API 510 Guide
API 510 Guide
This course is written by itcSkills, Schindler & Associates and Codewest. This document
represents a substantial investment of time and expense. It is provided to attendees of the
course as the course text. It is protected under the copyright laws of the United States of
America and Canada and may not be copied without written permission from Schindler &
Associates and Codewest. Do not copy or distribute this document. COPYRIGHT 2004,
itcSkills, SCHINDLER & ASSOCIATES AND CODEWEST. ALL RIGHTS RESERVED.
itcSkills
API-510 PRESTUDY GUIDE
COPYRIGHT 2004 – itcSkills/SCHINDLER & ASSOCIATES & CODEWEST - ALL RIGHTS RESERVED - DO NOT COPY OR DISTRIBUTE
TABLE OF CONTENTS
Page
Welcome to the pre-study guide for the 2004 API 510 Training class. We are very pleased that you have
entrusted your training to us for this important examination, and we take this responsibility very seriously.
Our mission together is quite simple, and one which we will remain focused on until the day of your
examination. Simply put, this mission is:
This is our only goal, and together, with diligence, patience, and hard work, I know that we will succeed in
making this mission a reality.
In this regard, this Preparatory Course is provided to help get you started and better prepared for the journey
ahead. it consists of the following items:
?? Course Outline
?? Schedule and location information
?? API 510 Body of Knowledge
?? ASME/API Quiz
?? ASME questions and 10 practice math questions that can be studied to prepare for the
up-coming test
?? Answer sheets for the Quizzes/Math Problems
?? Actual past examination questions
Remember! This is your examination and your training course. You will only get out of it what you are
willing to put into it. Therefore, if you do not complete this material, you will only be lowering your chances
of successfully completing our mission.
You must complete this Preparatory to increase your probability of passing the test! Please set
aside time every day until class starts to study the material in this book.
Please come to class as prepared as possible. it is very important to attend every class, complete all
homework assignments, and pay very strict attention to the classroom presentation. Again, your
participation is the key ingredient to passing the test.
Once again, we appreciate the opportunity to provide this training and we are willing to “go the extra mile” to
ensure your success in the examination.
Review the documents upon which the examination is based and become familiar with their layout. Be
honest and identify your strong a weak areas so you can develop a study plan. Use the pre-study Guide as
a tool to prepare for the course and then come prepared with questions.
1
itcSkills
API-510 PRESTUDY GUIDE
COPYRIGHT 2004 – itcSkills/SCHINDLER & ASSOCIATES & CODEWEST - ALL RIGHTS RESERVED - DO NOT COPY OR DISTRIBUTE
The API 510 inspector certification examinations consist of objective multiple-choice questions covering
knowledge essential to the professional practice of inspecting in-service pressure vessels and process
piping. Each exam is constructed according to detailed test specifications. Each question has four
alternative answers, only one of which is correct.
The examinations contain 150 questions and are divided into two parts. Part 1 is open-book, and consists
of 35-45 questions, which can be answered using API and ASME reference material. Candidates will have 4
hours to complete Part 1. Part 2 is closed-book, and consists of 105-115 questions which must be
answered without access to any reference material. Candidates will have 4 hours to complete Part 2. A
total of 8 hours is allowed to complete each exam.
ADMISSION PROCEDURE
If you application and fee is received before the deadline, and you meet the education and experience
requirements set by API, you will be allowed to sit for the exam. You should receive notification of the test
site from the jurisdiction prior to the exam date. Please be aware of any special instructions that may be
included in the jurisdiction notification.
Please report to the test site no later than 7:30 AM on the morning of the exam. Seating of candidates,
distribution of test materials, and testing instructions will begin at 8:00 AM. Remember to allow adequate
travel time to find the testing site on the morning of the exam.
On the morning of the exam, candidates should bring an appropriate form of picture identification bearing
their signature. Examples of acceptable forms of ID are a driver’s license, a passport, or an employee
identification card. Social security cards are not acceptable.
If you move or change your address, it is your responsibility to notify API and the jurisdiction of your new
mailing address at least 4 weeks before the exam date so that your score report can reach you in a timely
manner.
EXAMINATION PROCEDURES
?? The testing time for each part of the exam is 4 hours. Additional time has been allowed for instructions.
There is a one-hour lunch break scheduled after Part 1 of the exam, but if you complete Part 1 before
time is called, you may leave the testing room. However, you may not re-enter the room until Part 2 of
the exam is about to begin.
?? Candidates should bring some sharpened #2 pencils with erasers, a non-programmable calculator, and
a set of API and ASME reference materials. Highlighting, underlining, page tabs, or written notes in the
margins of the code books are acceptable. Note: API and ASME publications are copyrighted
material. Photocopies of these reference documents are not permitted in the examination
room.
?? No loose notes, papers, or other books of any sort may be brought into the examination room.
2
itcSkills
API-510 PRESTUDY GUIDE
COPYRIGHT 2004 – itcSkills/SCHINDLER & ASSOCIATES & CODEWEST - ALL RIGHTS RESERVED - DO NOT COPY OR DISTRIBUTE
?? No test materials, documents, notes or memoranda of any sort are to be taken from the examination
room.
?? No questions concerning the content of the examination may be asked during the testing period.
Candidates should listen carefully to instructions given by the proctor.
?? Candidates have the opportunity to comment on any question believed to be misleading or inaccurate at
the end of the examination. A form for this purpose will be provided to candidates upon request. Be
specific when commenting on a question as each comment will be individually reviewed by the
Examination Committee. Individual responses to question comments will not be provided.
?? Proctors are authorized to maintain secure and proper test administration procedures, including
relocation of candidates. Candidates may not communicate with each other during the examination.
?? Answer the questions in order, but don’t waste time on questions containing unfamiliar or difficult
material. You can come back to them later, time permitting.
?? Make educated guesses at correct answers rather than leaving the answer spaces blank. The score on
the test will be based on only the number of correct responses, with no penalty for wrong answers.
?? Record your answers carefully on the separate answer sheet. The numbering of the questions in the
test booklet should match the numbering of the responses on the answer sheet.
?? Should you change your mind on any answer, erase previously marked responses thoroughly. Multiple
responses to a question will be scored as incorrect. Avoid making any stray marks on the answer
sheet.
A criterion referenced passing score has been established by a panel of content experts using appropriate
standard setting procedures. The passing score for each administration of the API 510 and 570 inspector
certification examinations are based on a statistical equating process which adjusts for fluctuation in
difficulty levels across different examinations. Equating ensures that candidates are evaluated according to
the same competency standard from year to year.
After each examination administration, individual test questions subject to comments from candidates are
evaluated for their clarity and accuracy by the API Exam Construction Task Group prior to the grading
process. Questions determined to be ambiguous may be scored with multiple correct answers at no
penalty to the candidates.
Exams are scored using an automated system. Any grievance or requests for manual scoring must be
submitted in writing to API within 90 days after receipt of your score. Requests for manual scoring must
include a viable reason why your exam should be re-graded. There is a $50 fee for manual scoring of
exams. Requests should be submitted to:
3
itcSkills
API-510 PRESTUDY GUIDE
COPYRIGHT 2004 – itcSkills/SCHINDLER & ASSOCIATES & CODEWEST - ALL RIGHTS RESERVED - DO NOT COPY OR DISTRIBUTE
Approximately 8 weeks after the examination, candidates will receive score reports. These reports will
contain the date of the test administration, the title of the examination, the candidate’s name and address,
the candidate’s identification number, the candidate’s total score, and the candidate’s subscores on each of
the content areas covered in the test. Should you pass the exam, you will receive a wallet card and
certificate approximately 6 weeks after notification of your score. Please do not call API for test results;
these results will not be given over the telephone.
SPECIAL ACCOMMODATIONS
Candidates with special needs may request special testing arrangements by submitting, with their
application; (a) a letter describing the basis for the need, such as a physical disability or cognitive
impairment; (b) a detailed description of the type of accommodation, such as large print or extended time;
and (c) written verification of the need, such as a letter or report from a licensed health professional. The
request and its accompanying documentation should be sent to API with the application. There is no
additional charge for special accommodations.
API has not published a policy on rounding (either up or down) when calculations are performed as part of
the examination, although they have been asked to publish this policy. The calculation answers are
normally far enough apart so that rounding does not usually present a problem. However, we can only
instruct based on (historically) what has worked best (so far). This is the rounding policy that will be used
during this course (but may be modified on the exam by API):
1.) Thickness Calculations : Round to the third decimal place, and don’t round-up/down.
3. Square Root - Do not round any number under a square root. Simply hit the square root button
( ) on the calculator and utilize that full number.
4
itcSkills
API-510 PRESTUDY GUIDE
COPYRIGHT 2004 – itcSkills/SCHINDLER & ASSOCIATES & CODEWEST - ALL RIGHTS RESERVED - DO NOT COPY OR DISTRIBUTE
5
itcSkills
API-510 PRESTUDY GUIDE
COPYRIGHT 2004 – itcSkills/SCHINDLER & ASSOCIATES & CODEWEST - ALL RIGHTS RESERVED - DO NOT COPY OR DISTRIBUTE
6
itcSkills
API-510 PRESTUDY GUIDE
COPYRIGHT 2004 – itcSkills/SCHINDLER & ASSOCIATES & CODEWEST - ALL RIGHTS RESERVED - DO NOT COPY OR DISTRIBUTE
You require the following Code Books for the course and examination. Make sure you have the
correct editions and bring them with you.
Section II, Materials, Part D, External Pressure Graphs – We will give you these during the course
Guide for Inspection of Refinery Equipment Chapter II – Not Generally Available Ask for the Inspector
Certification Program Copy. Any problems call us.
7
itcSkills
API-510 PRESTUDY GUIDE
COPYRIGHT 2004 – itcSkills/SCHINDLER & ASSOCIATES & CODEWEST - ALL RIGHTS RESERVED - DO NOT COPY OR DISTRIBUTE
PRACTICE QUESTIONS
?? Answer Sheets for the above Math Problems and Code References for the Answers to the Practice
Questions.
