Water Monitor Specification
Water Monitor Specification
Capacity : Variable flow of 1000, 750 and 500 GPM with single Nozzle.
Type : Non-aspirating.
1.0 SCOPE
This specification covers the requirements regarding design, materials,
fabrication, performance, testing and supply of remote operated foam cum
water monitor to be used for fire fighting. The scope of supply shall include
UL listed or FM approved non-aspirating type foam-cum-water monitor to
be used for fire fighting along with the remote operation mechanism
(remote operated mechanism may or may not be UL listed or FM
approved), Motor Operated Isolation valve & flameproof control panel etc.
to facilitate remote operation of the monitor.
2.1.2 The Foam Inductor should be capable of feeding foam concentrate from a
horizontal distance of minimum 60 meters from the Monitor Nozzle.
Page 1 of 26
SPECIFICATION / DATA SHEET
2.1.3 The inlet and outlet of foam Inductor shall be provided with standard male and
female instantaneous couplings as per UL/FM Std.
2.1.4 The length of the foam pick up tube shall be 3-4 Meters. It should be
possible to induct 3% foam for all the flows, however, variation of +20% of
the induction rate is permissible. Manual valve shall be provided at foam
inductor to set foam induction as per 1000 USGPM, 750 USGPM or 500
USGPM water flows.
2.2 Monitor
2.2.1 The monitor shall be able to discharge 1000 USGPM, 750 USGPM and
500 USGPM (depending upon adjustment at the Nozzle) at a pressure of
2
7.0Kg/CM (g) at the mating/mounting flange. The foam compound shall
be AFFF/AR-AFFF.
2.2.2 The nozzle shall produce foam with foam expansion ratio 1:3 to 1:4.
2.2.3 The pattern of the Water/foam jet nozzle shall be adjustable from straight
to 140 deg wide spray.
2.2.4 The monitor shall have traversing mechanism to give 340 deg. in either
direction in horizontal plane and +90 deg. & -15 deg in vertical plane
through swivel joints operated by worm and worm wheel operated geared
unit. There shall be separate hand wheels for horizontal and vertical
movement of the monitor. The arrangement shall be such that monitor
movements can be done by a single person. All the gear mechanisms
shall be sealed by proper enclosure to avoid accumulation of dust on
lubricated parts. Both the traversing mechanisms shall be self locking type.
2.2.5 The Swivel Joints shall have SS ball bearing with efficient sealing.
2.2.6 The monitor shall be variable flow adjustment type and it should be
possible to set all three flow rates easily and quickly at site by the operator.
2.2.7 There shall not be any flanged joint on the monitor body, except one at
base flange. Other Joint between monitor body & nozzle shall be threaded
type. Monitor body shall be single cast without welded joints and tubing.
2.2.8 A pressure gauge to indicate the inlet pressure shall be fitted on the
monitor body near inlet of nozzle. Pressure drop across the monitor shall
be less than 10 PSI.
2.2.9 A drain connection with valve shall be provided near the base flange.
2.2.10 Monitor will be painted with Paint – RAL 3000, two part polyurethane
coating.
Page 2 of 26
SPECIFICATION / DATA SHEET
2.2.11 The monitor shall be so designed as to resist the nozzle reaction forces
during operation and shall be capable of being handled by one person.
4.0 APPROVAL
The Monitor, Foam Nozzle and Foam Induction device shall be UL Listed
or FM approved with following features:
i) Nozzle : Non-Aspirating type
Page 3 of 26
SPECIFICATION / DATA SHEET
ii) Monitor Flow : 1000 USGPM, 750 USGPM & 500 USGPM
foam solution with single nozzle.
iii) Operating Pressure : 100 PSI
iv) Induction : Aqua Powered variable flow Foam Inductor (single)
suitable for all the three flow rates (1000 USGPM,
750 USGPM & 500 USGPM) of monitor.
Instruments certified for use in the specific hazardous area classification shall
have certifications/ approvals from accredited international agencies like FM,
ENELEC, PTB, BASSEFA, ATEX,etc.
All enclosures for electrical equipment shall be suitable for use in Hazardous
are as per Haz. Area Classification and vendor shall submit valid test certificate
issued by CIMFR & PESO. Flameproof enclosures and instruments which are
manufactures outside India and certified by accredited international authorities
shall also have approval of PESO, India. In case bidder has got only
international approval on hand at the time of bid due date and already applied
for PESO approval, then bidder shall be required to get PESO approval before
despatch of materials. Bidder has to submit undertaking along with bid for that
effect and mention timeline of obtaining PESO approval. Decision of HPCL shall
be final and binding on the bidder in this regard.
