship
After you have established the correct task relationships, you can fine-tune your schedule by entering
overlap (called lead time) or delay (called lag time) between the finish or start dates of predecessor and
successor tasks. When two tasks have a finish-to-start relationship
▪ Lead time causes the successor task to begin before its predecessor task concludes.
▪ Lag time causes the successor task to begin sometime after its predecessor task concludes.
In this exercise, you enter lead and lag time and change task relationships between predecessor
and successor tasks. You’ll adjust the lag value on the task relationship to account for the time
between pull new conductor tools and install.
1. On the Task tab, in the Properties group, click Information
2. Click the Predecessors tab
3. In the Lag field for predecessor task 17, type 0.5 wks,, and then click OK to close the Task
Transformation dialog box
Task 17 is now scheduled to start half a week after the end of task 16.
Next, you will adjust the lag time between two other tasks.
4. Click the name of task 18, Hang Conductor Tool. It is started before task 16 is complete.
5. On the Task tab, in the Properties group, click Information, and then click the Predecessors tab.
TIP You can use the selected task’s shortcut menu for both commands: Scroll To Task and Information .
Right-click the task name and, in the shortcut menu, select the command you want .
6. In the Lag field for predecessor task 16, type –1.5 wks, and then click OK. Entering lag time as a
negative value results in lead time.
On between task 25 and 26, task 26 can only begin when task 25 have finished 60%.
7. Click the name of task 26.
8. On the Task tab, in the Properties group, click Information, and then click the Predecessors
9. In the Lag field for predecessor task 25, type –40%, and then click OK. Entering lag time as a
negative value results in lead time. Task 26 is now scheduled to start at the 40-percent-
remaining point of the duration of task 25.
Project changes the Task Mode icons and formatting of the tasks’ Gantt bars to indicate that they are now
automatically scheduled. Next, you’ll use a different method to change the scheduling mode for a task.
3. Click the Task Mode field of task 6, and then click the arrow that appears.
4. In the list that appears, click Auto Scheduled.
For this case, click all the tasks, and change it to autoscheduled.
4. In the next empty rows in the Resource Name column, enter the remaining resource as in table
II.2
Resources such as Manager and Supervisor are individual people. Meanwhile, Customer Services, Field
Workers and Handymen represents multiple people.
For a resource that represents not a specific person but a category of interchangeable people with a common
skill set, you can enter a larger maximum unit’s value to indicate the number of available people. Entering a
maximum unit’s value such as 800% for such a resource means you can expect that eight-individual people who
all belong to that resource category will be available to work full-time every workday.
For a resource that has a working schedule that is less than full-time, you can enter a smaller maximum
unit’s value. Entering a maximum unit’s value such as 75% for such a resource means you can expect that
resource’s capacity to be three quarters of a full-time resource.
In this exercise, you adjust the Max. Units values for one resource that represents multiple people.
1. Click the Max. Units field for the Customer Services resource.
2. Type or select 500%, and then press Enter.
3. Repeat for the other resources, and it will be shown like in this figure.
TIP When you click a numeric value in a field like Max. Units, up and down arrows appear. You can click
these to display the number you want, or simply type the number in the field.
Entering Resources Pay Rate
When a work resource has a standard pay rate entered and is assigned to a task, Project calculates the cost
of the assignment. Project does so by multiplying the assignment’s work value by the resource’s pay rate—
both using a common increment of time (such as hours). You can then see the cost per resource, cost per
assignment, and cost per task (as well as costs rolled up to summary tasks and the entire plan).
In this exercise, you enter standard and overtime pay rates for work resources.
1. In the Resource Sheet, click the Std. Rate field for Manager.
2. Refer to table II.2, Type 10000000/mo and press Enter.
Manager’s standard monthly rate of Rp10,000,000/mon appears in the Std. Rate column. Note that the
default standard rate is hourly, so you need to specify cost per month.
TIP If the currency symbol in your project are still in $, you can open File, click Options then click Display to
change it.
Figure II.29 Change the Currency Symbol
3. In the Std. Rate field for Field Workers, type 250000/w and press Enter. Field Workers’ weekly
pay rate appears in the Std. Rate column.
Next you will enter an overtime pay rate for one of the resources.
4. In the field for the overtime rate (labeled Ovt. Rate) for Handymen, type 20000, and then press
Enter. The resource sheet will be looked like this
5. In the Resource Name column in the Assign Resources dialog box, click Manager and
then click
Assign.
TIP To remove or unassigned a resource from a selected task, in the Assign Resources dialog box, click the
resource name and then click Remove.
6. In the Task Name column, click the name of task 3, Notice to customers of temporary
disconnection.
7. In the Resource Name column in the Assign Resources dialog box, click Customer Service, and
then
click Assign. And complete as specified in the case.
Next, you’ll take a closer look at the details of task 3. You’ll use a handy view called the Task Form.