8
itcSkills
API-510 PRESTUDY GUIDE
COPYRIGHT 2004 – itcSkills/SCHINDLER & ASSOCIATES & CODEWEST - ALL RIGHTS RESERVED - DO NOT COPY OR DISTRIBUTE
API DOCUMENTS
During the course the four API documents will be reviewed. The following practice questions cover these four
documents thoroughly. You must be able to answer all the practice questions without reference to any of
the documents to be considered to have an adequate knowledge of their content.
a. boilers
b. pressure vessels
c. power piping
d. all the above
2. Name three types of pressure vessels and cont ainers that are excluded from the requirements of
API 510.
3. How is the MAWP determined for the continued use of a pressure vessel?
8. Above ground vessels shall be given a visual external inspection at what interval?
10. What is the maximum test/inspection interval permitted for pressure-relieving devices?
12. Name four kinds of records that the owner/user must maintain for each pressure vessel?
15. How many years experience must a high school graduate have to qualify as an Owner-User
Inspector under API 510?
9
itcSkills
API-510 PRESTUDY GUIDE
COPYRIGHT 2004 – itcSkills/SCHINDLER & ASSOCIATES & CODEWEST - ALL RIGHTS RESERVED - DO NOT COPY OR DISTRIBUTE
17. When new vessels are placed into service or the service conditions are changed what are the three
methods for determining the probable rate of corrosion?
18. What other examination methods may be used to supplement the visual examinations?
19. Do you always have to remove insulation at the time of each external inspection?
24. Name and describe four items that must be considered when the minimum actual thickness and
maximum corrosion rate are adjusted?
25. For a corroded area of considerable size in which circumferential stress governs the least thickness
along a critical element may be averaged over a length not exceeding?
26. Can large vessels with two or more zones of differing corrosion rates have each zone treated
independently regarding inspection intervals?
27. List 15 features that must be covered in the owner-user quality assurance manual for pressure
vessel inspection systems.
28. What is the efficiency factor to be used when determining the MAWP for a corroded area in the
solid material area of a vessel (away from a weld by greater than 1” or twice the material
thickness)?
29. How are the intervals between pressure-relieving device testing/inspection determined?
31. When an internal inspection is to be performed name at least five safety precautions that should be
taken before entering the vessel.
32. For buried vessels what is the basis for establishing the external inspection frequency?
34. What three things must be done when the service conditions of a vessel are changed?
35. Repairs and alterations to pressure vessels are covered by API 510 provided what method is
employed?
36. When both ownership and location of a vessel are changed what must be done?
10
itcSkills
API-510 PRESTUDY GUIDE
COPYRIGHT 2004 – itcSkills/SCHINDLER & ASSOCIATES & CODEWEST - ALL RIGHTS RESERVED - DO NOT COPY OR DISTRIBUTE
39. What are the minimum and maximum pressure test temperatures recommended by API 510?
40. When a pneumatic pressure test is to be performed, what are the additional examinations required
by the ASME Code prior to the test being performed?
41. When the pressure test pressure will exceed the settings of any safety relief valves or
appurtenances what must be done?
42. Repair organizations that repair pressure relief valves are required to have what kind of a written
program?
43. Name at least 9 topics that are part of a pressure relief valve repair organizations quality control
manual?
44. In addition to the 16 topics covered in the pressure relief valve repair organizations quality program,
what additional requirement must be met?
45. What is the efficiency factor to be used when determining the MAWP for a corroded area in a weld?
46. What authorizations and approvals are required prior to the commencement of repairs or
alterations?
47. What ASME Code section are welding procedures and welders qualified in accordance with?
48. What is the welding technique that is used as an alternative to PWHT for P-1 and P-3 materials?
50. Is it permissible to substitute local PWHT for 360 degree banding on local repairs?
51. When local PWHT is substituted what are the four conditions that must be adhered to?
53. When fillet welded patches are used for repairs what design considerations must be made?
54. What are the requirements that must be met when a pressure vessel is rerated?
55. Sketch the basic nameplate or stamping that is used for a rerated vessel.
56. What alternative method may be used to determine acceptability vessel walls when corrosion has
reduced the thickness below the minimum required wall thickness?
57. If a corroded area is found in the center portion of an ellipsoidal or torispherical head, what formula
would be used to calculate the minimum required thickness?
58. Which is the preferred method to use internal inspection or on-stream inspection?
59. Who must review and endorse the repair procedures used on stainless steel weld overlay and
cladding?
11
itcSkills
API-510 PRESTUDY GUIDE
COPYRIGHT 2004 – itcSkills/SCHINDLER & ASSOCIATES & CODEWEST - ALL RIGHTS RESERVED - DO NOT COPY OR DISTRIBUTE
60. For the controlled-deposition welding technique using SMAW, the weld area shall be maintained at
what temperature and for what minimum time after completion of the repair? (assuming 7018 H4
electrodes are not used)
61. The repair area on stainless steel weld overlay and clad vessels constructed of P-3, P-4 or P-5 base
materials should have the base materials examined for what type defects and by which NDE
method?
62. When a pressure test is not performed following a repair or alteration what is required as a
substitute?
63. When is the controlled deposition welding method used (i.e., what additional testing is required?)
64. What is the minimum number of thickness measurements that must be taken on each vessel to
satisfy the internal or on-stream requirements?
66. Who must be consulted prior to repairs of cracks at high stress concentrations?
67. When there is a conflict between requirements specified in the ASME Code and API 510, which
document governs?
68. Do the requirements of API 510 apply to new construction of pressure vessels?
71. The RBI assessments must be reviewed and approved by whom, when used to increase or
decrease inspection intervals?
77. What do each of the specific sections of RP 579 cover (Sections 4 – 11)?
12
itcSkills
API-510 PRESTUDY GUIDE
COPYRIGHT 2004 – itcSkills/SCHINDLER & ASSOCIATES & CODEWEST - ALL RIGHTS RESERVED - DO NOT COPY OR DISTRIBUTE
1. Corrosion problems in refining operations are divided into three major groups. Name them?
2. Name four corrosive materials that may be added to the refinery processes?
4. Carburization, decarburization and metal dusting are considered to be what kinds of changes to
metals and their alloys?
6. The physical wearing away of vessels, piping, and other equipment by moving streams of gases or
liquids is called?
7. The formation and collapse of cavities in a liquid at the metal-liquid interface is called?
8. What two conditions are used to evaluate materials at high temperatures where the plastic
properties dominate?
9. Coarse grained materials are not suitable for high temperature service?
10. List and describe briefly three of the most serious structural changes that occur to refinery metals
and alloys?
11. What two metals and their alloys are seldom a problem from attack by oxygen?
13. Mercury will cause stress corrosion cracking in which two metals?
14. Metals having good notch toughness are best employed in high temperature service?
15. The metal temperature at which the type of failure changes from ductile to brittle is called?
16. What is the most common metallic material of construction used in refineries?
18. Of all the metals and alloys used in the refinery which is the only one to exhibit low-temperature
brittleness?
20. Overpressuring of shells and heads can cause what damaging results?
22. What are some typical observations that give evidence of overloading? Give five examples.
13
itcSkills
API-510 PRESTUDY GUIDE
COPYRIGHT 2004 – itcSkills/SCHINDLER & ASSOCIATES & CODEWEST - ALL RIGHTS RESERVED - DO NOT COPY OR DISTRIBUTE
24. Name three situations leading to improper selection of material and equipment and explain each
briefly?
25. List the equipment section(s) most likely affected by the following corrosive compounds:
a) hydrogen sulfide
b) sulfur compounds
c) organic acids
d) dissolved oxygen
e) hydrogen chloride
26. Name two types of linings that are used to resist erosion?
30. Sodium hydroxide will cause general corrosion of carbon steel above what temperature?
35. Name three considerations that control the amount of galvanic corrosion?
36. Organisms causing biological corrosion are divided into two categories, what are they?
38. Name the corrosive materials added to the process in the following process units?
a. alkylation unit.
b. olefin-extraction units.
c. acid-concentration facilities.
14
itcSkills
API-510 PRESTUDY GUIDE
COPYRIGHT 2004 – itcSkills/SCHINDLER & ASSOCIATES & CODEWEST - ALL RIGHTS RESERVED - DO NOT COPY OR DISTRIBUTE
1. What is the most common material used in the construction of pressure vessels?
2. Inspection of external parts while the unit is in service should be made when?
6. What are three materials that provide corrosion resistant surfaces in pressure vessels?
7. List the safety precautions that must be taken prior to entering a pressure vessel?
8. Prior to 1956 what pressure vessel construction code was used by refineries?
11. List at least three problems that can occur from using faulty materials?
13. The frequency with which a pressure vessel should be inspected depends on what factors?
16. What should the Inspector do before starting the inspection of a pressure vessel, particularly one in
severe service?
17. Is it necessary to remove all surface deposits for an inspection? Give reasons.
24. List six of the tools used in the inspection of a pressure vessel?
25. When inspecting a pressure vessel externally what should the inspection start with?
15
itcSkills
API-510 PRESTUDY GUIDE
COPYRIGHT 2004 – itcSkills/SCHINDLER & ASSOCIATES & CODEWEST - ALL RIGHTS RESERVED - DO NOT COPY OR DISTRIBUTE
26. Briefly describe the items to be checked when externally inspecting the following equipment:
27. Upon what will the number of thickness readings taken depend?
29. What must every pressure vessel manufacturer prepare in order to obtain the ASME Code
Certificate of Authorization?
30. In addition to checking for corrosion on an external inspection name three other items to check for?
31. What two methods of inspection are used when all the tubes in a bundle are to be checked
internally for through-wall defects or thinning?
34. Briefly describe how you would make a detailed internal inspection of a pressure vessel?
35. What are the three most important factors to consider when checking metallic linings?
37. On what two factors does the degree of internal surface preparation depend?
40. When should hammer testing be used and when is it not recommended?
43. Describe briefly the steps to perform a hydrostatic test of a pressure vessel?
44. What test method would be used for testing a vacuum vessel for leaks?
45. What metallurgical changes would you be inspecting for and what tests would be used to determine
each change?
47. Name three conditions that will result in excess thickness of a pressure vessel shell?
16
itcSkills
API-510 PRESTUDY GUIDE
COPYRIGHT 2004 – itcSkills/SCHINDLER & ASSOCIATES & CODEWEST - ALL RIGHTS RESERVED - DO NOT COPY OR DISTRIBUTE
49. What code would you use to determine the minimum thickness required for pressure vessel
accessories such as trays and supports?
