Agile Project Plan Template

The document is a Gantt chart showing the project plan for the ARMS product from March 11 to December 31. It outlines 3 sprints with assigned tasks, resources, and estimated start and end dates. The overall progress of the project is currently 0% and some tasks are showing as overdue or not yet started according to the status column.

Uploaded by

rreddym
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
67 views3 pages

Agile Project Plan Template

The document is a Gantt chart showing the project plan for the ARMS product from March 11 to December 31. It outlines 3 sprints with assigned tasks, resources, and estimated start and end dates. The overall progress of the project is currently 0% and some tasks are showing as overdue or not yet started according to the status column.

Uploaded by

rreddym
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 3

Gantt Chart_x000D_

Agile Project Plan

Product Name ARMS


Product Manager Warren Nugara
Project Deliverable BAU
Scope Statement

Start Date 11-Mar


End Date 31-Dec
Overall Progress 0%

Task Name Responsible Start End Days


Sprint 1 Alex B. 3/11 3/15 4
Feature 1 Frank C. 3/16 9/7 175
Feature 2 Jacob S. 9/7 9/12 5
Feature 3 Jacob S. 9/9 9/13 4

Sprint 2 Jacob S. 9/16 9/24 8


Feature 4 Alex B. 9/16 9/17 1
Feature 5 Frank C. 9/17 9/21 4
Release 1
Feature 6 Shari W. 9/22 9/24 2
Sprint 3 Shari W. 9/25 10/5 10
Feature 7 Alex B. 9/25 9/29 4
Feature 8 Kennedy K. 9/24 10/2 8
Feature 9 Jacob S. 10/2 10/5 3
Gantt Chart_x000D_

9-3 12-12 3-22 6-30 10-8


Status
Sprint 1
In progress
Feature 1
In progress
Feature 2
Complete
Feature 3
Overdue
Sprint 2
In progress
Feature 4
In progress
Feature 5
Not started
Release 1

Feature 6
Not started
Sprint 3
Not started
Feature 7
Not started
Not started Feature 8

Not started Feature 9


Gantt Chart_x000D_

6-30 10-8 1-16 4-26 8-4 11-12