ALL DOUBLE COMPRESSION FLP CABLE GLANDS AND PLUGS FOR THE
HVLR AND CONTROL PANEL SHALL BE PROVIDED BY THE VENDOR.
UNUSED ENTRIES SHALL BE FITTED WITH FLP PLUGS.
5.1 Control Panel shall have minimum following indication and control
functions for each monitor.
a. Joystick / Push Buttons with indication for up, down, right and left
movements on the nozzle.
b. Push button/joystick with indication for adjustment of spray / jet.
c. Push Buttons with indication for Open/Close of Motor Operated
Isolation valve.
d. Indication Lamps for Power available.
Page 4 of 26
SPECIFICATION / DATA SHEET
5.2 Control Panel shall be complete with motor starters consisting of required rating
AC-3 motor duty switch, fuse, contactor and bimetal overload relay to suit motor
rating, motor start / stop push button, selector switch, voltmeter etc. and
suitable structural frame for mounting of the panel.
5.3 Controls panel shall be PLC based & mounted in flameproof enclosure. The
control panel shall be minimum Ex-n / Ex-e / Ex-d type in flameproof enclosure
suitable for Zone -2, Gas group – IIA / IIB with GI sheet canopy. Weather
protection for motor enclosure shall be minimum IP55. FM/UL approved
enclosure for Zone 2 environments will also be acceptable. The
monitor movement & controls shall be programmable by solid state
devices.
Control of the rotation, elevation and nozzle pattern (fog – jet) of the
RCM shall be by solid state devices housed in general purpose enclosures
and FM/UL approved for Zone 2 environments.
A solid state Motor Drive unit will contain the following features:
Power outputs to the RCM motors are handled by solid state relays or
equal.
5.3 Input power requirement is 240 VAC, 1 Phase, 50/60 Hz, 15 Amp
5.5 FM/UL Approved for NEC Class 1, Div 2, Groups B, C & D Locations
Page 5 of 26
SPECIFICATION / DATA SHEET
5.6 Motor shall be minimum Ex-n / Ex-e / Ex-d type suitable for Zone – 2, Gas group
IIA / IIB, temperature class: T3. Weather protection for motor enclosure shall be
minimum IP55. All the motors installed at monitor shall comply with
requirements enclosed as Annexure-A.
5.8 4 inch size Motor operated Isolation valve (MOV) shall be supplied along-
with each monitor . Specifications of Isolation valve to be used for MOV
are enclosed as Annexure-B.
5.9 The electrical motor operated valve actuator for the isolation valve shall be
minimum Ex-n / Ex-e / Ex-d type suitable for Zone – 2, Gas group IIA / IIB
& temperature class: T3. Specifications of the Motor operated valve
actuator are enclosed as Annexure – C.
2
5.10 Minimum conductor size for power cable for Control panel shall be 4 mm
copper and all cables between control panel & monitor junction box shall
be 1100 V grade PVC insulated, PVC sheathed, armoured fire retardant
type. The power cables from monitor junction box to monitor motors and
limit/proximity switches shall be flexible fire retardant type.
5.11 Power and Signal cable of 200 meters length for each motor shall
be provided along with the supplies for connection between the monitor
motors and control panel. Flameproof Junction Box, Signal & power cable
of 200 meters length for motor operated isolation valve and common cable
tray for above cables shall be supplied along with each monitor. Power
supply cable from emergency feeder to control panel and shall be under
purchaser‟s scope.
6.0 With pressure of 7 Kg/CM2 (g) at base flange, and Nozzle at 300 to 35 deg. from
horizontal the Monitor shall be capable of giving following performance:
1000 70 64
750 60 55
500 50 45
Page 6 of 26
SPECIFICATION / DATA SHEET
10.0 EXCLUSION
10.1 Fire water mains up-to inlet base of monitors is excluded from vendor‟s
scope.