51. What are the three types of records that should be kept in the record file?
54. When an exchanger is removed from service what test is recommended prior to dismantling?
61. Some jurisdictions require the repair firm to possess what authorization to perform the repair?
63. What would be checked during the visual inspection of an extended plate exchanger?
64. What must be done to the finned tubes of an air-cooled exchanger before starting an inspection?
69. What two NDE methods are now primarily used to measure thickness?
71. The selection of thickness measuring tools depends on what five factors?
17
itcSkills
API-510 PRESTUDY GUIDE
COPYRIGHT 2004 – itcSkills/SCHINDLER & ASSOCIATES & CODEWEST - ALL RIGHTS RESERVED - DO NOT COPY OR DISTRIBUTE
a. safety valve
b. relief valve
c. safety relief valve
d. pilot operated safety relief valve
e. balanced safety relief valve
f. rupture disk
5. What is a primary consideration used to establish the inspection frequency of relieving devices?
6. There are three basis for establishing the frequency of shop inspections/overhauls. What is each
and briefly describe?
7. What inspections and testing should be done on new relieving device installations?
10. What should be done after extended shutdowns with relieving devices left on a unit?
11. Following reassembly of the relieving device what tests should be done?
12. What is the principle objective in keeping records of safety relieving devices?
13. What precautions should be observed when inspecting pressure relief devices?
14. What service information should be contained in the history of a relieving device?
16. What medium is normally used to test relieving devices in the shop test block?
17. Briefly describe the shop test block used for testing with air? Make a sketch.
18
itcSkills
API-510 PRESTUDY GUIDE
COPYRIGHT 2004 – itcSkills/SCHINDLER & ASSOCIATES & CODEWEST - ALL RIGHTS RESERVED - DO NOT COPY OR DISTRIBUTE
18. What should be done immediately after the removal of HF relief devices that will be sent to the
shop?
19. List the nine points that should be visually checked during the dismantle of a relieving device?
20. Prior to the start of dismantling what test should be performed and why?
21. During the relieving device test after reassembly what two items are to be checked?
26. What should be done with connecting piping and block valves before disconnecting relief valves?
27. What should be done before relief lines are opened to the atmosphere?
28. What are two types of hydrocarbon that can cause plugging or sticking?
29. List two limitations for each of the following pressure relief devices:
a. safety valve
b. relief valve
c. safety relief valve
d. pilot operated safety relief valve
e. balanced safety relief valve
f. rupture disk
30. Rupture disks should not be re-used after dismantling of the rupture disk device, even if they are
sound and have not ruptured, why?
19
itcSkills
API-510 PRESTUDY GUIDE
COPYRIGHT 2004 – itcSkills/SCHINDLER & ASSOCIATES & CODEWEST - ALL RIGHTS RESERVED - DO NOT COPY OR DISTRIBUTE
The following articles fall within the scope of the examination and should be studied:
Article 5 Ultrasonic Examination Methods for Materials and Fabrication, concentrate on general
requirements and the specific requirements for castings and welds.
Article 7 Magnetic Particle Examination, concentrate on the prod and yoke methods only.
In the day to day inspection activities nondestructive examinations are used and the API Inspector must
have both an understanding of the practical applications as well as the specific requirements.
It is not necessary for the API Inspector to have the in-depth knowledge of the SNT-TC-IA Level II Examiner
for the nondestructive methods but should know where in the ASME Code to find the requirements.
7. What are the IQI thickness and hole sizes for a number 30 IQI?
8. What are the two radiographic exposure techniques permitted by the Code?
10. What is the recommended minimum thickness that steel can be radiographed using Iridium 192?
11. Can the minimum thickness limitations for gamma radiation be further reduced?
12. Is geometric unsharpness an essential variable when radiographing welds in pressure vessels to
ASME VIII?
13. For single wall viewing source side markers shall be used on what components?
a. source side
b. film side
15. Where is the lead letter "F" placed when film side IQI’s are used?
20
itcSkills
API-510 PRESTUDY GUIDE
COPYRIGHT 2004 – itcSkills/SCHINDLER & ASSOCIATES & CODEWEST - ALL RIGHTS RESERVED - DO NOT COPY OR DISTRIBUTE
16. A circumferential seam is to radiographed as a single exposure, what are the minimum number of
IQI’s to be used?
18. When viewing single film radiographs made with an X-ray source what is the minimum and
maximum permitted density?
19. It is required to radiograph a steel plate with a weld. The plate thickness is 7/16 inch and the weld
reinforcement is 1/16 inch. What source side IQI is required and what is the essential hole
20. Are intensifying screens permitted by ASME Code Section VIII Div. 1?
21. For which NDE methods are there alternative personnel qualification requirements in Section VIII?
22. What is the permitted density variation anywhere through the area of interest?
23. What minimum RT detail information must be provided to the Inspector along with the radiographic
film?
25. What type of technique is required for all ultrasonic examination of forging and bars?
26. Couplant used in ultrasonic examination of nickel base alloys shall contain no more than _____ppm
of sulfur.
32. When using penetrant materials on nickel base alloys, austenitic stainless steels and titanium what
certifications must be obtained?
34. The scanning of welds shall be performed at a gain setting that is how many times the primary
reference level?
a. three times
b. two times
c. one-one half times
21
itcSkills
API-510 PRESTUDY GUIDE
COPYRIGHT 2004 – itcSkills/SCHINDLER & ASSOCIATES & CODEWEST - ALL RIGHTS RESERVED - DO NOT COPY OR DISTRIBUTE
a. slightly subsurface
b. open to the surface
c. both a and b
37. What are the essential variables that when changed in a PT procedure may require a new procedure
to be prepared?
38. List the two types of penetrants and the three basic penetrant processes?
41. The acceptance tolerance for the MT units ammeter shall be that the reading shall not deviate by
more than _______% of full scale relative to the actual current value as shown by the test meter?
42. Describe briefly the basic steps in making a liquid penetrant examination?
43. What is considered to be the standard temperature range for liquid penetrant examination?
44. What is the retention time for radiographic film and reports for radiography performed on pressure
vessels?
45. To remove excess penetrant after the penetration time has elapsed for the solvent removable
penetrant is it permissible to flush the test piece gently with solvent then wipe it dry?
48. What are the two types of radiation sources used in radiography?
49. What are the acceptance standards for liquid penetrant examinations of welds in pressure vessels?
50. The written procedure for the magnetic particle examination shall contain what minimum
information?
52. Each piece of magnetizing equipment with an ammeter shall be calibrated at what frequency?
53. What is the acceptance criteria for the lifting power of yokes when they are checked annually?
54. What are the acceptance standards for magnetic particle examinations of welds in pressure
vessels?
55. Any imperfection that causes an indication in excess of ______% DAC shall be investigated?
22
itcSkills
API-510 PRESTUDY GUIDE
COPYRIGHT 2004 – itcSkills/SCHINDLER & ASSOCIATES & CODEWEST - ALL RIGHTS RESERVED - DO NOT COPY OR DISTRIBUTE
23
itcSkills
API-510 PRESTUDY GUIDE
COPYRIGHT 2004 – itcSkills/SCHINDLER & ASSOCIATES & CODEWEST - ALL RIGHTS RESERVED - DO NOT COPY OR DISTRIBUTE
The examination concentrates mainly on the math problems, which accounts for 20% of the total possible
grade. While it is important to study the entire Code the emphasis should be placed on a complete
understanding of the various formulas and their application in solving the five examination math problems.
When solving math problems whether for the examination or for actual work situations a few simple rules are
necessary.
The examination math problems are normally based on the concept that the vessel or vessel part has been
in service. This means that there are no original design questions to consider.
Under these circumstances there are certain basic points that must be understood when solving the math
problems. These are:
1. Efficiencies are determined by the extent of radiography, type of joint and the application of Table
UW-12, UW-11(a)(5)(b) and UW-12(d) as applicable.
2. When determining allowable pressure or thickness in corroded conditions for cylindrical shells or
pipe the inside radius is taken at the bottom of the corroded area exclusive of corrosion allowance.
3. When solving a problem to determine tmin for use in a remaining life problem the inside radius to use
is the original radius increased by the amount of corrosion allowance specified in the problem.
4. Radii may have to be adjusted depending on the existence of corrosion allowances. Unless
specifically stated otherwise in the problem corrosion allowance is assumed to be "0".
5. Static head is to be considered only when the problem gives relevant height or other data, otherwise
it is assumed to be "0".
The following are some typical math problems which cover each of the formulas that you will study.
24
itcSkills
API-510 PRESTUDY GUIDE
COPYRIGHT 2004 – itcSkills/SCHINDLER & ASSOCIATES & CODEWEST - ALL RIGHTS RESERVED - DO NOT COPY OR DISTRIBUTE
QUESTION: 1
During the inspection of a horizontal pressure vessel a corroded area was found on the inside surface, the
thickness at the point was measured to be .906 inches thick. Checking the ASME Data Report for the
vessel it was found that the shell plate was 1-1/4 inch purchased thickness, 48 inch inside diameter, of
SA-516 Gr. 70 material, the shell was rolled and welded using a type 1 longitudinal seam with full
radiographic examination. No corrosion allowance was specified. The MAWP is 600 psig at 300 F. All
openings in the vessel are fully reinforced, welded connections. S is 17500.
As the Inspector what position would you take with regard to this area of thinned shell? (Show your
calculations upon which you based your decision.)
QUESTION: 2
A vessel has fixed tube sheets with 40, 4 inch outside diameter by 0.120 inch minimum wall thickness
tubes of SA-192 material installed between tubesheets. The total unsupported length is 72 inches. The
vessel is stamped 500 psig at 400 F.
on the shell side. Do these tubes comply with Code requirements?
QUESTION: 3
A seamless 2:1 elliptical head on a horizontal pressure vessel is found by inspection to have a minimum
thickness of 7/8 inch. The nameplate shows a MAWP of 500 psi at 600 degrees. The vessel has not been
radiographed and the Data Report shows that UW-11(a)(5)(b) has not been applied. The inside length of the
major axis is 42 inches. The material is SA-516 Grade 60, S = 15,000. Must the MAWP be reduced?
