0% found this document useful (0 votes)
90 views

Scada-Ems Interface v6

The document describes the data exchange between a SCADA system and an EMS. It lists various parameters related to inverters, batteries, PV systems, and other equipment that the SCADA system will provide to the EMS every minute. It also lists setpoint values related to scheduling and forecasts that the EMS will provide to the SCADA system.

Uploaded by

Nguyen Ke Nhut
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
90 views

Scada-Ems Interface v6

The document describes the data exchange between a SCADA system and an EMS. It lists various parameters related to inverters, batteries, PV systems, and other equipment that the SCADA system will provide to the EMS every minute. It also lists setpoint values related to scheduling and forecasts that the EMS will provide to the SCADA system.

Uploaded by

Nguyen Ke Nhut
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 3

Version Date: 1/20/2014

SCADA - EMS Initial values SCADA will upadate these values every minute for EMS

Description from to Value type original source EMS Energy Management System

Inverter 1 ON/OFF SCADA EMS ON/OFF inverter


Inverter 1 - active power - actual SCADA EMS KW value inverter
Inverter 1 - reactive power - actual SCADA EMS KVAR value inverter
Inverter 1 - max power - limit SCADA EMS KW value inverter
Battery 1- State of charge SCADA EMS SOC % Battery to check
Inverter 2 ON/OFF SCADA EMS ON/OFF inverter
Inverter 2 - active power - actual SCADA EMS KW value inverter
Inverter 2 - reactive power - actual SCADA EMS KVAR value inverter
Inverter 2 - active power - limit SCADA EMS KW value inverter
Battery 2- State of charge SCADA EMS SOC % Battery
12.5 KV Circuit breaker - ON/OFF SCADA EMS ON/OFF Circuit breaker
PV inverter 1 - ON/OFF SCADA EMS ON/OFF PV SCADA
PV inverter 1 - KW SCADA EMS ON/OFF PV SCADA
PV inverter 2 - ON/OFF SCADA EMS ON/OFF PV SCADA
PV inverter 2 - KW SCADA EMS ON/OFF PV SCADA
PV inverter 3 - ON/OFF SCADA EMS ON/OFF PV SCADA
PV inverter 3 - KW SCADA EMS ON/OFF PV SCADA
PV inverter 4 - ON/OFF SCADA EMS ON/OFF PV SCADA
PV inverter 4 - KW SCADA EMS ON/OFF PV SCADA
PV inverter 5 - ON/OFF SCADA EMS ON/OFF PV SCADA
PV inverter 5 - KW SCADA EMS ON/OFF PV SCADA
PV inverter 6 - ON/OFF SCADA EMS ON/OFF PV SCADA
PV inverter 6 - KW SCADA EMS ON/OFF PV SCADA
Total demand - KW SCADA EMS KW value PV SCADA
Desired Power factor at PCC SCADA EMS PF value PV SCADA optional
Total electric load SCADA EMS KVAR value
Building 1- active power SCADA EMS KW value building KW meter future
Building 1- main CB ON/OFF SCADA EMS ON/OFF Circuit breaker future
Building 2- active power SCADA EMS KW value building KW meter future
Building 2- main CB ON/OFF SCADA EMS ON/OFF Circuit breaker future
Building 3- active power SCADA EMS KW value building KW meter future
Building 3- main CB ON/OFF SCADA EMS ON/OFF Circuit breaker future
Building 4- active power SCADA EMS KW value building KW meter
Building 4 - main CB ON/OFF SCADA EMS ON/OFF Circuit breaker
EMS - SCADA (Instructions) EMS will update these values and SCADA will read every minute
Description from to Value type original source
Day Ahead Scheduling (DHS) Setpoints
Inverter 1 for battery 1- active power - set point EMS SCADA KW value EMS
Inverter 1 for battery 1- reactive power - set point EMS SCADA KVAR value EMS
Inverter 2 for battery 2 - active power - set point EMS SCADA KW value EMS
Inverter 2 for battery 2 - reactive power - set point EMS SCADA KVAR value EMS
PV inverter 1 - reactive power set point EMS SCADA KW value EMS
PV inverter 1 - active power set point EMS SCADA KVAR value EMS
PV inverter 2 - reactive power set point EMS SCADA KW value EMS
PV inverter 2 - active power set point EMS SCADA KVAR value EMS
PV inverter 3 - reactive power set point EMS SCADA KW value EMS
PV inverter 3 - active power set point EMS SCADA KVAR value EMS
PV inverter 4 - reactive power set point EMS SCADA KW value EMS
PV inverter 4 - active power set point EMS SCADA KVAR value EMS
PV inverter 5 - reactive power set point EMS SCADA KW value EMS
PV inverter 5 - active power set point EMS SCADA KVAR value EMS
PV inverter 6 - reactive power set point EMS SCADA KW value EMS
PV inverter 6 - active power set point EMS SCADA KVAR value EMS

Rolling Forecasts (RF) Setpoints


Inverter 1 for battery 1- active power - set point EMS SCADA KW value EMS
Inverter 1 for battery 1- reactive power - set point EMS SCADA KVAR value EMS
Inverter 2 for battery 2 - active power - set point EMS SCADA KW value EMS
Inverter 2 for battery 2 - reactive power - set point EMS SCADA KVAR value EMS
PV inverter 1 - reactive power set point EMS SCADA KW value EMS
PV inverter 1 - active power set point EMS SCADA KVAR value EMS
PV inverter 2 - reactive power set point EMS SCADA KW value EMS
PV inverter 2 - active power set point EMS SCADA KVAR value EMS
PV inverter 3 - reactive power set point EMS SCADA KW value EMS
PV inverter 3 - active power set point EMS SCADA KVAR value EMS
PV inverter 4 - reactive power set point EMS SCADA KW value EMS
PV inverter 4 - active power set point EMS SCADA KVAR value EMS
PV inverter 5 - reactive power set point EMS SCADA KW value EMS
PV inverter 5 - active power set point EMS SCADA KVAR value EMS
PV inverter 6 - reactive power set point EMS SCADA KW value EMS
PV inverter 6 - active power set point EMS SCADA KVAR value EMS

PV on/off status
PV inverter 1 - ON/OFF EMS SCADA ON/OFF EMS ON needed- safety?
PV inverter 2 - ON/OFF EMS SCADA ON/OFF EMS ON needed- safety?
PV inverter 3 - ON/OFF EMS SCADA ON/OFF EMS ON needed- safety?
PV inverter 4 - ON/OFF EMS SCADA ON/OFF EMS
PV inverter 5 - ON/OFF EMS SCADA ON/OFF EMS
PV inverter 6 - ON/OFF EMS SCADA ON/OFF EMS
Building 1- main CB ON/OFF EMS SCADA ON/OFF EMS ON needed- safety?
Building 2- main CB ON/OFF EMS SCADA ON/OFF EMS ON needed- safety?
Building 3- main CB ON/OFF EMS SCADA ON/OFF EMS ON needed- safety?
Building 4 - main CB ON/OFF EMS SCADA ON/OFF EMS ON needed- safety?

Weather forecasts will be downloaded from the internet directly


Comment:
We will also need historic electricity data and weather data for at least a year to be able to build the load forecaster for DER-CAM

We assume that we always set a constant power factor