Notes
Notes
types
1 as late as posible
2 as soon as posible(default)
3 finish no earlier than
4 finish no later than
5 must finish on…
6 must start on…
7 start no earlier than
8 start no later then…
over allocated resourcce occurs when the work assigned to a resource exceeds his max units
formula d=w/u
1 ex. A painting job requires 80 hrs to finish if a painter can works 8 hrs/ day how long can he finish the job
d= ? 10
w= 80
u= 8
TASK TYPES
1. Fixed UNITS(DEFAULT) D=W/VF
2. Fixed Duration Df=W/U
Resource loading
1. best
2 ideal
bad
S-curve-is the graphical representation of cum. Cash flow plotted against time
task cost w1 w2 w3 w4 w5
a 50000 50000
b 60000 20000 20000 20000
c 150000 50000 50000 50000
d 200000 100000 100000
e 40000 40000
500000
TRACKING PROJECT
BASE LINE- IS A COPY OF "ORIGINAL PLAN" USED AS REFERENCE TO TRACK PROGRESS OF PROJECT
STATUS DATE- THE DATE WHEN THE PROJECT IS UPDATED
PROGRESS LINE- IS A TOOL THAT SHOWS WHETHER THE TASK IS AHEAD OR BEHIND SCHEDULE
eds his max units
4740
4300
440
5
TIME