QUESTION: 4
A seamless flat circular head, attached to a cylinder as shown in Fig. UG-34(b-1), has been subjected to
corrosion near the center of the head which has reduced the thickness below acceptable limits. The reduced
area is to be restored by weld buildup. The head is made of SA-105 material, S = 17500 with an inside
diameter d of 36 inches. The hydrostatic head acting on the flat head is 10 psig. From the nameplate, the
MAWP is 550 psi at 475 F and RT-3 is the extent of radiography. What is the minimum required thickness
of the head after the weld buildup has been completed?
QUESTION: 5
A vessel is to be altered to add a new nozzle to a cylindrical shell. The Engineer has provided the following
information:
Does this nozzle have adequate reinforcement to meet Code without additional reinforcement?
25
itcSkills
API-510 PRESTUDY GUIDE
COPYRIGHT 2004 – itcSkills/SCHINDLER & ASSOCIATES & CODEWEST - ALL RIGHTS RESERVED - DO NOT COPY OR DISTRIBUTE
QUESTION: 6
A hydrostatic test is to be performed on a pressure vessel using the same methodology as required by
Section VIII, Div. 1 Code where the MAWP is 725 psig at 700 F. The vessel is a single chamber vessel
constructed of SA-516 Gr. 70 or equal materials. Sd= 16600, St = 17500. Describe the hydrostatic test
along with the required test pressure. (Show your calculations.)
QUESTION: 7
Calculate the pneumatic test pressure and describe the pressure test for a vessel of SA-515 Gr 60, S =
15000, with a temperature of 450 F and an MAWP of 800 psig. The MDMT is 100 F.
QUESTION: 8
A welded nozzle is installed into a vessel shell using two fillet welds as shown in Figure UW-16.1(i). The
nozzle thickness tn = 0.75 in., the shell thickness t = 1.5 in., t1= 0.5 in., and t2 = 0.375 inch. Does the as
measured weld throat dimension meet Code requirements?
QUESTION: 9
A pressure vessel shell with the following characteristics is to have a plate replaced using SA-515-70
material.
QUESTION: 10
A vertical pressure vessel is to be hydrostatically tested for an MAWP of 125 psi. Two pressure gages will
be used to monitor pressure. One is placed at the top of the vessel at the 175 ft. The other is placed at the
25 ft. level. Stress ratio is 1.0 for the materials. As the Inspector you are to read the test pressure gauge at
the 25 ft level. What pressure reading would you expect to observe?
26
itcSkills
API-510 PRESTUDY GUIDE
COPYRIGHT 2004 – itcSkills/SCHINDLER & ASSOCIATES & CODEWEST - ALL RIGHTS RESERVED - DO NOT COPY OR DISTRIBUTE
The following general knowledge areas of Section VIII, Division 1 must be studied as a basis for answering
the quiz questions. These areas are:
27
itcSkills
API-510 PRESTUDY GUIDE
COPYRIGHT 2004 – itcSkills/SCHINDLER & ASSOCIATES & CODEWEST - ALL RIGHTS RESERVED - DO NOT COPY OR DISTRIBUTE
1. The ASME Code used for the construction of pressure vessels is:
a. Section I
b. Section IV
c. Section VIII, Division 1
2. When designing pressure vessels containing cast material what corrections are required to be made
to the allowable stress values?
a. ASTM standards
b. API-ASME specifications
c. ASME Section II, with specified limitations
4. Can material that is not identified with one of the permitted specifications in Section VIII be
accepted as meeting the requirements of a permitted specification?
7. When calculating the required thickness or internal design pressure of a cylindrical shell the formula
most commonly used considers:
a. circumferential stress
b. longitudinal stress
c. both a and b
9. A torispherical head on a vessel must be replaced, what formula would apply if the knuckle radius is
6% of the inside crown radius?
10. What are the two methods of calculating the MAWP for a convex head with the pressure on the
convex side?
11. An circular unstayed flat head is to be replaced on a pressure vessel. The head is similar to that
shown in Figure UG-34(h). What formula would you use and what "C" factor would apply?
12. What product forms are required to have a material test report or certificate of compliance?
13. Welding materials must be provided with a Certified Test Report or a Certificate of Compliance?
True or False
15. Are openings in pressure vessels limited to only those of circular shape? If not, If no, what are the
permitted shapes?
16. What classes of vessels are not considered to be within the scope of Section VIII Division 1?
28
itcSkills
API-510 PRESTUDY GUIDE
COPYRIGHT 2004 – itcSkills/SCHINDLER & ASSOCIATES & CODEWEST - ALL RIGHTS RESERVED - DO NOT COPY OR DISTRIBUTE
17. Certain openings that are not subject to rapid fluctuation do not require reinforcement other than that
inherent in the construction. What are the size limitations for these openings?
18. When calculating the required thickness of vessel and nozzle walls to determine the required
reinforcement what "E" factor is used?
20. What are the limits of reinforcement measured parallel to and normal to the vessel wall?
21. Can credit be taken for reinforcement material having an allowable stress value higher than that of
the vessel wall?
22. UG-41(b) requires that strength calculations be made for certain welded nozzle configurations.
Which configurations are exempt from these strength calculations?
23. Nozzle necks other than those for access openings and openings for inspection require special
attention regarding their required thickness. Where are these requirements found and briefly explain
their application?
24. A replacement torispherical head of P-No. 1, Group No. 1 material is required for a low alloy steel
vessel. The head thickness before forming is 1 inch and the knuckle radius is 3 inches. The head is
to be formed at 8000F. Does this head require heat treating after forming?
25. When nozzles are welded into a pressure vessel what must be done to the exposed inside edges?
26. What are the requirements for identification of material at the completion of a newly constructed
pressure vessel?
27. What is the maximum out of roundness permitted for any shell cross section?
28. Under what conditions may the out of roundness tolerance exceed the 1% value?
29. What are the shape tolerances that apply to torispherical and ellipsoidal heads?
31. The material specifications specify either a material test report or a certificate of compliance. What
is the difference between the two?
32. When a pressure part is to be welded to a flat plate thicker than 1/2 inch to form a corner joint some
additional examinations must be made. Where are these requirements found?
33. Define Maximum Allowable Working Pressure for a completed vessel and a part of a vessel?
34. All pressure vessels for external pressure service must have stiffener rings installed?
True or False
35. When determining the minimum required hydrostatic test pressure what correction factor must be
taken into account?
36. Non pressure parts that are welded to a vessel shall meet what criteria?
29
itcSkills
API-510 PRESTUDY GUIDE
COPYRIGHT 2004 – itcSkills/SCHINDLER & ASSOCIATES & CODEWEST - ALL RIGHTS RESERVED - DO NOT COPY OR DISTRIBUTE
37. What is the minimum and maximum range permitted for dial indicating test gages?
38. When openings are to pass through welded joints what additional provisions apply?
39. Is there any upper limit on the hydrostatic test pressure that is applied to a vessel?
40. Sketch a typical form of stamping with the following data included:
X Y Z Company
MAWP 400 psi @ 350 0F
MDMT - 200F @ 400 psi
Serial No. 12345
Vessel completed 4-25-91
Welded main seams
Vessel completely spot radiographed
41. What are the markings that can be applied to the stamping for vessels that have been
radiographed?
42. A carbon steel vessel has a required thickness of 3/16 inch. The shell is seamless and the vessel is
stamped RT3. Must additional corrosion allowance be provided?
43. You are reviewing the stamping on a vessel and note that the extent of radiography is RT 3. The
vessel was constructed in the year 1994. What "E" factor would you use when calculating the shell
and head thicknesses if type 1 joints were used?
44. What special service conditions are applicable in Section VIII and where are they found?
46. What is the mandatory minimum test temperature that shall be used during a hydrostatic or a
pneumatic pressure test?
a. location of joint
b. type of joint
48. You are welding a seamless torispherical head to a seamless shell. To be able to allow the full
allowable stress value on the head what must be done to the weld joint?
49. Do butt welds in nozzles and communicating chambers that neither exceed NPS 10 nor 1-1/8 inch
wall thickness in a lethal vessel require any radiographic examination?
51. A nozzle neck is to be replaced. What are the requirements for determining the correct weld sizes
for partial penetration welds?
52. You are reviewing the stamping on a pressure vessel and find two nameplates, one of which is for a
part. What would you expect to find when you are reviewing the Manufacturer's Data Report for the
vessel?
30
itcSkills
API-510 PRESTUDY GUIDE
COPYRIGHT 2004 – itcSkills/SCHINDLER & ASSOCIATES & CODEWEST - ALL RIGHTS RESERVED - DO NOT COPY OR DISTRIBUTE
53. What is the permitted alignment tolerance when joining a torispherical head to a seamless shell
with both having a section thickness of 9/16 inch?
54. A finished Category B joint with a nominal thickness of 1-1/16 inch has a maximum reinforcement of
9/32 inch. Does this meet Code requirements?
55. You are replacing the head on a vessel constructed in 1994. The Data Report shows the material to
be SA-516 Grade 60 not normalized. The nominal thickness is 1-1/2 inch. What would be the
MDMT for this material considering the required thickness times E* equals the nominal thickness
minus corrosion allowance?
56. You are replacing the bolting on a vessel with SA-193 Grade B5 bolts. The MDMT is - 210F. Is
impact testing required?
57. You must replace the reinforcing plate around a nozzle. What is the requirement regarding the size
of the telltale hole?
59. What alternatives to SNT-TC-1A are allowed for personnel qualifications for radiographers or UT
operators?
60. What are the minimum sizes permitted for elliptical or obround manways or circular manways?
31
itcSkills
API-510 PRESTUDY GUIDE
COPYRIGHT 2004 – itcSkills/SCHINDLER & ASSOCIATES & CODEWEST - ALL RIGHTS RESERVED - DO NOT COPY OR DISTRIBUTE
A good general knowledge of Section IX is required to evaluate the acceptability of a Welding Procedure
Specification (WPS) its qualifying Procedure Qualification Record (PQR) and the Welders Performance
Qualification Record (WPQ). The actual examination is limited to the welding portion of the Code only and to
the processes shielded metal arc welding (SMAW), gas tungsten arc welding (GTAW), gas metal arc
welding (GMAW) and submerged arc welding (SAW). No more than one process will be included on a WPS,
PQR or WPQ.
A technical knowledge of welding such as that held by a welding engineer or technician is not necessary to
perform the evaluation of the WPS, PQR and WPQ or to answer any of the quiz questions or those on the
examination.
