Fluid List: Pag/Pag. - Din/from

This document is a fluid list for the Gathering Point 7 installation. It provides information on the medium, line routing, pipe material specifications, and design parameters for various lines including mixing crude oil-water lines from tie-ins 101-106 and a line from a calibrated tank to a drain pit. The pipe material for all lines is 275NL1 steel and the maximum operating temperature is 90°C and pressure is 25 barg.

Uploaded by

Andreea
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
138 views2 pages

Fluid List: Pag/Pag. - Din/from

This document is a fluid list for the Gathering Point 7 installation. It provides information on the medium, line routing, pipe material specifications, and design parameters for various lines including mixing crude oil-water lines from tie-ins 101-106 and a line from a calibrated tank to a drain pit. The pipe material for all lines is 275NL1 steel and the maximum operating temperature is 90°C and pressure is 25 barg.

Uploaded by

Andreea
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

03.2014 ing. Otves M. ing.Olaru C.

Production Measurement and Calibration Data/ Intocmit/ Verificat/


Asset I Crisana, Banat Date Designer Checked

Fluid List Pag/Pag._ 1_din/from _2_

Fluid List

03 FC – For Use/Approved 10.2014 ing. Otves M. ing. Olaru C. ing. Baltaga V.


02 FR – For Review/Check (after HAZOP) 17.04.2014 ing. Otves M. ing. Olaru C. ing. Baltaga V.
01 Issued for approval 03.2014 ing. Otves M. ing. Olaru C. ing. Baltaga V.
Rev/Rev. Denumirea modificarii/Change description Data/Date Intocmit/Designer Verificat/Checked Aprobat/Approved
Nr. proiect / Project no. Nr. desen / Drawing no. Rev/Rev
ROA01134227587 PE-D-ROA01134227587-PS-LST-102
Instalatia/Plant Cod Instalatie/Plant Code 03
Gathering point 7 GP7
Beneficiar/Customer : OMV PETROM S.A. Romania, E&P, Asset I Crisana,
Specialitate doc./Specialty doc. F
Banat
Instalatia/Plant : Gathering point 7 Suplac Process A4
Scara/Scale Denumire document/Document name
- Fluid List
03.2014 ing. Otves M. ing.Olaru C.
Production Measurement and Calibration Asset I Crisana, Banat Data/ Intocmit/ Verificat/
Date Designer Checked
Fluid List
Pag/Pag._ 2_din/from _2_

Max. operating
Medium Line routing Pipes material specification Design parameters
parameters

Nominal Nominal
Code

Piping Type of CA, Temp., Pressure, Temp., Pressure,


Description from To diameter pressure o o
class material mm C barg C barg
(DN) (PN)
Flange of 21-
HV-101;
PO Mixing Crude oil-water Tie-in 101; ACP3A 100 40 275NL1 3 90 21,5 105 25
Flange of 21-
HV-102
Flange of 21-
HV-103;
Flange of 21- Flange of 21-
PO Mixing Crude oil-water ACP3A 100 40 275NL1 3 90 21,5 105 25
HV-102 HV-104;
Flange of 21-
HV-105
Flange of 21-
Flange of 21- HV-101;
PO Mixing Crude oil-water ACP3A 100 40 275NL1 3 90 21,5 105 25
HV-103 Tie-in 102
existing flange;
Calibrated
Flange of 21-
PO Mixing Crude oil-water Tank 21-TK- ACM3A 100 16 275NL1 3 90 0,3 105 1
HV-104
101
Flange of 21- Drain Pit 57-Z-
PO Mixing Crude oil-water ACM3A 50 16 275NL1 3 90 0,3 105 1
HV-105 002
PO Mixing Crude oil-water Flange of 21-
Tie-in 103 ACM3A 100 16 275NL1 3 90 0,3 105 1
HV-106

Nr. Proiect/Project no. Nr. document/Document no. Rev/Rev Specialitate doc./Specialty doc.
ROA01134227587 PE-D-ROA01134227587-PS-LST-102 03 Process