10.2 Construction of Elevated platform / Structure.
10.3 Power supply up to the monitor control panel.
10.4 Erection of monitor, MOV & Cables.
Page 7 of 26
SPECIFICATION / DATA SHEET
Prior to dispatch from vendor‟s shop the following acceptance tests shall
be carried out by the vendor to the complete satisfaction of owner‟s
representative/HPCL authorized third party inspection agency(TPIA)
without any extra cost to owner. All consumable (e.g. water, foam
compound etc.) shall be arranged by vendor at his own cost. Vendor shall
arrange all facilities to carry out inspection & testing as follows:
Positive Material Identification (PMI) test for 10% of the
monitors.
Visual and dimensional check.- 100%witness by TPIA
2
• Hydraulic test of each monitor body at minimum 25 Kg/CM or
hydraulic test pressure specified by UL Listing/ FM approval
whichever is higher. The pressure shall be held for minimum
five minutes without any leakage or distortion of any part.
100% performance by vendor, 20% witness by TPIA
VALVE: Every valve, its components and auxiliaries must be subjected to all the
mandatory tests and checks called for in the respective codes, datasheets etc. by the
Page 8 of 26
SPECIFICATION / DATA SHEET
d) Strip check is required for 1% of total ordered qty. of valves (min.1No.) Samples for
strip check shall be selected at random and shall generally be in the highest size in the
lot.
Following routine and acceptance tests shall be carried out at the manufacturers’
works under his supervision and at his own cost for all the actuators.
d) Variation of frequency
f) Life test
Tests listed at Cl. nos. (b), (c), (d), (e), (f) and (g) above arethe acceptance tests.
Page 9 of 26
SPECIFICATION / DATA SHEET
14.0 Commissioning Assistance: The owner shall give commissioning call through e-
mail/ Fax to the vendor, the vendor shall depute their representative within 10
days of the commissioning call failing which owner may proceed ahead with
commissioning through other party at the risk and cost of the vendor. The broad
scope of erection and commissioning includes but not limited to the following:
f. Owner shall arrange for erection team with standard tools and tackles required
for erection, cable termination etc. Special commissioning and testing tools, if
required shall be arranged by vendor.
Page 11 of 26
SPECIFICATION / DATA SHEET
Annexure-A
The Motor and their components shall comply with the latest editions of
relevant standard issued by BIS (Bureau of Indian Standards).
The motor shall also conform to the provisions of Indian Electricity Rules
and other regulation currently in force in the country.
In case, Indian standards are not applicable or not covering any part , the
standards issued by IEC /BS /VED /IEEE /NEMA or equivalent agency shall
be applicable.
3. Operating Conditions:
Page 12 of 26
SPECIFICATION / DATA SHEET
4. Starting
4.1 Unless otherwise specified, motor shall be designed for on-line starting with
suitable protection.
4.2 Motor shall be designed for reacceleration under full load after a momentary
loss of Voltage with residual voltage being 100 % and is in phase opposition
to the applied Voltage.
4.3 Unless otherwise specified, all motors shall be suitable for starting under
specified load conditions with 75% of the rated voltage at the motor
terminals.
5. Performance
- Motor shall be rated for intermittent duty cycle (S3), unless otherwise
specified.
6. Construction
6.1 Insulation
Unless otherwise specified the motor shall be with Class „B‟ insulation as a
minimum. In case of motor with class „F‟ insulation the permissible
temperature rise above the specified ambient temperature shall be limited to
those specified in the applicable Indian Standard for class „B‟ insulation.
In case of motors driving equipment with pulsating loads, special care shall
be taken for the joints of rotor bars and end rings to avoid premature failure
due to induced fatigue stress.
6.2 Terminal Box and Cable entries
The terminal box shall be suitable enough to facilitate easy connection of the
cables. The terminal box shall be with necessary clearances, creepage
distances between live parts and between live parts to earth considering air
insulation and without any compound filling.
The terminal box shall be provided with cable lugs and entries for suitable
cable glands corresponding to the size of the specified cable. Nickel plated
brass (or aluminium if specifically required) , double compression type cable
Page 13 of 26
SPECIFICATION / DATA SHEET
glands / flame proof cable gland shall be supplied along with the motors for
the specific cable size.
Page 14 of 26
SPECIFICATION / DATA SHEET
Annexure –B
DESIGN PARTICULARS
CONSTRUCTION
13 Disc Cast
Page 15 of 26
SPECIFICATION / DATA SHEET
MATERIAL
25 Pin/Nut/Washers SS 316
TESTING
27 Body Hydro-test 1.5 times the flange rating (30 bar #150)
2.1 General
Page 16 of 26
SPECIFICATION / DATA SHEET
enclosures.
c) One copy of the valve specification sheets signed as “Accepted” with all
deviations marked clearly.