1. Are all of the essential, supplemental essential variables when applicable and nonessential variables
as required by the process addressed on the Welding Procedure Specification and are there any
errors or incompatibilities?
2. Are all the essential and supplemental essential variables when applicable as required by the
process recorded on the Procedure Qualification Record and are there any other errors or
incompatibilities?
3. Are all the required essential variables addressed for the qualification of the welder and are actual
values and qualified ranges recorded and are they correct or do incompatibilities exist?
1. Part QW
You will be given several sample WPS’s and PQR’s to review during the course. The following
comprehensive quiz on ASME Section IX will help you prepare for that portion of the presentation.
32
itcSkills
API-510 PRESTUDY GUIDE
COPYRIGHT 2004 – itcSkills/SCHINDLER & ASSOCIATES & CODEWEST - ALL RIGHTS RESERVED - DO NOT COPY OR DISTRIBUTE
1. If a performance qualification is made on a groove weld in a pipe over 24" in the 3G test position for
what position(s) is the welder qualified?
3. The performance qualification of a welder/welding operator shall expire when no welding is performed
in the process for what period of time?
4. If a tension test specimen breaks in the base metal outside of the weld or fusion zone what are the
acceptance criteria?
5. When corrosion resistant weld overlay cladding is not a factor would a 1/16" open defect be
acceptable for a guided bend specimen?
7. Pipe diameter is not an essential variable for a welder under the GMAW process?
9. Does procedure qualification on a 1-1/2" thick base metal qualify the procedure to be used to repair
groove welds and to make weld buildups on base metal thicknesses no exceeding 8"?
10. 1G and 6G are test positions or positions for which a welder is qualified?
11. Groove design and retainers are essential variables for the SMAW process?
12. Anyone can supervise the welders making procedure and performance test coupons?
13. Performance test coupons are required to be visually examined to confirm complete joint
penetration and fusion?
14. The base metals and filler metals used during qualification do not have to be one or more of those
listed in the WPS?
15. Can an existing PQR be used to support a newly written WPS?
16. Can organizations with two or more companies having different names exchange WPS's and
PQR's?
17. The WPS specifies a single V groove design. Can the PQR use a double V groove to qualify the
WPS?
18. For what processes and P-No.'s may welders be alternatively qualified by radiographic examination?
19. When and immediate retest is made following failure of the visual examination how many test
coupons are required for each position which failed?
20. If a welder/welding operator has left the employ of an organization and has not welded for a period of
five years what are the qualification renewal requirements?
21. If QW-404.15 is shown as a variable can a welder who has welded F-No. 4 filler metal without
backing also weld F-No's 3, 2 and 1 without backing?
33
itcSkills
API-510 PRESTUDY GUIDE
COPYRIGHT 2004 – itcSkills/SCHINDLER & ASSOCIATES & CODEWEST - ALL RIGHTS RESERVED - DO NOT COPY OR DISTRIBUTE
22. Multiple reduced section specimens can be used for tension tests on thicknesses not exceeding 1
inch?
23. If QW-406.1 is shown as a variable and the preheat temperature qualified was 3500F, would a
preheat of 4520F require requalification?
25. What is the minimum specified tensile strength of the following base metals:
a) SA-53 Type F
b) SA336 Type F3V
26. If a welder uses a P-No. 1 material for a qualification test coupon what base metals is he qualified to
weld?
27. Can a welder who has passed the required tests for groove welds make fillet in all thicknesses and
pipe diameters of any size?
28. What ASME Specification and F-No. is the filler metal E-6010?
29. What are the procedure qualification bend test requirements for a 3/8" test coupon?
31. How many tension test specimens are required to qualify a welder?
32. If a 2-7/16" OD test coupon is welded by a welder what is the minimum and maximum outside
diameters qualified?
33. If a filler metal is A-No. 1 what elements must be shown on the analysis?
34. What is the specimen width of a tension test reduced section - plate?
34
itcSkills
API-510 PRESTUDY GUIDE
COPYRIGHT 2004 – itcSkills/SCHINDLER & ASSOCIATES & CODEWEST - ALL RIGHTS RESERVED - DO NOT COPY OR DISTRIBUTE
ANSWER KEYS
The references listed below for the written questions are where the answers to the quizzes can be found.
API 510
1. 1.1
2. Appendix A
3. 5.4
4. 5.5
5. 3.1 and 3.15
6. 3.1
7. 6.1
8. 6.3
9. 5.5
10. 6.6
11. 3.11
12. 6.7
13. 3.15
14. 3.16
15. App. B
16. 5.2
17. 5.3
18. 5.5
19. 6.3
20. 5.5
21. 6.4
22. 5.6
23. 5.7
24. 5.7
25. 5.7
26. 6.4
27. 4.3
28. 5.7
29. 6.6
30. 6.4
31. 5.1
32. 6.3
33. 5.6
34. 6.4
35. 7.1
36. 6.4
37. 6.5
38. 7.2.7
39. 6.5
40. 6.5
41. 6.5
42. 6.6
43. 6.6
44. 6.6
45. 5.7
46. 7.1
47. 7.2
48. 7.2.3.1
49. 6.5
35
itcSkills
API-510 PRESTUDY GUIDE
COPYRIGHT 2004 – itcSkills/SCHINDLER & ASSOCIATES & CODEWEST - ALL RIGHTS RESERVED - DO NOT COPY OR DISTRIBUTE
50. 7.2.5
51. 7.2.5
52. 6.4
53. 7.2.7
54. 7.3
55. 7.3
56. 5.7
57. 5.7
58. 6.4
59. 7.2.6
60. 7.2.3.2
61. 7.2.6
62. 7.2.10
63. 7.2.3.2
64. 6.4
65. 5.7
66. 7.1
67. 3.2
68. 3.2
69. 7.2
70. 6.2
71. 6.2
72. 6.2
73. 6.6
74. 3.20
75. 5.8
76. 3.21
77. 5.8
78. 6.4
IRE CHAPTER II
1. 202.01
2. 202.031
3. 202.064
4. 204.032 thru 204.034
5. 202.052
6. 203.01
7. 203.022
8. 204.011, 204.012, 204.013
9. 204.014
10. 204.022(a) thru (g)
11. 202.052
12. 202.06
13. 202.036
14. 205.01
15. 205.01
16. 202.041
17. 202.04
18. 205.01
19. 206.021 thru 206.025
20. 206.03
21. 202.021
36
itcSkills
API-510 PRESTUDY GUIDE
COPYRIGHT 2004 – itcSkills/SCHINDLER & ASSOCIATES & CODEWEST - ALL RIGHTS RESERVED - DO NOT COPY OR DISTRIBUTE
22. 207.02
23. 209.02
24. 210.021 thru 210.023
25. 202.021
26. 203.02
27. 202.022, 202.024(a), 202.064
28. 207
29. 202.033
30. 202.035
31. 202.034
32. 208
33. 209.01
34. 202.037
35. 202.067
36. 202.069
37. 203.022
38. 202.03
39. 204.012
RP572
1. 4.3
2. 9.2
3. 9.3
4. 10.4.5
5. Figure A-11
6. 4.3
7. 10.2.1
8. Section 5
9. 8.2
10. 8.5
11. 8.5
12. 10.3.7
13. 9.1
14. 9.1
15. 9.2
16. 10.1
17. 10.1
18. 10.1
19. 8.3.7
20. 10.5
21. 4.3
22. 7.1
23. 8.2
24. 10.2.2
25. 10.3.2
26. 10.3.3, 10.3.6, 10.3.8
27. 10.5
28. Figure 4
29. Section 5
30. 10.3.13
31. A.9.1
32. 10.3.13
33. 10.8.1
34. 10.4
37
itcSkills
API-510 PRESTUDY GUIDE
COPYRIGHT 2004 – itcSkills/SCHINDLER & ASSOCIATES & CODEWEST - ALL RIGHTS RESERVED - DO NOT COPY OR DISTRIBUTE
35. 10.4.5
36. 10.4.6
37. 10.4.2
38. 10.4.3
39. 10.5
40. 10.8.1
41. 10.4.6
42. 12.2
43. 10.8.2
44. 10.8.2
45. 10.7
46. 10.9
47. 10.9
48. Section 11
49. 10.9
50. Section 11
51. 12.1
52. 12.2
53. 12.2
54. 10.8.3
55. 12.1
56. 12.1
57. Figure A-11
58. A.9.1
59. A.9.1
60. Section 11
61. Section 11
62. A.9.2
63. A.11
64. A.12
65. A.12
66. 3.7
67. 4.2
68. 8.5.3
69. 10.5
70. 10.4.4
71. 10.5
RP576
1. 4.2 – 4.9
2. 6.3
3. 4.9.2
4. 6.1
5. 6.4
6. 6.4.1.1 – 6.4.1.3
7. 6.5.2
8. 6.4.2
9. 6.5.1
10. 6.5.4
11. 6.2.14 – 6.2.21
12. 7.1
13. 6.2.1
14. 7.2
38
itcSkills
API-510 PRESTUDY GUIDE
COPYRIGHT 2004 – itcSkills/SCHINDLER & ASSOCIATES & CODEWEST - ALL RIGHTS RESERVED - DO NOT COPY OR DISTRIBUTE
15. 4.2.1
16. B.2
17. Figure B-1
18. 6.2.5
19. 6.2.9
20. 6.2.8
21. 6.2.14 – 6.2.15
22. 7.2
23. 7.2
24. 5.1 – 5.10
25. 4.3
26. 6.2.4
27. 6.2.4
28. 5.5
29. 4.2 – 4.9
30. 6.2.21
Section V
1. T-150
2. T-140
3. T-223
4. T-224
5. T-225
6. T-522/Table T-522
7. Table T-233.1
8. T-271
9. T-276 or T-233
10. T-272.2
11. T-272.2
12. T-285 & Section VIII, UW-51(a)(3)
13. T-275.1
14. T-277.1
15. T-277.1(b)
16. T-277.2(b)(1)
17. T-277.3
18. T-282.1
19. T-276.2(a) & Table T-276
20. T-232
21. Section VIII, Appendices 6 & 8
22. T-282.2
23. T-291, T-292 & Section VIII UW-51(a)(1)
24. T-621.1
25. T-571.2(A)(B)
26. T-533.2(A)
27. T-574
28. T-534
29. T-591.2
30. T-532
31. T-277.1(c)
32. T-641
33. T-593 & Section VIII Appendix 12-4
34. b, T-542.7.2.2
35. T-277.1
36. b, T-600
37. T-621.2
39
itcSkills
API-510 PRESTUDY GUIDE
COPYRIGHT 2004 – itcSkills/SCHINDLER & ASSOCIATES & CODEWEST - ALL RIGHTS RESERVED - DO NOT COPY OR DISTRIBUTE
38. T-651
39. T-592
40. T-631
41. T-761(c)
42. T-642, T-643, T-670
43. T-652
44. Section VIII UW-51(a)(1)
45. T-673.3
46. c, T-720
47. T-676.1
48. T-272
49. Section VIII Appendix 8-4
50. T-750
51. T-752
52. T-761(a)
53. T-762(b) & (c)
54. Section VIII Appendix 6-4
55. T-580
56. T-778.1
QUESTION: 1
GIVEN:
ASSUMPTIONS:
FORMULA: UG-27(c)(1)
P= SEt
R + .6t
40
itcSkills
API-510 PRESTUDY GUIDE
COPYRIGHT 2004 – itcSkills/SCHINDLER & ASSOCIATES & CODEWEST - ALL RIGHTS RESERVED - DO NOT COPY OR DISTRIBUTE
24.344 + .6 x .906
P = 637 psi
CONCLUSION:
No action necessary since remaining thickness is adequate to sustain present MAWP. Area should be
monitored at future inservice inspections to determine corrosion rate per API 510 paragraph 3.3.
