Daily Work Report Name: Balaji Radhakrishnan DATE: 14.04.2017 S.No Today Remarks Tomorrow Work Progress

Balaji Radhakrishnan's daily work report from April 14, 2017 shows that he was working on checking the CT cable line from Generator #4 to the PRP panel, which was ongoing. He also completed function testing of Unit #4's Turbine AOP panel from local and DCS. His work for the next day was not documented.

Uploaded by

BALACHITRA
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
28 views2 pages

Daily Work Report Name: Balaji Radhakrishnan DATE: 14.04.2017 S.No Today Remarks Tomorrow Work Progress

Balaji Radhakrishnan's daily work report from April 14, 2017 shows that he was working on checking the CT cable line from Generator #4 to the PRP panel, which was ongoing. He also completed function testing of Unit #4's Turbine AOP panel from local and DCS. His work for the next day was not documented.

Uploaded by

BALACHITRA
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 2

DAILY WORK REPORT

NAME: BALAJI RADHAKRISHNAN

DATE: 14.04.2017
S.NO TODAY
REMARKS TOMORROW
WORK PROGRESS

1 Generator# 4 to PRP panel CT cable line On Going


check under progress
Unit#4 Turbine AOP panel function test
3 Done
done from Local and DCS