Page 17 of 26
SPECIFICATION / DATA SHEET
h) Spiral wound bonnet gaskets are to be provided with inner / outer ring
except when encapsulated gaskets type body-bonnet joints are employed.
a) Every valve, its components and auxiliaries must be subjected to all the
mandatory tests and checks called for in the respective codes, data sheets
etc. by the manufacturer.
b) Vendor shall arrange Inspection by approved third party inspection (TPI)
agency. The inspection plan shall be approved by the purchaser and shall
include :
b) Each valve shall have a corrosion resistant tag giving size, valve tag /
code no. securely attached to the valve body.
c) Paint of ink for marking shall not contain any harmful metal or metal salts
Page 18 of 26
SPECIFICATION / DATA SHEET
d) Valves shall be painted with one coat of inorganic zinc silicate (minimum
DFT 65 to 75 microns).
2.6 Packing
a) Valve shall be dry, clean and free from moisture, dirt loose foreign
materials of any kind.
Page 19 of 26
SPECIFICATION / DATA SHEET
Annexure -C
SPECIFICATION FOR ELECTRICAL MOTOR OPERATED VALVE
ACTUATOR
1.0 SCOPE
2.1 The equipment shall comply with the requirements of latest revision of the
following standards issued by BIS (Bureau of Indian Standards) unless
specified otherwise:
2.3 The equipment shall also conform to the provisions of Indian Electricity
Rules and other statutory regulations currently in force in the country.
2.4 In case Indian standards are not available for any equipment, standards
issued by IEC/ BS/ VDE/ IEEE/ NEMA or equivalent agency shall be
applicable.
2.5 In case of any contradiction between various referred standards / data
sheets and statutory regulations, the following order of decreasing priority
shall govern:
a) Statutory regulations
Page 20 of 26
SPECIFICATION / DATA SHEET
b) Tender specification
c) Codes and standards
3.1 The offered equipment shall be brand new with state of the art technology
and a proven field track record. No prototype equipment shall be offered.
3.2 Vendor shall ensure availability of spare parts and maintenance support
services for the offered equipment for at least 15 years from the date of
supply.
Each MOV actuator shall include the motor, actuator unit, gears, position
indicators, limit switches, hand wheel, electrical starter and controls,
terminal box etc. as a self-contained unit. The actuator shall be sized to
provide adequate torque and/ or thrust to ensure the complete intended
travel of the valve under the worst operating and electrical power supply
conditions.
MOV Actuator shall be minimum Ex-n/Ex-e /Ex-d type suitable for Zone–2,
Gas group IIA /IIB, temperature class: T3 & shall meet the requirements of
IS 2148, IEC 79 or equivalent international standards. Weather protection
for motor enclosure shall be minimum IP55. The manufacturer shall
possess valid test certificates issue by a recognized independent test
house (CIMFR/ BASEEFA/ LCIE/ UL/ FM or equivalent) for the offered
actuators. All indigenous equipment shall conform to Indian standards and
shall have been tested and certified by Indian testing agencies. All
equipment (indigenous and imported) shall also have valid statutory
approvals as applicable for the specified hazardous locations from
Petroleum and Explosives Safety Organization (PESO)/ CCE or any other
applicable statutory authority. All indigenous flameproof equipment shall
have valid BIS license and corresponding marking as required by statutory
authorities.
4.1 Motor
4.1.1 The motor shall be 3-phase squirrel cage induction type unless specified
otherwise in the data sheet. It shall have totally enclosed, non-ventilated
construction.
Page 21 of 26
SPECIFICATION / DATA SHEET
4.1.2 The motor shall be designed for valve actuator service with high starting
torque and shall be suitable for Direct on line starting. It shall be rated for
S2-15 minute duty and shall conform to IS 325 or equivalent international
standards.
4.1.3 The motor shall be provided with thermister(s) embedded in the hot spots
of motor winding for protecting the motor.
4.1.4 The motor shall be suitable for starting under required torque with 75% of
rated voltage at motor terminals.
4.1.5 The motor shall have class „F‟ insulation with temperature rise limited to
class „B‟ limits. Motor winding shall be treated to resist corrosive agents
and moisture.
4.1.6 Motor rotor shall preferably be of die-cast aluminum and, if brazed, shall
be free from phosphorous.