41
itcSkills
API-510 PRESTUDY GUIDE
COPYRIGHT 2004 – itcSkills/SCHINDLER & ASSOCIATES & CODEWEST - ALL RIGHTS RESERVED - DO NOT COPY OR DISTRIBUTE
QUESTION: 2
GIVEN:
FORMULA: UG-28(c)(1)
A = 0.001
B = 9800
Pa = 4B
3(Do/t)
P a = 4 x 9800
3 x 33.33
P a = 392.039 psi
CONCLUSION:
42
itcSkills
API-510 PRESTUDY GUIDE
COPYRIGHT 2004 – itcSkills/SCHINDLER & ASSOCIATES & CODEWEST - ALL RIGHTS RESERVED - DO NOT COPY OR DISTRIBUTE
QUESTION: 3
GIVEN:
P = 500
t = .875"
S = 15,000
D = 42
E = 0.85
ASSUMPTIONS:
P = 2SEt
D + 0.2t
P = 529.046 psi
CONCLUSION:
43
itcSkills
API-510 PRESTUDY GUIDE
COPYRIGHT 2004 – itcSkills/SCHINDLER & ASSOCIATES & CODEWEST - ALL RIGHTS RESERVED - DO NOT COPY OR DISTRIBUTE
QUESTION: 4
GIVEN:
S = 17,500
d = 36"
P = 550
E = 0.85
Hydrostatic head = 10 psi
C = 0.17
ASSUMPTIONS:
Head is seamless.
FORMULA: UG-34(c)(2)
t=d CP
SE
t = 2.88"
CONCLUSION:
44
itcSkills
API-510 PRESTUDY GUIDE
COPYRIGHT 2004 – itcSkills/SCHINDLER & ASSOCIATES & CODEWEST - ALL RIGHTS RESERVED - DO NOT COPY OR DISTRIBUTE
QUESTION: 5
GIVEN:
FORMULA: UG-37
Limits of reinforcement:
Parallel:
d = 12"
Normal:
t r = PRv / SE - 0.6P
t r = 1.488"
t rn = PRn / SE - 0.6P
t rn = 0.248"
45
itcSkills
API-510 PRESTUDY GUIDE
COPYRIGHT 2004 – itcSkills/SCHINDLER & ASSOCIATES & CODEWEST - ALL RIGHTS RESERVED - DO NOT COPY OR DISTRIBUTE
or
CONCLUSION:
Nozzle reinforcement and weld sizes meet Code requirements. Nozzle adequately reinforced.
46
itcSkills
API-510 PRESTUDY GUIDE
COPYRIGHT 2004 – itcSkills/SCHINDLER & ASSOCIATES & CODEWEST - ALL RIGHTS RESERVED - DO NOT COPY OR DISTRIBUTE
QUESTION: 6
GIVEN:
P = 725
Design temperature = 700F
Material Sd = 16,600 psi at design temperature
Material St = 17,500 psi at test temperature
FORMULA: UG-99
P t = 993.39 psi
CONCLUSION:
The required test pressure is 994 psi. The steps necessary to perform the hydrostatic test are as follows:
47
itcSkills
API-510 PRESTUDY GUIDE
COPYRIGHT 2004 – itcSkills/SCHINDLER & ASSOCIATES & CODEWEST - ALL RIGHTS RESERVED - DO NOT COPY OR DISTRIBUTE
QUESTION: 7
GIVEN:
P = 800 psi
Design Temperature = 450 F
MDMT = 100 F
Material Sd = 15,000 psi at design temperature
Material St = 15,000 psi at test temperature
FORMULA: UG-100
P t = 880 psi
CONCLUSION:
The test pressure is 880 psi and the test temperature is 130 F per API 510, 4.4 and UG-100 (c).
48
itcSkills
API-510 PRESTUDY GUIDE
COPYRIGHT 2004 – itcSkills/SCHINDLER & ASSOCIATES & CODEWEST - ALL RIGHTS RESERVED - DO NOT COPY OR DISTRIBUTE
QUESTION: 8
GIVEN:
t = 1.5"
t n = 0.75"
t 1 = 0.500" throat dimension
t 2 = 0.375" throat dimension
Figure UW -16.1(i)
FORMULA: UW-16(d)
t 1 + t2 1-1/4 tmin
and
t min = the smaller of 3/4 in. or the thickness of the thinner of the parts joined.
REQUIRED:
0.7 x .75 = 0.525 use 1/4 in. because it is smaller of 0.525 in. and 1/4 in.
ACTUAL:
CONCLUSION:
Construction does not meet Code because t1 + t2 is less than 1-1/4 tmin.
49
itcSkills
API-510 PRESTUDY GUIDE
COPYRIGHT 2004 – itcSkills/SCHINDLER & ASSOCIATES & CODEWEST - ALL RIGHTS RESERVED - DO NOT COPY OR DISTRIBUTE
QUESTION: 9
GIVEN:
t min = 1.125"
R = 30 in.
P = 641 psi
S = 17,500 psi at design temperature
E = 1.00
S d/S a = 1.00
MDMT stamped on vessel nameplate = -20 F.
PWHT has been performed but not required by Code.
SA-515-70 material is a Curve A material per Fig. UCS -66 note (a).
ASSUMPTION:
t = PR/SE - 0.6P
Using Table UCS -66 or Figure UCS -66 the MDMT of the material is 75F.
MDMT = +75
Reduction per UCS-68(c) +30 -
+45 F
CONCLUSION:
Since the MDMT for the plate is 45 F. and no further exemptions are available the plate must be impact
tested at - 20 F. In accordance with UG-84, acceptance criteria is as shown in Figure UG-84.1.
50
itcSkills
API-510 PRESTUDY GUIDE
COPYRIGHT 2004 – itcSkills/SCHINDLER & ASSOCIATES & CODEWEST - ALL RIGHTS RESERVED - DO NOT COPY OR DISTRIBUTE
QUESTION: 10
GIVEN:
FORMULA: UG-99
P t = 162.5 psi
CONCLUSION:
51
itcSkills
API-510 PRESTUDY GUIDE
COPYRIGHT 2004 – itcSkills/SCHINDLER & ASSOCIATES & CODEWEST - ALL RIGHTS RESERVED - DO NOT COPY OR DISTRIBUTE
52
itcSkills
API-510 PRESTUDY GUIDE
COPYRIGHT 2004 – itcSkills/SCHINDLER & ASSOCIATES & CODEWEST - ALL RIGHTS RESERVED - DO NOT COPY OR DISTRIBUTE
54. UW-35
55. Figure UCS -66 +120
56. Yes, Figure UCS-66 [note (e)]
57. UW-15(d)
Section IX
1. QW-461.9
2. QW-100.1
3. QW-322.1
4. QW-153(d)
5. QW-163
6. QW-200.1(a)
7. QW-355
8. QW-200.2(c)
9. QW-202.3(b)
10. QW-120
11. QW-253
12. QW-201 & 300.2
13. QW-190
14. QW-211
15. QW-200.2(f)
16. QW-201
17. QW-212
18. QW-304
19. QW-321.1
20. QW-322.2(a)
21. QW-433
22. QW-151.1(a)
23. QW-406.1
24. QW-161.5
25. QW/QB-422
26. QW-423
27. QW-303.1
28. QW-432
29. QW-451.1
30. QW-401
31. QW-452.1
32. QW-452.3
33. QW-422
34. QW-462.1(a)
53
itcSkills
API-510 PRESTUDY GUIDE
COPYRIGHT 2004 – itcSkills/SCHINDLER & ASSOCIATES & CODEWEST - ALL RIGHTS RESERVED - DO NOT COPY OR DISTRIBUTE
1. There are 3 pressure gages on a 200 ft tower that is being hydrostatically tested. One gage is
installed 110 ft from the top and reads 198 psi. A second gage is on the 120 ft level and reads 185
psi. What would the pressure gage at the top of the vessel read? UG-98
1) 160 psi
2) 150 psi
3) 135 psi
4) 180 psi
2. An SA-240 Type 410S test specimen was used on a PQR. Which of the following would be the
minimum permitted tensile strength of a tensile test coupon to pass the tensile test? QW-153
1) 54,000 psi
2) 57,000 psi
3) 60,000 psi
4) 66,500 psi
3. The corrosion rate for a vessel is 0.004 in. per year based on a 5 year inspection interval. Which of
the following cannot be used to exempt the vessel from internal inspection if it remains in the same
service? API 510, 7.2.6
4. An eight foot diameter vessel has a large area of general corrosion (32 in. in length and width) and
has thickness readings taken in the circumferential (lettered rows) and longitudinal (numbered rows)
directions as shown below. What would be the least thickness along the most critical element
considering circumferential stress applies. API 510, 5.7
1) 0.206"
54
itcSkills
API-510 PRESTUDY GUIDE
COPYRIGHT 2004 – itcSkills/SCHINDLER & ASSOCIATES & CODEWEST - ALL RIGHTS RESERVED - DO NOT COPY OR DISTRIBUTE
2) 0.191"
3) 0.179"
4) 0.195"
5. A vessel that is 1.1375 in. thick is to have a butt welded patch installed of SA-515 Gr. 70 material.
The nameplate on the vessel is stamped HT under the Code symbol stamp and a MDMT of 600F.