8. On the View tab, in the Split View group, select the Details check box. Project splits the window
into two panes. In the upper pane is the Gantt Chart view, and below it is the Task Form view.
9. Click anywhere in the Task Form view and then, on the Format tab, in the Details group, click
Work. The Work details appear.
10. Using the Assign Resources dialog box, assign the following resources to tasks, complete the
case asked.
Next you will assign two resources to a single task.
11. In the Task Name column, click the name of task 8, Procurement of pile and materials.
12. In the Assign Resources dialog box, select Supervisor and Customer Services, and then click
Assign.
TIP To select nonadjacent resource names, select the first name, hold down the Ctrl key, and then
select additional names. This technique also works with tasks and other items in lists.
16. In the list of resource names, select the check boxes for Field workers and Handymen, and then
press the Enter key.
17. Field worker and Handyman are assigned to task 9.
18. Click in the Resource Names column for task 10, Coordinate pile location, and then click the
arrow that appears. In the list of resource names that appears, select Field Workers and then
press the Enter key. Field Worker is assigned to task 10
19. Drag the vertical divider bar to the right edge of the Finish column.
The work of a task remains constant as you assign or unassign resources. As more resources are assigned
to a task, the duration decreases, but the total work remains the same and is distributed among the assigned
resources. You have flexibility in how you apply effort-driven scheduling.
Next you will use a feature called the Actions list to control how Project schedules the work on a task when
adding or removing resources. Note the small green triangle in the upper-left corner of the name of task 5.
This is a graphical indicator that an action is now available. Until you perform another action, you can use
the Actions list to choose how you want Project to handle the additional resource assignment.
You can use these options to choose the scheduling result that you want. You can adjust the task’s duration,
the resources’ work, or the assignment units.
TIP You will see other Actions indicators while using Project. They generally appear when you might
otherwise ask yourself, “Hmm, why did Project just do that?” (such as when a task’s duration changes after
you assign an additional resource). The Actions list gives you the chance to change how Project responds
to your actions.
In this exercise, you explore various project status-reporting features, including views and reports.
1. To begin, you will show the Timeline view. On the View tab, in the Split View group, select the
Timeline check box.
You can see the plan’s start and finish dates at either end of the timeline. Note the current finish date:
11/22/18.
The timeline does not tell you the plan’s specific duration; however, that’s visible in the project summary
task in the Gantt Chart view. You can display the project summary task in the Gantt Chart view, by doing
the following:
a. Click anywhere in the Gantt Chart view.
b. On Format tab, in the Show/Hide group, select the Project Summary Task check box. Project
displays the project summary task at the top of the Gantt Chart view with an ID of 0.
Here you’ll see the same duration and start and finish values displayed in Project Statistics as
well as a Gantt bar that’s drawn from the start and finish dates of the overall plan.
2. If necessary, scroll the Gantt Chart view up so that task 0 Project is visible. This shorter duration
you see now is the result of assignment changes you made earlier.
Both the Timeline view and the project summary task in the Gantt Chart view are good options for
quickly seeing the project’s overall duration and finish date; you can incorporate these views into your
status reporting needs. Next, you’ll look at project costs.
3. On the View tab, in the Data group, click Tables, and then click Cost. The Cost table appears,
replacing the Entry table. The Cost table includes various cost values for each subtask. These
subtask cost values roll up to their summary tasks, and ultimately all cost values roll up to the
project summary task.
Project includes several built-in reports, and you can customize those or create your own for the unique
information needs of your project’s stakeholders .
In this exercise, you change the formatting of a built-in report .
3. On the Report tab, in the View Reports group, click Dashboards and then click Work Overview .
The Work Overview report appears
Figure II.44 Work Overview
This report includes several charts that describe work over time and per resource . Depending on your
screen resolution, you might need to vertically scroll the report to see all of the charts .
4. For Cost Overview, on the Report tab, in the View Reports group, click Dashboards and then click
Cost Overview . The Work Overview report appears
3. Click OK
Project records the completion percentage for the tasks that were scheduled to start before June
27. It displays that progress by drawing progress bars in the Gantt bars for those tasks.
In this exercise, you record actual work values for some tasks, as well as actual start dates and durations for
other tasks.
1. On the View tab, in the Data group, click Tables and then click Work. The Work table appears.
TIP You can display whichever table is most relevant to the details you are focused on while tracking
progress in a plan. Useful tables include the Work table, which focuses on work values, and the Cost table,
which focuses on cost values. The Tracking table is a good all-around table when recording or viewing
progress.
2. If needed, drag the vertical divider bar to the right to expose the last column in the Work table,
%W. Comp (% Work Complete).
3. In the Actual field type the actual duration of the work that has been done, and then press Enter.
4. On the Task tab, in the Schedule group, click the down arrow to the right of the Mark on
Track button, and then click Update Tasks.
References:
Chatfield, C., and Johnson, T. 2013. Step by Step Microsoft Project 2013. Microsoft Press: Washington