4.2 Integral Starter and Control Transformer
c) Terminal block for external cable connection fully prewired for internal
devices of valve actuator.
The following local control devices shall be provided integral with the MOV
actuator:
a) Push buttons for “Opening/ Closing/ Stop” or alternatively “Open/ Close”
selector switch.
Page 22 of 26
SPECIFICATION / DATA SHEET
Torque limit switches shall be provided to protect the motor from over-
loading by cutting-off the power supply to motor during opening and
closing operations. The limit switches shall be preset. However, it shall be
possible to set the value of maximum torque during closing from 50% to
100% of rated torque of actuators. Travel limit switch shall be provided to
cut-off the power supply to the motor at the end of preset limit of valve
travel. The switches shall be provided with requisite number of potential-
free contacts for valve actuator operation and for indication on remote
panels. Instead of mechanical torque limit switches, magnetic pulse
counter / encoders to measure and control the stroke of actuator may be
provided, wherever this feature exists in manufacturer‟s design.
4.5 Control Facilities
A hand wheel with auto lockable lever shall be provided for emergency
operation of the MOV. The energisation of the motor shall automatically re-
engage power operation.
Page 23 of 26
SPECIFICATION / DATA SHEET
4.8 Nameplate
4.9 The enclosure of complete MOV actuator including motor, integral starter,
control transformer unit and all control devices shall have minimum IP-55
degree of ingress protection.
4.10 Wiring and Terminals
All devices provided in the actuator shall be wired up to the terminal block.
The contacts for remote operation and indication shall also be wired up to
the terminal block. Minimum 10% spare terminals shall be provided for
future interlocks. Internal wiring for power and control circuits shall be
appropriately sized for MOV actuator rating. Each wire shall be identified at
both ends using PVC ferrules. The terminal compartment shall be
separated from the inner electrical components of the actuator by means
of a watertight seal so that the actuator electrical components are
protected from the ingress of moisture and foreign materials when the
terminal cover is removed during installation and maintenance.
Page 24 of 26
SPECIFICATION / DATA SHEET
4.11 Vendor shall be solely responsible for the compatibility of the MOV
actuator with the valve and for the selection and sizing of various electrical
devices and components in the actuator.
4.12 The actuator shall be provided with minimum three adequately sized cable
entries viz., one for power cable and two for control cables. However, the
actual number of control cable entries in actuator with 2-wire control
system shall be provided based on job requirements as specified in data
sheets/ specification for control systems for MOVs. Suitable double
compression cable glands shall be provided with each actuator for all
cable entries and sealing plugs for all control cable entries. The cable
glands and plugs shall be made of Nickel-plated brass.
5.0 Inspection, testing and acceptance
5.2 Following routine and acceptance tests shall be carried out at the
manufacturers‟ works under his supervision and at his own cost for all the
actuators.
d) Variation of frequency
f) Life test
Tests listed at Cl. nos. 5.2(b), 5.2(c), 5.2(d), 5.2(e), 5.2(f) and 5.2(g) above
are the acceptance tests.
5.4 Type test certificates, original drawings referred in certificates and statutory
approval certificates and BIS license, where applicable, shall be shown to
the inspection agency on demand. The certificates and BIS license must
be valid at the time of dispatch.
Page 25 of 26
SPECIFICATION / DATA SHEET
All the equipment shall be divided into multiple sections for protection and
ease of handling during transportation. The equipment shall be properly
packed for the selected mode of transportation, i.e. by ship, rail or trailer.
The equipment shall be wrapped in polythene sheets before being placed in
crates/ cases to prevent
damage to finish. The crates/ cases shall have skid bottoms for handling. Special
notations such as “Fragile‟. “This side up”, “Center of gravity”, “Weight‟, “Owner‟s
particulars‟, „PO no.‟ etc. shall be clearly and indelibly marked on the packages
together with other details as per purchases as per purchase order.
The equipment may be stored outdoors for long periods before installation. The
packing shall be completely suitable for outdoor storage in areas with heavy rains
and high ambient temperature unless otherwise agreed. In order to prevent
movement of equipment/ components within the crates, proper packing supports
shall be provided. A set of instruction manuals for erection, testing and
commissioning, a set of operation and maintenance manuals and a set of final
drawings shall be enclosed in a waterproof cover along with the shipment.
Page 26 of 26