Below what temperature would impact testing be required? UCS-66
1) 400F
2) 450F
3) 600F
4) 750F
6. To prevent brittle failure below - 500F which of the following materials would be best suited? UCS-
66
8. Which of the following is an essential variable for the SMAW process?, QW-253
12. Question on range of fillet weld that could have been specified on WPS for SMAW WPS/PQR, QW-
202.2
14. Reinforcement math problem asking to determine A2. All parameters given, UG-37
15. Reinforcement math problem asking to determine A. All parameters given, UG-37
16. Elliptical head math problem asking to find corrosion allowance, UG-32(d)
55
itcSkills
API-510 PRESTUDY GUIDE
COPYRIGHT 2004 – itcSkills/SCHINDLER & ASSOCIATES & CODEWEST - ALL RIGHTS RESERVED - DO NOT COPY OR DISTRIBUTE
17. Elliptical head math problem to determine P, UG-32(d)
23. Determine correct source side IQI size for a given metal thickness, Table T-276
24. What is the maximum range permitted for a pressure gage used for a leak test? UG-102
27. Which of the following standards is used for air cooled heat exchangers? RP572, 1.2
1) API 510
2) Std. 661
3) Std. 660
4) RP 576
34. Question on education and experience for an API 510 inspector, API 510, 4.2
35. Question on length over which the least thickness may be averaged, API 510, 5.7
38. What is the maximum permitted geometric unsharpness for a material 2" thickness, T-285
39. What is allowable offset for a 1/4" shell joined to a 3/4" shell? UW-33
40. What is the maximum permitted out of roundness for a cylindrical shell, UG-80
56
itcSkills
API-510 PRESTUDY GUIDE
COPYRIGHT 2004 – itcSkills/SCHINDLER & ASSOCIATES & CODEWEST - ALL RIGHTS RESERVED - DO NOT COPY OR DISTRIBUTE
1. For a new vessel or a vessel for which service conditions are being changed, what time period is
required prior to on-steam determinations being made to determine the new corrosion rate?
API 510, 5.3
1) 2 weeks
2) 3 weeks
3) 6 weeks
4) 6 months
1) UT
2) MT
3) RT
4) ET
5. Per API 510 how long is temperature held after completion of a temper bead repair? API 510, 7.2.4
6. Which of the following must be considered when making repairs to stainless steel weld overlay and
cladding for vessels in hydrogen service? API 510, 7.2.6
1) Outgassing
2)
3)
4)
57
itcSkills
API-510 PRESTUDY GUIDE
COPYRIGHT 2004 – itcSkills/SCHINDLER & ASSOCIATES & CODEWEST - ALL RIGHTS RESERVED - DO NOT COPY OR DISTRIBUTE
7. How often are eye examinations required for MT or PT examiners? Appendix 6 & 8
8. Which of the following best describes the SMAW welding process? QW-492
1) Dirty
2) High viscosity
3) Low differential between operating and set pressures
4)
10. What is the best service for a safety valve? RP576, 2.2.1.2
11. For a large vessel with two or more zones of differing corrosion rates what is the best way to treat
the vessel regarding each zone? API 510, 6.3
12. Determine short term corrosion rate, several past readings given. API 510, 6.3
1) .005 mils
2) .05 mils
3) .5 mils
4) 5 mils
13. When is it not necessary to remove external insulation for inspection? API 510, 6.2
58
itcSkills
API-510 PRESTUDY GUIDE
COPYRIGHT 2004 – itcSkills/SCHINDLER & ASSOCIATES & CODEWEST - ALL RIGHTS RESERVED - DO NOT COPY OR DISTRIBUTE
22. Question on use of filler metals having lower tensile strength than base material, API 510, 7.2.11
25. Question on as received pop test for relief device, RP576, 6.2.1
26. What is considered to by on schedule for inspection of relief device, RP576, 5.2.3
28. What are the methods of constructing shell rings, RP572, 2.2
30. What are the most common internal corrodents, RP572, 6.2
31. What are the first things to inspect on a vessel during an external inspection, RP572, 8.3.2
33. What are the most important conditions to check when inspecting metallic linings, RP572, 8.4.5
37. Question on galvanic corrosion between carbon steel and magnesium, Chapter II, 202.067
38. Step wedge comparison films shall be traceable to what standard, T-262
40. What examination must be performed prior to a shear wave examination, T-542.7.2.1
42. What is the maximum permitted rate of search unit movement, T-523.2
43. What must be done when both ownership and location of a vessel change, API 510, 6.3
59
itcSkills
API-510 PRESTUDY GUIDE
COPYRIGHT 2004 – itcSkills/SCHINDLER & ASSOCIATES & CODEWEST - ALL RIGHTS RESERVED - DO NOT COPY OR DISTRIBUTE
44. A weep hole in a reinforcement plate is left open so that leaks can be seen and for what other
reason? UG-UW-15
45. When performing a Charpy V-notch toughness test you are performing a/an, QW -171.1
1) Impact test
2) Brinnell hardness test
3) Thickness test
4) Bend test
46. Which of the following qualifies a welder to weld in all positions? QW -461.9
1) 1G
2) 3G
3) 2G & 5G
4) 6F
47. What type corrosion occurs at the point of contact between a metal and nonmetal? Chapter II,
202.068
1) Galvanic
2) Conductivity
3) Crevice
4) Biological
48. The rerating of a pressure vessel is complete when: API 510, 7.3
49. During an internal inspection of a pressure vessel a blister is found in one of the heads between the
knuckle and the circumferential head to shell weld. What would be the most appropriate action?
API 510, 7.1
50. A pressure vessel contains the following nozzles, (2-NPS 6, 1-NPS 10 and 4-NPS 3). Which of the
following would be an alteration? API 510, 3.1
60
itcSkills
API-510 PRESTUDY GUIDE
COPYRIGHT 2004 – itcSkills/SCHINDLER & ASSOCIATES & CODEWEST - ALL RIGHTS RESERVED - DO NOT COPY OR DISTRIBUTE
3) Addition of an NPS 3/4 nozzle
4) Addition of three NPS 1 nozzles
51. A pressure vessel is in service and has no corrosion data available. Where should thickness
readings be taken? RP572, 8.3.12
The open book portion was reported to be very straight forward with no difficult math involved. Most values
including E were given.
Closed book questions were worded in suc h a manner that two possible answers seemed correct. A
complete understanding of what was being asked was essential to choose the correct answer.
The following questions or similar to those from the Final Examination of the May 1999 Schindler &
Associates course were included in this examination;
61
itcSkills
API-510 PRESTUDY GUIDE
COPYRIGHT 2004 – itcSkills/SCHINDLER & ASSOCIATES & CODEWEST - ALL RIGHTS RESERVED - DO NOT COPY OR DISTRIBUTE
2, 12, 14, 15, 16, 22, 23, 26, 29, 32, 33, 35, 36, 38, 39, 42, 43, 44, 45, 46, 47, 48, 49, 52, 53, 55, 56, 58,
62, 66, 69, 72, 73, 74, 78, 84, 87, 89, 90, 92, 98, 100, 103, 105, 111, 116, 118, 123, 127, 129, 131, 132,
136, 140.
The following questions or similar to those from the Post Study Course Guide of the May 1999 Schindler &
Associates course were included in this examination.
1, 3, 5, 7, 9, 10, 12, 13, 14, 16, 18, 19, 21, 22, 23, 24, 25, 27, 28, 30, 32, 33, 34, 35, 37, 38, 41, 43, 48, 51,
52, 54, 55, 56, 57, 60, 63, 64, 67, 68, 69, 71, 72, 73, 74, 75, 76, 79, 81, 84, 85, 86, 88, 89, 92, 93, 96, 98,
100, 101, 103, 104, 107, 108, 115, 122, 126, 127, 129, 130, 134, 135, 144, 145, 148, 149.
Some specific questions remembered are as follows. There may be duplication from the numbered
questions listed above.
2. Remaining life and corrosion rate problems (many) API 510, 6.3
8. An E7018 designated filler metal is what kind of filler metal (covered electrode) QW-492
10. What examination method to check for surface cracks for vessels in amine service (wet mag)
RP572, 8.4.4
11. Questions on the temper bead process (4-5) API 510 7.2.4
(a) Holding time and temperature
(b) preheat
(c) P-No. 3 thickness limit
13. Welding positions for welders (several on closed book portion) QW-461.9
62
itcSkills
API-510 PRESTUDY GUIDE
COPYRIGHT 2004 – itcSkills/SCHINDLER & ASSOCIATES & CODEWEST - ALL RIGHTS RESERVED - DO NOT COPY OR DISTRIBUTE
14. For a weld repair on a vessel what are the PWHT requirements? API 510, 7.2.4
15. For new construction of a vessel what are the PWHT requirements? VIII, UCS-56
16. Amount of slag inclusion permitted in a 3/4 in. thick weld that was fully RT’d. VIII, UW-51
22. Which of the following welding documents needs to have a signature? IX, QW-200.2 & 484
26. API 510, 6.4 pressure test temperature question. API 510, 6.4
28. Question on a rerated vessel. Are you going to take more TML readings.
30. Question on using radiography to qualify welder for GMAW process. IX, QW-304
It appears that this examination is almost identical to the one in December 2001.
63
itcSkills
API-510 PRESTUDY GUIDE
COPYRIGHT 2004 – itcSkills/SCHINDLER & ASSOCIATES & CODEWEST - ALL RIGHTS RESERVED - DO NOT COPY OR DISTRIBUTE
SMAW welding procedure with three questions:
1.Do the tensile tests meet the requirements of Section IX - No, because one specimen failed in weld and
strength was below MSTS of base metal. IX, QW-153(d)
2.Do the bend tests meet Section IX, No because they used face & root instead of side bends. IX, QW
451.1
3. Did the base metal range on the WPS meet the requirements of Section IX, Yes, because the PQR
was 1" and the range shown was 3/16" - 2" and the ½" weld pass was addressed on both WPS and
PQR. IX, QW-451.1
6. Weld surface distance from center of weld per API 510, 5.7(g).
7. Math problem involving a torispherical head with corrosion in center. Must use Spherical shell formula
in UG-27 to solve. Gave inside diameter of head to use as L =54", MAWP = 250, S = 17500, C.A. to
maintain = 0.125 API 510, 5.7(h)
8. Question on when can you substitute on stream for internal. See API 510, 6.4(b).
9. Who besides inspector has to approve using preheat in lieu of PWHT. API 510, 7.2.3
10. How long do you hold the 500 degrees +/- 50 degree temperature after completing a controlled
deposition welding method? API 510, 7.2.3.2(f)(8)
11. What NDE after completing weld repair to stainless weld overlay? API 510, 7.2.6
12. How is welding material identified in lieu of having a MTR or CofC? VIII, UG-9
13. Flat head thickness calculation with sketch UG-34(b-1) given. VIII, UG-34
15. Reinforcement problem to find A=dt r with d and t r given. VIII, UG-37
18. What type weld joint with data given? VIII, Table UW-12
19. What is alignment tolerance for 3/4" weld in a Category A joint? VIII, UW-33
20. What is overlap when heating vessel in more than one heat? VIII, UW-40(a)(2)
21. What is retention time for radiographs for fabrication and assembly of a vessel? VIII, UW -51(a)(1)
22. What is maximum length of a slag inclusion when vessel stamped RT 1 and 2.25" thick? VIII, UW
51(b)(2)
64
itcSkills
API-510 PRESTUDY GUIDE
COPYRIGHT 2004 – itcSkills/SCHINDLER & ASSOCIATES & CODEWEST - ALL RIGHTS RESERVED - DO NOT COPY OR DISTRIBUTE
23. What is minimum holding temperature for PWHT of a P-1 material? VIII, UCS-56
24. What is minimum holding time for a 3" weld in SA-516 Grade 70 material? VIII, UCS-56
25. What is MDMT for SA-515 Grade 70 material given a 0.5 St/S d as ratio and the stat ement that PWHT
required for a 1.125" thickness. VIII, UCS -66
26. What is the basic MDMT for SA-516 Grade 60 normalized? VIII, Table UCS-66
27. Which of the following is an essential variable for the SMAW process? Answer was preheat. IX,
QW-406.1
28. Densitometers are calibrated against what standard? national standard V, T262.1
29. What source side hole type IQI is used to radiograph a 1.5" weld? #30 V, Table T-276
30. What is maximum permitted density for a radiograph made with gamma source? V, T-282.1
32. What is geometric unsharpness maximum for a weld under 2" thick? V, T-285
33. Which of the following is not required to be recorded on a radiographic evaluation sheet? Geometric
unsharpness V, T-292
34. What is frequency of calibration for magnitizing equipment? Whenever subjected to major repair of
overhaul. V, T761
35. What is calibration tolerance for a unit meter on MT equipment? +/- 10% V, T-761
36. What is lifting power for a DC yoke when calibrating? 40 lbs. V, T-762
38. Frequency of vision check for a PT/MT NDE Examiner. VIII, Appendices 6 & 8
39. External shell pressure problem with Factor B, Do, t given. VIII, UG-28
42. Question on progressive records requiring regular updating. API 510, 6.7
43. Preheat and controlled-deposition welding may be used in lieu of PWHT. What condition must be
satisfied prior to using this alternative method? API 510, 7.2.3
65
itcSkills
API-510 PRESTUDY GUIDE
COPYRIGHT 2004 – itcSkills/SCHINDLER & ASSOCIATES & CODEWEST - ALL RIGHTS RESERVED - DO NOT COPY OR DISTRIBUTE
Closed Book
12. Static head math problem with two pressure gages. Vertical vessel 125 ft high is under a hydro.
Pressure gage 100 ft from top reads 193.5 psi. Pressure gage 45 ft from top reads 169.5 psi. What
pressure does gage at top of vessel read? VIII, UG-98
13. What Standard is referenced for qualification of RT personnel? SNT-TC-1A VIII, UW -51(a)(2)
14. Which of the following is not part of a PT procedure? Amount of developer applied V, T-621
15. What is the immediate retest criteria if a welder was qualifying on a production weld of 6"? 12" IX,
QW-321.3(b)
18. What two welding positions qualify a welder to weld all positions? IX, QW-461.9
19. Question on termination of Code where external piping attached to vessel. Weld end connection
VIII, U-1(e)(1)(a)
20. Which of following can be exempted from API 510? Vessel on truck API 510, Appendix A
21. What is maximum tolerance permitted for setting of a PRV set at 400 psi? VIII, UG-126(d)
22. Who has to assist inspector when a crack is found in the knuckle of a toriconical head? PV Engineer
API 510, 7.1.3
66
itcSkills
API-510 PRESTUDY GUIDE
COPYRIGHT 2004 – itcSkills/SCHINDLER & ASSOCIATES & CODEWEST - ALL RIGHTS RESERVED - DO NOT COPY OR DISTRIBUTE
23. Making a repair, which of following types of material require an MTR? Plate VIII, UG-93(a)(1)
24. Hydrotest problem with ratio of 1.0 and MAWP given. VIII, UG-99
25. Maximum range for pressure gage during hydrotest. 4 times test pressure VIII, UG-102
28. What is carbon maximum in material for welding? 0.35% API 510, 7.2.8 & VIII, UCS-5
29. What is the maximum depth that can be welded in a 3" plate of P-No. 3 material and have PWHT
waived? 5/8", however this was taken out of API 510 with the #2 Addendum. See 7.2.3
30. What is frequency of eye examination for an PT NDE examiner. VIII, Appendix 8-2
31. Who is responsible for maintaining WPS’s, PQR’s and WPQ’s? Repair organization API 510, 7.2.2
34. Question on corrosion rate determination using 6 weeks time? API 510, 5.3
35. Which of the following is not considered corrosion? Cavitation Chap. II, 203.022
36. At what temperature range is CUI most active? 25 - 250 degrees F API 510, 6.3
37. At what temperature is CUI most active? -4 to 120 degrees C API 510, 6.3
39. What is maximum inspection interval for PRV’s? 10 years API 510, 6.6
40. How is inspection interval for PRV determined? Operational experience API 510, 6.6
41. You have a vessel with only one TML and localized corrosion is found in bottom shell, head and
nozzles. What would you do? Assign more TML’s to bottom head, shell and nozzles API 510, 6.4
42 You have a vessel 2.5" thick, when hydrotesting what temperature increase above MDMT to avoid
brittle fracture failure? API 510, 6.5
43. What must a company who repairs PRV’s have? QC program API 510, 6.6
44. How long are inspection records kept? Service life of vessel API 510, 6.7
45. Question on who authorizes repairs and alterations API 510, 7.1 & 7.1.1
46. Who qualifies welding procedures and welders? Repair organization API 510, 7.2.1
47. Who has to review the application and prepare procedures for the local postweld heat treatment
method? PV Engineer API 510, 7.2.5
48. When repairs are made to stainless overlay or cladding for equipment in hydrogen service which
67
itcSkills
API-510 PRESTUDY GUIDE
COPYRIGHT 2004 – itcSkills/SCHINDLER & ASSOCIATES & CODEWEST - ALL RIGHTS RESERVED - DO NOT COPY OR DISTRIBUTE
factor does the PV engineer consider? Outgassing base metal API 510, 7.2.6
49. A rerating is being performed on a vessel which of the following could be done with only a
calculation? API 510, 7.3
52. Mercury causes stress corrosion cracking in what metals? Chap. II, 202.036
53. Nonferrous metals contain less than what % iron? Chap. II, Appendix IB
54. Contact corrosion is also called what? Crevice corrosion Chap. II, 202.608
55. Materials having low energy values are usually prone to what type failure? Brittle
fracture Chap. II, 205.01
56. Improper heat treatment can cause which of the following? Loss of tensile
strength if kept at temperature too long RP572, 6.7.3
57. The continued use of a pressure vessel shall be based on which of the following? Latest ASME Code
or the original construction code API 510, 5.4
58. Which of the following progressive records shall be maintained? All new and previous thickness
readings API 510, 6.7
59. What cleaning methods would apply for wet sulfide cracking? See RP572, 8.4.2, hot water, steaming
and abrasive grit blasting
60. You find cracks in a metallic lining what would you do? (a) Remove some lining to inspect base metal
surface, (b) Check base metal for damage, ( c) Do nothing, (d) Repair liner. RP572, 8.4.5
61. If the vessel is insulated effectively to preclude entrance of moisture what must be done to the outer
jacketing? Observed every 5 years and repaired if necessary API 510, 6.3
62. What does an external inspection start with? Ladders, platforms and walkways? RP572, 8.3.2
63. How are ladders, platforms and walkways inspected? Visually, supplemented by hammering and
scraping. RP572, 8.3.2
64. What is major cause of failure in springs of PRV’s? Corrosion RP576, 5.3
65. What type of PRV uses a control unit? Pilot-operated RP576, 4.7
66. A vessel is in hydrogen service and is carbon steel with a titanium stabilized austenitic stainless steel
overlay. What is a probable type failure and how would you inspect for it? Cracking, UT and PT Chap.
II, 204.035 & API 510, 7.2.6
67. How long must an MT examiner be in darkened room prior to performing examinations? V, T-778.2
68
itcSkills
API-510 PRESTUDY GUIDE
COPYRIGHT 2004 – itcSkills/SCHINDLER & ASSOCIATES & CODEWEST - ALL RIGHTS RESERVED - DO NOT COPY OR DISTRIBUTE
72. Question on what type of inspection cannot be used for determining thickness. API 510, 6.4
74. Question on AI authorization prior to start of work and exception permitted. API 510, 7.1.1
75. Question on minimum preheat temperature to avoid PWHT. API 510, 7.2.3.1
76. When pressure test will exceed set pressure of safety relief valve, what can be done as an alternative to
removing valve? API 510, 6.5
78. At what temperature does incipient melting take place? Chap. II, 204.022(b)
80. Is a preliminary hydrotest allowed prior to PWHT? VIII, UCS -56(f) & UW-40(e)
69